• Anchors into
rock form a
‘Frame’
• Soil Anchors do
NOT create a
‘Frame’. Only a
Restrained
Cantilever
• Soil Anchor
MUST be able to
‘self tension’
Shoring Wall
Anchor
Restrained Zone
Anchorage Zone
Shoring Wall
Tendon
Anchor Head
PW Working Load The Maximum or Ultimate calculated load in the anchor during the
construction processes.
PP Proof Load The load to which the ground anchor is to be loaded to check the
adequacy.
PLO ‘Lock Off’ Load The load which will be left in the ground anchor when stressed.
[i.e. The residual anchor load after the proof loading is complete].
PLT Long-term The long-term residual load in the anchorage following its
design load construction, prestressing, creep and subsequent ground
movements.
Note: Whilst AS4678 (2002) describes the Working load as the “load necessary to ensure that the structure behaves in
a satisfactory manner”, in the context of a shoring system and as the load changes during construction, the
above definition is considered to be more precise.
• Deformation of the
Retained Soil
• Deflection of the Wall.
• Increased Anchor Load
• Increased Passive
Pressure at the Toe of
the Wall
Soil Passive
Material Pressure
30
25
20
Optimal Range
15
10
6m Excavation
5
5m Excavation
0
0 50 100 150 200 250 300 350 400
300
PP = 256 kN
Anchor Load [kN]
250
PW = 206 kN 1.25x
200
Deflection
Lock-off
Optimal
PLO =
150
150 kN
100
50
For a 6m
Excavation
0
1 2 3 4 5 6
MONITORING:
Long Term
• The Builder [over 100 years in operation] incurred significant losses
on the project, and was placed in Liquidation 3 years later.
• The Piling Contractor was placed in liquidation 4 years later.
• The Engineer who designed the system has now retired.
Action Limit
Warning Limit
Design Deflection
Monitoring Marks
‘Greasy backs’
Construction
• Collapse of the excavation, with consequent backfilling delaying
construction.
• Loss of parking and limited access for the neighbouring residential
building.
Long Term
• Delayed project delivery due to the backfilling and additional
stabilisation works required.
• Increased future insurance costs for the Builder on the project.
Anchor Shaft
Grout
Construction Errors
• Not following the geotechnical warnings given
• Ignoring the warning signs that something was wrong