418,142,996
2,395,417,854 Rp 1,593,055
3,643,209,933 Rp 1,292,054
781,940,709
6,188,979,455 Rp 1,767,775
13,427,690,947 4,652,884
DAFTAR HARGA BAHAN BANGUNAN DAN UPAH
TAHUN ANGGARAN 2017
Rp 237,952.00 228,800
Rp 130,657.28 125,632
Rp 153,370.88 147,472
Rp 286,624.00 275,600
Rp 297,440.00 286,000
Rp 292,032.00 280,800
Rp 281,216.00 270,400
Rp 270,400.00 260,000
Rp 259,584.00 249,600
Rp 194,688.00 187,200
Rp 1,492.61 1,435
Rp 1,946.88 1,872
Rp 1,297.92 1,248
Rp 259,584.00 249,600
Rp 54.08 52
Rp 30,068.48 28,912
Rp 153,370.88 147,472
Rp 40,884.48 39,312
Rp 10,707.84 10,296
Rp 10,924.16 10,504
Rp 10,924.16 10,504
Rp 10,924.16 10,504
Rp 178,464.00 171,600
Rp 43,155.84 41,496
Rp 223,783.04 215,176
Rp 20,550.40 19,760
Rp 1,297,920.00 1,248,000
Rp 1,514,240.00 1,456,000
Rp 1,676,480.00 1,612,000
Rp 1,784,640.00 1,716,000
Rp 62,516.48 60,112
Rp - -
Rp 1,189,760.00 1,144,000
Rp 2,487.68 2,392
Rp 30,068.48 28,912
Rp - -
Rp 11,356.80 10,920
Rp 11,897.60 11,440
Rp 12,546.56 12,064
Rp 24,227.84 23,296
Rp 23,903.36 22,984
Rp 14,817.92 14,248
Rp 13,628.16 13,104
Rp 13,520.00 13,000
Rp - -
Rp 26,715.52 25,688
Rp 64,896.00 62,400
Rp 34,611.20 33,280
Rp 30,284.80 29,120
Rp 34,611.20 33,280
Rp 19,360.64 18,616
Rp 34,611.20 33,280
Rp 528,145.28 507,832
Rp 3,136,640.00 3,016,000
Rp 21,632.00 20,800
Rp 40,560.00 39,000
Rp 98,858.24 95,056
Rp 108,700.80 104,520
Rp 194,688.00 187,200
Rp 411,008.00 395,200
Rp 832,832.00 800,800
Rp - -
Rp - -
Rp 81,120.00 78,000
Rp 53,214.72 51,168
Rp 141,473.28 136,032
Rp 110,864.00 106,600
Rp 183,006.72 175,968
Rp 29,419.52 28,288
Rp 18,603.52 17,888
Rp 12,579.01 12,095
Rp 3,947.84 3,796
Rp 40,527.55 38,969
Rp 47,049.60 45,240
Rp 10,188.67 9,797
Rp 73,548.80 70,720
Rp - -
Rp 12,438.40 11,960
Rp 14,850.37 14,279
Rp 16,224.00 15,600
Rp 32,448.00 31,200
Rp 21,632.00 20,800
Rp 6,489.60 6,240
Rp 42,182.40 40,560
Rp 84,500.00 81,250
Rp - -
Rp 92,584.96 89,024
Rp 174,894.72 168,168
Rp 58,406.40 56,160
Rp 59,488.00 57,200
Rp 194,688.00 187,200
Rp 129,792.00 124,800
Rp 12,979.20 12,480
Rp 36,774.40 35,360
Rp 102,752.00 98,800
Rp 2,866.24 2,756
Rp 15,142.40 14,560
Rp 12,979.20 12,480
Rp 146,016.00 140,400
Rp 3,893.76 3,744
Rp 129,792.00 124,800
Rp - -
Rp 15,493.92 14,898
Rp 21,632.00 20,800
Rp 43,155.84 41,496
Rp 8,003.84 7,696
Rp 29,527.68 28,392
Rp 17,089.28 16,432
Rp 27,580.80 26,520
Rp 39,153.92 37,648
Rp 40,992.64 39,416
Rp 27,040.00 26,000
Rp 43,155.84 41,496
Rp 43,155.84 41,496
Rp 19,512.06 18,762
Rp 29,203.20 28,080
Rp 34,070.40 32,760
Rp 3,693,664.00 3,551,600
Rp 14,817.92 14,248
Rp 30,068.48 28,912
Rp 2,920,320.00 2,808,000
Rp 23,903.36 22,984
Rp 2,895,984.00 2,784,600
Rp 5,408.00 5,200
Rp 540.80 520
Rp 12,979.20 12,480
Rp 48,672.00 46,800
Rp 36,341.76 34,944
