RENCANA ANGGARAN BIAYA

PROYEK : HOTEL. BANGUNAN 1 ( L=113.46M2)


LOKASI : DESA PENYABANGAN, KEC.GEROKGAK, KAB.BULELENG A Biasa
OWNER : 14

NO URAIAN VOLUME SAT HARGA SAT JUMLAH SAT JUMLAH


(Rp) (Rp) (Rp)
I PEKERJAAN PERSIAPAN
1 Pembersihan lapangan 113.460 m2 5,100.00 578,646.00
2 Pengukuran & Bowplank 80.000 m 47,559.10 3,804,728.00
4,383,374.00
II PEKERJAAN TANAH & PASIR
1 Galian pondasi menerus 26.020 m3 70,025.00 1,822,050.50
3 Urugan kembali tanah pondasi 12.773 m3 110,500.00 1,411,416.50
3 Urugan pasir bawah pondasi (t= 5 cm) 9.301 m3 16,300.00 151,606.30
3,385,073.30
III PEKERJAAN BETON
1 Beton K175sloof struktur 1 ; 2 ; 3 (15/25) 2.991 m3 2,883,435.50 8,624,355.58
2 Beton K175 kolom struktur 1 ; 3 ;5(15/15) 2.911 m3 2,883,435.50 8,393,680.74
3 Beton K225 balok struktur 1 ; 2 ; 3(15/25) 2.991 m3 2,883,435.50 8,624,355.58
4 Rabatan (t=5cm) 5.673 m3 594,413.00 3,372,104.95
29,014,496.85
IV PEKERJAAN PASANGAN
1 Pasangan pondasi batu kali 1:5 21.250 m3 527,340.00 11,205,975.00
2 Pasangan batu kosong 10.820 m3 249,015.00 2,694,342.30
3 Pasangan bata 1:5 21.780 m3 1,033,730.00 22,514,639.40
36,414,956.70
V PEKERJAAN KAP KAYU
1 Pek. Kuda-Kuda KAYU + Genteng 112.000 m2 547,106.85 61,275,967.20
2 Pek. List plank 41.000 m 57,716.12 2,366,360.92
63,642,328.12
VI PEKERJAAN KOSEN, PINTU
1 Kosen pintu + jendela 15.700 m 150,000.00 2,355,000.00
2 Daun pintu panel 4.000 bh 1,000,000.00 4,000,000.00
3 Daun jendela panel+kaca 5mm 4.000 bh 450,000.00 1,800,000.00
VII PEKERJAAN LANTAI 8,155,000.00
1 Keramik Lantai 60cm x 60cm 113.456 m2 208,211.00 23,622,787.22
2 Keramik dingding KM 10cm x 20cm 26.400 m2 90,235.00 2,382,204.00
26,004,991.22
VIIIPEKERJAAN PLESTERAN
1 Plesteran 1:5 290.220 m2 47,811.60 13,875,882.55
2 Acian 290.220 m2 22,532.00 6,539,237.04
20,415,119.59
IX PEKERJAAN PLAFOND
1 Pekerjaan Plafond 90.480 m2 125,330.50 11,339,903.64
2 Pekerjaan List Plafond 82.100 m 15,000.00 1,231,500.00
12,571,403.64
X PEKERJAAN PENGUNCI DAN PENGGANTUNG
1 Engsel Pintu + jendela 12.000 bh 17,000.00 204,000.00
2 Kait angin 8.000 bh 12,000.00 96,000.00
3 Slot pintu 4.000 bh 120,000.00 480,000.00
780,000.00
XI PEKERJAAN SANITASI
1 Pasangan Pipa 4" 15.000 m 166,762.00 2,501,430.00
2 Pasangan Pipa 3" 15.000 m 166,762.00 2,501,430.00
3 Closet duduk 2.000 bh 1,250,000.00 2,500,000.00
4 Kran air 4.000 bh 125,000.00 500,000.00
5 Pasangan floordrain 2.000 bh 20,000.00 40,000.00
8,042,860.00
XII PEKERJAAN FINISHING
1 Cat kosen & pintu 25.920 m2 26,737.50 693,036.00
2 Cat Dingding 290.220 `m2 20,857.00 6,053,118.54
3 Cat Plafond 90.480 m2 16,378.00 1,481,881.44
8,228,035.98
XIIIPEKERJAAN INSTALASI LISTRIK
1 Pemasangan instalasi 12.000 titik 200,000.00 2,400,000.00
2 Pemasangan PLN 2200 WATT 1.000 unit 3,500,000.00 3,500,000.00
5,900,000.00
Total Anggaran Biaya 226,937,639.40
Dibulatkan 226,930,000.00

