BILL Of QUANTITY
PROYEK : CNG - MS - TAPEN
PEKERJAAN : OFFICE
LOKASI : NGAWUN PERENGAN, TUBAN - JAWA TIMUR
HARGA
VOL SAT JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN
1 OFFICE 12X10
1 PEKERJAAN PERSIAPAN
1 Manajemen Proyek 1.00 ls 10,000,000 10,000,000
2 Air kerja. 1.00 ls 4,000,000 4,000,000
3 Listrik kerja 1.00 ls 4,000,000 4,000,000
4 Pembersihan lokasi & buang gragal / tanah 1.00 ls 5,000,000 5,000,000
5 Uitseet & bouwplank 1.00 ls 5,000,000 5,000,000
6 Alat bantu kerja (Scafolding, lampu, kabel, dll) 1.00 ls 5,000,000 5,000,000
33,000,000
2 PEKERJAAN TANAH
1 Galian tanah untuk pondasi 26.29 m3 120,000 3,154,620
2 urugan pasir bawah pondasi (tebal = ± 10 cm) 7.34 m3 150,000 1,101,450
3 Urugan Peninggian lantai padat setamper +40 cm 100.00 m3 150,000 15,000,000
19,256,070
3 PEKERJAAN STRUKTUR
a PEKERJAAN PONDASI
1 Mob demob alat stross 1.00 ls 1,500,000 1,500,000
2 Setrous pile 36.00 m1 210,000 7,560,000
3 Merapikan setros kepala tiang pancang 12.00 titik 30,000 360,000
4 lantai kerja (tebal = ± 5 cm) 3.67 m3 1,200,000 4,405,800
5 Cor Sloof 15x20 K 225 5.79 m3 4,325,241 25,043,148
6 Cor Pondasi poor 20x50x30 K 225 0.90 m3 5,654,367 5,088,930
7 Cor Plat Tebal 6 cm K-225 15.00 m3 1,291,950 19,379,250
4 PEKERJAAN ARSITEKTURAL
PEKERJAAN PASANGAN & PLESTERAN
1 Pasangan dinding Bata m2 683.25 135,000 92,238,750
2 Plester aci m2 1,366.50 97,500 133,233,750
3 Plesteran Kolom K1 m2 4.20 97,500 409,500
4 Plester aci ruang pintu jendela m2 23.06 97,500 2,247,863
5 Pekerjaan benangan sudut Kolom m1 168.00 17,500 2,940,000
6 Benangan Sudut dinding m1 224.00 17,500 3,920,000
7 Benangan Pintu Jendela m1 307.40 17,500 5,379,500
240,369,363
5 PEKERJAAN KERAMIK
Pekerjaan Penutup Lantai - -
1 Pasangan Keramik 60x60 cm motif / warna terang m2 220.00 220,000 48,400,000
2 Pasangan Keramik 60x60 cm motif / kasar teras m2 49.00 280,000 13,720,000
62,120,000
6 PEKERJAAN KAMAR MANDI
1 Keramik Lantai Asia Roxy grey 20x20 M2 30.00 183,000 5,490,000
2 Keramik Dinding Asia tile eksel white 20x25 M2 47.25 195,000 9,213,750
3 Avour lantai ex. Toto TX1A (Rp. 263.900) Unit 2.00 325,000 650,000
4 Pasang Closet duduk porselen ex. Amstad Unit 2.00 3,500,000 7,000,000
5 Bak Mandi Unit - 750,000 -
6 Avur Bak Unit - 100,000 -
7 Karan dinding ex.TOTO Unit 2.00 750,000 1,500,000
8 Kran shower ex. TOTO Unit 2.00 1,272,000 2,544,000
9 Tempat sabun dinding Unit 2.00 350,000 700,000
10 Waterproofing dinding 1m M2 27.00 120,000 3,240,000
30,337,750
7 PEKERJAAN SANITAIR DAN PLUMBING POS
1 Saluran air kotor PVC 4" D m' 12.00 95,000 1,140,000
2 Pipa avur PVC 3" D m' 10.00 75,000 750,000
3 Septictank 6 m3 Unit 1.00 27,000,000 27,000,000
4 Resapan beton buis dia 60 cm m' 3.00 240,000 720,000
5 Saluran air bersih PVC 1" AW M' 10.00 65,000 650,000
6 Saluran air bersih PVC 3/4" AW M' 20.00 55,000 1,100,000
31,360,000
8 PEKERJAAN KUSEN, JENDELA, PINTU ALLUMUNIUM
Kusen aluminium 4", pintu Kayu Ex.Tulus & jendela all. + kaca
1.3 PJ1 Pasangan Kusen + Daun Pintu (Doble) Almini bh 1.00 16,009,675 16,009,675
