Unit Price
2) Name and Specification Quantity Unit Total Cost (PhP)
(PhP)
M
Clearing and Grubbing 57.00 m2 -
A
T
E
R
I
-
A
L -
S
Total Materials Cost -
No. of
3) Name and Capacity No. of Units Hourly Rate Total Cost (PhP)
Hours
E -
Q
U -
I
P
M
E
N
T
Total Equipment Cost -
No. of
4) Designation of Personnel No. of Men Hourly Rate Total Cost (PhP)
Hours
L
A
Construction Foreman 1 24 71.05 1,705.20
B Unskilled Laborer 8 24 37.50 7,200.00
O
R
Total Labor Cost 8,905.20
5) ESTIMATED DIRECT COST (2+3+4) 8,905.20
6) UNIT DIRECT COST (5 /1) 156.23
7) MARK-UP ( 22% OF 5) 1,959.14
8) VALUE ADDED TAX [ 5% OF (5+7)] 543.22
9) TOTAL COST OF ITEM (5+7+8) 11,407.56
10) UNIT COST OF ITEM (9/1) 200.13
DETAILED UNIT PRICE ANALYSIS
Unit Price
2) Name and Specification Quantity Unit Total Cost (PhP)
(PhP)
Demolition of Existing Structure
Assorted Coco Lumber 200.00 bd.ft. 22.00 4,400.00
Assorted C.W. Nails 3.00 kg. 70.00 210.00
-
-
Total Materials Cost 4,610.00
No. of
3) Name and Capacity No. of Units Hourly Rate Total Cost (PhP)
Hours
Backhoe- 0.80 Cu.m 1 34 1,300.00 44,200.00
E
Q
U
I
P
M
E
N
T
Total Equipment Cost 44,200.00
No. of
4) Designation of Personnel No. of Men Hourly Rate Total Cost (PhP)
Hours
L
A
Construction Foreman 1 8 71.05 568.40
B Unskilled Laborer 2 8 37.50 600.00
O
R
Total Labor Cost 1,168.40
5) ESTIMATED DIRECT COST (2+3+4) 49,978.40
6) UNIT DIRECT COST (5 /1) 49,978.40
7) MARK-UP ( 22% OF 5) 10,995.25
8) VALUE ADDED TAX [ 5% OF (5+7)] 3,048.68
9) TOTAL COST OF ITEM (5+7+8) 64,022.33
10) UNIT COST OF ITEM (9/1) 64,022.33
DETAILED UNIT PRICE ANALYSIS
Unit Price
2) Name and Specification Quantity Unit Total Cost (PhP)
(PhP)
M
Structure Excavation 41.96 m3
A
T
E
R
I
-
A
L -
S
Total Materials Cost -
No. of
3) Name and Capacity No. of Units Hourly Rate Total Cost (PhP)
Hours
Backhoe- 0.80 Cu.m 1 34 1,300.00 44,200.00
-
E
Q -
U
I -
P
M
E
N
T
Total Equipment Cost 44,200.00
No. of
4) Designation of Personnel No. of Men Hourly Rate Total Cost (PhP)
Hours
E
-
Q
U
I
P
M
-
E
N
T
Total Equipment Cost -
No. of
4) Designation of Personnel No. of Men Hourly Rate Total Cost (PhP)
Hours
Columns
Carpenter 3 20 54.38 3,262.80
Unskilled Laborer 2 20 37.50 1,500.00
Beams
Carpenter 3 20 54.38 3,262.80
Reversible Electric Drill 2 20 37.50 1,500.00
Suspended Slab
Carpenter 3 16 54.38 2,610.24
Unskilled Laborer 2 16 37.50 1,200.00
Total Labor Cost 13,335.84
5) ESTIMATED DIRECT COST (2+3+4) 77,707.98
6) UNIT DIRECT COST (5 /1) 448.66
7) MARK-UP ( 22% OF 5) 17,095.76
8) VALUE ADDED TAX [ 5% OF (5+7)] 4,740.19
9) TOTAL COST OF ITEM (5+7+8) 99,543.93
10) UNIT COST OF ITEM (9/1) 574.73
DETAILED UNIT PRICE ANALYSIS
Project Name: Rehabilitation of Training Center
Location: AES Sogod Satellite Station, Sogod, Southern Leyte
ITEM: 1001 (2)
DESCRIPTION: Concrete Gutter
1) QUANTITY 7.08 m
OUTPUT
2) Name and Specification Quantity Unit Unit Price (PhP) Total Cost (PhP)
