Step 8: After the completion of 12th platform, the first platform fabrication will start.
Step 9: Cutting and welding edges should be cleaned and smoothen and should be painted.
Crane usage:
Upto 20 meter (5th platform) 50 ton crane will be used for erection.
Above 20 meter 250 crane will be used for the erection
PLATFORM ERECTION
ERECTION STEP:
Step 3: Angle bolt up in between reactor cleats and platform bottom side.
Step 5: Same method will be followed for all the platform erection
Step 7: After the completion of 12th platform, the first platform erection will start
Step 8: Inspections will be carried out after the completion of 12th platform and after the completion of
the inspection the scaffolding will be removed.
Step 11: For the height work Mobile communicator will be provided from SAFCO/Contractor will provide
and verification will do by the client safety, Authorized persons only handling the communicator.
2nd level
platform
MONKEY LADDER INSTALLATION:
Pre fabricated ladder lifting by crane and bolt up with reactor cleats.
Safety precaution will follow as per JSA
Field modification as per site condition and approved by the client
Bolt up verify by the client/contractor QC
For the emergency purpose can be use those ladder
3RD LEVEL PLATFORM ERECTION:
Step 2: The instrument line surrounding the reactor should be checked by the client.
Step 3: Toe plate will be spiral bend between the two platform (top and bottom)
Step 5: Spiral checker plate welding start from bottom to top at the marked location
Step 6: Checkers steps welding with inner and outer stringer at the degree point, toe plate
Step 6: Fabrication, welding, NDT and alignment inspection done as per ITP