1.4 P1 Pasangan Kusen + Daun Pintu (Single) Ruangan Almini bh 12.00 3,615,000 43,380,000
1.5 P2 Pasangan Kusen + Daun Pintu (Single) Toilet bh 2.00 2,265,000 4,530,000
1.6 J1 Pasagan Jendela + Daun bh 4.00 5,110,000 20,440,000
1.7 J1' Pasagan Jendela + Daun bh 4.00 5,110,000 20,440,000
1.8 J2 Pasagan Jendela + Daun bh 2.00 2,738,000 5,476,000
1.9 J3 Pasagan Jendela + Daun bh 1.00 2,395,000 2,395,000
2,0 BV Pasagan BV bh 2.00 502,000 1,004,000
113,674,675
9 PEKERJAAN ATAP
1 Rangka atap Baja ringan M2 250.00 135,000 33,750,000
2 Penutup atap Zincallum M2 250.00 120,000 30,000,000
3 Wuwung M1 25.00 55,000 1,375,000
4 Jorongan talang bh 6.25 40,000 250,000
5 Pipa tegak PVC 3" m1 50.00 75,000 3,750,000
69,125,000
10 PEKERJAAN PLAFOND
1 Plafond Gypsum t=9mm + Rangka plafond holow 4x4cm, 2x4xm t=0,4 mm M2 250.00 125,000 31,250,000
2 List 339.00 35,000 11,865,000
43,115,000
11 PEKERJAAN INSTALASI LISTRIK
1 Titik lampu Titik 25.00 175,000 4,375,000
2 Titik stop kontak Titik 22.00 200,000 4,400,000
3 Box + MCB 12 Group Titik 1.00 750,000 750,000
4 Titik stop kontak telepon Titik 8.00 250,000 2,000,000
5 Titik stop kontak TV Titik - 350,000 -
6 Titik stop kontak AC Titik 10.00 200,000 2,000,000
7 Ground Titik 1.00 750,000 750,000
8 Test fungsi ls 1.00 500,000 500,000
9 Lampu RMI 2x36 LED titik 12.00 -
10 Lampu Downligth 6 watt LED titik 13.00 -
11 Armateur stop kontak titik 15.00 150,000 2,250,000
12 Armateur Saklar ganda Unit 6.00 150,000 900,000
13 Armateur Saklar tunggal Unit 9.00 150,000 1,350,000
14 Unit AC 1 PK Unit 10.00 -
15 Armateur Telephone Unit 8.00 250,000 2,000,000
16 Smoke detektor Unit 10.00 -
21,275,000
12 PEKERJAAN PENGECATAN
1 Pengecatan dinding interior M2 1,438.00 65,000 93,470,000
2 Pengecatan dinding exterior M2 336.00 95,000 31,920,000
3 Pengecatan plafon M2 250.00 95,000 23,750,000
4 Pengecatan waterprofing talang + Screed M2 63.00 120,000 7,560,000
Pengecatan waterprofing Kanopy + Screed M2 21.87 120,000 2,624,400
159,324,400
TOTAL PEKERJAAN ARSITEKTURAL 974,611,997
LB 258
3,779,837
MOTHER STATION - CNG TAPEN
SURAT PENAWARAN HARGA
BILL Of QUANTITY
PROYEK : CNG - MS - TAPEN
PEKERJAAN : R. GENSET DAN OFFICE BELAKANG
LOKASI : NGAWUN PERENGAN, TUBAN - JAWA TIMUR
HARGA
VOL SAT JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN
1 PEKERJAAN PERSIAPAN
1 Pembersihan lokasi & buang gragal / tanah 1.00 ls 5,000,000 5,000,000
2 Uitseet & bouwplank 1.00 ls 5,000,000 5,000,000
3 Alat bantu kerja (Scafolding, lampu, kabel, dll) 1.00 ls 5,000,000 5,000,000
15,000,000
2 PEKERJAAN TANAH
1 Galian tanah untuk pondasi 12.78 m3 120,000 1,533,210
2 urugan pasir bawah pondasi (tebal = ± 10 cm) 3.48 m3 150,000 522,375
3 Urugan Peninggian lantai padat setamper +40 cm 32.90 m3 150,000 4,935,000
6,990,585
3 PEKERJAAN STRUKTUR
PEKERJAAN PONDASI
1 Mob demob alat stross ls 1,500,000 -
2 Setrous pile 36.00 m1 210,000 7,560,000
3 Merapikan setros kepala tiang pancang 12.00 titik 30,000 360,000
