EARTH WORKS
b) Concrete Column V=
Quantity Unit Description Unit cost Total Cost
Bags Portland Cement ₱ 250.00 ₱ -
Pcs 25 mm Ø x 6m RSB ₱ -
Pcs 20 mm Ø x 6m RSB ₱ -
Pcs 16 mm Ø x 6m RSB ₱ -
Pcs 12 mm Ø x 6m RSB ₱ 250.00 ₱ -
Pcs 10 mm Ø x 6m RSB ₱ 175.00 ₱ -
Pcs Washed Sand ₱ 700.00 ₱ -
Cu.m Washed Gravel ₱ 1,000.00 ₱ -
Kls #16 G.I Wire ₱ 95.00 ₱ -
Material Cost ------ ₱ -
Labor Cost ---------- ₱ -
Sub Total ----------- ₱ -
Unit Cost -----------
c) Roof Beam V=
Quantity Unit Description Unit cost Total Cost
Bags Portland Cement ₱ 250.00 ₱ -
Pcs 25 mm Ø x 6m RSB ₱ -
Pcs 20 mm Ø x 6m RSB ₱ -
Pcs 16 mm Ø x 6m RSB ₱ -
Pcs 12 mm Ø x 6m RSB ₱ 250.00 ₱ -
Pcs 10 mm Ø x 6m RSB ₱ 175.00 ₱ -
Pcs Washed Sand ₱ 700.00 ₱ -
Cu.m Washed Gravel ₱ 1,000.00 ₱ -
Kls #16 G.I Wire ₱ 95.00 ₱ -
Material Cost ------ ₱ -
Labor Cost ---------- ₱ -
Sub Total ----------- ₱ -
Unit Cost -----------
d) Tie Beam V=
Quantity Unit Description Unit cost Total Cost
Bags Portland Cement ₱ 250.00 ₱ -
Pcs 25 mm Ø x 6m RSB ₱ -
Pcs 20 mm Ø x 6m RSB ₱ -
Pcs 16 mm Ø x 6m RSB ₱ -
Pcs 12 mm Ø x 6m RSB ₱ 250.00 ₱ -
Pcs 10 mm Ø x 6m RSB ₱ 175.00 ₱ -
Pcs Washed Sand ₱ 700.00 ₱ -
Cu.m Washed Gravel ₱ 1,000.00 ₱ -
Kls #16 G.I Wire ₱ 95.00 ₱ -
Material Cost ------ ₱ -
Labor Cost ---------- ₱ -
Sub Total ----------- ₱ -
Unit Cost -----------
e) Flooring V=
Quantity Unit Description Unit cost Total Cost
Bags Portland Cement ₱ 250.00 ₱ -
Pcs 25 mm Ø x 6m RSB ₱ -
Pcs 20 mm Ø x 6m RSB ₱ -
Pcs 16 mm Ø x 6m RSB ₱ -
Pcs 12 mm Ø x 6m RSB ₱ 250.00 ₱ -
Pcs 10 mm Ø x 6m RSB ₱ 175.00 ₱ -
Pcs Washed Sand ₱ 700.00 ₱ -
Cu.m Washed Gravel ₱ 1,000.00 ₱ -
Kls #16 G.I Wire ₱ 95.00 ₱ -
Material Cost ------ ₱ -
Labor Cost ---------- ₱ -
Sub Total ----------- ₱ -
Unit Cost -----------
f) Canopy V=
Quantity Unit Description Unit cost Total Cost
Bags Portland Cement ₱ 250.00 ₱ -
Pcs 12 mm Ø x 6m RSB ₱ 250.00 ₱ -
Pcs 10 mm Ø x 6m RSB ₱ 175.00 ₱ -
Pcs Washed Sand ₱ 700.00 ₱ -
Cu.m Washed Gravel ₱ 1,000.00 ₱ -
Kls #16 G.I Wire ₱ 95.00 ₱ -
Material Cost ------ ₱ -
Labor Cost ---------- ₱ -
Sub Total ----------- ₱ -
Unit Cost -----------
g) Lintel Beam V=
Quantity Unit Description Unit cost Total Cost
Bags Portland Cement ₱ 250.00 ₱ -
Pcs 12 mm Ø x 6m RSB ₱ 250.00 ₱ -
Pcs 10 mm Ø x 6m RSB ₱ 175.00 ₱ -
Pcs Washed Sand ₱ 700.00 ₱ -
Cu.m Washed Gravel ₱ 1,000.00 ₱ -
Kls #16 G.I Wire ₱ 95.00 ₱ -
Material Cost ------ ₱ -
Labor Cost ---------- ₱ -
Sub Total ----------- ₱ -
Unit Cost -----------
VI. Painting
A = 1,801.22 Sq.m
QTY Unit Description Unit Cost Total Cost
135 gals Flat latex 701 Boysen ₱ 650.00 ₱ 87,750.00
180 gals Semi Gloss Latex 715 ₱ 750.00 ₱ 135,000.00
14 can TTC Latex Raw Sienna ₱ 95.00 ₱ 1,330.00
14 can TTC Latex Hansa Sienna ₱ 95.00 ₱ 1,330.00
