Unit Cost
ITEM ITEM DESCRIPTION UNIT QTY TOTAL (PHP)
Total
DIVISION 1 - GENERAL REQUIREMENT
1 Mobilization / Demobilization lot 1.00 25,000.00 25,000.00
License & Permitting By Owner
Electrical & Water By Owner
2 Temfacil lot 1.00 30,000.00 30,000.00
Warehouse/field office lot 1.00 5,000.00 5,000.00
Sub-total 60,000.00
DIVISION 2 - SITE WORKS
1.0 Clearing and grubbing sq.m. 80.00 13.00 1,040.00
2.0 Batterboard Installation l.m. 54.00 63.55 3,431.70
3.0 Layouting grid line 54.00 - -
4.0 Soil Poisoning sq.m. 118.00 9.00 1,062.00
a Soil Poison lit 2.00 10,462.50 20,925.00
5.0 Excavation cu.m. 32.00 365.00 11,680.00
6.0 Disposal cu.m. 10.00 284.00 2,840.00
7.0 Backfilling & Compaction cu.m. 22.00 284.00 6,248.00
8.0 General Cleaning & Lot Leveling sq.m. 118.00 21.00 2,478.00
Sub-total - 49,704.70
DIVISION 3 - CONCRETE -
Wall Concrete Footings -
1.0 Gravel Bed Laying cu.m. 1.00 1,552.50 1,552.50
2.0 Reinforcement kgs. 377.00 63.00 23,751.00
a GI Tie Wire #16 kgs. 5.00 120.00 600.00
3.0 Concrete Pouring ( one-bagger ) 3200 Psi
a Portland Cement (40 kg) bags 50.00 352.50 17,625.00
b Sand cu.m. 3.00 1,417.50 4,252.50
c Gravel, 3/4" cu.m. 5.00 1,620.00 8,100.00
Sub-total - 55,881.00
Slab on Fill -
1.0 Gravel Bed Laying cu.m. 3.00 1,620.00 4,860.00
2.0 Wire Mesh Laying
a Wiremesh; 150x150x6mm (MD30) sq.m. 80.00 297.00 23,760.00
b Deform Bar 10mm pcs 40.00 202.50 8,100.00
3.0 Concrete Pouring ( one-bagger ) 3200 Psi
a Portland Cement (40 kg) bags 66.00 352.50 23,265.00
b Sand cu.m. 4.00 1,417.50 5,670.00
c Gravel, G-1 cu.m. 7.00 2,100.00 14,700.00
4.0 Concrete Floor Finishing sq.m. 80.00 169.50 13,560.00
Sub-total - 93,915.00
Column -
1.0 Reinforcement
a Deform Bar 16mm pcs 48.00 517.50 24,840.00
b Deform Bar 10mm pcs 40.00 202.50 8,100.00
d GI Tie Wire #16 kgs 5.00 120.00 600.00
3.0 Formworks sq.m. 34.00 135.00 4,590.00
4.0 Concrete Pouring ( one-bagger ) 3200 Psi
a Portland Cement (40 kg) bags 30.00 352.50 10,575.00
b Sand cu.m. 2.00 1,417.50 2,835.00
c Gravel, G-1 cu.m. 4.00 2,100.00 8,400.00
Sub-total - 59,940.00
Beam -
1.0 Reinforcement
a Deform Bar 16mm pcs 36.00 517.50 18,630.00
b Deform Bar 10mm pcs 40.00 202.50 8,100.00
d GI Tie Wire #16 kgs 5.00 120.00 600.00
3.0 Formworks sq.m. 34.00 135.00 4,590.00
4.0 Concrete Pouring ( one-bagger ) 3200 Psi
a Portland Cement (40 kg) bags 30.00 352.50 10,575.00
b Sand cu.m. 2.00 1,417.50 2,835.00
c Gravel, G-1 cu.m. 4.00 2,100.00 8,400.00
Sub-total - 53,730.00
DIVISION 4 - Masonry -
CHB Laying -
1.0 CHB Laying 5" including Rebars; Class C
a CHB 5" pcs 500.00 25.50 12,750.00
b. Sand cu.m. 4.00 1,417.50 5,670.00
c Portland Cement (40 kg) bag 40.00 352.50 14,100.00
2.0 CHB Laying 4" including Rebars; Class C
a CHB 4" pcs 350.00 24.00 8,400.00
b. Sand cu.m. 3.00 1,417.50 4,252.50
c Portland Cement (40 kg) bag 30.00 352.50 10,575.00
3.0 Plastering (1/2" thick); Class B
b Plastering sq.m. 336.00 195.00 65,520.00
c Skimcoating sq.m. 336.00 75.00 25,200.00
d Concrete Pouring 3200 psi
Portland Cement (40 kg) bags 70.00 352.50 24,675.00
Sand cu.m. 10.00 1,417.50 14,175.00
Skimcoating bags 20.00 675.00 13,500.00
Sub-total - 198,817.50
Kitchen Counter Base & Sink -
1.0 CHB Laying 4" including Rebars; Class C
a CHB 4" - 400psi pc 15.00 24.00 360.00
b Portland Cement (40 kg) bags 1.00 352.50 352.50
c Rebars, 10 mm dia x 6m (Grade 33) pcs 6.00 232.50 1,395.00
d Tie wires #16 kgs 0.30 148.50 44.55
e Sand cu.m. 0.20 1,417.50 283.50
2.0 Plastering (1/2" thick); Class B sq.m. 0.40 195.00 78.00
4.0 Formworks sq.m. 5.00 135.00 675.00
5.0 Reinforcement kgs 19.00 63.00 1,197.00
6.0 Concrete Slab Base & Counter (Assume 2500psi)
a Portland Cement (40 kg) bags 2.00 352.50 705.00
b Sand cu.m. 0.30 1,417.50 425.25
c Gravel cu.m. 0.40 2,100.00 840.00
Sub-total - 6,355.80
DIVISION 5 - METALS -
Structural Steel (Roof Framing ) - - -
1.0 Rafters, cleats and runners lot 1.00 120,000.00 120,000.00
Stiffeners, Angle Bar, & Plates
Tie Bar, Purlins
2.0 Consumables lot 1.00 7,500.00 7,500.00
3.0 Terrace Grills lot 1.00 45,000.00 45,000.00
Windows Grills
1.0 Window grilles 9 sets lot 1.00 45,000.00 45,000.00
Sub-total - 217,500.00
DIVISION 7 - Roofing -
ROOFING -
1.0 Roofing Rib type Color
a Rib Type Color Roof .05 sq.m 120.00 600.00 72,000.00
b Gutter pcs 15.00 450.00 6,750.00
c Ridge pcs 18.00 450.00 8,100.00
2.0 Fascia Installation
a Fascia board, 12mm thick x 10" x 8' pc 24.00 630.00 15,120.00
INSULATION - - -
1.0 Insulation sq.m 100.00 337.50 33,750.00
Sub-total - 135,720.00
DIVISION 8 - DOORS & WINDOWS -
Doors -
1.0 Panel Door -
a Door (D1) - Wooden Panel Door; 90x 2100mm pc 1.00 15,000.00 15,000.00
b Door (D2)- Wooden Panel Door 800 x 2100mm pc 3.00 7,830.00 23,490.00
Term of Payment
50% Downpayment
20% 50% Accomplishment
20% 70% Accomplishment
10% Upon Completion of project
Prepared By:
Benigno A. Masaredo Jr
General Manager
JOHN GERALD ENTERPRISES
09564566780/09999814638