Anda di halaman 1dari 1

PASAR BERDASARKAN VOLUME KONTRAK

KEBUTUHAN MATERIAL
ITEM URAIAN VOLUME KOEF SAT TOTAL VOLUME SATUAN VOLUME SATUAN
PONDASI BATU KALI BATU KALI 72.80 1.2 m3 87.36 m3 12.48 RIT (7m3)
pasir 72.80 0.544 m3 39.60 m3 5.66 RIT (7m3)
semen 72.80 136 Kg 9,900.80 Kg 198.02 SAK (PER 50KG)
besi sloof besi 13 647.22 1.04 Kg 673.11 Kg 56.09 lonjor
besi 12 - 0.89 Kg - Kg - lonjor
besi 8 257.36 0.39 Kg 100.37 Kg 8.36 lonjor
kolom besi 10 538.57 0.62 Kg 333.91 Kg 27.83 lonjor
besi 8 361.92 0.39 Kg 141.15 Kg 11.76 lonjor
ring balok besi 10 850.77 0.62 Kg 527.48 Kg 43.96 lonjor
besi 8 571.72 0.39 Kg 222.97 Kg 18.58 lonjor
meja beton besi 10 196.19 0.62 Kg 121.64 Kg 10.14 lonjor
Angkur besi 12 41.00 titik bawah
TOTAL BESI 8 464.49 KG 38.71 lonjor
TOTAL BESI 10 983.03 KG 81.92 lonjor
TOTAL BESI 12 - KG - lonjor
TOTAL BESI 13 673.11 KG 56.09 lonjor