Singaraja, AGUSTUS 2015


Mengetahui :
RENCANA ANGGARAN BIAYA

PROYEK : TOKO
ALAMAT : JALAN PULAU MENJANGAN , BANYUNING A Biasa
OWNER : IMAM SYAFI'I 14

NO URAIAN VOLUME SAT HARGA SAT JUMLAH SAT JUMLAH


(Rp) (Rp) (Rp)
I PEKERJAAN PERSIAPAN
1 Pembersihan lapangan 67.000 m2 5,100.00 341,700.00
2 Pengukuran & Bowplank 32.000 m 41,397.50 1,324,720.00
1,666,420.00
II PEKERJAAN TANAH & PASIR
1 Galian pondasi menerus 16.100 m3 23,812.50 383,381.25
2 Galian pondasi telapak 1.100 m3 53,250.00 58,575.00
3 Urugan kembali tanah pondasi 2.100 m3 8,025.00 16,852.50
4 Urugan pasir bawah pondasi (t= 5 cm) 1.700 m3 81,765.00 139,000.50
597,809.25
III PEKERJAAN BETON
1 Beton K175 foot plat/ plat 1; 2 ; 3 1.345 m3 3,164,189.50 4,255,834.88
2 Beton K175sloof struktur 1 ; 2 ; 3 (15/25) 1.910 m3 3,164,189.50 6,043,601.95
4 Beton K175 kolom struktur 1 ; 3 ;5(15/15) 1.789 m3 3,016,762.00 5,396,987.22
5 Beton K225 balok struktur 1 ; 2 ; 3(15/25) 2.120 m3 3,164,189.50 6,708,081.74
6 Rabatan (t=5cm) 3.210 m3 749,547.00 2,406,045.87
24,810,551.65
IV PEKERJAAN PASANGAN
1 Pasangan pondasi batu kali 1:5 12.120 m3 474,519.00 5,751,170.28
2 Pasangan batu kosong 3.800 m3 199,507.50 758,128.50
3 Pasangan bata 1:5 27.000 m3 830,874.50 22,433,611.50
28,942,910.28
V PEKERJAAN KAP BAJA
1 Pek. Kuda-Kuda Baja Ringan + genteng 64.000 m2 265,250.00 16,976,000.00
2 Pek. List plank 31.000 m 82,040.72 2,543,262.32
19,519,262.32
VI PEKERJAAN KOSEN, PINTU
1 Kosen pintu + jendela 14.100 m 150,000.00 2,115,000.00
2 Daun pintu panel 3.000 bh 1,000,000.00 3,000,000.00
3 Daun jendela panel 6.000 bh 450,000.00 2,700,000.00
VII PEKERJAAN LANTAI 7,815,000.00
1 Keramik Lantai 50cm x 50cm 55.000 m2 118,211.00 6,501,605.00
2 Keramik dingding KM 10cm x 20cm 13.000 m2 86,235.00 1,121,055.00
7,622,660.00
VIIIPEKERJAAN PLESTERAN
1 Plesteran 1:5 97.750 m2 27,987.50 2,735,778.13
2 Acian 47.230 m2 12,633.50 596,680.21
3,332,458.33
IX PEKERJAAN PLAFOND
1 Pekerjaan Plafond 160.870 m2 85,175.00 13,702,102.25
2 Pekerjaan List Plafond 78.000 m 15,000.00 1,170,000.00
14,872,102.25
X PEKERJAAN PENGUNCI DAN PENGGANTUNG
1 Engsel Pintu + jendela 36.000 bh 10,000.00 360,000.00
2 Kait angin 24.000 bh 7,500.00 180,000.00
3 Slot pintu 6.000 bh 65,000.00 390,000.00
930,000.00
XI PEKERJAAN SANITASI
1 Pasangan Pipa 4" 7.000 m 46,000.00 322,000.00
2 Pasangan Pipa 3" 12.000 m 44,000.00 528,000.00
3 Closet jongkok 1.000 bh 145,000.00 145,000.00
4 Kran air 4.000 bh 125,000.00 500,000.00
5 Pasangan floordrain 3.000 bh 20,000.00 60,000.00
1,555,000.00
XII PEKERJAAN FINISHING
1 Cat kosen & pintu 70.000 m2 15,000.00 1,050,000.00
2 Cat Dingding 88.000 `m2 9,000.00 792,000.00
3 Cat Plafond 87.000 m2 9,000.00 783,000.00
2,625,000.00
XIIIPEKERJAAN INSTALASI LISTRIK
1 Pemasangan instalasi 20.000 titik 125,000.00 2,500,000.00
2 Pemasangan PLN 2200 WATT 1.000 unit 3,500,000.00 3,500,000.00
6,000,000.00
Total Anggaran Biaya 120,289,174.08
Dibulatkan 120,290,000.00