4 lantai kerja (tebal = ± 5 cm) 1.74 m3 1,200,000 2,089,500
6 Cor Pondasi poor 50x50x30 K 225 0.90 m3 5,654,367 5,088,930
5 Cor Sloof 15x20 K 225 2.48 m3 4,325,241 10,730,924
7 Cor Plat Tebal 6 cm K-225 4.94 m3 1,291,950 6,375,773
4 PEKERJAAN ARSITEKTURAL
PEKERJAAN PASANGAN & PLESTERAN
1 Pasangan dinding Bata m2 243.00 135,000 32,805,000
2 Plester aci m2 486.00 97,500 47,385,000
3 Plester aci ruang pintu jendela m2 3.99 97,500 389,025
4 Benangan Sudut dinding m1 98.00 17,500 1,715,000
5 Benangan Pintu Jendela m1 40.40 17,500 707,000
83,001,025
5 PEKERJAAN KERAMIK
Pekerjaan Penutup Lantai - -
1 Pasangan Keramik 60x60 cm motif / warna terang m2 80.00 220,000 17,600,000
2 Pasangan Keramik 60x60 cm motif / kasar teras m2 15.75 280,000 4,410,000
22,010,000
6 PEKERJAAN KAMAR MANDI
1 Keramik Lantai Asia Roxy grey 20x20 M2 7.50 183,000 1,372,500
2 Keramik Dinding Asia tile eksel white 20x25 M2 17.85 195,000 3,480,750
3 Avour lantai ex. Toto TX1A (Rp. 263.900) Unit 1.00 325,000 325,000
4 Pasang Closet duduk porselen ex. Amstad Unit 1.00 3,500,000 3,500,000
5 Bak Mandi Unit - 750,000 -
6 Avur Bak Unit - 100,000 -
7 Karan dinding ex.TOTO Unit 1.00 750,000 750,000
8 Kran shower ex. TOTO Unit 1.00 1,272,000 1,272,000
9 Tempat sabun dinding Unit 1.00 350,000 350,000
10 Waterproofing dinding 1m M2 11.00 120,000 1,320,000
12,370,250
7 PEKERJAAN SANITAIR DAN PLUMBING POS
1 Saluran air kotor PVC 4" D m' 8.00 95,000 760,000
2 Pipa avur PVC 3" D m' 8.00 75,000 600,000
3 Septictank 6 m3 Unit 1.00 27,000,000 27,000,000
4 Resapan beton buis dia 60 cm m' 3.00 240,000 720,000
5 Saluran air bersih PVC 1" AW M' 15.00 65,000 975,000
6 Saluran air bersih PVC 3/4" AW M' 15.00 55,000 825,000
30,880,000
8 PEKERJAAN KUSEN, JENDELA, PINTU ALLUMUNIUM
Kusen aluminium 4", pintu Kayu Ex.Tulus & jendela all. + kaca
1 PJ1 Pasangan Kusen + Daun Pintu (Doble) Almini bh 2.00 9,327,000 18,654,000
2 P1 Pasangan Kusen + Daun Pintu (Single) Ruangan Almini bh 1.00 3,615,000 3,615,000
3 P2 Pasangan Kusen + Daun Pintu (Single) Toilet bh 1.00 2,265,000 2,265,000
4 BV Pasagan BV bh 1.00 502,000 502,000
25,036,000
9 PEKERJAAN ATAP
1 Rangka atap Baja ringan M2 70.00 135,000 9,450,000
2 Penutup atap Zincallum M2 70.00 120,000 8,400,000
3 Wuwung M1 - 55,000 -
4 Jorongan talang bh 7.00 40,000 280,000
5 Pipa tegak PVC 3" m1 42.00 75,000 3,150,000
21,280,000
10 PEKERJAAN PLAFOND
1 Plafond Gypsum t=9mm + Rangka plafond holow 4x4cm, 2x4xm t=0,4 mm M2 70.00 125,000 8,750,000
2 List 67.00 35,000 2,345,000
11,095,000
11 PEKERJAAN INSTALASI LISTRIK
1 Titik lampu Titik 8.00 175,000 1,400,000
2 Titik stop kontak Titik 6.00 200,000 1,200,000
3 Box + MCB 12 Group Titik 1.00 750,000 750,000
4 Titik stop kontak telepon Titik 2.00 250,000 500,000
5 Titik stop kontak AC Titik 2.00 200,000 400,000
6 Ground Titik 1.00 750,000 750,000
7 Test fungsi ls 1.00 500,000 500,000
8 Armateur stop kontak titik 6.00 150,000 900,000
9 Armateur Saklar ganda Unit 4.00 150,000 600,000
10 Armateur Telephone Unit 2.00 250,000 500,000
7,500,000
