Anda di halaman 1dari 17

MOTHER STATION - CNG TAPEN

SURAT PENAWARAN HARGA

BILL Of QUANTITY
PROYEK : CNG - MS - TAPEN
PEKERJAAN : OFFICE
LOKASI : NGAWUN PERENGAN, TUBAN - JAWA TIMUR

HARGA
VOL SAT JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN

1 OFFICE 12X10

1 PEKERJAAN PERSIAPAN
1 Manajemen Proyek 1.00 ls 10,000,000 10,000,000
2 Air kerja. 1.00 ls 4,000,000 4,000,000
3 Listrik kerja 1.00 ls 4,000,000 4,000,000
4 Pembersihan lokasi & buang gragal / tanah 1.00 ls 5,000,000 5,000,000
5 Uitseet & bouwplank 1.00 ls 5,000,000 5,000,000
6 Alat bantu kerja (Scafolding, lampu, kabel, dll) 1.00 ls 5,000,000 5,000,000
33,000,000
2 PEKERJAAN TANAH
1 Galian tanah untuk pondasi 26.29 m3 120,000 3,154,620
2 urugan pasir bawah pondasi (tebal = ± 10 cm) 7.34 m3 150,000 1,101,450
3 Urugan Peninggian lantai padat setamper +40 cm 100.00 m3 150,000 15,000,000
19,256,070
3 PEKERJAAN STRUKTUR
a PEKERJAAN PONDASI
1 Mob demob alat stross 1.00 ls 1,500,000 1,500,000
2 Setrous pile 36.00 m1 210,000 7,560,000
3 Merapikan setros kepala tiang pancang 12.00 titik 30,000 360,000
4 lantai kerja (tebal = ± 5 cm) 3.67 m3 1,200,000 4,405,800
5 Cor Sloof 15x20 K 225 5.79 m3 4,325,241 25,043,148
6 Cor Pondasi poor 20x50x30 K 225 0.90 m3 5,654,367 5,088,930
7 Cor Plat Tebal 6 cm K-225 15.00 m3 1,291,950 19,379,250

b PEKERJAAN KOLOM BETON


1 Cor Kolom 20x20 K-225 m3 1.92 5,922,530 11,371,258
2 Kolom Praktis 15x15 K-225 m3 2.07 6,094,797 12,616,229

c PEKERJAAN BALOK BETON


1 Cor Balok B1 15x20 K-225 m3 3.51 5,605,452.44 19,675,138
2 Cor Balok Ring 15x15 K-225 m3 1.71 6,073,694.25 10,386,017
3 Cor Plat Talang Tebal 10 cm K-225 m3 6.30 4,037,819 25,438,259
4 Cor Plat Canopy Tebal 10 cm K-225 m3 2.19 4,037,819 8,830,710
151,654,740

