PERIODE MINGGU KE : I
TANGGAL : 22 - 28 OKTOBER 2008
MINGGU : X ( SEPULUH )
PERIODE : ( 22 Desember - 27 Desember 2008 )
LOKASI : DESA PADANULOYO KEC. AMPANA TETE
No Pekerjaan Luas Sat Bobot Prestasi Bobot
Fisik Prestasi
A. KONSTRUKSI
1 Kantor Kima 1 BH 156 M2 2.30% 100% 2.30%
2 Rumah Jaga 1 BH 96 M2 1.66% 100% 1.66%
3 Pos Jaga 2 BH 6 M2 0.32% 100% 0.32%
4 Gudang Senjata 1 BH 60 M2 1.11% 100% 1.11%
5 Gudang Amunisi 1 BH 90 M2 2.84% 100% 2.84%
6 Dapur Kompi 1 BH 150 M2 1.61% 100% 1.61%
7 Barak Siaga 1 BH 325 M2 4.27% 100% 4.27%
8 Rumah Type H 70 (1KK) 5 BH 350 M2 6.45% 100% 6.45%
9 Rumah Type K 45 (4 KK) 19 BH 3,420 M2 66.45% 58% 38,48 %
87.02% 59,04 %
B. PRASARANA
1 Pematangan Tanah 64,417 M2 1.22% 100% 1,22%
2 Jalan Sirtu 7,468 M2 2.10% 100% 2.10%
3 Selokan U-60 597 M3 1.26% 100% 1.26%
4 Gorong-gorong 60 M' 0.44% 100% 0.44%
5 Inst. Listrik Luar 47 Tg 2.04% 100% 2.04%
6 Pas. Kabel Twisted 2 x 16 mm 410 M' 0.05% 100% 0.05%
7 BP Listrik 100 KVA 1.28% 100% 1.28%
8 Pas. Pipa PVC 2" 900 M' 0.08% 100% 0.08%
9 Pas. Pipa PVC 1" 582 M' 0.04% 100% 0.04%
10 Pas. Pipa PVC 3/4" 820 M' 0.04% 100% 0.04%
11 Tower Air 1 BH 0.62% 100% 0.62%
12 Pompa Air 10 Hp 1 Zet 0.38% 100% 0.38%
13 Lapangan Apel / Olahraga 12,000 M2 1.44% 100% 1.44%
14 Pagar Tembok Depan 342 M2 1.39% 100% 1.39%
15 Pagar Kawat 582 M' 0.60% 100% 0.60%
12.98% 12.98%
PRESTA
SA BOBOT
NO URAIAN PEKERJAAN VOLUME BOBOT SI
T PRESTA
FISIK
SI
1 2 3 4 5 6
1 2 3 4 5 6
PRESTA
SA BOBOT
NO URAIAN PEKERJAAN VOLUME BOBOT SI PRESTA
T FISIK
SI
1 2 3 4 5 6
1 2 3 4 5 6
MINGGU : X
DARI TANGGAL : 22 Desember - 27 Desember 2008
HARI KALENDER : ( 150 HARI)
PEKERJAAN : GUDANG SENJATA
LOKASI : PADAULOYO -AMPANA TETE
PEMBORONG : PT. CIPTALAKSA GRAHA PRIMA
1 2 3 4 5 6
VIII PEK.LANTAI
1 Tegel Keramik 30 x 30 63.00 m2 4.38% 100% 4.38%
2 Tegel Plint Keramik 10 x 30 61.60 m1 0.90% 100% 0.90%
3 Tegel Keramik Lantai KM 20 x 20 3.00 m2 0.15% 100% 0.15%
4 Tegel Keramik Dinding KM 20 x 25 12.25 m2 1.06% 100% 1.06%
5 Rabat Beton (tebal 10 cm) 40.00 m2 1.59% 100% 1.59%
8.07% 8.07%
IX PEK.ALAT PENGGANTUNG
1 Kunci Tanam 2 x 4.00 bh 0.46% 100% 0,46%
2 Kunci Pintu Kaca 3.20 bh 0.25% 100% 0.25%