14 gals Body Filler (Grip) ₱ 1,000.00 ₱ 14,000.00
21 kls Patching Compound ₱ 40.00 ₱ 840.00
14 pcs Roller Paint 7" w/ Fan ₱ 150.00 ₱ 2,100.00
14 pcs Paint Brush 4" ₱ 100.00 ₱ 1,400.00
14 pcs Paint brush 2" ₱ 40.00 ₱ 560.00
3 gals QDE Flat White ₱ 725.00 ₱ 2,175.00
3 gals QDE Semi Gloss ₱ 750.00 ₱ 2,250.00
2 gals Fulatite (Body Filler) ₱ 1,000.00 ₱ 2,000.00
2 gals Epoxy Primer ₱ 750.00 ₱ 1,500.00
4 gals Lacquer Thinner ₱ 500.00 ₱ 2,000.00
4 gals Paint Thinner ₱ 300.00 ₱ 1,200.00
8 rolls Masking Tape (big) ₱ 35.00 ₱ 280.00
8 kls Old News Paper ₱ 25.00 ₱ 200.00
2 mtrs Sanding Paper ₱ 200.00 ₱ 400.00
8 pcs 3" Paint Brush ₱ 60.00 ₱ 480.00
4 gals Paint Sealer Boysen ₱ 750.00 ₱ 3,000.00
Sub-Total ₱ 259,795.00
Labor ₱ 10,287.70
Total ₱ 270,082.70
Unit Cost
3. Catch Basin
V =( (0.40x0.40x0.40) - (0.20x0.20x0.25))x32 = 1.728 Cu.m
P = 122.64 Sq.m
QTY Unit Description Unit Cost Total Cost
8 pcs Portland Cement 250.00 2,000.00
1 pcs Washed Sand 700.00 700.00
1 pcs Washed Gravel 1,000.00 1,000.00
256 pcs 4" CHB 15.00 3,840.00
68 pcs 10mmØ x 6m RSB 164.00 11,152.00
6 pcs #16 G.I. Wire 70.00 420.00
65 pcs 100mmØ x 10' PVC Pipe Atlanta S=1000 792.00 51,480.00
8 Qrts. PVC Solvent 150 1,200.00
Sub-Total ₱ 71,792.00
Labor ₱ 25,889.20
Total ₱ 96,099.20
Unit Cost
2. Sanitary Line
QTY Unit Description Unit Cost Total Cost
25 pcs 150mmØ x 10' PVC Pipe Orange Atlanta S=1000 1,500.00 37,500.00
30 pcs 100mmØ x 10' PVC Pipe Orange Atlanta S=1000 792.00 23,760.00
40 pcs 50mmØ x 10' PVC Pipe Orange Atlanta S=1000 280.00 11,200.00
5 pcs 150mmØ x 150mmØ PVC Wye Orange Atlanta 450.00 2,250.00
8 pcs 150mmØ x 100mmØ PVC Wye Orange Atlanta 380.00 3,040.00
2 pcs 150mmØ x 50mmØ PVC Wye Orange Atlanta 290.00 580.00
5 pcs 100mmØ x 100mmØ PVC Wye Orange Atlanta 140.00 700.00
35 pcs 100mmØ x 50mmØ PVC Wye Orange Atlanta 115.00 4,025.00
100mmØ x 50mmØ PVC Double Wye Orange
20 pcs Atlanta 150.00 3,000.00
10 pcs 50mmØ x 50mmØ PVC Wye Orange Atlanta 65.00 650.00
10 pcs 100mmØ x 50mmØ PVC Tee Orange Atlanta 105.00 1,050.00
35 pcs 50mmØ x 50mmØ PVC Tee Orange Atlanta 40.00 1,400.00
100 pcs 50mmØ x PVC Elbow 45 Orange Atlanta 45.00 4,500.00
30 pcs 50mmØ x P-trap PVC Orange Atlanta 110.00 3,300.00
50mmØ Floor Drain Stainless Finish w/ Screen &
Strainer
65 pcs 50.00 3,250.00
2 pcs 150mmØ PVC Clean Out Plug Atlanta 250.00 500.00
15 pcs 50mmØ PVC Vent Pipe 280.00 4,200.00
16 pcs Porcelain Lavatory HCG 2,500.00 40,000.00
25 pcs Shower Heads w/ Accessories 1,500.00 37,500.00
70 pcs Hose Bib 150.00 10,500.00
8 pcs Urinal HCG 4,500.00 36,000.00
30 pcs Water Closet HCG 10,000.00 300,000.00
10 qrts PVC Cement Solvent 150.00 1,500.00
Sub-Total ₱ 492,905.00
Labor ₱ 172,516.75
Total ₱ 665,421.75
Unit Cost
-
160