12 PEKERJAAN PENGECATAN
1 Pengecatan dinding interior M2 285.99 65,000 18,589,350
2 Pengecatan dinding exterior M2 204.00 95,000 19,380,000
3 Pengecatan plafon M2 10.50 95,000 997,500
4 Pengecatan waterprofing talang + Screed M2 15.75 120,000 1,890,000
Pengecatan waterprofing Kanopy + Screed M2 21.87 120,000 2,624,400
43,481,250
TOTAL PEKERJAAN ARSITEKTURAL 352,809,606
LB 258
1,368,301
MOTHER STATION - CNG TAPEN
SURAT PENAWARAN HARGA
BILL Of QUANTITY
PROYEK : CNG - MS - TAPEN
PEKERJAAN : POS SECURITY
LOKASI : NGAWUN PERENGAN, TUBAN - JAWA TIMUR
HARGA
VOL SAT JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN
1 PEKERJAAN PERSIAPAN
1 Manajemen Proyek -
2 Air kerja. -
3 Listrik kerja -
1 Pembersihan lokasi & buang gragal / tanah 1.00 ls 5,000,000 5,000,000
2 Uitseet & bouwplank 1.00 ls 5,000,000 5,000,000
3 Alat bantu kerja (Scafolding, lampu, kabel, dll) 1.00 ls 5,000,000 5,000,000
15,000,000
2 PEKERJAAN TANAH
1 Galian tanah untuk pondasi 10.71 m3 120,000 1,285,200
2 urugan pasir bawah pondasi (tebal = ± 10 cm) 1.79 m3 150,000 267,750
3 Urugan Peninggian lantai padat setamper +40 cm 6.40 m3 150,000 960,000
2,512,950
3 PEKERJAAN STRUKTUR
a PEKERJAAN PONDASI
1 Pasangan Batu kali 8.03 m3 850,000 6,827,625
2 Sloof 15x20 1.34 m3 4,325,241 5,790,417
4 PEKERJAAN ARSITEKTURAL
PEKERJAAN PASANGAN & PLESTERAN
1 Pasangan dinding Bata m2 83.08 135,000 11,215,800
2 Plester aci m2 166.16 97,500 16,200,600
3 Plester aci ruang pintu jendela m2 2.57 97,500 250,088
4 Benangan Sudut dinding m1 63.00 17,500 1,102,500
5 Benangan Pintu Jendela m1 34.20 17,500 598,500
29,367,488
5 PEKERJAAN KERAMIK
Pekerjaan Penutup Lantai - -
1 Pasangan Keramik 40x40 cm m2 20.88 185,000 3,861,875
3,861,875
6 PEKERJAAN KAMAR MANDI
1 Keramik Lantai Asia Roxy grey 20x20 M2 3.00 183,000 549,000
2 Keramik Dinding Asia tile eksel white 20x25 M2 12.25 195,000 2,388,750
3 Avour lantai ex. Toto TX1A (Rp. 263.900) Unit 1.00 325,000 325,000
4 Pasang Closet duduk porselen ex. Amstad Unit 1.00 3,500,000 3,500,000
5 Karan dinding ex.TOTO Unit 1.00 750,000 750,000
6 Kran shower ex. TOTO Unit 1.00 1,272,000 1,272,000
7 Tempat sabun dinding Unit 1.00 350,000 350,000
8 Waterproofing dinding 1m M2 7.00 120,000 840,000
9,974,750
7 PEKERJAAN SANITAIR DAN PLUMBING POS
1 Saluran air kotor PVC 4" D m' 8.00 95,000 760,000
2 Pipa avur PVC 3" D m' 4.00 75,000 300,000
3 Septictank 6 m3 Unit 1.00 27,000,000 27,000,000
4 Resapan beton buis dia 60 cm m' 3.00 240,000 720,000
5 Saluran air bersih PVC 1" AW M' 15.00 65,000 975,000
6 Saluran air bersih PVC 3/4" AW M' 10.00 55,000 550,000
30,305,000
8 PEKERJAAN KUSEN, JENDELA, PINTU ALLUMUNIUM
Kusen aluminium 3", pintu Kayu Ex.Tulus & jendela all. + kaca
1 P1 Pasangan Kusen + Daun Pintu (Single) Ruangan Almini bh 1.00 3,615,000 3,615,000
2 P2 Pasangan Kusen + Daun Pintu (Single) Toilet bh 1.00 2,265,000 2,265,000
5 J2 Pasagan Jendela + Daun bh - -
6 J3 Pasagan Jendela + Daun bh 1.00 2,395,000 2,395,000
7 BV Pasagan BV bh 1.00 502,000 502,000
8,777,000
