PROJECT :
OWNER :
OWNER’S ENGINEER :
CONTRACTOR :
SUB CONTRACTOR :
METHODE STATEMENT
CHECKED BY DATE OF
ESP / MECHANICAL
METHODE STATEMENT
METHODE STATEMENT OF
ELECTROSTATIC PRECIPITATOR
1. SCOPE
2. OBJECTIVE
3. REFERENCE
4. PREPARATION
5. INSTALLATION
1. SCOPE
METHODE STATEMENT OF
ELECTROSTATIC PRECIPITATOR
2. OBJECTIVE
This is to assure that all the installation of Electrostatic precipitator is follow the
Specification and Client requirements. To maintained the acceptable workmanship
during the installation works.
3. REFERENCE
3.1 A.I.S.C - American Institute of Steel Construction, USA.
3.2 A.N.S.I - American National Standards Institute.
3.3 A.P.I - American Petroleum Institute.
3.4 A.S.M.E - American Society for Non-destructive Testing.
3.5 A.S.T.M - American Society for Testing & Materials.
3.6 A.W.S - American Welding Society.
3.7 B.S - British Standards.
3.8 D.I.N - Deutsche Industrie Normen.
3.9 N.A.C.E - National Association of corrosion Engineers.
3.10 N.B.S. - National Bureau of Standards, U.S.A
3.11 S.I.S - Sveriges Standardiserings Kommission, Sweden.
3.12 S.S.P.C - Steel-Structures Panting council, USA
Applicable specification and standarts.
4. PREPARATION
4.1 Use the latest revised drawing for E.P.
4.2 Complete all necessary equipment and installation teams.
4.3 Make sure parts of E.P are complete, good condition and ready to install, if
there is any damage due to fabrication or transportation, report it to the
client representative as soon as possible.
4.4 Checks and markings of concrete foundations.
5. INSTALLATION PROCEDURE
5.1 Foundation Work
5.1.1 Foundation Check
Center line and elevation marks are given on each foundation.
METHODE STATEMENT OF
ELECTROSTATIC PRECIPITATOR
Check required bolt tension by use of a calibrated wrench and that report
shall be recorded in accordance with Structure Steel Procedure.
METHODE STATEMENT OF
ELECTROSTATIC PRECIPITATOR
METHODE STATEMENT OF
ELECTROSTATIC PRECIPITATOR
Weld the cuted piece one (1) top corner with hopper.
Hopper sub-ass’y.
5.5 Grouting
Check that mixing ratio and condition of grouting mortar meet the
requirement specified in applicable drawing.
Check that the proper curing is performed for the grout after filling.
After solidifying, crack, peeling-off, cavities, etc in mortar shall be visually
checked.
METHODE STATEMENT OF
ELECTROSTATIC PRECIPITATOR
Nozzle erection.
METHODE STATEMENT OF
ELECTROSTATIC PRECIPITATOR
C.E. erection.
D.E. erection.
5.9 Hot Roof & Penthouse Erection
5.9.1 Hot roof & penthouse erection
Carrying materials of hot roof and penthouse.
Pre-assemble the hot roof on the ground.
Erect the pre-assembled hot roof panels according to the drawings.
Erect penthouse side frames & roof panels according to the drawings.
METHODE STATEMENT OF
ELECTROSTATIC PRECIPITATOR