REKAPITULASI EE

PEKERJAAN : PEMBANGUNAN MASJID BAITUS SALAM


LOKASI : KEL. DUSUN KEBUN
TAHUN ANGGARAN : 2015

JML HARGA
NO. URAIAN PEKERJAAN
( Rp.)
1 2 3

I. PEKERJAAN PENDAHULUAN 4.987.424,00


II. PEKERJAAN TANAH DAN URUGAN 2.356.970,00
III. PEKERJAAN PONDASI DAN SLOOF 71.736.364,58
IV. PEKERJAAN BETON STRUKTUR 255.472.862,46
V. PEKERJAAN PASANGAN DAN PLASTERAN 139.623.945,57
VI. PEKERJAAN PINTU, JENDELA, VENTILASI 102.976.344,36
VII. PEKERJAAN LANTAI DAN DINDING 267.815.433,82
VIII. PEKERJAAN INSTALASI AIR -
IX. PEKERJAAN PLAFOND 95.478.010,46
X. PEKERJAAN INSTALASI LISTRIK 2.131.600,00
XI. PEKERJAAN PENGECATAN 48.875.835,11
XII. PEKERJAAN ATAP 355.349.720,60
XIII. PEKERJAAN LAIN LAIN 53.400.000,00

TOTAL FISIK 1.400.204.510,96


PPn 10 % 140.020.451,10
TOTAL KESELURUHAN 1.540.224.962,05
PEMBULATAN 1.540.000.000,00

TERBILANG : Satu Milyar Lima ratus Juta Empat Puluh Ribu Rupiah

JAMBI, 2017
Eksindo Desain

echo
Team Leader
ENGINEERING ESTIMATE ( EE )
PEKERJAAN : PEMBANGUNAN MASJID BAITUS SALAM
LOKASI : KEL. DUSUN KEBUN
TAHUN ANGGARAN : 2017

H. SATUAN JML HARGA


NO. URAIAN PEKERJAAN VOLUME
( Rp. ) ( Rp. )
1 2 3 4 5

I. PEKERJAAN PENDAHULUAN
1 Pek. Papan nama proyek 1,00 Ls 300.000,00 300.000,00
2 Pek. Pembersihan Lokasi Awal dan akhir Kegiatan 1,00 Ls 750.000,00 750.000,00
3 Pek. Pembongkaran 1,00 Ls 2.500.000,00 2.500.000,00
4 Pek. Bouplank 16,00 M' 71.089,00 1.137.424,00
5 Pek. Dokumentasi dan pelaporan 1,00 Ls 300.000,00 300.000,00
>> JUMLAH 4.987.424,00
II. PEKERJAAN TANAH DAN URUGAN
1 Pek. Galian Tanah Pondasi teRAS 30,80 M3 63.000,00 1.940.400,00
2 Pek. Urugan Tanah Kembali 10,27 M3 21.000,00 215.600,00
3 Pek. Urugan Pasir Bawah Pondasi t. 5 cm 1,65 M3 121.800,00 200.970,00
>> JUMLAH 2.356.970,00
III. PEKERJAAN PONDASI DAN SLOOF
1 Pek. Pondasi Pas. 1 bata ad. 1 : 3 99,00 M2 206.624,40 20.455.815,60
2 Pek. Pondasi Tapak uk. 80x80 ad. 1 : 2 : 3 4,61 M3 4.055.673,00 18.688.541,18
3 Pek. Sloof uk. SL 20/30ad. 1 : 2 : 3 6,60 M3 4.938.183,00 32.592.007,80
>> JUMLAH 71.736.364,58
IV. PEKERJAAN BETON STRUKTUR
1 Pek. Kolom Utama Bulat D.40cm 4,52 m3 5.326.718,00 24.085.288,11
2 Pek. Kolom uk. 25/25 ad. 1 : 2 : 3 6,56 M3 5.326.718,00 34.956.586,88
3 Pek. Kolom teras uk. 20/20 ad. 1 : 2 : 3 5,76 M3 5.326.718,00 30.681.895,68
4 Pek. Balok gantung 20/40,elv. +9.00, ad. 1 : 2 : 3 2,21 M3 5.485.208,00 12.146.444,60
5 Pek. Balok top kubah 20/40,elv. +10.00, ad. 1 : 2 : 3 1,66 M3 5.485.208,00 9.109.833,45
6 Pek. Balok teras 20/30,elv. +4.00, ad. 1 : 2 : 3 4,64 M3 5.485.208,00 25.451.365,12
7 Pek. Balok anak teras uk. 20/30, ad. 1 : 2 : 3 2,24 M3 5.485.208,00 12.286.865,92
8 Pek. Ring Balok ad. 15/20 ad 1 : 2 : 3 2,00 M3 5.485.208,00 10.970.416,00
9 Pek. Plat Beton Teras T. 10 cm ad. 1 : 2 : 3 22,96 M3 5.220.113,00 119.869.454,82
>> JUMLAH 255.472.862,46
V. PEKERJAAN PASANGAN DAN PLASTERAN
1 Pek. Pas. Dinding Bata ad. 1 : 4 576,29 M2 95.289,80 54.914.558,84
2 Pek. Plasteran Dinding + Kolom ad. 1 : 4 1.152,58 M2 56.402,76 65.008.693,12
4 Pek. Dinding Batu Andesit bakar ad. 1 : 3 52,53 M2 375.037,00 19.700.693,61
>> JUMLAH 139.623.945,57
VI. PEKERJAAN PINTU, JENDELA, VENTILASI
1 Pek. Teralis Besi Hollow 7,20 M2 500.000,00 3.600.000,00
2 Pek. Kusen jendela alumunium 40,32 M2 1.414.801,50 57.044.796,48
3 Pek. Kusen pintu + jendela alumunium 21,75 M2 1.414.801,50 30.771.932,63
4 Pek. Kusen + ventilasi Jendela Kaca mati 5 mm 14,31 M2 528.275,00 7.559.615,25
5 Pek, Pintu Panel 2,00 Unit 2.000.000,00 4.000.000,00
>> JUMLAH 102.976.344,36
H. SATUAN JML HARGA
NO. URAIAN PEKERJAAN VOLUME
( Rp. ) ( Rp. )
1 2 3 4 5

