OBRAS ATRASADAS

AMPLIACIÓN DE PLAZO
CRONOGRAMA DE OBRA
PARALIZACIÓN

CALENDARIO DE AVANCE DE OBRA PROGRAMADO - VALORIZADO


MES 1 MES 2 MES 3 MES 4 MES 5 ACUMULADO
PARTIDA "A" 2,000.00 2,000.00 1,000.00 5,000.00
PARTIDA "B" 1000 1,000.00 14,000.00
PARTIDA "C" 1,000.00 2,000.00 500.00 3,000.00
PARTIDA "D" 1,000.00 1,000.00 1,000.00 3,000.00 12,000.00

VAL. MES 3,000.00 4,000.00 4,000.00 1,000.00 500.00


10,000.00
VAL. ACUM. 3,000.00 7,000.00 11,000.00 12,000.00 12,500.00
8,000.00
AVANCE DE OBRA REAL - VALORIZADO
MES 1 MES 2 MES 3 MES 4 MES 5 ACUMULADO 6,000.00
PARTIDA "A" 1,000.00 4,000.00 5,000.00
PARTIDA "B" 1000 1,000.00 4,000.00

PARTIDA "C" 2,000.00 1,000.00 500.00 3,500.00


2,000.00
PARTIDA "D" 500.00 1,500.00 1,000.00 3,000.00
VAL. MES 1,500.00 7,500.00 1,000.00 1,000.00 1,500.00 -
VAL. ACUM. 1,500.00 9,000.00 10,000.00 11,000.00 12,500.00 1

CALENDARIO DE AVANCE DE OBRA PROGRAMADO - VALORIZADO


MES 1 MES 2 MES 3 MES 4 MES 5 ACUMULADO
PARTIDA "A" 2,000.00 2,000.00 1,000.00 5,000.00
PARTIDA "B" 1000 1,000.00 14,000.00
PARTIDA "C" 1,000.00 2,000.00 500.00 3,000.00
PARTIDA "D" 1,000.00 1,000.00 1,000.00 3,000.00 12,000.00
VAL. MES 3,000.00 4,000.00 4,000.00 1,000.00 500.00
VAL. ACUM. 3,000.00 7,000.00 11,000.00 12,000.00 12,500.00 10,000.00
VAL. ACUM. (80%) 2,400.00 5,600.00 8,800.00 9,600.00 10,000.00
8,000.00

AVANCE DE OBRA REAL - VALORIZADO


6,000.00
MES 1 MES 2 MES 3 MES 4 MES 5 ACUMULADO
PARTIDA "A" 1,000.00 1,000.00
4,000.00
PARTIDA "B" -
PARTIDA "C" -
2,000.00
PARTIDA "D" 500.00 500.00
VAL. MES 1,500.00 - - - - -
VAL. ACUM. 1,500.00 1,500.00 1,500.00 1,500.00 1,500.00 1
2,000.00

-
1

CALENDARIO DE AVANCE DE OBRA REPROGRAMADO ACELERADO - VALORIZADO


MES 1 MES 2 MES 3 MES 4 MES 5 ACUMULADO
PARTIDA "A" 1,000.00 4,000.00 1,000.00 6,000.00
PARTIDA "B" 1000 1,000.00 14,000.00
PARTIDA "C" 1,000.00 2,000.00 500.00 3,000.00
PARTIDA "D" 500.00 500.00 1,000.00 2,000.00 12,000.00
VAL. MES 1,500.00 5,500.00 4,000.00 1,000.00 500.00
VAL. ACUM. 1,500.00 7,000.00 11,000.00 12,000.00 12,500.00 10,000.00
VAL. ACUM. (80%) 1,200.00 5,600.00 8,800.00 9,600.00 10,000.00
8,000.00

AVANCE DE OBRA REAL - VALORIZADO


6,000.00
MES 1 MES 2 MES 3 MES 4 MES 5 ACUMULADO
PARTIDA "A" 1,000.00 1,000.00
4,000.00
PARTIDA "B" -
PARTIDA "C" -
2,000.00
PARTIDA "D" 500.00 500.00
VAL. MES 1,500.00 - - - - -
VAL. ACUM. 1,500.00 1,500.00 1,500.00 1,500.00 1,500.00 1

