Anda di halaman 1dari 37

BHARAT NIRMAN

Cost Estimate for The Construction of Retaining Wall (3mtr. ht.)


for10mtr Length

BLOCK :- DANSAL Package No. :- JKO5-


DISTRICT :- JAMMU LENGTH OF ROAD :- 8.0 KM
Amount
S.No Description of Item Unit Quantity Rate in Rs.

1 Earth work excavation in structures (70%


hard soil , 20% soft rock & 10% hard rock) CuM 12.6 373.3 4703.58
2 PCC M-10 grade using (40-10)mm agg. CuM 1.44 3740 5385.6
3 R.R. masonary in 1:6 mix CuM 18.27 3258 59523.66
4 R.R. masonary dry. CuM 11.44 1978.03 22628.663
5
PCC M-15 coping using (20mm-10mm)agg. Cum 0.3 4089 1226.7
Back filing stones behind abutment, wing
6
wall, R/wall CuM 9 659 5931
Total 99399.203
Carriages
Cement Mt 0.26 558.65 145.249
sand Cum 6.28 576.42 3619.9364
bajree Cum 1.59 717.38 1140.6342
stone Cum 24.2 737.56 17849
Granular filling Cum 9 737.56 6638.058
Total 29392.878
G.total 128792.08

Say Rs. 12879 .00 Per R mtr.

Asstt. Executive Engineer Executive Engineer


PMGSY Sub- division -I PMGSY Division
Jammu Jammu
PROFORMA – B
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
PACKAGE No. JKO5- State:- J&K District : Jammu
Proposed Total Av.
Name No. of
S. Name of Road Type of Proposal Length (IN Cost of Bridge Estimated Cost /
of Bridge
No. Mtr) cost Rmt
Block
From To N/U Span Nos. (in Lacs) (in Lacs) (in Lacs)
1 Dansal Kathar Ponthal 60.00 1 191.35 191.35
60 Mtr.Span Single Lane
Through Truss Girder i) Road Safty and Traffic sign Boards 0.75
ii) Preparation of DPR
Motorable Bridge over 0.10
Gambhir Nallah in Km-4th iii) Load Tesing of Super Structures/ 1.96
RD 750 to RD 850. Soil Testing/ Design etc. (1.5% of 3.87
Bridge Cost)
Total 196.07

Total Estimated Cost of Package = 196.07 Lacs


N – New connectivity
U- Up gradation

Prepared by: Checked by:


Signature Signature
Name Name
Designation Asstt. Executive Engineer Designation Executive Engineer
PMGSY Sub Division PMGSY Division
Jammu Jammu

Scrutinized by: Technical Scrutiny done by:


Signature
Name
Designation Superintending Engineer Signature
PMGSY Circle Name Dr. S. K. Gupta
Jammu Designation HOD (Civil) & STA
PMGSY Jammu

Item
Cost per Km
in Lakhs
Pavement
26.778
CD
12.05
Total
38.828
General Abstract of Cost

S.No Particular's of Items Amount (Rs)

1 Sub-Structure 70.81

2 Super-Structure 98.21

3 Approaches/Wing Walls/Approach Slab 22.32

Total 191.35

4 Soil testing (L.S) 1.00

5 Add for Design of Bridge @ 1.5% of item 1,2,3 2.87

Add for survey, setting out and preperation of DPR


6 0.10
etc

Add PMGSY Logo, Sign board and inauguration/


7 0.75
foundation stone etc.

8 Total 4.72

9 G. Total 196.07
Proforma C (For Long Span Brdiges
PRADHAN MANTRI GRAM SADAK YOJANA ( PMGSY)
CHECK LIST FOR P.I.U. & S.T.A.
( For Indvidual Bridge works with length more than15 m )
(To be filled by PIU)

1. Location :- State: J&K District : Jammu Block :

2. Package No:- JK05

3. Name of the Road: From Kathar To Ponthal

4. Total Length of Road (Kms) - 8.000

5. Name of Proposed Bridge 60.00 mtr span single lane steel trussed motorable bridge on G
Nallah on Kathar to Ponthal road.