3 Engsel Pintu Panil 12.00 bh 0.07% 100% 0.07%
4 Engsel Pintu Terali Besi 4.80 bh 0.11% 100% 0.11%
5 Grendel Pintu Terali Besi 3.20 bh 0.05% 100% 0.05%
6 Grendel Jendela 1.00 bh 0.01% 100% 0.01%
7 Engsel Jendela 2.00 bh 0.01% 100% 0.01%
8 Hak Angin 2.00 bh 0.02% 100% 0.02%
0.97% 0.97%
X PEK.PENGECATAN
1 Residu 337.50 m2 2.33% 100% 2.33%
2 Cat Kayu 44.12 m2 0.98% 100% 0.98%
3 Cat Dinding 340.43 m2 6.29% 100% 6.29%
4 Cat Plafond 109.00 m2 1.84% 100% 1.84%
5 Cat Besi 9.14 m2 0.19% 100% 0.19%
11.64% 11.64%
X PEK.SANITASI
1 Kloset Jongkok 1.00 bh 0.07% 100% 0.07%
2 Got Bangunan 53.00 m1 5.23% 100% 5.23%
3 Septicktank / Peresapan 1.00 bh 1.32% 100% 1.32%
6.62% 6.62%
XI PEK.PRASARANA
1 Titik Lampu 9.00 ttk 0.78% 100% 0.78%
2 Stop Kontak 1.00 ttk 0.08% 100% 0.08%
3 MCB 10 A 2.00 grup 0.06% 100% 0.06%
4 Jalan Masuk 5.000 m2 0.20% 100% 0.20%
5 Jembatan Masuk 0.120 m3 0.27% 100% 0.27%
0.00% 100% 0.00%
1.40% 1.40%
Jumlah 100.00% 100,00%
MINGGU : X
DARI TANGGAL : 22 Desember - 27 Desember 2008
HARI KALENDER : ( 150 HARI)
PEKERJAAN : GUDANG AMUNISI
LOKASI : PADAULOYO -AMPANA TETE
PEMBORONG : PT. CIPTALAKSA GRAHA PRIMA
MINGGU : I
DARI TANGGAL : 22 Oktober - 25 Oktober 2008
HARI KALENDER : ( 150 HARI)
PEKERJAAN : BARAK SIAGA
LOKASI : PADAULOYO -AMPANA TETE
PEMBORONG : PT. CIPTALAKSA GRAHA PRIMA
1 2 3 4 5 6
VI PEK.ATAP
1 Atap Sakura Roof 564.75 m2 8,08%
2 Bubung Sakura Roof 76.50 m1 0.51%
3 List / Topi Sakura Roof 41.00 m1 0.27%
4 Jurai Dalam 21.00 m1 0.33%
9.19%
VII PEK.LANTAI
1 Tegel Keramik 30 x 30 278.00 m2 4.99%
2 Tegel Plint Keramik 10 x 30 124.00 m1 0.47%
3 Tegel Keramik Lantai KM 20 x 20 52.00 m2 0.66%
4 Tegel Keramik Dinding KM 20 x 25 109.60 m2 2.44%
5 Rabat Beton (tebal 10 cm) 462.00 m2 4.76%
13.32%
VIII PEK.ALAT PENGGANTUNG
1 Kunci Tanam 2 x 8.00 bh 0.24%
2 Engsel Pintu 42.00 bh 0.06%
3 Grendel Pintu 12.00 bh 0.02%
4 Grendel Jendela 36.00 bh 0.05%
5 Engsel Jendela 72.00 bh 0.10%
6 Hak Angin 72.00 bh 0.14%
0.61%
IX PEK.PENGECATAN
1 Residu 1,374.40 m2 2.46%
2 Cat Kayu 180.90 m2 1.04%
3 Cat Dinding 1,006.52 m2 4.81%
4 Cat Plafond 485.00 m2 2.12%
10.43%
X PEK.SANITASI
1 Kloset Jongkok 8.00 bh 0.14%