Rp 13,087.36 12,584
Rp 15,142.40 14,560
Rp 19,360.64 18,616
Rp 29,744.00 28,600
Rp 71,385.60 68,640
Rp 13,520.00 13,000
Rp 200,096.00 192,400
Rp 99,507.20 95,680
Rp 178,464.00 171,600
Rp 194,688.00 187,200
Rp 7,354.88 7,072
Rp 2,595.84 2,496
Rp - -
Rp 70,033.60 67,340
Rp 68,140.80 65,520
Rp 12,762.88 12,272
Rp 19,265.46 18,524
Rp 18,170.88 17,472
Rp 52,241.28 50,232
Rp 282,297.60 271,440
Rp - -
Rp 9,950.72 9,568
Rp 10,275.20 9,880
Rp 10,383.36 9,984
Rp 151,424.00 145,600
Rp 454,272.00 436,800
Rp 10,599.68 10,192
Rp 10,781.77 10,367
Rp 10,816.00 10,400
Rp 10,816.00 10,400
Rp 10,816.00 10,400
Rp 14,060.80 13,520
Rp 8,112.00 7,800
Rp 18,928.00 18,200
Rp 34,611.20 33,280
Rp 15,142.40 14,560
Rp 8,652.80 8,320
Rp 8,112.00 7,800
Rp 20,550.40 19,760
Rp 12,979.20 12,480
Rp 93,017.60 89,440
Rp 21,632.00 20,800
Rp 96,262.40 92,560
Rp 96,262.40 92,560
Rp 96,262.40 92,560
Rp 95,180.80 91,520
Rp 200,096.00 192,400
Rp 237,952.00 228,800
Rp 367,744.00 353,600
Rp 14,017.54 13,478
Rp 21,632.00 20,800
Rp 29,203.20 28,080
Rp 66,626.56 64,064
Rp 19,468.80 18,720
Rp 8,436,480.00 8,112,000
Rp 12,979.20 12,480
Rp 681.41 655
Rp 4,867,200.00 4,680,000
Rp 16,224,000.00 15,600,000
Rp 584,064.00 561,600
Rp 36,774.40 35,360
Rp 181,708.80 174,720
Rp 292,032.00 280,800
Rp 12,979,200.00 12,480,000
Rp 10,599,680.00 10,192,000
DAFTAR UPAH PEKERJA BANGUNAN
TAHUN ANGGARAN 2017
93,854.218 90,244.440
162,240.000 156,000.000
117,317.974 112,805.744
129,792.000 124,800.000
129,792.000 124,800.000
117,317.974 112,805.744
117,317.974 112,805.744
129,792.000 124,800.000
162,240.000 156,000.000
162,240.000 156,000.000
140,781.564 135,366.889
164,245.166 157,928.045
DAFTAR ANALISA HARGA SATUAN
Kelengkapan
6 lain-lain ls 1 7,000,000.00 7,000,000.00 Penunjang
Lembur
TOTAL PEKERJAAN STRUKTUR JUMLAH 94,076,570.00
III PEKERJAAN ARSITEKTUR
A. PEKERJAAN PASANGAN DINDING Q-PANELDAN SEKAT MDF
1 Pasangan Dinding Con Block Hebel M2 99 221,880.00 21,966,120.00
2 Sekat ruang kantor Dinding Beton Ringan M2 243 282,990.00 68,766,570.00
3 Plesteran kolom/balok 1 PC : 5 PS plus aci M 2
263 60,710.00 15,966,730.00
4 Pek.Olah Panel pada Kolom r.Lobby/Pelayanan M' 145 280,800.00 40,716,000.00
Kelengkapan
5 Lain-lain ls 1 9,000,000.00 9,000,000.00 Penunjang
Lembur
JUMLAH 156,415,420.00
B. PEKERJAAN PINTU DAN JENDELA
1 Pasang Kusen Pintu Jendela Alumunium 4" M' 168 127,940.00 21,493,920.00
2 Pasangan Daun Pintu Putar stainless (PPJ1) M 2
17 2,400,000.00 40,800,000.00
3 Pasangan Daun Pintu Panil (teak wood finishing melamic) buah 21 1,764,820.00 37,061,220.00
4 Pasangan Daun Pintu Almunium (kaca dof 5 mm) M 2
12 838,900.00 10,066,800.00
4 Pasangan Engsel Pintu Bh 16 59,680.00 954,880.00
5 Pasangan Engsel Jendela Bh 22 56,566.00 1,244,452.00