6. Length of Proposed Bridge (Excluding Approaches) 60.00

7. Width of Bridge in m: 4.250Mtr. (Crriage way)

8. Through Route/ Link Route Nos as per Core Network.:


(i) Is the road a part of core network :
if Yes, Sl no. of road CN-I : Sl no. of road CN -VI :
If Yes Through Route/ Link Route No. T- or L-

(ii) Name of the benefitted Habitation (s) (to be cross Sr.N Name of Village Population
checked with CN-VI) with population 1 KATHAR

2 PONTHAL

Total 0
9. Whether the Road proposal was sanctioned earlier : Yes / No

(i) If Yes, please mention the Phase, MoRD Sanction letter No and Date of sanction
Phase : XIIth MoRD Sanction No.

Length 8.00 Chainage : From To:

(ii) Cost of the Road work sanctioned (For Stage-Ist): 1750.46 Lacs
(For Stage-II):
Total:
(iii) Whether any CD/ Causeway was Sanctioned at or nearby location with the road
proposal and whether the same was constructed or not (if yes, the details thereof with chainage: NO
(iv) Whether the roadwork has been completed or in progress and likely date of completion:

(v) If not, How the connectivity and movement of traffic was ensured:

(vi) Reasons for not proposing the Bridge at the time of submission of Road proposal:
Because of Long Span Bridge, the Proposal was not incorporated in Stage-Ist.

10. Estimated Cost (Rs. In Lakhs) Item Total Cost (` in Lacs)

Approaches 22.32

Bridge Super
98.21
Structure

Bridge Sub
Structure / 70.81
Foundation
Others 4.72
Total 196.07
MoRD Share- 176.46 Lacs State Share 19.60 Lacs
(MoRD share and State share to be calculated as per the norms of MoRD/NRRDA)
11. INDEX MAP (not to scale ) : Attached
saperately
MDR-42
MSH-6

Kathar

60.00 mtr span single lane steel trussed motorable


bridge on Gambir Nallah on Kathar to Ponthal road.

12 Typical Sketch of proposed bridge showing schematic arrangement of span- Atttached as


submitted by the Consultant (copy enclosed)

13. Typical Photographs of proposed Bridge Location.

PHOTO
PHOTO

PHOTO (ii) U/

PHOTO

(iii) D/

14. Type of Proposed Bridge :


(I) Submersible Structures like Vented Causeway or Submersible Bridge
(ii) Box Culvert
(iii) Bridge With RCC Piers and Abutments-- YES

a. Type of foundation Open / Raft /Well / Pile / Any other Open


b. Bearing Capacity at Foundation Level

c. Arrangement of Spans 60 Mtr. Span


Total Span 60 Mtr No. of Vents 1 Clear Span of Vent

d. Critical Levels Road top level (RTL) 100.00 mtrs.


Nala Bed Level (NBL) 87.500 mtrs.
High flood level (HFL) 92.00 mtrs.
Foundation level (FL) 85.00 mtrs.
Ht. of bridge h= (RTL-NBL) 12.50 mtrs.
Ht. of bridge H=(RTL-FL) 15.00 mtrs.

e. Catchment Area
(Catchment area should be based on hydrological survey or from toposheet)
Catchment area served Hect
Heaviest Rainfall mm/hr.
Basis of Design Discharge
Waterway required Sq.M
Waterway provided Sq.M

f. Scour Depth (m)

15. Cost Details Cost (in Lacs)


A. General Costs
Cost of Preparation of DPR (Limited to 1 % of Total cost of Bridge) 0.10
B. Brdige Components

Description of Components units Quantity Cost (in Lacs)