4 PEKERJAAN ARSITEKTURAL
PEKERJAAN PASANGAN & PLESTERAN
1 Pasangan dinding Bata m2 683.25 135,000 92,238,750
2 Plester aci m2 1,366.50 97,500 133,233,750
3 Plesteran Kolom K1 m2 4.20 97,500 409,500
4 Plester aci ruang pintu jendela m2 23.06 97,500 2,247,863
5 Pekerjaan benangan sudut Kolom m1 168.00 17,500 2,940,000
6 Benangan Sudut dinding m1 224.00 17,500 3,920,000
7 Benangan Pintu Jendela m1 307.40 17,500 5,379,500
240,369,363
5 PEKERJAAN KERAMIK
Pekerjaan Penutup Lantai - -
1 Pasangan Keramik 60x60 cm motif / warna terang m2 220.00 220,000 48,400,000
2 Pasangan Keramik 60x60 cm motif / kasar teras m2 49.00 280,000 13,720,000
62,120,000
6 PEKERJAAN KAMAR MANDI
1 Keramik Lantai Asia Roxy grey 20x20 M2 30.00 183,000 5,490,000
2 Keramik Dinding Asia tile eksel white 20x25 M2 47.25 195,000 9,213,750
3 Avour lantai ex. Toto TX1A (Rp. 263.900) Unit 2.00 325,000 650,000
4 Pasang Closet duduk porselen ex. Amstad Unit 2.00 3,500,000 7,000,000
5 Bak Mandi Unit - 750,000 -
6 Avur Bak Unit - 100,000 -
7 Karan dinding ex.TOTO Unit 2.00 750,000 1,500,000
8 Kran shower ex. TOTO Unit 2.00 1,272,000 2,544,000
9 Tempat sabun dinding Unit 2.00 350,000 700,000
10 Waterproofing dinding 1m M2 27.00 120,000 3,240,000
30,337,750
7 PEKERJAAN SANITAIR DAN PLUMBING POS
1 Saluran air kotor PVC 4" D m' 12.00 95,000 1,140,000
2 Pipa avur PVC 3" D m' 10.00 75,000 750,000
3 Septictank 6 m3 Unit 1.00 27,000,000 27,000,000
4 Resapan beton buis dia 60 cm m' 3.00 240,000 720,000
5 Saluran air bersih PVC 1" AW M' 10.00 65,000 650,000
6 Saluran air bersih PVC 3/4" AW M' 20.00 55,000 1,100,000
31,360,000
8 PEKERJAAN KUSEN, JENDELA, PINTU ALLUMUNIUM
Kusen aluminium 4", pintu Kayu Ex.Tulus & jendela all. + kaca
1.3 PJ1 Pasangan Kusen + Daun Pintu (Doble) Almini bh 1.00 16,009,675 16,009,675
1.4 P1 Pasangan Kusen + Daun Pintu (Single) Ruangan Almini bh 12.00 3,615,000 43,380,000
1.5 P2 Pasangan Kusen + Daun Pintu (Single) Toilet bh 2.00 2,265,000 4,530,000
1.6 J1 Pasagan Jendela + Daun bh 4.00 5,110,000 20,440,000
1.7 J1' Pasagan Jendela + Daun bh 4.00 5,110,000 20,440,000
1.8 J2 Pasagan Jendela + Daun bh 2.00 2,738,000 5,476,000
1.9 J3 Pasagan Jendela + Daun bh 1.00 2,395,000 2,395,000
2,0 BV Pasagan BV bh 2.00 502,000 1,004,000
113,674,675
9 PEKERJAAN ATAP
1 Rangka atap Baja ringan M2 250.00 135,000 33,750,000
2 Penutup atap Zincallum M2 250.00 120,000 30,000,000
3 Wuwung M1 25.00 55,000 1,375,000
4 Jorongan talang bh 6.25 40,000 250,000
5 Pipa tegak PVC 3" m1 50.00 75,000 3,750,000
69,125,000
10 PEKERJAAN PLAFOND
1 Plafond Gypsum t=9mm + Rangka plafond holow 4x4cm, 2x4xm t=0,4 mm M2 250.00 125,000 31,250,000
2 List 339.00 35,000 11,865,000
43,115,000
11 PEKERJAAN INSTALASI LISTRIK
1 Titik lampu Titik 25.00 175,000 4,375,000
2 Titik stop kontak Titik 22.00 200,000 4,400,000
3 Box + MCB 12 Group Titik 1.00 750,000 750,000
4 Titik stop kontak telepon Titik 8.00 250,000 2,000,000
5 Titik stop kontak TV Titik - 350,000 -
6 Titik stop kontak AC Titik 10.00 200,000 2,000,000
7 Ground Titik 1.00 750,000 750,000
8 Test fungsi ls 1.00 500,000 500,000
9 Lampu RMI 2x36 LED titik 12.00 -
10 Lampu Downligth 6 watt LED titik 13.00 -
11 Armateur stop kontak titik 15.00 150,000 2,250,000
12 Armateur Saklar ganda Unit 6.00 150,000 900,000
13 Armateur Saklar tunggal Unit 9.00 150,000 1,350,000
14 Unit AC 1 PK Unit 10.00 -
15 Armateur Telephone Unit 8.00 250,000 2,000,000
16 Smoke detektor Unit 10.00 -
21,275,000
12 PEKERJAAN PENGECATAN
1 Pengecatan dinding interior M2 1,438.00 65,000 93,470,000
2 Pengecatan dinding exterior M2 336.00 95,000 31,920,000
3 Pengecatan plafon M2 250.00 95,000 23,750,000
4 Pengecatan waterprofing talang + Screed M2 63.00 120,000 7,560,000
Pengecatan waterprofing Kanopy + Screed M2 21.87 120,000 2,624,400
159,324,400
TOTAL PEKERJAAN ARSITEKTURAL 974,611,997
LB 258
3,779,837
MOTHER STATION - CNG TAPEN
SURAT PENAWARAN HARGA

BILL Of QUANTITY
PROYEK : CNG - MS - TAPEN
PEKERJAAN : R. GENSET DAN OFFICE BELAKANG
LOKASI : NGAWUN PERENGAN, TUBAN - JAWA TIMUR

HARGA
VOL SAT JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN

2 R. GENSET DAN OFFICE BELAKANG (4X5) (12X4)

1 PEKERJAAN PERSIAPAN
1 Pembersihan lokasi & buang gragal / tanah 1.00 ls 5,000,000 5,000,000
2 Uitseet & bouwplank 1.00 ls 5,000,000 5,000,000
3 Alat bantu kerja (Scafolding, lampu, kabel, dll) 1.00 ls 5,000,000 5,000,000
15,000,000
2 PEKERJAAN TANAH
1 Galian tanah untuk pondasi 12.78 m3 120,000 1,533,210
2 urugan pasir bawah pondasi (tebal = ± 10 cm) 3.48 m3 150,000 522,375
3 Urugan Peninggian lantai padat setamper +40 cm 32.90 m3 150,000 4,935,000
6,990,585
3 PEKERJAAN STRUKTUR
PEKERJAAN PONDASI
1 Mob demob alat stross ls 1,500,000 -
2 Setrous pile 36.00 m1 210,000 7,560,000
3 Merapikan setros kepala tiang pancang 12.00 titik 30,000 360,000
4 lantai kerja (tebal = ± 5 cm) 1.74 m3 1,200,000 2,089,500
6 Cor Pondasi poor 50x50x30 K 225 0.90 m3 5,654,367 5,088,930
5 Cor Sloof 15x20 K 225 2.48 m3 4,325,241 10,730,924
7 Cor Plat Tebal 6 cm K-225 4.94 m3 1,291,950 6,375,773