6 Pasangan Kunci Double Slag Bh 6 339,610.00 2,037,660.00
7 Pasangan Kunci Pintar ex SAMSUNG Bh 14 3,328,776.70 46,602,873.82
8 Pasangan Hak Angin Bh 4 62,310.00 249,240.00
9 Pasangan Sekat Kaca Bening t = 5 mm M2 34 154,220.00 5,243,480.00
10 Pasangan Kaca Tempered t = 10 mm M 2
48 922,040.00 44,257,920.00
11 Pasangan Spring Knip Bh 12 46,180.00 554,160.00
Kelengkapan
lain-lain ls 1 7,000,000.00 7,000,000.00 Penunjang
Lembur
JUMLAH 217,566,605.82
C. PEKERJAAN LANTAI
1 Lantai Dasar - keramik Tile 40x40 /Roman setara M2 98 162,970.00 15,971,060.00
Dinding r Wudhu WC - Granit Tile 60 x 60 Garuda/setara M 2
66 303,160.00 20,008,560.00
2 Lantai 1 - Keramik Tile 40x40/Roman setara M 2
102 162,970.00 16,622,940.00
Dinding WC - Granit Tile 60 x 60 Garuda/setara M 2
76 303,160.00 23,040,160.00
3 Lantai 2 - Keramik Tile 40x40/setara (menuju B. Penghubung M2 76 162,970.00 12,385,720.00
Dinding r.Wudhu WC - Granit Tile 60 x 60 Garuda/setara M 2
86 303,160.00 26,071,760.00
4 Pelapis Vinil untuk tangga 1 dan 2 M 2
36 290,590.00 10,461,240.00
Kelengkapan
lain-lain ls 1 7,000,000.00 7,000,000.00 Penunjang
Lembur
JUMLAH 131,561,440.00
D. PEKERJAAN PLAFOND DAN PENGECATAN (Lt Dasar, 1, 2)
1 Pasangan rangka Baja ringan Hollow 40 x 40 t = 1.2 mm M2 102 147,556.00 15,050,712.00
2 Pasangan Plafond Gypsum Akustik Setara Tombo M 2
69.2 180,000.00 12,456,000.00
3 Pengecatan Dinding Cat Weathershield (Outdoor) M 2
587.68 38,530.00 22,643,310.40 Outdoor
4 Pengecatan Dinding Panel (Indoor) M 2
730 21,770.00 15,892,100.00
5 Polituran Daun Pintu double akustik M2 62 84,840.00 5,260,080.00 Indoor
6 Pasangan List Plafond Pinggir balok lantai M' 128 27,660.00 3,540,480.00
Kelengkapan
lain-lain ls 1 7,000,000.00 7,000,000.00 Penunjang
Lembur
JUMLAH 81,842,682.40
E. PEKERJAAN DEKORATIF DAN SOUNDPROFING
1 Perapihan tepian beton ekspos M2 900 18,000.00 16,200,000.00
2 Peredam Suara Diffuser pada Multipleks 9 mm M2 85 190,000.00 16,150,000.00
3 Vertical blind /roll M 2
132 390,000.00 51,480,000.00
4 Sekat Kaca ruang kadis dan sekdis unit 2 7,000,000.00 14,000,000.00
Wallsystem Unit Gypsum 9 mm, Rangka Multipleks 18 mm,
5 Melamin Cop, Kaca Polos 5 mm Unit 1 9,000,000.00 9,000,000.00
Kelengkapan
lain-lain ls 1 7,000,000.00 7,000,000.00 Penunjang
Lembur
JUMLAH 538,295,000.00
TOTAL PEKERJAAN ARSITEKTUR 1,125,681,148.22
JUMLAH GEDUNG A 1,303,736,890.22
Pekerjaan Lif
No Uraian Qty Satuan Harga Jumlah
Komponen Utama
1 Lift 1 unit 571,050,000 571,050,000
Pengiriman dan Commisioning
1 Pengiriman 1 ls 15,000,000 15,000,000
2 Pemasangan dan Testing Commisioning 1 ls 35,000,000 35,000,000
Pajak 10% ls 62,105,000 62,105,000
Jumlah 683,155,000
RENCANA ANGGARAN BIAYA
PEKERJAAN : Konstruksi Gedung Kantor DPKP3 Kodya Bandung
GEDUNG B
HARGA