Singaraja, JUNI 2015


Mengetahui :
IMAM SYAFI'I

RENCANA ANGGARAN BIAYA

PROYEK : HOTEL. BANGUNAN 1 ( L=113.46M2)


LOKASI : DESA PENYABANGAN, KEC.GEROKGAK, KAB.BULELENG A Biasa
OWNER : 14

NO URAIAN VOLUME SAT HARGA SAT JUMLAH SAT JUMLAH


(Rp) (Rp) (Rp)
I PEKERJAAN PERSIAPAN
1 Pembersihan lapangan 113.460 m2 5,100.00 578,646.00
2 Pengukuran & Bowplank 80.000 m 47,559.10 3,804,728.00
4,383,374.00
II PEKERJAAN TANAH & PASIR
1 Galian pondasi menerus 26.020 m3 70,025.00 1,822,050.50
3 Urugan kembali tanah pondasi 8.673 m3 110,500.00 958,366.50
3 Urugan pasir bawah pondasi (t= 5 cm) 1.301 m3 16,300.00 21,206.30
2,801,623.30
III PEKERJAAN BETON
1 Beton K175sloof struktur 1 ; 2 ; 3 (15/25) 1.991 m3 2,883,435.50 5,740,920.08
2 Beton K175 kolom struktur 1 ; 3 ;5(15/15) 1.811 m3 2,883,435.50 5,221,901.69
3 Beton K225 balok struktur 1 ; 2 ; 3(15/25) 1.991 m3 2,883,435.50 5,740,920.08
4 Rabatan (t=5cm) 5.673 m3 594,413.00 3,372,104.95
20,075,846.80
IV PEKERJAAN PASANGAN
1 Pasangan pondasi batu kali 1:5 21.240 m3 527,340.00 11,200,701.60
2 Pasangan batu kosong 10.620 m3 249,015.00 2,644,539.30
3 Pasangan bata 1:5 21.770 m3 1,033,730.00 22,504,302.10
36,349,543.00
V PEKERJAAN KAP KAYU
1 Pek. Kuda-Kuda KAYU + Genteng 112.000 m2 547,106.85 61,275,967.20
2 Pek. List plank 41.000 m 57,716.12 2,366,360.92
63,642,328.12
VI PEKERJAAN KOSEN, PINTU
1 Kosen pintu + jendela 15.700 m 150,000.00 2,355,000.00
2 Daun pintu panel 4.000 bh 1,000,000.00 4,000,000.00
3 Daun jendela panel+kaca 5mm 4.000 bh 450,000.00 1,800,000.00
VII PEKERJAAN LANTAI 8,155,000.00
1 Keramik Lantai 60cm x 60cm 113.456 m2 118,211.00 13,411,747.22
2 Keramik dingding KM 10cm x 20cm 26.400 m2 86,235.00 2,276,604.00
15,688,351.22

