CVG-INTERALUMINA
PUERTO ORDAZ
VENEZ UELA
This has been achieved by the introduction of the Alusuisse Precipitation Process, state of the
art process equipment and a particular hydrate classification arrangement where hydrocyclones
and gravity settlers have been combined to provide a four fold classification. These and other
process features will allow better control of the agglomeration of hydrate in the precipitation
process this being the key process point for optimizing quality parameters like granulometry
and occluded soda of the product.
This paper presents an overview of the process and the experience so far gained, hi ghlighting
the process innovations regarding the higher productivities and product quality control.
1.0 INTRODUCTION
CVG-Interalumina is an alumina plant, operating since 1983. The plant was originally
designed for 1 million tpy production of sandy alumina, based on standard trihydrate
American Bayer Process, -capable of treating a variety of imported bauxites with
eventual switch to indigenous bauxite.
'The production was progressively increased to 1.3 million tpy by 1987. The
expansion project was then initiated to increase the capacity to 2 million tpy, using
exclusively Venezuelan bauxite.
Detailed laboratory studies and plant tests with the Venezuelan bauxite, conducted in
1987, showed that an expansion, based on the liquor productivity increase was feasibleI
with the Alusuisse precipitation technology. Thereby, the flow through the digestion
was to be increased only marginally, maintaining the product quality at the same time.
Extensive liquor and seed recirculation tests were done in the laboratory to define the.
precipitation process parameters to give 80 g/l yield and the modifications needed to
handle the bauxite low in reactive silica, exceedingly high in quartz and containingI
substantial organics content. These indicated need for a predesilication stage to keep
the liquor silica in check, extensive upgrading of the sand separation area, and seed
washing for organic control.
Plant tests with polymers and equipment suppliers were carried out to upgrade the
mud thickeners and washers for high capacity operation; this would substantially
reduce the liquor retention time in the area, conducive to the higher yields.
Based on the above studies the expansion project was approved in 1988, for an
expenditure of approximately 400 million US Dollars.
The scope of the project:
*Increase production of the existing plant by 700.000 TPY to 2 million tpy.
* Increase the precipitation productivity to more than 80 g/l and install seed
washing required for the purpose .
* Set up hydrate classification to provide the seed control required for the
precipitation technology.
* Flow increase of 10 %
The high content of quartz which translates into high sand loads with marked
abrasivity .
Low content of reactive silica on one side is good for the consumption of soda
but on the other side obliged the installation of a predesilication stage.
Very low content of goethite giving to the mud good settling characteristic
even after the introduction of the predesilication phase.
The main effort in this side of the plant other than increased capacity of solids
handling was to increase oversaturation of the liquor feed to precipitation
without losing plant efficiency. This consistent achievement of oversaturation
is a fundamental parameter for control of the alumina quality when aiming for
the high productivity sought in Interalumina.
3.2.2 Desikahio
After analyzing various possibilities like predesilication, post-
desilication and mud recirculation to tackle problems of low reactiveI
silica bauxite, it was decided to go for the traditional predesilication
with four agitated tanks overflowing in series.
3.2.3 Disto
With the use of Pijiguaos bauxite, the sand load to this area more than
doubled., For this reason and due to the fact that in clarification and
mud washing the thickeners are of the flat bottom and outward racking,
the area was modified extensively to obtain a sand separation efficiency
higher than 98%. This has to be done within space. limitation of the
area, making full use of the equipment already there.
The flow of this area was completely rerouted for the transformation to
high capacity tanks (both settlers and washers) and for increasing
For handling the load increase the area was completely instrumented
and automated . Each tank was fitted for monitoring from the control
room mud and liquor interface and underflow density and flow. An
independent system was installed with sufficient redundancy for
polymer dosing.
DIGESTION EDT
SETTLERS
SAND
TO
0 ISPOSAL
TANKS
COLLECTING A CVG INTERALUMINA
EXPANSION 2.0 MTPY
As long as the fine and superfine fractions of primary seed are effectively
agglomerated and a steady balance is maintained in the generation of new
particles produced during the precipitation and classification processes, the
running of a coarse-circuit'allows charging of a relatively high quantity of fine
seed,. keeping the requirements of agglomeration low at the same time. ThisI
concept is illustrated in Figure 2 using actual plant data (tonnages are referred
to 100 ton of hydratelin pump off).
COARSE SEED
I
FINE SEED T 22umn 2.7 1/h
<44umn 2.81t/h Generation
<22umn 1.4 tjh of Fines
PRODUCT
70 HYDRATE
CALCINATION CLASSIFICATION A CVG INTERALUMINA
EXPANSION 2.0 MTPY
3.3.1 Precigitation
The material from the P/Ts would be coarse seed and it will be
subsequently treated in the coarse seed filtration area.
In the T/Ts the finest fraction of the seed, called fine -fine seed to be
charged in the agglomeration phase, would be obtained. This seed
should have the highest concentration of solid phase sodium oxalate,I
therefore is ideal for oxalate wash and its removal.
The process described was the one selected and the oxalate control area
was designed utilizing drum filters of 100. The area would have
sufficient flexibility to permit the utilization of the filters for the
different process line ups.
* The presence of organics in the liquor, especially sodium oxalate must put a
limit on production capacity and quality.
The process group of -this organization was charged of liaison with the operating.I
plant, bringing in at every step all their inputs and keeping them informed of
developments of all the expansion concepts.j
A detailed procedure was written and approved by the high management of the
company to formalize the following concepts:
* The -commissioning and start up of the new areas was done by an integrated
group both from the operation and project organization. This acted as a
separate entity reporting to the plant shift superintendent for coordination.
This continued until the field people were well trained and sufficient
operational stability reached for the operation people to take over completely .
* Operations were all time responsible for the modified areas and a group of
project people was put on shift as support for training and trouble shooting.I
* Lists of pre and post operating modifications were prepared along with the
operations people and executed under responsibility of the projectI
organization .
The last process installation to enable full operation of the new process in precipitation
was started up in march 1992.
Although by the first semester of the current year the pro ductio n target of the
expansion has not been reached, the basic process targets of the productivity and
product quality have been comfortably achieved as can be seen in table 1.
Productivity in precipitation 62 65 70 72 74 78 79
-(9/l) _ _
Occluded soda in Product 0.30 0.28 0.30 0.29 0.26 0.24 0.24
(% weight)_____
4, I,
Fine Seed New cyclone
Washing and area fully started
split seeding started increase of solids
in precipitation
Note also that the particle size held the same over various stages of expansion, despite
several crises of the oxalate precipitation after introduction of the indigenous bauxite, a
phenomenon relatively new to -the plant people. The oxalate crjse-are now
controllable therefore we expect to soon reach our target values ok89 /f the 44
micron fraction.
The achievement of the target production has been slowed, mainly due to the
following problems:
These problems are on the way to be solved and we expect to hit the production rate
of 2.0 MIMTPY by October end.