10mmØ Steel bars 92.50 kgs. 48.00 4,440.00
Volume 0.92 m3
M Portland Cement 9.00 bags 290.00 2,610.00
A Washed Sand 0.46 m3 1,300.00 598.00
T Crushed Gravel 0.92 m3 1,300.00 1,196.00
E Curing Compound 0.70 L. 80.00 55.64
R
I
A
L
S
292.00 m2
1) QUANTITY
OUTPUT 146.00 m2/day
Unit Price
2) Name and Specification Quantity Unit Total Cost (PhP)
(PhP)
Plain Cement Plaster Finish 292.00 m2
M Portland Cement 76.00 bags 290.00 22,040.00
A
T Sand 10.00 m 3 1,300.00 13,000.00
E (note : 16mm thk plastering) ###
R
I
A
L
S
Total Materials Cost 35,040.00
No. of
3) Name and Capacity No. of Units Hourly Rate Total Cost (PhP)
Hours
E
Q
U
I
P
M
E
N
T
DESCRIPTION: Masonry Works - (150mm CHB Non Load Bearing) including Reinforcing Steel
1) QUANTITY 150.00 m2
OUTPUT 31.58 m2/day
Unit Price
2) Name and Specification Quantity Unit Total Cost (PhP)
(PhP)
Wall 150.00
6" thk. Concrete Hollow Blocks 1,875.00 pcs. 18.00 33,750.00
Portland Cement 60.00 bags 290.00 17,400.00
Sand 6.53 m3 1,300.00 8,482.50
M
RSB 10mmf x 6.0m (Every 3rd Layer & 0.6m OC vert'l) 434.00 48.00 20,832.00
A kgs.
T # 16 G.I. Tie Wire 6.00 kgs. 70.00 420.00
E
R
I
A ###
L
S
###
Unit Price
2) Name and Specification Quantity Unit Total Cost (PhP)
(PhP)
Wall Tiles 19.44 m2
M Vetrified Glazed Wall Tiles (0.6m x 0.6m) 40.00 pcs. 160.00 6,400.00
A
T Cement 6.00 bags 290.00 1,740.00
E Sand 0.80 m3 1,200.00 960.00
R
I Tile Adhesive 25kg/bag 3.00
A bags 390.00 1,170.00
L
S
Minor Tools 120.00
Total Materials Cost 10,390.00
No. of
3) Name and Capacity No. of Units Hourly Rate Total Cost (PhP)
Hours
Grinder / Tile Cutter 1 24 37.50 900.00
E
Q
U
I
P
M
E
N
T
Total Equipment Cost 900.00
No. of
4) Designation of Personnel No. of Men Hourly Rate Total Cost (PhP)
Hours
Foreman 1 24 71.05 1,705.20
L Tile Installer 2 24 54.38 2,610.24
A
B Unskilled Laborer 2 24 37.50 1,800.00
O
R ###
Total Labor Cost 6,115.44
5) ESTIMATED DIRECT COST (2+3+4) 17,405.44
6) UNIT DIRECT COST (5 /1) 895.34
7) MARK-UP ( 20% OF 5) 3,481.09
8) VALUE ADDED TAX [ 5% OF (5+7)] 1,044.33
9) TOTAL COST OF ITEM (5+7+8) 21,930.86
10) UNIT COST OF ITEM (9/1) 1,128.13
DETAILED UNIT PRICE ANALYSIS
Project Name: Rehabilitation of Training Center
Location: AES Sogod Satellite Station, Sogod, Southern Leyte
ITEM: 1018 (2)
Unglazed Tiles
DESCRIPTION:
1) QUANTITY 56.00 m2 ###
OUTPUT 7.47 m /day 2
Unit Price
2) Name and Specification Quantity Unit Total Cost (PhP)
(PhP)
Floor Tiles 56.00 m2
.60mx.60m non skid homogenoues ceramic tiles 166.00 pcs. 220.00 36,520.00
M
A Cement 4.82 bags 290.00 1,396.64
T
Sand 1.10 m3 1,200.00 1,320.00
E
R Tile Adhesive 25kg/bag 6.00 bags 390.00 2,340.00
I
A Tile Grout 2.00
L bags 90.00 180.00
S
###
###
###
###
E
Q
U
I
P
M
E
N
T
HAULING COST
BUILDING COST
COST OF EVERY STRUCTURE
DIRECT COST TOTAL 12.000%
VINCENT T. SY III LETECIA M. OLARTE ALLAN D. EWAY MA. MARGARITA C. JUNIA, D.M.