Foundations/ sub structure

Earth work Cum 1584.03 6.01

M10 in foundation Cum 31.82 1.19

RCC M30 Cum 493.81 33.82

HYSD bar reinforcement MT 36.55 18.13

Carriage:-
Cement MT 285.91 1.59

sand Cum 295.34 1.70

Aggregate Cum 590.68 4.23

Steel MT 24.662 0.14

Super Structure
M30 in Deck slab, Kerb Cum 114.35 7.83

HYSD bar reinforcement MT 11.4 8.51

Pipe Railling Rmt 120 1.66

expansion Joints. Rmt 12.75 0.23

RSJ Steel for Composite Girders MT 91.2 76.49

Drainage Spoutes 100 mm dia. GI Pipes No. 24 0.31


Bearings- Elastomeric or Roller Bearing/ Rocker) No. 8 4.00

Carriage:-
Cement MT 85.90 0.47

sand Cum 85.90 0.49

Aggregate Cum 171.80 1.23

Steel MT 171.556 0.99

Approaches/ wing wall


Stone Masonry Retaining wall 4.0 mtr Ht. Rmt 20.00 2.58

Stone Masonry Retaining wall 5.0 mtr Ht. Rmt 24.00 9.88

Gabion Wall (Stud) No. 36.00 6.92

Embankment Filling from Barrow Pits Cum 374.85 1.10

Approach slab 1.84

E. Road Logo, other Road Furniture 0.75

Others 3.87

Total Cost of the Project (Rs) 196.07

16. Five Year Routine Maintenance


Year Cost in lakhs % Cost
I
II
III
IV
V
Total Maintenance Cost

17. Whether the Bridge has Geometrics as per latest Circular of NRRDA.:
DO.#P-17035/1/2007-Tech. 30th September, 2010.

18. Whether the Cost Etimates are as per standerd data analysis and S.S.R.
19. Sources and the Lead distances of Materials are as under
Lead
Material Source Distance Material Source Lead Distance
(Km)
Earth SAMBA 50 Cement JAMMU 60.00

GSB SAMBA 50 Emulsion JAMMU 60.00

Aggregate SAMBA 50 Bitumen JAMMU 60.00

Sand SAMBA 50 Steel JAMMU 60.00


This is to Certified that,
1. Span details of bridge tallies with DPR & data uploaded on omms.nic.in. & there is no deviation.
2. Information furnished herewith is true to the best of my knowledge.
3. Total cost of the project, State share & MoRD share worked out by PIU is justified.
4. The proposal of bridge is missing bridge proposal on sanctioned road & in the same stretch as it
sanctioend in previous phase under PMGSY.

Checked & recom


DPR Prepared By DPR Checked by
(Name & Sign) (Name & Sign) (Name & Sig

Assitant Executive Engineer Executive Engineer

Counter Signatures of
Co-ordinator STA :
To be filled by State Technical Agency
Name of the STA :
Name of Road : Jogwan To Neeli Nallah

Name of Bridge : 100 Mtr.Span Single Lane Through Truss Girder Motorable Bridge over Kanah Nallah in Km
750 to RD 850

20. Is the proposed work is for CD/Causeway of any length or brigde with span excluding approaches less than 15m.
STAs need not clear such proposals

21 Is the Proposal entered on the OMMS :


(Data entries to be verified by STA before Clicking the Propopsal)
a. Span of Bridge on web: b. Span of Bridge As per DPR

* Span of bridge: C/C distance along the centre line of the bridge between inner faces of dirt walls.

c. Whether type of foundation & resting strata as per survey report justified to be safe

d. Whether Hydraulic design is checked & found to be adequete as per site requirements

e. Whether RCC designs are checked and found to be economical & safe.

f. Whether the provisions made by PIU are sufficient & essentia from economy point of view.