VIIIPEKERJAAN PLESTERAN
1 Plesteran 1:5 290.220 m2 47,811.60 13,875,882.55
2 Acian 290.220 m2 22,532.00 6,539,237.04
20,415,119.59
IX PEKERJAAN PLAFOND
1 Pekerjaan Plafond 90.480 m2 125,330.50 11,339,903.64
2 Pekerjaan List Plafond 82.100 m 15,000.00 1,231,500.00
12,571,403.64
X PEKERJAAN PENGUNCI DAN PENGGANTUNG
1 Engsel Pintu + jendela 12.000 bh 17,000.00 204,000.00
2 Kait angin 8.000 bh 12,000.00 96,000.00
3 Slot pintu 4.000 bh 120,000.00 480,000.00
780,000.00
XI PEKERJAAN SANITASI
1 Pasangan Pipa 4" 15.000 m 166,762.00 2,501,430.00
2 Pasangan Pipa 3" 15.000 m 166,762.00 2,501,430.00
3 Closet jongkok 2.000 bh 1,250,000.00 2,500,000.00
4 Kran air 4.000 bh 125,000.00 500,000.00
5 Pasangan floordrain 2.000 bh 20,000.00 40,000.00
8,042,860.00
XII PEKERJAAN FINISHING
1 Cat kosen & pintu 25.920 m2 26,737.50 693,036.00
2 Cat Dingding 290.220 `m2 20,857.00 6,053,118.54
3 Cat Plafond 90.480 m2 16,378.00 1,481,881.44
8,228,035.98
XIIIPEKERJAAN INSTALASI LISTRIK
1 Pemasangan instalasi 12.000 titik 200,000.00 2,400,000.00
2 Pemasangan PLN 2200 WATT 1.000 unit 3,500,000.00 3,500,000.00
5,900,000.00
Total Anggaran Biaya 207,033,485.65
Dibulatkan

Singaraja, AGUTUS 2015


Mengetahui :
265F569F
2883435.5

#REF!
246928
RENCANA ANGGARAN BIAYA

PROYEK : HOTEL. BANGUNAN 2 ( L=90.58M2)