9 PEKERJAAN ATAP
1 Rangka atap Baja ringan M2 16.00 135,000 2,160,000
2 Penutup atap Zincallum M2 16.00 120,000 1,920,000
3 Jorongan talang bh 2.50 40,000 100,000
4 Pipa tegak PVC 2.5" m1 20.00 75,000 1,500,000
5 Flasing m1 12.00 50,000 600,000
5,680,000
10 PEKERJAAN PLAFOND
1 Plafond Gypsum t=9mm + Rangka plafond holow 4x4cm, 2x4xm t=0,4 mm M2 16.00 125,000 2,000,000
2 List 16.00 35,000 560,000
2,560,000
11 PEKERJAAN INSTALASI LISTRIK
1 Titik lampu Titik 5.00 175,000 875,000
2 Titik stop kontak Titik 2.00 200,000 400,000
3 Box + MCB 12 Group Titik 1.00 750,000 750,000
4 Titik stop kontak telepon Titik 1.00 250,000 250,000
5 Titik stop kontak TV Titik 1.00 350,000 350,000
6 Titik stop kontak AC Titik - 200,000 -
7 Ground Titik 1.00 750,000 750,000
8 Test fungsi ls 1.00 500,000 500,000
9 Lampu RMI 2x36 LED titik 2.00 -
10 Lampu Downligth 6 watt LED titik 3.00 -
11 Armateur stop kontak titik 2.00 150,000 300,000
12 Armateur Saklar ganda Unit 1.00 150,000 150,000
13 Armateur Saklar tunggal Unit 2.00 150,000 300,000
14 Unit AC 1 PK Unit - -
15 Armateur Telephone Unit 1.00 250,000 250,000
16 Smoke detektor Unit 1.00 -
4,875,000
12 PEKERJAAN PENGECATAN
1 Pengecatan dinding interior M2 68.75 65,000 4,468,750
2 Pengecatan dinding exterior M2 64.00 95,000 6,080,000
3 Pengecatan plafon M2 16.00 95,000 1,520,000
4 Pengecatan waterprofing talang + Screed M2 3.20 120,000 384,000
Pengecatan waterprofing Kanopy + Screed M2 6.75 120,000 810,000
13,262,750
TOTAL PEKERJAAN ARSITEKTURAL 144,105,262
MOTHER STATION - CNG TAPEN
SURAT PENAWARAN HARGA
BILL Of QUANTITY
PROYEK : CNG - MS - TAPEN
PEKERJAAN : FILLING POST
LOKASI : NGAWUN PERENGAN, TUBAN - JAWA TIMUR
HARGA
VOL SAT
NO URAIAN PEKERJAAN SATUAN
1 PEKERJAAN PERSIAPAN
1 Pembersihan lokasi & buang gragal / tanah 1.00 ls 5,000,000
2 Uitseet & bouwplank 1.00 ls 5,000,000
3 Alat bantu kerja (Scafolding, lampu, kabel, dll) 1.00 ls 5,000,000
2 PEKERJAAN TANAH
1 Galian tanah untuk pondasi 57.60 m3 120,000
2 urugan pasir bawah pondasi (tebal = ± 10 cm) 18.00 m3 150,000
3 PEKERJAAN STRUKTUR
PEKERJAAN PONDASI
1 Mob demob alat stross 1.00 ls 1,500,000
2 Setrous pile 54.00 m1 210,000
3 Merapikan setros kepala tiang pancang 18.00 titik 30,000
4 Lantai kerja (tebal = ± 5 cm) 9.00 m3 1,200,000
5 Cor Pondasi Plat 120x1200x70 30.24 m3 4,325,241
6 Cor Lantai 380x12000x20 27.36 m3 5,654,367
7 Pasang Keramik 40 x 40 55.35 m2 183,000
8 Finising Acian sika Floor Hardiner 136.80 m2 60,000
4 PEKERJAAN BAJA
Kolom HB.300.300.10.15
1 Kolom HB.300.300.10.15 1,974.00 kg 20,750
2 Plat 16 mm Base Plate (25 x 25) 95.19 kg 20,750
3 Angkur kolom 24.00 set 300,000
4 Baut Ø19 (kolom) 24.00 bh 17,500
5 Plat 5 mm = Rip Pengaku KOLOM ( 10 x 20 ) 65.81 kg 20,750
6 Plat 5 mm = Tutup Kolom ( 25 x 25 ) 6.00 kg 20,750
- - -
BALOK HB.300.300.10.15 - - -
1 Balok HB.300.300.10.15 3,384.00 kg 20,750
2 Baut Ø19 (kolom) 24.00 bh 17,500
3 Plat 5 mm = Rip Pengaku KOLOM ( 10 x 30 ) 32.91 kg 20,750
4 Plat 5 mm = Tutup Balok ( 30 x 30 ) 6.00 kg 20,750