2 Got Bangunan 138.00 m1 3.52%
3 Septicktank / Peresapan 8.00 bh 2.73%
6.40%
XI PEK.PRASARANA
1 Titik Lampu 35.00 ttk 0.79%
2 Stop Kontak 17.00 ttk 0.37%
3 MCB 10 A 3.00 grup 0.02%
4 Instalasi Air Dalam 12.00 ttk 0.24%
5 Jalan Masuk Paving Block 10.000 m2 0.10%
6 Jembatan Masuk 0.240 m3 0.14%
1.66%
Jumlah 100.00% 15,00%
MINGGU : X
DARI TANGGAL : 22 Desember - 27 Nopember 2008
HARI KALENDER : ( 150 HARI)
PEKERJAAN : RMH TYPE H.70
LOKASI : PADAULOYO -AMPANA TETE
PEMBORONG : PT. CIPTALAKSA GRAHA PRIMA
1 2 3 4 5 6
VII PEK.LANTAI
1 Tegel Keramik 30 x 30 69.65 m2 4.14% 4.14%
2 Tegel Plint Keramik 10 x 30 71.10 m1 0.89% 100% 0.89%
3 Tegel Keramik Lantai KM 20 x 20 5.62 m2 0.24% 100% 0.24%
4 Tegel Keramik Dinding KM 20 x 25 25.35 m2 1.87% 100% 1.87%
5 Rabat Beton (tebal 10 cm) 35.00 m2 1.19% 100% 1.19%
8.33% 8.33%
VIII PEK.ALAT PENGGANTUNG
1 Kunci Tanam 2 x 6.00 bh 0.59% 100% 0.59%
2 Engsel Pintu 18.00 bh 0.09% 100% 0.09%
3 Grendel Jendela 10.00 bh 0.05% 100% 0.05%
4 Engsel Jendela 20.00 bh 0.09% 100% 0.09%
5 Hak Angin 20.00 bh 0.13% 100% 0.13%
0.95% 0.95%
IX PEK.PENGECATAN
1 Residu 335.79 m2 1.99% 100% 1.99%
2 Cat Kayu 65.41 m2 1.25% 100% 1.25%
3 Cat Dinding 447.87 m2 7.09% 100% 7,09%
4 Cat Plafond 115.20 m2 1.67% 100% 1.67%
11.99% 11.99%
X PEK.SANITASI
1 Bak Cuci Piring 1.000 bh 0.15% 100% 0.15%
2 Kloset Jongkok 2.00 bh 0.12% 100% 0.12%
3 Got Bangunan 33.25 m1 2.81% 100% 2.81%
4 Septicktank / Peresapan 2.00 bh 2.26% 100% 2.26%
5.34% 5.34%
XI PEK.PRASARANA
1 Titik Lampu 12.00 ttk 0.89% 100% 0.89%
2 Stop Kontak 5.00 ttk 0.36% 100% 0.36%
3 MCB 10 A 2.00 grup 0.05% 100% 0.05%
4 Instalasi Air Dalam 4.00 ttk 0.26% 100% 0.26%
5 Jalan Masuk Paving Block 13.750 m2 0.47% 100% 0.47%
6 Jembatan Masuk 0.330 m3 0.64% 100% 0.64%
2.68% 2.68%
Jumlah 100.00% 100,00%
MINGGU : I
DARI TANGGAL : 22 Oktober - 25 Oktober 2008
HARI KALENDER : ( 150 HARI)
PEKERJAAN : RMH TYPE K.45
LOKASI : PADAULOYO -AMPANA TETE
PEMBORONG : PT. CIPTALAKSA GRAHA PRIMA
II PEK.TANAH
1 Pek.Galian Tanah 123.32 m3 0.68% 15% 0.10%
2 Urugan Tanah Pondasi 30.83 m3 0.05%
3 Urugan Tanah Bangunan 64.22 m3 1.06% 15% 0.15%
4 Urugan Pasir 27.52 m3 0.46% 15% 0.06%
2.25%
III PEK.PASANGAN
