Weekly test run for GD-9950 conducted,ok. Newly installed TACHOMETER is working properly.
ACID WASHING of Biocide cells started at 1730H
Backwashed dual media filter/online filtration unit/switched G9108 t0 G9109
JAN 10
1. Valve greasing of SW outlet valve Bypass E-9253B outlet valve/ E-9253A main valve
2.Electrician replaced temperature gauge at EDG -9950 with new spare.
3.Installation of industrial outlet at filtration unit
1. EESI Contr. installation of scaffoldings, power cable, fixture & bracket support/ installation & erection of steel post w/
2. Crane mobilization/demobilization for transfer of equipments/materials at BFO Jetty wharf area.
3. Mechanical Mtce. preparation activities for rehabilitation of DMF i.e. blinding and re-routing of RW flow going to FW
4. Behn Meyer Contr. started rehabilitation of C-9106C1 (DMF); started removal of the vessel's content.