22 If the Proposal is for a Bridge for which Road was already Sanctioned
If Yes, Have you verified and satisfied yourself with all the items listed at Sr. No. 7, by PIU
Have you satisfied yourself that the road is a part of Core Network
23 Are you satisfied with the following
Engineering Surveys (L section, X sections must be verified)
Soil/ Material Investigation
Hydraulic Studies.
( Catchment for structures to be verified from topo sheet. Location and requirement of structures to be verified from
L section and catchment area to be marked on Topo Sheet Copy )
24 Is the design of the following elements as per relevant I S/ IRC codes

Foundations / Abutments / Piers / Deck Slab / Wing Walls

25 Does the Estimation Conform to Standard Rate Analysis and SoR generated for the
current Phase for PMGSY works and a copy of SoR provided to STA

26 Does the proposal have provisions for


PMGSY Logo Sign Boards and Information Board

27 Whether STA and Superintendent Engineer have visited the site? If Yes, Date of Visit :

Kindly indicate whether the program of visit was informed to NRRDA for prior approval ?
28 Secific Remarks, if any, by STA
( Specific remarks of STA about the overall Bridge Project are necessary on each DPR)

29. Certificates:
Certified that the proposal of bridge is checked & found to be it is missing bridge on sanctioned roa
the same stretch as it was sanctioend in previous phase under PMGSY.

Certified that the Design and Estimation for the Proposed bridge are based on the latest Circular o
NRRDA:vide DO.letter #P-17035/1/2007-Tech. 30th September, 2010.

Certified that the Design and Estimation for the Proposed bridge are based on the data and SSR pro
PIU Engineers . The Proposal after final Correction is entered on the OMMS.The Propasal may be co
for clearance.

Technical Scrutiny at STA done by:


Signature Signature Co-ordinator STA:
Name Name Signature
Date Date Name
Date
C (For Long Span Brdiges only)
PMGSY)

ore than15 m )

Dansal

Ponthal

ed motorable bridge on Gambir

YES / NO

0 5 5

Population

:
Date

ad
with chainage: NO
In Progress

Cost per m

0.22

0.98

0.71

0.05
1.96
Lacs
ms of MoRD/NRRDA)

Ponthal

t of span- Atttached as

RD 3/935-3/995
RD 3/935-3/995

(ii) U/S of Bridge Site

(iii) D/S of Bridge Site

Open
T/Sqm

ar Span of Vent
r from toposheet)

Cost (in Lacs)

0.10

Grade of
Cost (in Lacs)
Concrete

6.01

1.19 M-10

33.82 M-30

18.13

1.59

1.70

4.23

0.14

7.83 M30

8.51

1.66

0.23

76.49

0.31
4.00

0.47

0.49

1.23

0.99

2.58

9.88

6.92

1.10

1.84

0.75

3.87

196.07 1.96

% Cost

YES

YES

Lead Distance

60.00

60.00

60.00

60.00
the same stretch as it was

Checked & recommended

(Name & Sign)

Suprintending Engineer
over Kanah Nallah in Km-4th RD

YES / NO
approaches less than 15m.

Yes/ No
100.00
Mtr.

aces of dirt walls.

YES / NO

YES / NO

YES / NO

oint of view. YES / NO

PIU Yes / No
Yes / No

Yes / No
Yes / No
Yes / No
f structures to be verified from
Wing Walls Yes / No
Yes / No

Yes / No
Visit :

ridge on sanctioned road & in

on the latest Circular of

on the data and SSR provided by


The Propasal may be considered

Co-ordinator STA:
Signature
Name
60.00 mtr span single lane steel trussed motorable bridge on Gambir Nallah on Kathar
to Ponthal road RD 3/935-3/995

PART-A (Sub-Structure)
Amount (in
S.No Description Lacs)
1
Earth Work in excavation for structure as per Drawing and Technical specification clause
305.1 including setting out construction of shoring and bracing removal of stumps and
other deleterious material and disposal up to a leads of 50 metre. Dressing of sides and
bottoms and back filling in trenches with excavated suitable material.(With Side slope
1H : 2V)

Ordinary Soil 60%,Ordinary Rock 25%,Hard Rock 15%.


