0 penilaian0% menganggap dokumen ini bermanfaat (0 suara)
9 tayangan3 halaman
This document provides a schedule of materials and estimated costs for erecting a 220 KV substation at a residential project in Thane, Maharashtra, India. The schedule includes 13 line items with descriptions of work like surveys, excavation, concrete work, tower erection, stringing of conductors, earthing work, and protection wall construction. The total estimated cost for all the work is Rs. 109,102,199.89.
This document provides a schedule of materials and estimated costs for erecting a 220 KV substation at a residential project in Thane, Maharashtra, India. The schedule includes 13 line items with descriptions of work like surveys, excavation, concrete work, tower erection, stringing of conductors, earthing work, and protection wall construction. The total estimated cost for all the work is Rs. 109,102,199.89.
This document provides a schedule of materials and estimated costs for erecting a 220 KV substation at a residential project in Thane, Maharashtra, India. The schedule includes 13 line items with descriptions of work like surveys, excavation, concrete work, tower erection, stringing of conductors, earthing work, and protection wall construction. The total estimated cost for all the work is Rs. 109,102,199.89.
LILO on 220 KV Bapgoan-Kalwa for proposed 220 KV Substation at LODHA residential project village Mankoli Dist Thane
SCHEDULE ‘B’ (Erection OF MATERIAL)
Erection unit Ex Erection erection ex works 1% Labour works Erection Sr. No. Description Unit Qty Unit Rate amount GST cess rate+GST+1% Amount Ex works Labour cess 1 Survey
Detail survey 0.5
Km 12900 6450 2322.00 152.22 15374.22 7687.11 Check Survey Km 0.5 4300 2150 774.00 50.74 5124.74 2562.37 2 Excavation of pits for Tower footings in earth oil / Of all types including removing of excavated material beyond Tower Limits upto 50 mtrs. Dewatering etc. complete in all respect. 0 0.00 0.00 0.00 0.00 a) Normal Soil. Cum. 240 179.85 43164 32.37 2.12 214.35 51442.86 b) B.C. Soil / Submerged Soil Cum. 1175 303 356025 54.54 3.58 361.12 424310.60 c) Hard Murum / Soft Rock Cum. 355 372.35 132184.25 67.02 4.39 443.77 157537.19 d) Dry Fissured Rock Cum. 475 909 431775 163.62 10.73 1083.35 514589.45 e) Hard Rock Cum. 120 1173.9 140868 211.30 13.85 1399.05 167886.48 3 Stub setting in all type of soil 0 0.00 0.00 0.00 0.00 per ND loc 5 5000 25000 900.00 59.00 5959.00 29795.00 4.1 Providing and Casting in situ cement concrete of trap metal of size 20 to 40 mm including fixing of stub. 0 0.00 0.00 0.00 0.00 a) 1:3:6 (M-10) Cum. 39 5708.35 222625.65 1027.50 67.36 6803.21 265325.25 b) 1:1.5:3(M-20) Cum. 512.42 7016.08 3595179.714 1262.89 82.79 8361.76 4284735.18 4.2 Providing and fixing position of ms Tar Bars for reinforcement of various sizes including 42.00 supply of steel cutting. MT 72180 3031560 12992.40 851.72 86024.12 3613013.21 5 Erection of Tower with its extensions and tightening, punching, Fixing of Bolts and 50 Nuts. MT 6525 326250 1174.50 77.00 7776.50 388824.75 Stringing of conductor on D/C (6 6 km 0.5 81950.64 conductors) 40975.32 14751.12 967.02 97668.77 48834.39 Installation of OPGW (Off-line) & FOAC 7 alongwith splicing, fitting of all Hardwares & Km 0.5 60229.157 30114.58 10841.25 710.70 71781.11 35890.55 Accessories etc. 8 Earthing 0 0.00 0.00 0.00 0.00
Pipe type earthing with supply of material 4
Nos 5050 20200 909.00 59.59 6018.59 24074.36 Counter poise earthing with supply of 1 material Nos 11110 11110 1999.80 131.10 13240.90 13240.90 9 Electric tack welding to tower upto two towe sections and painting with anticorrossive r 5 2400 paint D/C tower 12000 432.00 28.32 2860.32 14301.60 10 providing dewatering of excavated pits /Hp/ sorrounding area during excavation and 8Hrs 750 202 concreting with diesel/electrical pump. 151500 36.36 2.38 240.74 180557.70 11 Benching 0 0.00 0.00 0.00 0.00 a) Normal Soil / B.C. Cum. 100 179.85 17985 32.37 2.12 214.35 21434.52 b) Hard Murum / Soft Rock Cum. 150 372.35 55852.5 67.02 4.39 443.77 66565.01 12.0 Protection of Tower footing by uncoursed rubble stone . 0 0.00 0.00 0.00 0.00 A Excavation for foundation of revetment wall/protection wall in all type of soil, sand, gravels, soft murum. Soft murum with boulders, normal soil including shoring, shuttering wherever necessary & disposing of the excavated stuff as directed upto 50mtrs. Lead in 0 0.00 0.00 0.00 0.00 a Normal Soil/Sand/Gravel/Soft Murum Cum. 20.00 179.85 3597 32.37 2.12 214.35 4286.90 b Black cotton soil/Submerged soil Cum. 12.0 303.00 3636 54.54 3.58 361.12 4333.38 c Soft rock/Hrad Murum Cum. 60.00 372.35 22341 67.02 4.39 443.77 26626.00 d Dry Fissured Rock Cum. 110.00 909 99990 163.62 10.73 1083.35 119168.08 Providing & casting in situ cement concrete of 1:3:6 of trap metal for copping of retaining wall including cost of the cement, 12.2 Cum. 15.00 5608.35 sand, metal, water and form work, compaction & curing etc. complete in all respect. 84125.25 1009.50 66.18 6684.03 100260.47 Providing & casting in situ cement concrete of 1:2:4 of trap metal for copping of 12.3 retaining wall including cost of the cement, Cum. 5.00 6288.35 sand, metal, water, dewatering, form work, compaction & curing etc. complete in all 31441.75 1131.90 74.20 7494.46 37472.28 respect. Providing & constructing of UCR masonry of trap stone in cement mortar 1:6 in super structure including racking out joints on the inside as no plastering to be done from inside, scaffolding, dewatering, compacting, 12.4 Cum. 105.00 2441 curing etc. complete in all respects as per the drawings to be furnished by the MSETCL. All the material such as trap stones, cement, sand, metal, water etc. to be provided by the contractor as his own cost including 256305 439.38 28.80 2909.18 305464.30 following activities. Total 9154405.012 10910219.89