LOKASI : DESA PENYABANGAN, KEC.GEROKGAK, KAB.BULELENG A Biasa
OWNER : 14

NO URAIAN VOLUME SAT HARGA SAT JUMLAH SAT JUMLAH


(Rp) (Rp) (Rp)
I PEKERJAAN PERSIAPAN
1 Pembersihan lapangan 50.000 m2 5,100.00 255,000.00
2 Pengukuran & Bowplank 40.000 m 47,559.10 1,902,364.00
2,157,364.00
II PEKERJAAN TANAH & PASIR
1 Galian pondasi menerus 26.020 m3 70,025.00 1,822,050.50
3 Urugan kembali tanah pondasi 12.673 m3 110,500.00 1,400,366.50
3 Urugan pasir bawah pondasi (t= 5 cm) 9.301 m3 16,300.00 151,606.30
3,374,023.30
III PEKERJAAN BETON
1 Beton K175sloof struktur 1 ; 2 ; 3 (20/40) 2.991 m3 2,883,435.50 8,624,355.58
2 Beton K175 kolom struktur 1 ; 3 ;5(30/30) 2.811 m3 2,883,435.50 8,105,337.19
3 Beton K225 balok struktur 1 ; 2 ; 3(20/40) 2.991 m3 2,883,435.50 8,624,355.58
4 Beton K175 plat t=12cm 5.590 m3 2,883,435.50 16,118,404.45
4 Rabatan (t=5cm) 2.198 m3 594,413.00 1,306,519.77
42,778,972.57
IV PEKERJAAN PASANGAN
1 Pasangan pondasi batu kali 1:5 12.240 m3 527,340.00 6,454,641.60
2 Pasangan batu kosong 8.620 m3 249,015.00 2,146,509.30
3 Pasangan bata 1:5 14.770 m3 1,033,730.00 15,268,192.10
23,869,343.00
V PEKERJAAN KAP KAYU
1 Pek. Kuda-Kuda KAYU + Genteng 128.480 m2 347,106.85 44,596,288.09
2 Pek. List plank 68.000 m 57,716.12 3,924,696.16
48,520,984.25
VI PEKERJAAN KOSEN, PINTU
1 Kosen pintu + jendela 15.700 m 150,000.00 2,355,000.00
2 Daun pintu panel 4.000 bh 1,000,000.00 4,000,000.00
3 Daun jendela panel+kaca 5mm 4.000 bh 450,000.00 1,800,000.00
VII PEKERJAAN LANTAI 8,155,000.00
1 Keramik Lantai 60cm x 60cm 90.580 m2 208,211.00 18,859,752.38
2 Keramik dingding KM 10cm x 20cm 26.400 m2 90,235.00 2,382,204.00
21,241,956.38
VIII PEKERJAAN PLESTERAN
1 Plesteran 1:5 58.044 m2 47,811.60 2,775,176.51
2 Acian 58.044 m2 22,532.00 1,307,847.41
4,083,023.92
IX PEKERJAAN PLAFOND
1 Pekerjaan Plafond 128.480 m2 125,330.50 16,102,462.64
2 Pekerjaan List Plafond 128.000 m 15,000.00 1,920,000.00
18,022,462.64
X PEKERJAAN PENGUNCI DAN PENGGANTUNG
1 Engsel Pintu + jendela 8.000 bh 17,000.00 136,000.00
2 Kait angin 8.000 bh 12,000.00 96,000.00
3 Slot pintu 4.000 bh 120,000.00 480,000.00
712,000.00
XI PEKERJAAN FINISHING
1 Cat kosen & pintu 25.920 m2 26,737.50 693,036.00
2 Cat Dingding 58.044 `m2 20,857.00 1,210,623.71
3 Cat Plafond 90.480 m2 16,378.00 1,481,881.44
3,385,541.15
XII PEKERJAAN INSTALASI LISTRIK
1 Pemasangan instalasi 7.000 titik 200,000.00 1,400,000.00
2 Pemasangan PLN 2200 WATT 1.000 unit 3,500,000.00 3,500,000.00
4,900,000.00
Total Anggaran Biaya 181,200,671.20
Dibulatkan 181,200,000.00

Singaraja, AGUSTUS 2015


Mengetahui :
RENCANA ANGGARAN BIAYA
PROYEK : HOTEL. BANGUNAN 3 ( L=54M2)
LOKASI : DESA PENYABANGAN, KEC.GEROKGAK, KAB.BULELENG A Biasa
OWNER : 14