Left Abutment and Right Abutment
[(13.50+9.50)/2+(6.50+10.50)/2] x 10.20 x 7.80 =1584.03
Total = 1584.03 m3
O/S 60%= 950.41 m3@336/ m3 3.19
O/R 25% = 396.00 m @353/ m
3 3
1.39
H/R 15% = 237.60 m3@602/ m3 1.43
2
Providing and laying of cement concrete in open foundation complete as per drawing and
technical specification clause 802,803,1202 and 1203 P.C.C grade M-10 nominal mix
(using 40mm/20mm down size aggregate)
Left & Right Abutments = 31.82m3 (as per abstract sheet no 8)
1.19
Total= 31.82 m3@3740/ m3
3
Providing and laying / reinforced cement concrete in open foundation complete as per
drawing and technical specification clause 802,803,1202and 1203 PCC grade M-30
mix(using 20mmsize aggregate)

Left & Right Abutments = 493.81m3


Total = 493.81m3 @ 6850/m3 33.82
4
Supplying ,fitting and placing HYSD bar reinforcement(Fe 415) in substructure complete
as per drawing and technical specification clauses 1002,1005,1010 and 1202.

Left & Right Abutments =36.55 MT


Total= 36.55 MT@73526/MT 18.13
5 Metallic Bearing Rocker and Roller Steel (capacity 80 T)
Qty = 8Nos@50000/No 4.00
6
Loading , Unloading and Haulage of material
A)Haulage of Cement
Quantity= 285.91MT @ 558.65/MT 1.59
B)Carriage of Sand
Quantity=295.34m3 @/576.42cum 1.70
C)Carriage of Aggregate to the site
Quantity=590.68m3 @/717.38cum 4.23
D)Carriage of Steel
Quantity=24.662 MT@580.65/MT 0.14
Total 70.81
Part-B (Superstructure)
S.No Description Amount
1
Providing and laying / reinforced cement concrete in open foundation complete as per
drawing and technical specification clause 802,803,1202and 1203 PCC grade M-30
mix(using 20mmsize aggregate)

Dech Slab + Kerb = 114.35m3


Total = 114.35m3@ 6850/m3 7.83
2
Supplying ,fitting and placing HYSD bar reinforcement(Fe 415) in substructure complete
as per drawing and technical specification clauses 1002,1005,1010 and 1202.

Dech Slab + Kerb = 11.40MT


Total = 11.40 MT@74715/MT 8.51
3
Providing and fixing in position pipe railing consisting of IS rolled steel joints posts
designation ISNB 100(100x75) at 1.0 m interval and 3 rolls of 40mm dia steel
pipes(light)including fixing position on bridge deck complete as per drawing and technical
specifications clause1208.2
40 mm dia M.S Pipe railing 120 rmt@1385/rmt 1.66
4 Providing and laying a buried expansion joint covered with 12 mm thick,200mmwide
galvanised weld able structural steel plate as per IS:2062, place symmetrical to central
line of the joint, resting freely over the top surface of the deck concrete, welding of 8 mm
dia ,100mm long galvanised nails spaced 300mm C/C along the central line of the plate as
per technical specification clauses 1207.2.3

3x4.250= 12.75 rmt@1837/RMt 0.23


5
A) Providing steel R.S.J.S/Built up steel section including cutting , welding/riveting,
hosting ,fixing in position for composite girders with shear connectors complete with
painting as per drawing and technical specification clause 12.6

Plate girder or Other steel member (Structural Steel) 91.20 76.49


MT @ 83880/MT
6 Drainage supports complete as per drawing and technical specification clause 24 Nos 0.31
@1306/No
7 Loading and Unloading and haulage
A)Haulage of cement
Quantity = 85.9MT @558.65 /MT 0.47
B)Carriage of sand
Quantity = 85.9cum @ 576.42/cum 0.49
C)Carriage of aggregate to the site
Quantity = 171.80cum @ 717.38/cum 1.23
D)Carriage of steel
Quantity = 171.556 MT @ 580.65 /MT 0.99
Total 98.21
G.Total PART (A+B) 169.03
BHARAT NIRMAN
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
ABSTRACT OF COST
NAME OF ROAD :- KATHAR TO PONTHAL
BLOCK :- Dansal PACKAGE No. :- JKO5-