- - -
Kuda kuda HB. 150x150X6.5 - - -
1 Kuda kuda HB. 150x150X6.5 1,467.40 kg 20,750
2 Plat 5 mm = Rip Pengaku 16.45 kg 20,750
3 Plat 5 mm = Tutup Kolom miring ( 35 x 35 ) 16.45 kg 20,750
- - -
Gording CNP 125.50.2,3. 6m - - -
1 Gording CNP 125.50.2,3. 6m 1,138.20 kg 20,750
2 Plat 6 mm Pangkon gording ( 12.5 x 12.5 ) 47.85 kg 20,750
3 Trekstang nok 12mm - kg 20,750
4 Trek stang besi polos 12 mm 44.14 kg 20,750
5 Ikatan Angin besi beton dia 19 mm 160.80 kg 20,750
6 Plat 8 mm pangkon ikatan angin 10x10 7.79 kg 20,750
7 Baut Ø12 mm (trekstang) 42.00 bj 4,500
8 Baut Ø10 mm (GORDING) 84.00 bj 4,500
9 Jarum keras 6.00 bj 200,000
10 Penutup Atap Zicallum tebal 03.5 mm 187.20 m2 120,000
11 Flasing 45 cm 105.00 m2 50,000
JUMLAH HARGA
5,000,000
5,000,000
5,000,000
15,000,000
6,912,000
2,700,000
9,612,000
1,500,000
11,340,000
540,000
10,800,000
130,795,302
154,703,472
10,129,050
8,208,000
309,678,774
40,960,500
1,975,249
7,200,000
420,000
1,365,609
124,500
-
-
70,218,000
420,000
682,805
124,500
-
-
30,448,467
341,402
341,402
-
-
23,617,650
992,920
-
915,853
3,336,600
161,677
189,000
378,000
1,200,000
22,464,000
5,250,000
213,128,135
2,100,000
500,000
-
-
900,000
-
3,500,000
550,918,909
MOTHER STATION - CNG TAPEN
SURAT PENAWARAN HARGA
BILL Of QUANTITY
PROYEK : CNG - MS - TAPEN
PEKERJAAN : CUBIKLE
LOKASI : NGAWUN PERENGAN, TUBAN - JAWA TIMUR
HARGA
VOL SAT JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN
5 CUBIKLE 4 X 10
1 PEKERJAAN PERSIAPAN
1 Pembersihan lokasi & buang gragal / tanah 1.00 ls 5,000,000 5,000,000
2 Uitseet & bouwplank 1.00 ls 5,000,000 5,000,000
3 Alat bantu kerja (Scafolding, lampu, kabel, dll) 1.00 ls 5,000,000 5,000,000
15,000,000
2 PEKERJAAN TANAH
1 Galian tanah untuk pondasi 5.24 m3 120,000 629,160
2 urugan pasir bawah pondasi (tebal = ± 10 cm) 1.41 m3 150,000 212,100
3 Urugan Peninggian lantai padat setamper +40 cm 16.00 m3 150,000 2,400,000
3,241,260
3 PEKERJAAN STRUKTUR
PEKERJAAN PONDASI
1 Setrous pile 18.00 m1 210,000 3,780,000
2 Merapikan setros kepala tiang pancang 6.00 titik 30,000 180,000
3 lantai kerja (tebal = ± 5 cm) 0.71 m3 1,200,000 848,400
4 Cor Pondasi poor 50x50x30 K 225 0.45 m3 5,654,367 2,544,465
5 Cor Sloof 15x20 K 225 0.96 m3 4,325,241 4,152,232
6 Cor Plat Tebal 6 cm K-225 2.40 m3 1,291,950 3,100,680
5 PEKERJAAN ARSITEKTURAL
PEKERJAAN PASANGAN & PLESTERAN
1 Pasangan dinding Bata m2 115.16 135,000 15,546,600
2 Plester aci m2 230.32 97,500 22,456,200
3 Plester aci ruang pintu jendela m2 14.15 97,500 1,379,138
4 Benangan Sudut dinding m1 42.00 17,500 735,000
5 Benangan Pintu Jendela m1 33.20 17,500 581,000
40,697,938
6 PEKERJAAN KERAMIK
Pekerjaan Penutup Lantai - -
1 Pasangan Keramik 40x40 cm m2 400.00 220,000 88,000,000
2 Pasangan Keramik 60x60 cm motif / kasar teras m2 8.50 280,000 2,380,000
90,380,000
7 PEKERJAAN KUSEN, JENDELA, PINTU ALLUMUNIUM
Kusen aluminium 4", pintu Kayu Ex.Tulus & jendela all. + kaca
1 PJ1 Pasangan Kusen + Daun Pintu (Doble) Almini bh 2.00 22,255,000 44,510,000