PEKERJAAN KOLOM BETON


1 Kolom Praktis 15x15 K-225 m3 2.16 6,094,797 13,164,761

PEKERJAAN BALOK BETON


1 Cor Balok B1 15x20 K-225 m3 1.23 5,605,452.44 6,894,706
2 Cor Balok Ring 15x15 K-225 m3 1.86 6,073,694.25 11,301,627
3 Cor Plat Talang Tebal 10 cm K-225 m3 1.05 4,037,819 4,239,710
4 Cor Plat Canopy Tebal 10 cm K-225 m3 1.58 4,037,819 6,359,565
74,165,496

4 PEKERJAAN ARSITEKTURAL
PEKERJAAN PASANGAN & PLESTERAN
1 Pasangan dinding Bata m2 243.00 135,000 32,805,000
2 Plester aci m2 486.00 97,500 47,385,000
3 Plester aci ruang pintu jendela m2 3.99 97,500 389,025
4 Benangan Sudut dinding m1 98.00 17,500 1,715,000
5 Benangan Pintu Jendela m1 40.40 17,500 707,000
83,001,025
5 PEKERJAAN KERAMIK
Pekerjaan Penutup Lantai - -
1 Pasangan Keramik 60x60 cm motif / warna terang m2 80.00 220,000 17,600,000
2 Pasangan Keramik 60x60 cm motif / kasar teras m2 15.75 280,000 4,410,000
22,010,000
6 PEKERJAAN KAMAR MANDI
1 Keramik Lantai Asia Roxy grey 20x20 M2 7.50 183,000 1,372,500
2 Keramik Dinding Asia tile eksel white 20x25 M2 17.85 195,000 3,480,750
3 Avour lantai ex. Toto TX1A (Rp. 263.900) Unit 1.00 325,000 325,000
4 Pasang Closet duduk porselen ex. Amstad Unit 1.00 3,500,000 3,500,000
5 Bak Mandi Unit - 750,000 -
6 Avur Bak Unit - 100,000 -
7 Karan dinding ex.TOTO Unit 1.00 750,000 750,000
8 Kran shower ex. TOTO Unit 1.00 1,272,000 1,272,000
9 Tempat sabun dinding Unit 1.00 350,000 350,000
10 Waterproofing dinding 1m M2 11.00 120,000 1,320,000
12,370,250
7 PEKERJAAN SANITAIR DAN PLUMBING POS
1 Saluran air kotor PVC 4" D m' 8.00 95,000 760,000
2 Pipa avur PVC 3" D m' 8.00 75,000 600,000
3 Septictank 6 m3 Unit 1.00 27,000,000 27,000,000
4 Resapan beton buis dia 60 cm m' 3.00 240,000 720,000
5 Saluran air bersih PVC 1" AW M' 15.00 65,000 975,000
6 Saluran air bersih PVC 3/4" AW M' 15.00 55,000 825,000
30,880,000
8 PEKERJAAN KUSEN, JENDELA, PINTU ALLUMUNIUM
Kusen aluminium 4", pintu Kayu Ex.Tulus & jendela all. + kaca
1 PJ1 Pasangan Kusen + Daun Pintu (Doble) Almini bh 2.00 9,327,000 18,654,000
2 P1 Pasangan Kusen + Daun Pintu (Single) Ruangan Almini bh 1.00 3,615,000 3,615,000
3 P2 Pasangan Kusen + Daun Pintu (Single) Toilet bh 1.00 2,265,000 2,265,000
4 BV Pasagan BV bh 1.00 502,000 502,000
25,036,000
9 PEKERJAAN ATAP
1 Rangka atap Baja ringan M2 70.00 135,000 9,450,000
2 Penutup atap Zincallum M2 70.00 120,000 8,400,000
3 Wuwung M1 - 55,000 -
4 Jorongan talang bh 7.00 40,000 280,000
5 Pipa tegak PVC 3" m1 42.00 75,000 3,150,000
21,280,000
10 PEKERJAAN PLAFOND
1 Plafond Gypsum t=9mm + Rangka plafond holow 4x4cm, 2x4xm t=0,4 mm M2 70.00 125,000 8,750,000
2 List 67.00 35,000 2,345,000
11,095,000
11 PEKERJAAN INSTALASI LISTRIK
1 Titik lampu Titik 8.00 175,000 1,400,000
2 Titik stop kontak Titik 6.00 200,000 1,200,000
3 Box + MCB 12 Group Titik 1.00 750,000 750,000
4 Titik stop kontak telepon Titik 2.00 250,000 500,000
5 Titik stop kontak AC Titik 2.00 200,000 400,000
6 Ground Titik 1.00 750,000 750,000
7 Test fungsi ls 1.00 500,000 500,000
8 Armateur stop kontak titik 6.00 150,000 900,000
9 Armateur Saklar ganda Unit 4.00 150,000 600,000
10 Armateur Telephone Unit 2.00 250,000 500,000
7,500,000
12 PEKERJAAN PENGECATAN
1 Pengecatan dinding interior M2 285.99 65,000 18,589,350
2 Pengecatan dinding exterior M2 204.00 95,000 19,380,000
3 Pengecatan plafon M2 10.50 95,000 997,500
4 Pengecatan waterprofing talang + Screed M2 15.75 120,000 1,890,000
Pengecatan waterprofing Kanopy + Screed M2 21.87 120,000 2,624,400
43,481,250
TOTAL PEKERJAAN ARSITEKTURAL 352,809,606
LB 258
1,368,301
MOTHER STATION - CNG TAPEN
SURAT PENAWARAN HARGA