Engineer II Engineer III Assistant District Engineer District Engineer
Chief - Planning and Design Section Chief - Construction Section
Project Name: Rehabilitation of Training Center
Location: AES Sogod Satellite Station, Sogod, Southern Leyte
HOURLY RATE
REF. NO. Name & Capacity DAILY RATE (PhP)
(PhP)
E01 Asphalt Paver, 10 Ft. Width /80Hp 1,833.00 14,664.00
E02 Asphalt Distributor, 5 Tons / 100Hp 936.00 7,488.00
E03 Batching Plant, 30 Cu.M. 1,503.32 12,026.56
E04 Transit Mixer, 5-6 Cu.M. 1,279.00 10,232.00
E04 1-Bagger Concrete Mixer 173.00 1,384.00
E05 Bulldozer (D65A-8/155Hp) 2,299.00 18,392.00
E06 Backhoe, ( Cap. 0.80 Cu. M.) 1,537.00 12,296.00
E07 Backhoe W/ Pavm't Breaker, (E110B) 1,767.55 14,140.40
E08 Payloader, 1.5 Cu.M. 1,733.00 13,864.00
E09 Wheel Loader, 918F 1,329.00 10,632.00
E10 Road Grader, 140Hp / G710A 2,173.00 17,384.00
E11 Tandem Steel Roller (10.00 MT) 567.00 4,536.00
E12 Road Roller, Pneumatic (13.00 MT) 553.00 4,424.00
E13 Vibratory Roller 1,507.00 12,056.00
E14 Dump Truck, (Cap.10-11 Cu.M.) 1,352.00 10,816.00
E15 Concrete Vibrator 121.00 968.00
E16 Air Compressor, 86-125cfm / 42Hp 358.00 2,864.00
E17 Concrete Mixer, 1.5 - 2 Bagger 172.00 1,376.00
E18 Concrete Screeder 129.39 1,035.12
E19 Water Truck, (Cap.1000 Gal) 1,065.00 8,520.00
E20 Cargo Truck /Stake Truck,(Cap.6-8 MT/195 Hp) 851.00 6,808.00
E21 Rebar Cutter, Max Dia.(20mm) 219.00 1,752.00
E22 Rebar Bender,Max. Dia(25mm) 334.00 2,672.00
E23 Concrete Saw, 12" Blade Diam. 139.00 1,112.00
E24 Tower Lights, 5Hp / 2.70 KW generator 328.00 2,624.00
E25 Power Broom ( 20m Wide) 87.03 696.24
E24 Welding Machine 61.25 490.00
E24 Grinder 30.00 240.00
E24 Electric Drill 25.00 200.00
PROGRAM OF WORK
NAME/LOCATION OF PROJECT: APPROPRIATION 1,833,427.00
CONCURRED:
SUBMITTED:
APPROVED:
LETECIA M. OLARTE
Chief, Construction Section
I - A. DIRECT COST
B. INDIRECT COST
III - CONTENGENCIES/RESERVES
CONCURRED:
SUBMITTED:
PART A : EARTHWORK
800 (1) Clearing and Grubbing 0.62% 57.00 m2 ₱ 8,905.20 ₱ 156.23
803 (1) a Structure Excavation - (Common Soil ) 3.86% 41.96 m3 ₱ 55,330.84 ₱ 1,318.66
801 (1) Removal of Structures and Obstruction 3.49% 1.00 l.s ₱ 49,978.40 ₱ 49,978.40
Sub-Total of Part A 7.97% ₱ 114,214.44
PART B : PLAIN AND REINFORCED CONCRETE WORK
900 (1) c1 Structural Concrete, Class A, 28 Days 13.15% 26.43 m3 ₱ 188,427.99 ₱ 7,130.40
