PROYEK : TOKO
ALAMAT : JALAN PULAU MENJANGAN , BANYUNING A Biasa
OWNER : IMAM SYAFI'I 14
VIIIPEKERJAAN PLESTERAN
1 Plesteran 1:5 290.220 m2 47,811.60 13,875,882.55
2 Acian 290.220 m2 22,532.00 6,539,237.04
20,415,119.59
IX PEKERJAAN PLAFOND
1 Pekerjaan Plafond 90.480 m2 125,330.50 11,339,903.64
2 Pekerjaan List Plafond 82.100 m 15,000.00 1,231,500.00
12,571,403.64
X PEKERJAAN PENGUNCI DAN PENGGANTUNG
1 Engsel Pintu + jendela 12.000 bh 17,000.00 204,000.00
2 Kait angin 8.000 bh 12,000.00 96,000.00
3 Slot pintu 4.000 bh 120,000.00 480,000.00
780,000.00
XI PEKERJAAN SANITASI
1 Pasangan Pipa 4" 15.000 m 166,762.00 2,501,430.00
2 Pasangan Pipa 3" 15.000 m 166,762.00 2,501,430.00
3 Closet jongkok 2.000 bh 1,250,000.00 2,500,000.00
4 Kran air 4.000 bh 125,000.00 500,000.00
5 Pasangan floordrain 2.000 bh 20,000.00 40,000.00
8,042,860.00
XII PEKERJAAN FINISHING
1 Cat kosen & pintu 25.920 m2 26,737.50 693,036.00
2 Cat Dingding 290.220 `m2 20,857.00 6,053,118.54
3 Cat Plafond 90.480 m2 16,378.00 1,481,881.44
8,228,035.98
XIIIPEKERJAAN INSTALASI LISTRIK
1 Pemasangan instalasi 12.000 titik 200,000.00 2,400,000.00
2 Pemasangan PLN 2200 WATT 1.000 unit 3,500,000.00 3,500,000.00
5,900,000.00
Total Anggaran Biaya 207,033,485.65
Dibulatkan
#REF!
246928
RENCANA ANGGARAN BIAYA