DISTRICT :- JAMMU Span of Bridge :-60.00 Mt


Amount
S.NO Items Quantity Unit Rate (Rs.
inLacs)

1 Stone Masonry Retaining wall 3.00 ht 20.00 Rmt. 12879.21 2.58

2 Stone Masonry Retaining wall 5.00 ht 24.00 Rmt. 41174.24 9.88

4 Gabions Studs 36.00 nos. 19229.32 6.92

5 Embankment Filling From Borrow Pits 374.85 cum 293.00 1.10

5 Approach Slab 1.84

Total 22.32

Asstt. Executive Engineer Executive Engineer


PMGSY Sub- division -II PMGSY Division
Jammu Jammu
BHARAT NIRMAN
CARRIAGE OF MATERIAL BY MECHNICAL TRANSPORT CHART
NAME OF ROAD :- KATHAR TO PONTHAL
BLOCK :- Dansal PACKAGE No :-
DISTRICT :- JAMMU LENGTH OF ROAD :- 8.00 Kms.

Total
Grand
Distance (in Total (in Haulage as
Haulage Total
Km) R.s) per
(in R.s)
Distance

Density
Un For
S.No Items Loading For
loading For BT @ Kacha
Gravel @
R.s @ R.s B =
B.T Gravel Kacha Rs. (f
4.49/mt 10.86/m
A = (d+e) 5.40/mt [g+h+i] ) (A+B)
Km t Km
Km

g=ax h =b x i=cx
a b c d e f
4.49 5.40 10.86
1 Sand 50.00 1.50 6.50 50.00 11.00 61.00 1.70 224.5 8.1 70.59 515.42 576.42
Stone
2 50.00 1.50 6.50 100.00 11.00 111.00 2.00 224.5 8.1 70.59 606.38 717.38
Aggregate
3 Stone 60.00 1.50 6.50 100.00 11.00 111.00 1.80 269.4 8.1 70.59 626.56 737.56
4 Cement 60.00 1.50 2.50 127.00 127.00 254.00 1.00 269.4 8.1 27.15 304.65 558.65
5 Steel 60.00 1.50 2.50 138.00 138.00 276.00 1.00 269.4 8.1 27.15 304.65 580.65
6 Bitumen 60.00 1.50 2.50 149.00 135.00 284.00 1.00 269.4 8.1 27.15 304.65 588.65
7 GSB 50.00 1.50 6.50 100.00 11.00 111.00 2.00 224.5 8.1 70.59 606.38 717.38

NP3 1000mm
8 125.00 1.50 2.50 84.00 379.00 463.00 0.88 561.25 8.1 27.15 524.92 987.92
dia. H/P

Asstt. Executive Engineer Executive Engineer


PMGSY Sub.Divn. -1 PMGSY Division
Jammu Jammu
BHARAT NIRMAN
Cost Estimate for The Stone Masonry Construction of Retaining Wall (5mtr. ht.)
for 39.60mtr Length
NAME OF ROAD :- KATHAR TO PONTHAL
BLOCK :- DANSAL PACKAGE No. :-JK05-
DISTRICT :- JAMMU Span of Bridge :- 60.00 Mt

S.No Description of Item Unit Quantity

Earth work excavation in structures for all


1
kind of soil
CuM 172.500 332 57270.00
2 PCC M-10 grade using (40-10)mm agg. CuM 18.400 3740.00 68816.00
3 PCC M-20 Coping. Cum 1.180 4672.00 5512.96
4 R.R. masonary in 1:6 mix cement mortar CuM 277.200 2984.53 827311.72
5 R.R. masonary dry. CuM 100.560 1978.03 198910.70
Back filing stones behind abutment, wing
6
wall, R/wall
CuM 83.160 659.00 54802.44
Total 1212623.81
7 Carriages
Sand CuM 100.29 576.4257807.73
Stone Aggregate CuM 17.62 717.3812641.67
Cement MT 30.02 558.6516772.01
Stone CuM 460.92 330654.79
717.38
Total 417876.21
Grand Total 1630500.02
Say Rs. 41174.24 Per R mtr.