VII. PEKERJAAN LANTAI DAN DINDING


1 Pek. Lantai Kerja T. 5 cm ad. 1 : 3 : 5 62,50 M3 983.869,00 61.491.812,50
2 Pek. Lantai Granite Uk. 60 x 60 cm 625,00 M2 326.833,66 204.271.037,50
3 Pek. Plint Lantai 82,00 M' 25.031,51 2.052.583,82
>> JUMLAH 267.815.433,82
VIII. PEKERJAAN INSTALASI AIR
1 Pek. Pas. Pipa Air Hujan 3" - M' 46.511,75 -
>> JUMLAH -
IX. PEKERJAAN PLAFOND
1 Pek. Plafond Gypsum 9 mm 490,83 M2 49.075,80 24.087.874,91
2 Pek. Rangka Hollow 490,83 M2 142.385,00 69.886.829,55
3 Pek. List Plafond Gypsum 82,00 M' 18.333,00 1.503.306,00
>> JUMLAH 95.478.010,46
X. PEKERJAAN INSTALASI LISTRIK
1 Pek. Instalasi Listrik dan Cahaya 4,00 Ttk 162.500,00 650.000,00
2 Pek. Lampu Sorot LED 10 watt 2,00 Bh 150.000,00 300.000,00
3 Pek. Lampu XL 20 watt 2,00 Bh 102.000,00 204.000,00
4 Pek. Saklar Ganda 1,00 Bh 23.000,00 23.000,00
5 Pek. Kabel Power NYM 2x2.5 mm 70,00 M' 12.500,00 875.000,00
6 Pek. MCB + Box 1,00 Bh 79.600,00 79.600,00
>> JUMLAH 2.131.600,00
XI. PEKERJAAN PENGECATAN
1 Pek. Cat Dinding Tembok 1.152,58 M2 29.740,50 34.278.305,49
2 Pek. Cat Plafond 490,83 M2 29.740,50 14.597.529,62
>> JUMLAH 48.875.835,11
XII. PEKERJAAN ATAP
1 Pek. Rangka atap baja ringan 524,02 M2 156.000,00 81.747.120,00
2 Pek. Atap Genteng Metal Pasir 524,02 M2 137.480,00 72.042.269,60
3 Pek. Papan lisplank GRC Board 80,60 M' 65.885,00 5.310.331,00
4 Pekk Pembuatan Kubah Enimail 1,00 unit 196.250.000,00 196.250.000,00
>> JUMLAH 355.349.720,60
XIII. PEKERJAAN LAIN LAIN
1 Huruf Timbul BETON T. 1CM t. 15 cm Finish Cat 6,00 Bh 700.000,00 4.200.000,00
2 Huruf Timbul Plat T. 1 mm t. 20 cm Finish Cat Duco 12,00 Bh 350.000,00 4.200.000,00
3 Pembuatan Profil Tiang Bulat 4,00 Bh 11.250.000,00 45.000.000,00
>> JUMLAH 53.400.000,00

JAMBI, 2017
Eksindo Desain