BILL Of QUANTITY
PROYEK : CNG - MS - TAPEN
PEKERJAAN : POS SECURITY
LOKASI : NGAWUN PERENGAN, TUBAN - JAWA TIMUR

HARGA
VOL SAT JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN

3 POS SECURITY 4X4

1 PEKERJAAN PERSIAPAN
1 Manajemen Proyek -
2 Air kerja. -
3 Listrik kerja -
1 Pembersihan lokasi & buang gragal / tanah 1.00 ls 5,000,000 5,000,000
2 Uitseet & bouwplank 1.00 ls 5,000,000 5,000,000
3 Alat bantu kerja (Scafolding, lampu, kabel, dll) 1.00 ls 5,000,000 5,000,000
15,000,000
2 PEKERJAAN TANAH
1 Galian tanah untuk pondasi 10.71 m3 120,000 1,285,200
2 urugan pasir bawah pondasi (tebal = ± 10 cm) 1.79 m3 150,000 267,750
3 Urugan Peninggian lantai padat setamper +40 cm 6.40 m3 150,000 960,000
2,512,950
3 PEKERJAAN STRUKTUR
a PEKERJAAN PONDASI
1 Pasangan Batu kali 8.03 m3 850,000 6,827,625
2 Sloof 15x20 1.34 m3 4,325,241 5,790,417

b PEKERJAAN KOLOM BETON


1 Kolom Praktis 15x15 K-225 m3 0.99 6,094,797 6,033,849

c PEKERJAAN BALOK BETON


1 Cor Balok 15x30 K-225 m3 0.72 6,073,694 4,373,060
2 Cor Balok Ring 15x15 K-225 m3 0.66 6,073,694 4,008,638
3 Cor Plat Talang Tebal 10 cm K-225 m3 0.24 4,037,819 969,077
4 Cor Plat Canopy Tebal 10 cm K-225 m3 0.63 4,037,819 2,543,826
17,928,449

4 PEKERJAAN ARSITEKTURAL
PEKERJAAN PASANGAN & PLESTERAN
1 Pasangan dinding Bata m2 83.08 135,000 11,215,800
2 Plester aci m2 166.16 97,500 16,200,600
3 Plester aci ruang pintu jendela m2 2.57 97,500 250,088
4 Benangan Sudut dinding m1 63.00 17,500 1,102,500
5 Benangan Pintu Jendela m1 34.20 17,500 598,500
29,367,488
5 PEKERJAAN KERAMIK
Pekerjaan Penutup Lantai - -
1 Pasangan Keramik 40x40 cm m2 20.88 185,000 3,861,875
3,861,875
6 PEKERJAAN KAMAR MANDI
1 Keramik Lantai Asia Roxy grey 20x20 M2 3.00 183,000 549,000
2 Keramik Dinding Asia tile eksel white 20x25 M2 12.25 195,000 2,388,750
3 Avour lantai ex. Toto TX1A (Rp. 263.900) Unit 1.00 325,000 325,000
4 Pasang Closet duduk porselen ex. Amstad Unit 1.00 3,500,000 3,500,000
5 Karan dinding ex.TOTO Unit 1.00 750,000 750,000
6 Kran shower ex. TOTO Unit 1.00 1,272,000 1,272,000
7 Tempat sabun dinding Unit 1.00 350,000 350,000
8 Waterproofing dinding 1m M2 7.00 120,000 840,000
9,974,750
7 PEKERJAAN SANITAIR DAN PLUMBING POS
1 Saluran air kotor PVC 4" D m' 8.00 95,000 760,000
2 Pipa avur PVC 3" D m' 4.00 75,000 300,000
3 Septictank 6 m3 Unit 1.00 27,000,000 27,000,000
4 Resapan beton buis dia 60 cm m' 3.00 240,000 720,000
5 Saluran air bersih PVC 1" AW M' 15.00 65,000 975,000
6 Saluran air bersih PVC 3/4" AW M' 10.00 55,000 550,000
30,305,000
8 PEKERJAAN KUSEN, JENDELA, PINTU ALLUMUNIUM
Kusen aluminium 3", pintu Kayu Ex.Tulus & jendela all. + kaca
1 P1 Pasangan Kusen + Daun Pintu (Single) Ruangan Almini bh 1.00 3,615,000 3,615,000
2 P2 Pasangan Kusen + Daun Pintu (Single) Toilet bh 1.00 2,265,000 2,265,000
5 J2 Pasagan Jendela + Daun bh - -
6 J3 Pasagan Jendela + Daun bh 1.00 2,395,000 2,395,000
7 BV Pasagan BV bh 1.00 502,000 502,000
8,777,000
9 PEKERJAAN ATAP
1 Rangka atap Baja ringan M2 16.00 135,000 2,160,000
2 Penutup atap Zincallum M2 16.00 120,000 1,920,000
3 Jorongan talang bh 2.50 40,000 100,000
4 Pipa tegak PVC 2.5" m1 20.00 75,000 1,500,000
5 Flasing m1 12.00 50,000 600,000
5,680,000
10 PEKERJAAN PLAFOND
1 Plafond Gypsum t=9mm + Rangka plafond holow 4x4cm, 2x4xm t=0,4 mm M2 16.00 125,000 2,000,000
2 List 16.00 35,000 560,000
2,560,000
11 PEKERJAAN INSTALASI LISTRIK
1 Titik lampu Titik 5.00 175,000 875,000
2 Titik stop kontak Titik 2.00 200,000 400,000
3 Box + MCB 12 Group Titik 1.00 750,000 750,000
4 Titik stop kontak telepon Titik 1.00 250,000 250,000
5 Titik stop kontak TV Titik 1.00 350,000 350,000
6 Titik stop kontak AC Titik - 200,000 -
7 Ground Titik 1.00 750,000 750,000
8 Test fungsi ls 1.00 500,000 500,000
9 Lampu RMI 2x36 LED titik 2.00 -
10 Lampu Downligth 6 watt LED titik 3.00 -
11 Armateur stop kontak titik 2.00 150,000 300,000
12 Armateur Saklar ganda Unit 1.00 150,000 150,000
13 Armateur Saklar tunggal Unit 2.00 150,000 300,000
14 Unit AC 1 PK Unit - -
15 Armateur Telephone Unit 1.00 250,000 250,000
16 Smoke detektor Unit 1.00 -
4,875,000
12 PEKERJAAN PENGECATAN
1 Pengecatan dinding interior M2 68.75 65,000 4,468,750
2 Pengecatan dinding exterior M2 64.00 95,000 6,080,000
3 Pengecatan plafon M2 16.00 95,000 1,520,000
4 Pengecatan waterprofing talang + Screed M2 3.20 120,000 384,000
Pengecatan waterprofing Kanopy + Screed M2 6.75 120,000 810,000
13,262,750
TOTAL PEKERJAAN ARSITEKTURAL 144,105,262
MOTHER STATION - CNG TAPEN
SURAT PENAWARAN HARGA