902 (1) a Reinforcing Steel (Deformed) - Grade 40 12.25% 2,289.14 kgs. ₱ 175,445.22 ₱ 76.64
903 (2) Formworks and Falseworks 5.42% 173.20 m2 ₱ 77,707.98 ₱ 448.66
Sub-Total of Part B 30.82% ₱ 441,581.19
PART C : FINISHINGS AND OTHER CIVIL WORKS
1001 (2) Concrete Gutter 1.18% 7.08 m ₱ 16,947.24 ₱ 2,394.72
1001 (8) Sewer Line Works 0.88% 1.00 l.s. ₱ 12,653.56 ₱ 12,653.56
1001 (11) Septic Vault - Concrete/CHB 2.71% 1.00 l.s. ₱ 38,876.60 ₱ 38,876.60
1001 (9) Storm Drainage & Downspout 0.34% 1.00 l.s. ₱ 4,902.58 ₱ 4,902.58
1002 (24) Cold Water Lines 2.97% 1.00 l.s. ₱ 42,481.70 ₱ 42,481.70
1047 (1) Structural Steel 2.06% 1.00 l.s. ₱ 29,493.00 ₱ 29,493.00
1003 (1)-h Ceiling 4.85% 1.00 l.s. ₱ 69,432.80 ₱ 69,432.80
1005 (4) Steel Windows (Awning Ventilator) 3.00% 6.48 m2 ₱ 42,976.20 ₱ 6,632.13
1010 (2)-b Doors - Wood Panel 4.66% 14.49 m2 ₱ 66,731.18 ₱ 4,605.33
1027 (1) Cement Plaster Finish 2.85% 292.00 m2 ₱ 40,857.12 ₱ 139.92
1046 (2)-a2 Masonry Works - (150mm CHB Non Load Bearin 7.28% 150.00 m2 ₱ 104,305.04 ₱ 695.37
1018 (1) Glazed Tiles and Trims 1.21% 19.44 m2 ₱ 17,405.44 ₱ 895.34
1018 (2) Unglazed Tiles 4.30% 56.00 m2 ₱ 61,545.24 ₱ 1,099.02
1032 (1) a Painting Works - Masonry/ Concrete 5.78% 270.00 m2 ₱ 82,842.52 ₱ 306.82
1032 (1) b Painting Works - Wood 2.06% 110.00 m2 ₱ 29,469.12 ₱ 267.90
1032 (1) c Painting Works - Steel 3.09% 180.00 m2 ₱ 44,221.40 ₱ 245.67
Sub-Total of Part C 38.30% ₱ 705,140.74
PART D : ELECTRICAL
1100 (10) Conduits, Boxes and Fittings (Conduit Works 1.31% 1.00 l.s. ₱ 18,727.04 ₱ 18,727.04
1102 (1) Panelboard with Main & Branch Breakers 1.06% 1.00 l.s. ₱ 15,158.60 ₱ 15,158.60
1101 (33) Wires and Wiring Devices 6.55% 1.00 l.s. ₱ 93,839.04 ₱ 93,839.04
Sub-Total of Part D 8.92% ₱ 127,724.68
PART E : MECHANICAL
0.00% 0.00 - -
Sub-Total of Part D 0.00% -
length 180
Reblocking WIDTH = 3.65
AREA = 657.00
ASSUME WIDENING 3%
SPACING = 3M @ EVERY 6M = 9M
WIDTH = 0.10 M
LENGTH = 0.00 M (for both sides multiply by 2)
AREA = 0.00 SQ.M.
TOTAL AREA = 0.45 SQ.M.
SAY = 0.00 SQ.M.
PREPARED:
ERIC D. RABI
Engineer II
Rehabilitation of Training Center
AES Sogod Satellite Station, Sogod, Southern Leyte
PORTLAND CEMENT
LOADING: FREE
UNLOADING:
Manual unloading:
Rate of Manual unloading = 0.35 min. per bag
No. of bags/truck = 10000 kg. / 40 kg. per bag
= 250 bags
Time = 250 bags x 0.35 min. per bag
= 87.5 min.