2 BV Pasagan BV bh 2.00 502,000 1,004,000
45,514,000
8 PEKERJAAN ATAP
1 Rangka atap Baja ringan M2 40.00 135,000 5,400,000
2 Penutup atap Zincallum M2 40.00 120,000 4,800,000
3 Wuwung M1 - 55,000 -
4 Jorongan talang bh 2.50 40,000 100,000
5 Pipa tegak PVC 3" m1 24.00 75,000 1,800,000
12,100,000
9 PEKERJAAN PLAFOND
1 Plafond Gypsum t=9mm + Rangka plafond holow 4x4cm, 2x4xm t=0,4 mm M2 40.00 125,000 5,000,000
2 List 36.00 35,000 1,260,000
6,260,000
10 PEKERJAAN INSTALASI LISTRIK
1 Titik lampu Titik 4.00 175,000 700,000
2 Titik stop kontak Titik 4.00 200,000 800,000
3 Box + MCB 12 Group Titik 1.00 750,000 750,000
5 Ground Titik 1.00 750,000 750,000
6 Test fungsi ls 1.00 500,000 500,000
7 Armateur stop kontak titik 4.00 150,000 600,000
8 Armateur Saklar ganda Unit 2.00 150,000 300,000
9 Smoke detektor Unit 2.00 -
4,400,000
11 PEKERJAAN PENGECATAN
1 Pengecatan dinding interior M2 118.32 65,000 7,690,800
2 Pengecatan dinding exterior M2 112.00 95,000 10,640,000
3 Pengecatan plafon M2 40.00 95,000 3,800,000
4 Pengecatan waterprofing talang + Screed M2 9.00 120,000 1,080,000
Pengecatan waterprofing Kanopy + Screed M2 9.00 120,000 1,080,000
24,290,800
TOTAL PEKERJAAN ARSITEKTURAL 277,320,565
LB 40
6,933,014
MOTHER STATION - CNG TAPEN
SURAT PENAWARAN HARGA
BILL Of QUANTITY
PROYEK : CNG - MS - TAPEN
PEKERJAAN : CONTROL ROOM
LOKASI : NGAWUN PERENGAN, TUBAN - JAWA TIMUR
HARGA
VOL SAT JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN
1 PEKERJAAN PERSIAPAN
1 Pembersihan lokasi & buang gragal / tanah 1.00 ls 5,000,000 5,000,000
2 Uitseet & bouwplank 1.00 ls 5,000,000 5,000,000
3 Alat bantu kerja (Scafolding, lampu, kabel, dll) 1.00 ls 5,000,000 5,000,000
15,000,000
2 PEKERJAAN TANAH
1 Galian tanah untuk pondasi 4.31 m3 120,000 517,440
2 urugan pasir bawah pondasi (tebal = ± 10 cm) 1.18 m3 150,000 176,400
3 Urugan Peninggian lantai padat setamper +40 cm 11.52 m3 150,000 1,728,000
2,421,840
3 PEKERJAAN STRUKTUR
PEKERJAAN PONDASI
1 Mob demob alat stross ls 1,500,000 -
2 Setrous pile 12.00 m1 210,000 2,520,000
3 Merapikan setros kepala tiang pancang 4.00 titik 30,000 120,000
4 lantai kerja (tebal = ± 5 cm) 0.59 m3 1,200,000 705,600
6 Cor Pondasi poor 50x50x30 K 225 0.30 m3 5,654,367 1,696,310
5 Cor Sloof 15x20 K 225 0.84 m3 4,325,241 3,633,203
7 Cor Plat Tebal 6 cm K-225 1.73 m3 1,291,950 2,232,490
4 PEKERJAAN ARSITEKTURAL
PEKERJAAN PASANGAN & PLESTERAN
1 Pasangan dinding Bata m2 77.47 135,000 10,457,775
2 Plester aci m2 154.93 97,500 15,105,675
3 Plesteran Kolom K1 m2 1.60 97,500 156,000
4 Plester aci ruang pintu jendela m2 1.34 97,500 130,163
5 Benangan Sudut dinding m1 28.00 17,500 490,000
6 Benangan Pintu Jendela m1 13.50 17,500 236,250
26,575,863
5 PEKERJAAN KERAMIK
Pekerjaan Penutup Lantai - -
1 Pasangan Keramik 60x60 cm motif / warna terang m2 14.00 220,000 3,080,000
2 Pasangan Keramik 60x60 cm motif / kasar teras m2 5.40 280,000 1,512,000
4,592,000
8 PEKERJAAN KUSEN, JENDELA, PINTU ALLUMUNIUM
Kusen aluminium 3", pintu Kayu Ex.Tulus & jendela all. + kaca