NO URAIAN VOLUME SAT HARGA SAT JUMLAH SAT JUMLAH


(Rp) (Rp) (Rp)
I PEKERJAAN PERSIAPAN
1 Pembersihan lapangan 54.000 m2 5,100.00 275,400.00
2 Pengukuran & Bowplank 40.000 m 47,559.10 1,902,364.00
2,177,764.00
II PEKERJAAN TANAH & PASIR
1 Galian pondasi 21.600 m3 70,025.00 1,512,540.00
2 Urugan kembali tanah pondasi 7.673 m3 110,500.00 847,866.50
3 Urugan pasir bawah pondasi (t= 5 cm) 0.072 m3 16,300.00 1,173.60
2,361,580.10
III PEKERJAAN BETON
1 Beton K175sloof struktur 1 ; 2 ; 3 (20/40) 4.580 m3 2,883,435.50 13,206,134.59
2 Beton K175 kolom struktur 1 ; 3 ;5(30/30) 3.680 m3 2,883,435.50 10,611,042.64
3 Beton K225 balok struktur 1 ; 2 ; 3(20/40) 4.580 m3 2,883,435.50 13,206,134.59
4 Beton K175 plat t=12cm 6.480 m3 2,883,435.50 18,684,662.04
55,707,973.86
IV PEKERJAAN KAYU
1 Pek. Kuda-Kuda KAYU + zyncalume 79.104 m2 247,106.85 19,547,140.26
2 Pek. List plank 68.000 m 57,716.12 3,924,696.16
3 Kayu railing pembatas 43.000 m 50,000.00 2,150,000.00
23,471,836.42
V PEKERJAAN LANTAI
1 Keramik Lantai 60cm x 60cm 54.000 m2 190,211.00 10,271,394.00
10,271,394.00
VI PEKERJAAN PLESTERAN
1 Plesteran 1:5 9.870 m2 43,811.60 432,420.49
2 Acian 9.870 m2 17,532.00 173,040.84
605,461.33
VII PEKERJAAN PLAFOND
1 Pekerjaan Plafond 54.000 m2 120,330.50 6,497,847.00
2 Pekerjaan List Plafond 51.000 m 15,000.00 765,000.00
7,262,847.00
VIII PEKERJAAN FINISHING
1 Cat kayu railing 7.120 m2 25,737.50 183,251.00
2 Cat ekspose 7.890 `m2 18,857.00 148,781.73
3 Cat Plafond 54.000 m2 16,378.00 884,412.00
1,216,444.73
IX PEKERJAAN INSTALASI LISTRIK
1 Pemasangan instalasi 9.000 titik 200,000.00 1,800,000.00
2 Pemasangan PLN 2200 WATT 1.000 unit 3,500,000.00 3,500,000.00
5,300,000.00
Total Anggaran Biaya 108,375,301.44
Dibulatkan 108,375,000.00

Singaraja, AGUSTUS 2015


Mengetahui :
RENCANA ANGGARAN BIAYA

PROYEK : HOTEL. BANGUNAN 4 ( L=32M2)