1 Pek.Pondasi 68.40 m3 5.70% 15% 0.85%
2 Pek.Beton Praktis 13.930 m3 6.57% 15% 0.98%
3 Pek.Kolom Utama 1.710 m3 0.96% 15% 0.14%
4 Cor Meja Dapur 0.860 m3 0.62% 15% 0.09%
5 Pas.Trasraam Bataco 56.28 m2 1.37% 15% 0.20%
6 Pas.Batu Bataco 536.12 m2 10.70% 15% 1.60%
7 Plesteran Trasraam 112.56 m2 0.98% 15% 0.14%
8 Plesteran Dinding 1,072.24 m2 8.69% 15% 1.30%
9 Roster 10 x 20 cm 1.680 m2 0.17% 15% 0.02%
10 List Profil Dinding 2 x 5 cm 128.00 m1 1.09% 15% 0.16%
36.84%
IV PEK.KUSEN/PINTU/JENDELA
1 Kusen Kayu Kelas I 1.60 m3 1.48% 15% 0.22%
2 Pintu Panil 20.00 m2 3.89% 15% 0.58%
3 Pintu KM/WC 4.00 bh 0.29% 15% 0.04%
4 Jendela Kayu+Kaca 180 x 50 cm 8.00 bh 0.27% 15% 0.04%
5 Jendela Kayu+Kaca 100 x 50 cm 40.00 bh 1.22% 15% 0.18%
7.15%
V PEK.KAYU
1 Kuda-kuda kayu kelas II 3.18 m3 2.64% 15% 0.39%
2 Gording Kayu Kelas II 1.87 m3 0.90% 15% 0.13%
3 Rangka Atap 354.10 m2 3.16% 15% 0.47%
4 Listplank Kelas I 123.00 m1 1.26% 15% 0.18%
5 Rangka Plafond 324.50 m2 4.51% 15% 0.67%
6 Plafond Tripleks 324.50 m2 2.61% 15% 0.39%
7 List Plafond Kayu 3 x 3 cm 525.00 m1 1.91% 15% 0.28%
17.00%
VI PEK.ATAP
1 Atap Sakura Roof 354.10 m2 6.19% 15% 0.92%
2 Bubung Sakura Roof 50.00 m1 0.41% 15% 0.06%
3 List / Topi Sakura Roof 62.00 m1 0.51% 15% 0.07%
4 Jurai Dalam 22.00 m1 0.42% 15% 0.06%
7.53%
2
1 2 3 4
VII PEK.LANTAI
1 Tegel Keramik 30 x 30 208.15 m2 4.57% 15% 0.68%
2 Tegel Plint Keramik 10 x 30 177.60 m1 0.82% 18% 0.14%
3 Tegel Keramik Lantai KM 20 x 20 12.00 m2 0.19% 15% 0.02%
4 Tegel Keramik Dinding KM 20 x 25 55.00 m2 1.50% 20% 0.22%
5 Rabat Beton (tebal 10 cm) 89.50 m2 1.13% 15% 0.16%
8.20%
MINGGU : X
DARI TANGGAL : 22 Desember - 27 Desember 2008
HARI KALENDER : ( 150 HARI)
PEKERJAAN : DAPUR KOMPI
LOKASI : PADAULOYO -AMPANA TETE
PEMBORONG : PT. CIPTALAKSA GRAHA PRIMA
MINGGU : I
DARI TANGGAL : 22 Oktober - 25 Oktober 2008
HARI KALENDER : ( 150 HARI)
PEKERJAAN : PRASARANA
LOKASI : PADAULOYO -AMPANA TETE
PEMBORONG : PT. CIPTALAKSA GRAHA PRIMA
A. KONSTRUKSI
1 Kantor Kima 1 BH 2.30%
2 Rumah Jaga 1 BH 1.66%
3 Pos Jaga 2 BH 0.32%
4 Gudang Senjata 1 BH 1.11%
5 Gudang Amunisi 1 BH 2.84%
6 Dapur Kompi 1 BH 1.61%
7 Barak Siaga 1 BH 4.27%