= 1.46 hrs.
RETURN TRIP
Distance = 72 km.
Speed = 60 kph
Travel Time = 1.2 hrs.
SAND
Source: Lawigan, St. Bernard
RETURN TRIP
Distance = 59 km.
Speed = 60 kph
Travel Time = 0.9833333333 hrs.
LOADING/
TOTAL TIME = HAULING + UNLOADING +
= 1.3111111111 + 0.08 +
= 2.38 hrs.
= 0.2972222222 days (8 hrs work/day)
Truck capacity 10 cu m
GRAVEL
RETURN TRIP
Distance = 52 km.
Speed = 60 kph
Hauling Time = 0.8666666667 hrs.
LOADING/
TOTAL TIME = HAULING + UNLOADING +
= 1.1555555556 + 0.08 +
= 2.11 hrs.
= 0.2631944444 days (8 hrs work/day)
Truck capacity 10 cu m
EMBANKMENT BORROW
RETURN TRIP
Distance = 59 km.
Speed = 45 kph
Hauling Time = 1.3111111111 hrs.
Truck capacity 10 cu m
STEEL BARS
SOURCE: Sogod
LOADING: FREE
UNLOADING: FREE
RETURN TRIP
Distance = 59 km.
Speed = 55 kph
Hauling Time = 1.0727272727 hrs.
HAULING:
RETURN TRIP
Distance = 55 km.
Speed = 55 kph
Hauling Time = 1 hrs.
-
-
HAULING:
RETURN TRIP
Distance = 55 km.
Speed = 55 kph
Hauling Time = 1 hrs.
RETURN TRIP
1.2
3 min, Unloading= 2 min)
RETURN TRIP
0.9833333333
3 min, Unloading= 2 min)
RETURN TRIP
0.8666666667
ding , 2 min. Unloading)
RETURN TRIP
1.3111111111
alidated Monitoring
alidated Monitoring
min. per Pc
RETURN TRIP
1
-
-
alidated Monitoring
min. per Pc
RETURN TRIP
1
P 1,776,779.379574960000000000
3.0382778166
PROJECT NAME: REHABILITATION OF TRAINING CENTER
ITEM NO. DESCRIPTION UNIT
800 (1) Clearing and Grubbing m2
801 (1) Removal of Structures and Obstruction l.s
803 (1) a Structure Excavation - (Common Soil ) m3
900 (1) c1 Structural Concrete m3
902 (1) a Reinforcing Steel (Deformed) kgs.
903 (2) Formworks and Falseworks m2
1001 (2) Concrete Gutter m
1001 (8) Sewer Line Works l.s.
1001 (11) Septic Vault l.s.
1001 (9) Storm Drainage & Downspout l.s.
1002 (24) Cold Water Lines l.s.
1047 (1) Structural Steel l.s.
1003 (1)-e2 Ceiling l.s.
1005 (4) Steel Windows (Awning Ventilator) m2
1010 (2)-b Doors - Wood Panel m2
1027 (1) Cement Plaster Finish m2
1046 (1)-a2 Masonry Works - (150mm CHB) m2
1100 (10) Conduits, Boxes and Fittings (Conduit Works/ Conduit Rough-in) l.s.
1102 (1) Panelboard with Main & Branch Breakers l.s.
1101 (33) Wires and Wiring Devices l.s.
1018 (1) Glazed Tiles and Trims m2
1018 (2) Unglazed Tiles m2
1032 (1) a Painting Works - Masonry/ Concrete m2
1032 (1) b Painting Works - Wood m2
1032 (1) c Painting Works - Steel m2
B.1 Offices, Shops, Stores & Workemens Accomodation for Contractor l.s
B.5 Project Billboard / Signboard each
B.7 (1) Occupational Safety and Health Program Month
QUANTITY REMARKS
57.00
1.00
41.96
26.43
2289.14
173.20
7.08
1.00
1.00
1.00
1.00
1.00
1.00
6.48
14.49
292.00
150.00
1.00
1.00
1.00
19.44
56.00
270.00
110.00
180.00
1.00
1.00
3.00