JADWAL WAKTU PELAKSANAAN / TIME SCHEDULE

JADWAL WAKTU PELAKSANAAN PEKERJAAN SELAMA 90 HARI KALENDER


BOBOT
PERSENTASE
No. JENIS PEKERJAAN NILAI PEKERJAAN
THD PEKERJAAN
MINGGU KE
% 1-7 8-14 15-21 22-28 29-35 36-42 43-49 50-56 57-63 64-70 71-77 78-84 85-90

100
I. PEKERJAAN PERSIAPAN 93,354,551.97 13.04 3.26 3.26 3.26 3.26

II.1 PEKERJAAN TANAH DAN STRUKTUR BAWAH

II.1.1 PEKERJAAN TANAH 5,945,845.67 0.83 0.42 0.42

II.1.2 PEKERJAAN STRUKTUR BAWAH 187,417,392.74 26.18 4.36 4.36 4.36 4.36 4.36 4.36

II.2 STRUKTUR 429,072,697.52 59.94 8.56 8.56 8.56 8.56 7.49 7.49 7.49 1.61 1.61 0

JUMLAH 715,790,487.89 100.00 3.68 3.68 7.62 7.62 12.93 12.93 12.93 12.93 7.49 7.49 7.49 1.61 1.61

RENCANA PROGGRES 3.68 7.35 14.98 22.60 35.53 48.46 61.38 74.31 81.80 89.30 96.79 98.39 100.00

71,579,048.79
787,369,536.68