8 Rumah Type H 70 (1KK) 5 BH 6.45%
9 Rumah Type K 45 (4 KK) 19 BH 66.45%
87.02%
B. PRASARANA
1 Pematangan Tanah 64,417 M2 1.22%
2 Jalan Sirtu 7,468 M2 2.10%
3 Selokan U-60 597 M3 1.26%
4 Gorong-gorong 60 M' 0.44%
5 Inst. Listrik Luar 47 Tg 2.04%
6 Pas. Kabel Twisted 2 x 16 mm 410 M' 0.05%
7 BP Listrik 100 KVA 1.28%
8 Pas. Pipa PVC 2" 900 M' 0.08%
9 Pas. Pipa PVC 1" 582 M' 0.04%
10 Pas. Pipa PVC 3/4" 820 M' 0.04%
11 Tower Air 1 BH 0.62%
12 Pompa Air 10 Hp 1 Zet 0.38%
13 Lapangan Apel / Olahraga 12,000 M2 1.44%
14 Pagar Tembok Depan 342 M2 1.39%
15 Pagar Kawat 582 M' 0.60%
12.98%
JUMLAH 100.00%
A. KONSTRUKSI
1 Kantor Kima 1 BH 2.30%
2 Rumah Jaga 1 BH 1.66%
3 Pos Jaga 2 BH 0.32%
4 Gudang Senjata 1 BH 1.11%
5 Gudang Amunisi 1 BH 2.84%
Dapur Kompi 1 BH 1.61%
6 Barak Siaga 1 BH 4.27%
7 Rumah Type H 70 (1KK) 5 BH 6.45%
8 Rumah Type K 45 (4 KK) 19 BH 66.45%
87.02%
B. PRASARANA
1 Pematangan Tanah 64,417 M2 1.22%
2 Jalan Sirtu 7,468 M2 2.10%
3 Selokan U-60 597 M3 1.26%
4 Gorong-gorong 60 M' 0.44%
5 Inst. Listrik Luar 47 Tg 2.04%
6 Pas. Kabel Twisted 2 x 16 mm 410 M' 0.05%
7 BP Listrik 100 KVA 1.28%
8 Pas. Pipa PVC 2" 900 M' 0.08%
9 Pas. Pipa PVC 1" 582 M' 0.04%
10 Pas. Pipa PVC 3/4" 820 M' 0.04%
11 Tower Air 1 BH 0.62%
12 Pompa Air 10 Hp 1 Zet 0.38%
13 Lapangan Apel / Olahraga 12,000 M2 1.44%
Pagar Tembok Depan 342 M2 1.39%
Pagar Kawat 582 M' 0.60%
12.98%
JUMLAH 100.00%
Rencana Kemajuan Fisik Per Minggu 7.00% 19.50% 5.25% 6.50% 8.25%
Kumulatif Rencana Kemajuan Fisik 0.00% ### ### ### ### ###
EMBER 2008 DESEMBER 2008
4 1 2 3 4 5
7 MINGGU 23-Nov
1 SENIN 24-Nov
2 SELASA 25-Nov
3 RABU 26-Nov
6 4 KAMIS 27-Nov
5 JUMAT 28-Nov
6 SABTU 29-Nov
7 MINGGU 30-Nov
1 SENIN 1-Dec
2 SELASA 2-Dec
3 RABU 3-Dec
7 4 KAMIS 4-Dec
5 JUMAT 5-Dec
6 SABTU 6-Dec
7 MINGGU 7-Dec
1 SENIN 8-Dec
2 SELASA 9-Dec
3 RABU 10-Dec
8 4 KAMIS 11-Dec
5 JUMAT 12-Dec
6 SABTU 13-Dec
7 MINGGU 14-Dec
1 SENIN 15-Dec
2 SELASA 16-Dec
3 RABU 17-Dec
9 4 KAMIS 18-Dec
5 JUMAT 19-Dec
6 SABTU 20-Dec
7 MINGGU 21-Dec
1 SENIN 22-Dec
2 SELASA 23-Dec
3 RABU 24-Dec
10 4 KAMIS 25-Dec
5 JUMAT 26-Dec
6 SABTU 27-Dec
7 MINGGU 28-Dec
1 SENIN 29-Dec
11 2 SELASA 30-Dec
3 RABU 31-Dec