BILL Of QUANTITY
PROYEK : CNG - MS - TAPEN
PEKERJAAN : FILLING POST
LOKASI : NGAWUN PERENGAN, TUBAN - JAWA TIMUR

HARGA
VOL SAT
NO URAIAN PEKERJAAN SATUAN

4 FILLING POST 5X12X3

1 PEKERJAAN PERSIAPAN
1 Pembersihan lokasi & buang gragal / tanah 1.00 ls 5,000,000
2 Uitseet & bouwplank 1.00 ls 5,000,000
3 Alat bantu kerja (Scafolding, lampu, kabel, dll) 1.00 ls 5,000,000

2 PEKERJAAN TANAH
1 Galian tanah untuk pondasi 57.60 m3 120,000
2 urugan pasir bawah pondasi (tebal = ± 10 cm) 18.00 m3 150,000

3 PEKERJAAN STRUKTUR
PEKERJAAN PONDASI
1 Mob demob alat stross 1.00 ls 1,500,000
2 Setrous pile 54.00 m1 210,000
3 Merapikan setros kepala tiang pancang 18.00 titik 30,000
4 Lantai kerja (tebal = ± 5 cm) 9.00 m3 1,200,000
5 Cor Pondasi Plat 120x1200x70 30.24 m3 4,325,241
6 Cor Lantai 380x12000x20 27.36 m3 5,654,367
7 Pasang Keramik 40 x 40 55.35 m2 183,000
8 Finising Acian sika Floor Hardiner 136.80 m2 60,000

4 PEKERJAAN BAJA
Kolom HB.300.300.10.15
1 Kolom HB.300.300.10.15 1,974.00 kg 20,750
2 Plat 16 mm Base Plate (25 x 25) 95.19 kg 20,750
3 Angkur kolom 24.00 set 300,000
4 Baut Ø19 (kolom) 24.00 bh 17,500
5 Plat 5 mm = Rip Pengaku KOLOM ( 10 x 20 ) 65.81 kg 20,750
6 Plat 5 mm = Tutup Kolom ( 25 x 25 ) 6.00 kg 20,750
- - -
BALOK HB.300.300.10.15 - - -
1 Balok HB.300.300.10.15 3,384.00 kg 20,750
2 Baut Ø19 (kolom) 24.00 bh 17,500
3 Plat 5 mm = Rip Pengaku KOLOM ( 10 x 30 ) 32.91 kg 20,750
4 Plat 5 mm = Tutup Balok ( 30 x 30 ) 6.00 kg 20,750
- - -
Kuda kuda HB. 150x150X6.5 - - -
1 Kuda kuda HB. 150x150X6.5 1,467.40 kg 20,750
2 Plat 5 mm = Rip Pengaku 16.45 kg 20,750
3 Plat 5 mm = Tutup Kolom miring ( 35 x 35 ) 16.45 kg 20,750
- - -
Gording CNP 125.50.2,3. 6m - - -
1 Gording CNP 125.50.2,3. 6m 1,138.20 kg 20,750
2 Plat 6 mm Pangkon gording ( 12.5 x 12.5 ) 47.85 kg 20,750
3 Trekstang nok 12mm - kg 20,750
4 Trek stang besi polos 12 mm 44.14 kg 20,750
5 Ikatan Angin besi beton dia 19 mm 160.80 kg 20,750
6 Plat 8 mm pangkon ikatan angin 10x10 7.79 kg 20,750
7 Baut Ø12 mm (trekstang) 42.00 bj 4,500
8 Baut Ø10 mm (GORDING) 84.00 bj 4,500
9 Jarum keras 6.00 bj 200,000
10 Penutup Atap Zicallum tebal 03.5 mm 187.20 m2 120,000
11 Flasing 45 cm 105.00 m2 50,000