CALENDARIO DE AVANCE DE OBRA REPROGRAMADO ACELERADO - VALORIZADO


MES 1 MES 2 MES 3 MES 4 MES 5 ACUMULADO
PARTIDA "A" 1,000.00 4,000.00 1,000.00 6,000.00
PARTIDA "B" 1000 1,000.00 14,000.00
PARTIDA "C" 1,000.00 2,000.00 500.00 3,000.00
PARTIDA "D" 500.00 500.00 1,000.00 2,000.00 12,000.00
VAL. MES 1,500.00 5,500.00 4,000.00 1,000.00 500.00
VAL. ACUM. 1,500.00 7,000.00 11,000.00 12,000.00 12,500.00 10,000.00
VAL. ACUM. (80%) 1,200.00 5,600.00 8,800.00 9,600.00 10,000.00
8,000.00

AVANCE DE OBRA REAL - VALORIZADO


6,000.00
MES 1 MES 2 MES 3 MES 4 MES 5 ACUMULADO
PARTIDA "A" 1,000.00 3,000.00 4,000.00
4,000.00
PARTIDA "B" -
PARTIDA "C" 1,000.00 1,000.00
2,000.00
PARTIDA "D" 500.00 500.00 1,000.00
VAL. MES 1,500.00 4,500.00 - - - -
VAL. ACUM. 1,500.00 6,000.00 6,000.00 6,000.00 6,000.00 1
Chart Title
14,000.00

12,000.00

10,000.00

8,000.00

6,000.00

4,000.00

2,000.00

-
1 2 3 4 5

Chart Title
14,000.00

12,000.00

10,000.00

8,000.00

6,000.00

4,000.00

2,000.00

-
1 2 3 4 5
2,000.00

-
1 2 3 4 5

Chart Title
14,000.00

12,000.00

10,000.00

8,000.00

6,000.00

4,000.00

2,000.00

-
1 2 3 4 5

Chart Title
14,000.00

12,000.00

10,000.00

8,000.00

6,000.00

4,000.00

2,000.00

-
1 2 3 4 5
REAJUSTE

ACTUALIZAR PRECIOS
FACTOR "K"
INEI
IUPC

15 AL 20 15 AL 20

MES 1 MES 2 MES 3 MES 4 MES 5


MES 1

MES 1
EST. MERC.
DET. IUPC
MES 2

MES 2
EST. MERC.
DET. IUPC

5 d.h. último d.h.


VAL 1

VAL 2
K= c1 (𝐽𝑟/𝐽𝑜)+𝑐2(𝐶𝑟/𝐶𝑜)+𝑐3(𝐴𝑟/𝐴𝑜)+𝑐4(𝐵𝑟/𝐵𝑜)+𝑐5(𝑀𝑎𝑟/𝑀𝑎𝑜)+𝑐6(𝐴𝑔𝑟/���)

c1= 0.28 Jr= 582.52 Jo= 580.9 580.9


c2= 0.18 Cr= 431.73 Co= 431.73 431.73 J= mano de obra
c3= 0.12 Ar= 475.87 Ao= 464.75 464.75 C= cemento
c4= 0.20 Br= 867.79 Bo= 860.76 860.76 A= acero corrugado
c5= 0.12 Mar= 642.98 Mao= 643.05 643.05 B= bloque
c6= 0.10 Agr= 606.47 Ago= 605.77 605.77 Ma= madera para encofra
1.00 Ag= agregado grueso

EJEMPLO

CALCULAR LA VALORIZACIÓN REAJUSTADA, TENIENDO EN


CUENTA LOS SIGUIENTES DATOS:

FECHA DEL VALOR REFERENCIAL: 12/1/2017


FECHA DEL PRESUPUESTO DE OBRA: 11/1/2017
VALORIZACIÓN DE FEBRERO 2018: 1,000,000.00

Jo noviembre
Jr enero

K= 1.005
R= 5,000.00 Vx(K-1)
= mano de obra

= acero corrugado

Ma= madera para encofrado


g= agregado grueso