LOKASI : DESA PENYABANGAN, KEC.GEROKGAK, KAB.BULELENG A Biasa
OWNER : 14

NO URAIAN VOLUMESAT HARGA SAT JUMLAH SAT JUMLAH


(Rp) (Rp) (Rp)
I PEKERJAAN PERSIAPAN
1 Pembersihan lapangan 32.000 m2 5,100.00 163,200.00
2 Pengukuran & Bowplank 12.000 m 47,559.10 570,709.20
733,909.20
II PEKERJAAN TANAH & PASIR
1 Galian pondasi menerus 9.450 m3 70,025.00 661,736.25
3 Urugan kembali tanah pondasi 4.500 m3 110,500.00 497,250.00
3 Urugan pasir bawah pondasi (t= 5 cm) 3.100 m3 16,300.00 50,530.00
1,209,516.25
III PEKERJAAN BETON
1 Beton K175sloof struktur 1 ; 2 ; 3 (15/25 0.400 m3 2,583,435.50 1,033,374.20
2 Beton K175 kolom struktur 1 ; 3 ;5(15/15 0.700 m3 2,583,435.50 1,808,404.85
3 Beton K225 balok struktur 1 ; 2 ; 3(15/25 0.700 m3 2,583,435.50 1,808,404.85
4 Beton K175 plat t=8cm 2.240 m3 2,583,435.50 5,786,895.52
5 Rabatan (t=5cm) 1.400 m3 594,413.00 832,178.20
11,269,257.62
IV PEKERJAAN PASANGAN
1 Pasangan pondasi batu kali 1:5 9.300 m3 527,340.00 4,904,262.00
2 Pasangan batu kosong 3.200 m3 249,015.00 796,848.00
3 Pasangan bata 1:5 3.500 m3 1,033,730.00 3,618,055.00
9,319,165.00
V PEKERJAAN KAP KAYU
1 Pek. Kuda-Kuda KAYU + Zyncalume 36.620 m2 247,106.85 9,049,052.85
2 Pek. List plank 30.000 m 57,716.12 1,731,483.60
10,780,536.45
VI PEKERJAAN KOSEN, PINTU dan JENDELA
1 Kosen pintu + jendela 26.000 m 60,000.00 1,560,000.00
2 Daun pintu panel 4.000 bh 800,000.00 3,200,000.00
3 Daun jendela +kaca 5mm 1.000 bh 450,000.00 450,000.00
VII PEKERJAAN LANTAI 5,210,000.00
1 Keramik Lantai 60cm x 60cm 32.000 m2 167,211.00 5,350,752.00
2 Keramik dingding KM 10cm x 20cm 14.000 m2 70,235.00 983,290.00
6,334,042.00
VIIIPEKERJAAN PLESTERAN
1 Plesteran 1:5 36.278 m2 47,811.60 1,734,485.32
2 Acian 36.278 m2 22,532.00 817,404.63
2,551,889.95
IX PEKERJAAN PLAFOND
1 Pekerjaan Plafond 36.620 m2 120,330.50 4,406,502.91
2 Pekerjaan List Plafond 52.000 m 15,000.00 780,000.00
5,186,502.91
X PEKERJAAN PENGUNCI DAN PENGGANTUNG
1 Engsel Pintu 8.000 bh 17,000.00 136,000.00
2 Slot pintu 4.000 bh 100,000.00 400,000.00
536,000.00
XI PEKERJAAN SANITASI
1 Pasangan Pipa 4" 10.000 m 166,762.00 1,667,620.00
2 Pasangan Pipa 3" 10.000 m 130,762.00 1,307,620.00
3 Closet duduk 2.000 bh 1,250,000.00 2,500,000.00
4 Kran air 4.000 bh 125,000.00 500,000.00
5 Pasangan floordrain 2.000 bh 20,000.00 40,000.00
6,015,240.00
XII PEKERJAAN FINISHING
1 Cat kosen & pintu 25.920 m2 18,737.50 485,676.00
2 Cat Dingding 36.278 `m2 20,857.00 756,650.25
3 Cat Plafond 58.000 m2 16,378.00 949,924.00
2,192,250.25
XIIIPEKERJAAN INSTALASI LISTRIK
1 Pemasangan instalasi 6.000 titik 150,000.00 900,000.00
2 Pemasangan PLN 2200 WATT 1.000 unit 2,500,000.00 2,500,000.00
3,400,000.00
Total Anggaran Biaya 64,738,309.62
Dibulatkan 64,738,000.00

Singaraja, AGUSTUS 2015


Mengetahui :
REKAPITULASI BANGUNAN HOTEL
PROYEK : HOTEL
ALAMAT : DESA PENYABANGAN, KEC.GEROKGAK, KAB.BULELENG
OWNER : 14

NO NAMA BANGUNAN VOL SAT HARGA SAT JUMLAH SAT JUMLAH


(Rp) (Rp) (Rp)
1 BANGUNAN 1 ( L=113.456 M2 ) 3.000 unit 226,930,000.00 680,790,000.00
2 BANGUNAN 2 ( L= 90.58 M2 ) 1.000 unit 181,200,000.00 181,200,000.00
3 BANGUNAN 3 ( L= 54 M2 ) 1.000 unit 108,375,000.00 108,375,000.00
4 BANGUNAN 4 ( L = 32 M2 ) 1.000 unit 64,738,000.00 64,738,000.00
TOTAL 1,035,103,000.00