Asstt. Executive Engineer Executive Engineer


PMGSY Sub- division -II PMGSY Division
Akhnoor Jammu
BHARAT NIRMAN
Cost Estimate for the Filling Behind the Approaches of Bridge
NAME OF ROAD :- KATHAR TO PONTHAL
BLOCK :- DANSAL PACKAGE No. :- JKO5-
DISTRICT :- JAMMU Span of Bridge :- 60.00 Mt
S. No. Description of Item Unit Quantity
1 Embankment Filling From Borrow Pits CuM 374.85 293 109831.05
109831.05

Grand Total 109831.05

Asstt. Executive Engineer Executive Engineer


PMGSY Sub- division -II PMGSY Division
Jammu Jammu
BHARAT NIRMAN
Cost Estimate for The Construction of 2 No Stud for 12.00mtr length Each
NAME OF ROAD :- KATHAR TO PONTHAL
BLOCK :- DANSAL PACKAGE No. :- JKO5-
DISTRICT :- JAMMU Span of Bridge :- 60.00 Mt

S. No. Description of Item Unit Quantity


(in
1 Earth work excavation in structures CuM 172.80 363.2 62760.96

2 Filling of stones into GI wire crates. CuM 311.04 1719.00 534677.76


597438.72
3 Carriages

Stone CuM 311.04 717.38 223133.88


Gabion MT 2.16 1111.33 2400.47
Total 225534.35
Grand Total 822973.07
22860.36 Per Crate

Asstt. Executive Engineer Executive Engineer


PMGSY Sub- division -II PMGSY Division
Jammu Jammu
BHARAT NIRMAN
COST ESTIMATE FOR TRAFFIC SIGNS AND ROAD SAFFETY MEASURES
NAME OF ROAD :- KATHAR TO PONTHAL
BLOCK :- DANSAL PACKAGE No. :- JKO5-
DISTRICT :- JAMMU Span of Bridge :- 60.00 Mt
S. Rate Amount
Item of works No. Quantity Unit
No (Rs.) (in Lacs )
Construction of TBM (4No. Per KM.) as per
1 drawing and technical specification Clause 1 1 no. 437 0.004
1602.4
2 Preperation of dpr 1 no. 5000 0.05
Total 0.054

3 (ii) 60cm equilateral triangle


Speed limit 2 2
Right / Lift hand curve / S- Curve 0 0
School / Hospetal / Village Area/Bridge 2 2
4
Men at work 0
Horn 0 0
Total 4 each 1492 0.060
5 PMGSY Logo Boards 1
PMGSY Informatory Boards 1
PMGSY Citizen Information Boards 1
PMGSY Maintenance Information Boards 0
Total 3 14451 0.434
Laying of Foundation stone and Inaguration of
Bridge
2 2 10000 20000 0.200

Total 0.75
BHARAT NIRMAN
Cost Estimate for The Construction of Approach Slab on Both Side

NAME OF ROAD :- KATHAR TO PONTHAL


BLOCK :- DANSAL PACKAGE No. Rate
:- JKO5-
DISTRICT :- JAMMU Span of Bridge :- 60.00 Amount
Mt
S.N
Description of Item Unit Quantity
o
2 PCC M-10 grade using (40-10)mm agg. CuM 5.360 3740.00 (in Rs.)
20046.40
(in
3 PCC M-30 Slab Cum 9.100 6850.00
Rs.) 62335.00
4 Hysd Steel MT 1.139 74715.00 85100.39

Total 167481.79

7 Carriages

Sand CuM 6.51 576.42 3750.78


Stone Aggregate CuM 13.01 717.38 9335.98
Cement MT 5.27 558.65 2946.43
Steel CuM 1.14 580.65 661.36

Total 16694.56

Grand Total 184176.34

Say 1.84 Lacs


Asstt. Executive Engineer Executive Engineer
PMGSY Sub- division -II PMGSY Division
Akhnoor Jammu

Anda mungkin juga menyukai