5 PEKERJAAN INSTALASI LISTRIK


1 Titik lampu Titik 12.00 175,000
2 Test fungsi ls 1.00 500,000
3 Lampu RMI 2x36 LED titik 12.00
4 Lampu Downligth 6 watt LED titik 13.00
5 Armateur Saklar ganda Unit 6.00 150,000
6 Smoke detektor Unit 10.00
7 Timer switch unit 2.00
8 Lampu TL + armatur (LED Explotion Proof type AX) unit 6.00

TOTAL PEKERJAAN ARSITEKTURAL


HER STATION - CNG TAPEN
AT PENAWARAN HARGA

NGAWUN PERENGAN, TUBAN - JAWA TIMUR

JUMLAH HARGA

5,000,000
5,000,000
5,000,000
15,000,000

6,912,000
2,700,000
9,612,000

1,500,000
11,340,000
540,000
10,800,000
130,795,302
154,703,472
10,129,050
8,208,000

309,678,774

40,960,500
1,975,249
7,200,000
420,000
1,365,609
124,500
-
-
70,218,000
420,000
682,805
124,500
-
-
30,448,467
341,402
341,402
-
-
23,617,650
992,920
-
915,853
3,336,600
161,677
189,000
378,000
1,200,000
22,464,000
5,250,000
213,128,135
2,100,000
500,000
-
-
900,000
-

3,500,000
550,918,909
MOTHER STATION - CNG TAPEN
SURAT PENAWARAN HARGA

BILL Of QUANTITY
PROYEK : CNG - MS - TAPEN
PEKERJAAN : CUBIKLE
LOKASI : NGAWUN PERENGAN, TUBAN - JAWA TIMUR

HARGA
VOL SAT JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN

5 CUBIKLE 4 X 10

1 PEKERJAAN PERSIAPAN
1 Pembersihan lokasi & buang gragal / tanah 1.00 ls 5,000,000 5,000,000
2 Uitseet & bouwplank 1.00 ls 5,000,000 5,000,000
3 Alat bantu kerja (Scafolding, lampu, kabel, dll) 1.00 ls 5,000,000 5,000,000
15,000,000
2 PEKERJAAN TANAH
1 Galian tanah untuk pondasi 5.24 m3 120,000 629,160
2 urugan pasir bawah pondasi (tebal = ± 10 cm) 1.41 m3 150,000 212,100
3 Urugan Peninggian lantai padat setamper +40 cm 16.00 m3 150,000 2,400,000
3,241,260
3 PEKERJAAN STRUKTUR
PEKERJAAN PONDASI
1 Setrous pile 18.00 m1 210,000 3,780,000
2 Merapikan setros kepala tiang pancang 6.00 titik 30,000 180,000
3 lantai kerja (tebal = ± 5 cm) 0.71 m3 1,200,000 848,400
4 Cor Pondasi poor 50x50x30 K 225 0.45 m3 5,654,367 2,544,465
5 Cor Sloof 15x20 K 225 0.96 m3 4,325,241 4,152,232
6 Cor Plat Tebal 6 cm K-225 2.40 m3 1,291,950 3,100,680

4 PEKERJAAN KOLOM BETON


1 Kolom Praktis 15x15 K-225 m3 1.53 6,094,797 9,325,039

PEKERJAAN BALOK BETON


1 Cor Balok B1 15x20 K-225 m3 0.30 5,605,452.44 1,681,636
2 Cor Balok Ring 15x15 K-225 m3 0.72 6,073,694.25 4,373,060
3 Cor Plat Talang Tebal 10 cm K-225 m3 0.60 4,037,819 2,422,691
4 Cor Plat Canopy Tebal 10 cm K-225 m3 0.75 4,037,819 3,028,364
35,436,567