1 P1 Pasangan Kusen + Daun Pintu (Single) Ruangan Almini bh 1.00 3,495,000 3,495,000
2 P2 Pasangan Kusen + Daun Pintu (Single) Toilet bh - -
3 J1 Pasagan Jendela + Daun bh 1.00 2,552,000 2,552,000
6,047,000
9 PEKERJAAN ATAP
1 Rangka atap Baja ringan M2 24.00 135,000 3,240,000
2 Penutup atap Zincallum M2 24.00 120,000 2,880,000
3 Wuwung M1 - 55,000 -
4 Jorongan talang bh 2.00 40,000 80,000
5 Pipa tegak PVC 3" m1 14.00 75,000 1,050,000
7,250,000
10 PEKERJAAN PLAFOND
1 Plafond Gypsum t=9mm + Rangka plafond holow 4x4cm, 2x4xm t=0,4 mm M2 24.00 125,000 3,000,000
2 List 20.00 35,000 700,000
3,700,000
11 PEKERJAAN INSTALASI LISTRIK
1 Titik lampu Titik 2.00 175,000 350,000
2 Titik stop kontak Titik 2.00 200,000 400,000
3 Box + MCB 12 Group Titik 1.00 750,000 750,000
4 Armateur stop kontak titik 2.00 150,000 300,000
5 Armateur Saklar ganda Unit 1.00 150,000 150,000
1,950,000
12 PEKERJAAN PENGECATAN
1 Pengecatan dinding interior M2 79.23 65,000 5,150,015
2 Pengecatan dinding exterior M2 77.03 95,000 7,318,230
3 Pengecatan plafon M2 24.00 95,000 2,280,000
4 Pengecatan waterprofing talang + Screed M2 5.40 120,000 648,000
5 Pengecatan waterprofing Kanopy + Screed M2 5.40 120,000 648,000
16,044,245
TOTAL PEKERJAAN ARSITEKTURAL 110,327,469
LB 258
427,883
MOTHER STATION - CNG TAPEN
SURAT PENAWARAN HARGA
BILL Of QUANTITY
PROYEK : CNG - MS - TAPEN
PEKERJAAN : DRYER DAN KOMPRESOR
LOKASI : NGAWUN PERENGAN, TUBAN - JAWA TIMUR
HARGA
VOL SAT JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN
1 PEKERJAAN PERSIAPAN
1 Pembersihan lokasi & buang gragal / tanah 1.00 ls 5,000,000 5,000,000
2 Uitseet & bouwplank 1.00 ls 5,000,000 5,000,000
3 Alat bantu kerja (Scafolding, lampu, kabel, dll) 1.00 ls 5,000,000 5,000,000
15,000,000
GAS COMPRESOR 3 UNIT
2 PEKERJAAN TANAH
1 Galian tanah untuk pondasi 25.20 m3 120,000 3,024,000
2 Urugan pasir bawah pondasi (tebal = ± 10 cm) 3.60 m3 150,000 540,000
3,564,000
3 PEKERJAAN PONDASI
1 Setrous pile 36.00 m1 210,000 7,560,000
2 Merapikan setros kepala tiang pancang 4.00 titik 30,000 120,000
3 Lantai kerja (tebal = ± 5 cm) 1.80 m3 1,200,000 2,160,000
4 Cor Pondasi Plat 400x300x70 25.20 m3 4,325,241 108,996,085
5 Finishing Flor Hardiner 44.88 m2 60,000 2,692,800
121,528,885
PONDASI DRYER
4 PEKERJAAN TANAH
1 Galian tanah untuk pondasi 16.80 m3 120,000 2,016,000
2 Urugan pasir bawah pondasi (tebal = ± 10 cm) 2.40 m3 150,000 360,000
2,376,000
5 PEKERJAAN STRUKTUR
PEKERJAAN PONDASI
1 Setrous pile 12.00 m1 210,000 2,520,000
2 Merapikan setros kepala tiang pancang 4.00 titik 30,000 120,000
3 Lantai kerja (tebal = ± 5 cm) 1.20 m3 1,200,000 1,440,000
4 Cor Pondasi Plat 400x300x70 16.80 m3 3,675,625 61,750,501
5 Finishing Flor Hardiner 27.72 m2 60,000 1,663,200
67,493,701
Pembersihan Akhir 1 ls 5,000,000 5,000,000
5,000,000
TOTAL PEKERJAAN ARSITEKTURAL 214,962,586
54
3,980,789
MOTHER STATION - CNG TAPEN
SURAT PENAWARAN HARGA
PROYEK CNG - MS - TAPEN
PEKERJAAN DRYER DAN KOMPRESOR
LOKASI NGAWUN PERENGAN, TUBAN - JAWA TIMUR