QUANTITY HARGA
NO URAIAN PEKERJAAN
VOL SAT SATUAN
A PEKERJAAN PAGAR
1 PEK. PERSIAPAN & STRUKTUR
- Galian Pondasi Footplate 80x80x80 8.00 TTK Rp 250,000
- Pondasi Footplate 80x80x40 8.00 TTK Rp 1,250,000
- Urugan Tanah Eks. Pondasi Footplate 1.00 LS Rp 800,000
- Sloof Beton 15/30, 6D16, O8-15 25.00 M1 Rp 250,000
- Kolom K1 15/30, 4D16, 2D12, O8-15 120.00 M1 Rp 250,000
- Balok Beton Ukr- 15/30, 4D16, 2D12, O8-15 50.00 M1 Rp 250,000
- Pilar Perancah Ukr- 15/30, 4D16, 2D12, O8-15 58.00 M1 Rp 250,000
- Alat Bantu Scapollding 300.00 M2 Rp 120,000
Sub Total 1
2 PEK. PASANGAN BATA & BATU ALAM
- Pasangan Bata Dinding Heubeul 10/20/60 300.00 M2 Rp 130,000
- Plester Dinding bata Heubeul 300.00 M2 Rp 125,000
- Pasangan Batu Alam Palimanan 300.00 M2 Rp 350,000
- Perapihan & Pembersihan 1.00 LS Rp 1,500,000
- Buang Tanah Sisa Galian 1.00 LS Rp 2,500,000
Sub Total 2
HARGA SEWAKTU-WAKTU DAPAT BERUBAH BERDASARKAN SPESIFIKASI & HARGA MATERIAL TOTAL JUMLAH
BILAMANA ADA PRUBAHAN / PENAMBAHAN ITEM HARGA DEEL
PEKERJAAN MAKA DIHITUNG KERJA TAMBAH
DEMIKIAN RAB INI KAMI BUAT. ATAS PERHATIAN DAN KERJA SAMANYA KAMI UCAPKAN
TERIMA KASIH
ttd
NANO
JUMLAH SPESIFIKASI
Rp 2,000,000
Rp 10,000,000
Rp 800,000
Rp 6,250,000
Rp 30,000,000
Rp 12,500,000
Rp 14,500,000
Rp 36,000,000
Rp 112,050,000
Rp 39,000,000
Rp 37,500,000
Rp 105,000,000
Rp 1,500,000
Rp 2,500,000
Rp 185,500,000
Rp 297,550,000
MENYETUJUI
PIHAK KEDUA
ttd
Purwatiningsih