5 PEKERJAAN ARSITEKTURAL
PEKERJAAN PASANGAN & PLESTERAN
1 Pasangan dinding Bata m2 115.16 135,000 15,546,600
2 Plester aci m2 230.32 97,500 22,456,200
3 Plester aci ruang pintu jendela m2 14.15 97,500 1,379,138
4 Benangan Sudut dinding m1 42.00 17,500 735,000
5 Benangan Pintu Jendela m1 33.20 17,500 581,000
40,697,938
6 PEKERJAAN KERAMIK
Pekerjaan Penutup Lantai - -
1 Pasangan Keramik 40x40 cm m2 400.00 220,000 88,000,000
2 Pasangan Keramik 60x60 cm motif / kasar teras m2 8.50 280,000 2,380,000
90,380,000
7 PEKERJAAN KUSEN, JENDELA, PINTU ALLUMUNIUM
Kusen aluminium 4", pintu Kayu Ex.Tulus & jendela all. + kaca
1 PJ1 Pasangan Kusen + Daun Pintu (Doble) Almini bh 2.00 22,255,000 44,510,000
2 BV Pasagan BV bh 2.00 502,000 1,004,000
45,514,000
8 PEKERJAAN ATAP
1 Rangka atap Baja ringan M2 40.00 135,000 5,400,000
2 Penutup atap Zincallum M2 40.00 120,000 4,800,000
3 Wuwung M1 - 55,000 -
4 Jorongan talang bh 2.50 40,000 100,000
5 Pipa tegak PVC 3" m1 24.00 75,000 1,800,000
12,100,000
9 PEKERJAAN PLAFOND
1 Plafond Gypsum t=9mm + Rangka plafond holow 4x4cm, 2x4xm t=0,4 mm M2 40.00 125,000 5,000,000
2 List 36.00 35,000 1,260,000
6,260,000
10 PEKERJAAN INSTALASI LISTRIK
1 Titik lampu Titik 4.00 175,000 700,000
2 Titik stop kontak Titik 4.00 200,000 800,000
3 Box + MCB 12 Group Titik 1.00 750,000 750,000
5 Ground Titik 1.00 750,000 750,000
6 Test fungsi ls 1.00 500,000 500,000
7 Armateur stop kontak titik 4.00 150,000 600,000
8 Armateur Saklar ganda Unit 2.00 150,000 300,000
9 Smoke detektor Unit 2.00 -
4,400,000
11 PEKERJAAN PENGECATAN
1 Pengecatan dinding interior M2 118.32 65,000 7,690,800
2 Pengecatan dinding exterior M2 112.00 95,000 10,640,000
3 Pengecatan plafon M2 40.00 95,000 3,800,000
4 Pengecatan waterprofing talang + Screed M2 9.00 120,000 1,080,000
Pengecatan waterprofing Kanopy + Screed M2 9.00 120,000 1,080,000
24,290,800
TOTAL PEKERJAAN ARSITEKTURAL 277,320,565
LB 40
6,933,014
MOTHER STATION - CNG TAPEN
SURAT PENAWARAN HARGA

BILL Of QUANTITY
PROYEK : CNG - MS - TAPEN
PEKERJAAN : CONTROL ROOM
LOKASI : NGAWUN PERENGAN, TUBAN - JAWA TIMUR

HARGA
VOL SAT JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN

6 CONTROL ROOM 6X8

1 PEKERJAAN PERSIAPAN
1 Pembersihan lokasi & buang gragal / tanah 1.00 ls 5,000,000 5,000,000
2 Uitseet & bouwplank 1.00 ls 5,000,000 5,000,000
3 Alat bantu kerja (Scafolding, lampu, kabel, dll) 1.00 ls 5,000,000 5,000,000
15,000,000
2 PEKERJAAN TANAH
1 Galian tanah untuk pondasi 4.31 m3 120,000 517,440
2 urugan pasir bawah pondasi (tebal = ± 10 cm) 1.18 m3 150,000 176,400
3 Urugan Peninggian lantai padat setamper +40 cm 11.52 m3 150,000 1,728,000
2,421,840
3 PEKERJAAN STRUKTUR
PEKERJAAN PONDASI
1 Mob demob alat stross ls 1,500,000 -
2 Setrous pile 12.00 m1 210,000 2,520,000
3 Merapikan setros kepala tiang pancang 4.00 titik 30,000 120,000
4 lantai kerja (tebal = ± 5 cm) 0.59 m3 1,200,000 705,600
6 Cor Pondasi poor 50x50x30 K 225 0.30 m3 5,654,367 1,696,310
5 Cor Sloof 15x20 K 225 0.84 m3 4,325,241 3,633,203
7 Cor Plat Tebal 6 cm K-225 1.73 m3 1,291,950 2,232,490

PEKERJAAN KOLOM BETON


1 Cor Kolom 20x20 K-225 m3 0.64 3,675,625 2,352,400
2 Kolom Praktis 15x15 K-225 m3 0.36 6,094,797 2,194,127

PEKERJAAN BALOK BETON


1 Cor Balok B1 15x20 K-225 m3 0.36 5,605,452.44 2,017,963
2 Cor Balok Ring 15x15 K-225 m3 0.45 6,073,694.25 2,733,162
3 Cor Plat Talang Tebal 10 cm K-225 m3 0.36 4,037,819 1,453,615
4 Cor Plat Canopy Tebal 10 cm K-225 m3 1.26 4,037,819 5,087,652
26,746,521

4 PEKERJAAN ARSITEKTURAL
PEKERJAAN PASANGAN & PLESTERAN
1 Pasangan dinding Bata m2 77.47 135,000 10,457,775
2 Plester aci m2 154.93 97,500 15,105,675
3 Plesteran Kolom K1 m2 1.60 97,500 156,000
4 Plester aci ruang pintu jendela m2 1.34 97,500 130,163
5 Benangan Sudut dinding m1 28.00 17,500 490,000
6 Benangan Pintu Jendela m1 13.50 17,500 236,250
26,575,863
5 PEKERJAAN KERAMIK
Pekerjaan Penutup Lantai - -
1 Pasangan Keramik 60x60 cm motif / warna terang m2 14.00 220,000 3,080,000
2 Pasangan Keramik 60x60 cm motif / kasar teras m2 5.40 280,000 1,512,000
4,592,000
8 PEKERJAAN KUSEN, JENDELA, PINTU ALLUMUNIUM
Kusen aluminium 3", pintu Kayu Ex.Tulus & jendela all. + kaca
1 P1 Pasangan Kusen + Daun Pintu (Single) Ruangan Almini bh 1.00 3,495,000 3,495,000
2 P2 Pasangan Kusen + Daun Pintu (Single) Toilet bh - -
3 J1 Pasagan Jendela + Daun bh 1.00 2,552,000 2,552,000
6,047,000
9 PEKERJAAN ATAP
1 Rangka atap Baja ringan M2 24.00 135,000 3,240,000
2 Penutup atap Zincallum M2 24.00 120,000 2,880,000
3 Wuwung M1 - 55,000 -
4 Jorongan talang bh 2.00 40,000 80,000
5 Pipa tegak PVC 3" m1 14.00 75,000 1,050,000
7,250,000
10 PEKERJAAN PLAFOND
1 Plafond Gypsum t=9mm + Rangka plafond holow 4x4cm, 2x4xm t=0,4 mm M2 24.00 125,000 3,000,000
2 List 20.00 35,000 700,000
3,700,000
11 PEKERJAAN INSTALASI LISTRIK
1 Titik lampu Titik 2.00 175,000 350,000
2 Titik stop kontak Titik 2.00 200,000 400,000
3 Box + MCB 12 Group Titik 1.00 750,000 750,000
4 Armateur stop kontak titik 2.00 150,000 300,000
5 Armateur Saklar ganda Unit 1.00 150,000 150,000
1,950,000
12 PEKERJAAN PENGECATAN
1 Pengecatan dinding interior M2 79.23 65,000 5,150,015
2 Pengecatan dinding exterior M2 77.03 95,000 7,318,230
3 Pengecatan plafon M2 24.00 95,000 2,280,000
4 Pengecatan waterprofing talang + Screed M2 5.40 120,000 648,000
5 Pengecatan waterprofing Kanopy + Screed M2 5.40 120,000 648,000
16,044,245
TOTAL PEKERJAAN ARSITEKTURAL 110,327,469
LB 258
427,883
MOTHER STATION - CNG TAPEN
SURAT PENAWARAN HARGA

BILL Of QUANTITY
PROYEK : CNG - MS - TAPEN
PEKERJAAN : DRYER DAN KOMPRESOR
LOKASI : NGAWUN PERENGAN, TUBAN - JAWA TIMUR

HARGA
VOL SAT JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN

7 DRYER DAN KOMPRESOR (3 X 6) (3 X 4 X 3)

1 PEKERJAAN PERSIAPAN
1 Pembersihan lokasi & buang gragal / tanah 1.00 ls 5,000,000 5,000,000
2 Uitseet & bouwplank 1.00 ls 5,000,000 5,000,000
3 Alat bantu kerja (Scafolding, lampu, kabel, dll) 1.00 ls 5,000,000 5,000,000
15,000,000
GAS COMPRESOR 3 UNIT
2 PEKERJAAN TANAH
1 Galian tanah untuk pondasi 25.20 m3 120,000 3,024,000
2 Urugan pasir bawah pondasi (tebal = ± 10 cm) 3.60 m3 150,000 540,000
3,564,000
3 PEKERJAAN PONDASI
1 Setrous pile 36.00 m1 210,000 7,560,000
2 Merapikan setros kepala tiang pancang 4.00 titik 30,000 120,000
3 Lantai kerja (tebal = ± 5 cm) 1.80 m3 1,200,000 2,160,000
4 Cor Pondasi Plat 400x300x70 25.20 m3 4,325,241 108,996,085
5 Finishing Flor Hardiner 44.88 m2 60,000 2,692,800
121,528,885
PONDASI DRYER
4 PEKERJAAN TANAH
1 Galian tanah untuk pondasi 16.80 m3 120,000 2,016,000
2 Urugan pasir bawah pondasi (tebal = ± 10 cm) 2.40 m3 150,000 360,000
2,376,000
5 PEKERJAAN STRUKTUR
PEKERJAAN PONDASI
1 Setrous pile 12.00 m1 210,000 2,520,000
2 Merapikan setros kepala tiang pancang 4.00 titik 30,000 120,000
3 Lantai kerja (tebal = ± 5 cm) 1.20 m3 1,200,000 1,440,000
4 Cor Pondasi Plat 400x300x70 16.80 m3 3,675,625 61,750,501
5 Finishing Flor Hardiner 27.72 m2 60,000 1,663,200
67,493,701
Pembersihan Akhir 1 ls 5,000,000 5,000,000
5,000,000
TOTAL PEKERJAAN ARSITEKTURAL 214,962,586
54
3,980,789
MOTHER STATION - CNG TAPEN
SURAT PENAWARAN HARGA
PROYEK CNG - MS - TAPEN
PEKERJAAN DRYER DAN KOMPRESOR
LOKASI NGAWUN PERENGAN, TUBAN - JAWA TIMUR

NO. URAIAN HARGA


1 OFFICE 974,611,997
2 R. GENSET DAN OFFICE BELAKANG 352,809,606
3 POS SECURITY 144,105,262
4 FILLING POST 550,918,909
5 CUBIKLE 277,320,565
6 CONTROL ROOM 110,327,469
7 DRYER DAN KOMPRESOR 214,962,586
SUB TOTAL 2,625,056,393
PPN 10% 262,505,639
TOTAL 2,887,562,033