NO URAIAN PEKERJAAN SATUAN VOLUME JUMLAH HARGA (RP) KETERANGAN
SATUAN (RP)
I PEKERJAAN PERSIAPAN
1 Perbaikan Perkuatan - Lantai Dasar (dinding kolom balok) M' 113.2 320,000.00 36,224,000.00
2 Perbaikan Perkuatan - Lantai 1 (lantai dan Kolom Balok) M' 169.8 320,000.00 54,336,000.00
3 Perbaikan Perkuatan - Lantai 2 (lantai dan kolam Balok) M' 186.4 360,000.00 67,104,000.00
4 Pembersihan M 2
509.4 12,000.00 6,112,800.00
5 Lain-lain ( pembersihan dan pembuangan) ls 1 18,506,880.00 18,506,880.00
TOTAL PEKERJAAN PERSIAPAN JUMLAH 182,283,680.00
II PEKERJAAN STRUKTUR
1 Kap Rangka kuda2 IWF,Canal kg 2150 18,750.00 40,312,500.00
2 Pek Talang Beton Waterproofing M' 96 231,654.00 22,238,784.00
Kelengkapan
3 lain-lain ls 1 7,000,000.00 7,000,000.00 Penunjang
Lembur
TOTAL PEKERJAAN STRUKTUR JUMLAH 69,551,284.00
III PEKERJAAN ARSITEKTUR
A. PEKERJAAN PASANGAN DINDING DAN ATAP
1 Pasangan Dinding Bata Con Block Hebel M2 436 221,880.00 96,739,680.00
2 Sekat ruang kantor q panel M 2
235 282,990.00 66,502,650.00
3 Pek acian MU/setara M2 763.72 17,750.00 13,556,030.00
4 Plesteran dan Acian dinding luar/balok-Kolom M 2
480 60,710.00 29,140,800.00
5 Pekerjaan Rangka Atap Baja Ringan t = 0.75 mm M 2
286.23 168,042.00 48,098,661.66
6 Pekerjaan Atap Ondline + wuwung t = 0.3 mm M 2
246 235,220.00 57,864,120.00
7 Pasangan Pipa Air Hujan PVC dia 3'' M' 115 124,505.00 14,318,075.00
8 Kedap panas Alumunium foil/Glasswool M 2
182 166,000.00 30,212,000.00
Kelengkapan
9 lain-lain ls 1 7,000,000.00 7,000,000.00 Penunjang
Lembur
JUMLAH 363,432,016.66
B. PEKERJAAN PINTU DAN JENDELA
1 Pasangan Kusen Pintu Dan Jendela Almunium 4'' M' 194 127,940.00 24,820,360.00
2 Pasangan Daun Pintu Panil (teak wood finishing melamic) buah 18 1,764,820.00 31,766,760.00
3 Pasangan Rangka Jendela Almunium(kaca dof 5mm) M2 35 706,820.00 24,738,700.00
4 Pasangan Engsel Pintu Bh 46 59,680.00 2,745,280.00
5 Pasangan Engsel Jendela Bh 62 56,566.00 3,507,092.00
6 Pasangan Kunci pintar ex. SAMSUNG bh 14 3,328,770.00 46,602,780.00
7 Pasangan Kunci Double Slag Bh 6 339,610.00 2,037,660.00
8 Pasangan Hak Angin Bh 51 62,310.00 3,177,810.00
9 Pasangan Sekat Kaca Bening t = 8 mm M 2
94 251,680.00 23,657,920.00
10 Pasangan Spring Knip Bh 12 46,180.00 554,160.00
Kelengkapan
11 lain-lain ls 1 7,000,000.00 7,000,000.00 Penunjang
Lembur
JUMLAH 170,608,522.00
C. PEKERJAAN LANTAI
1 Lantai Dasar - keramik Tile 60 x 60 Garuda/setara M2 240 162,970.00 39,112,800.00
2 Dinding WC - Granit Tile 30 x 60 Garuda/setara M 2
79 303,160.00 23,949,640.00
3 Lantai 1 - keramik Tile 60 x 60 Garuda/setara M2 248 162,970.00 40,416,560.00
4 Dinding WC - Granit Tile 60 x 60 Garuda/setara M 2
86 303,160.00 26,071,760.00
5 Lantai 2 - granit Tile 60 x 60 Garuda/setara M 2
247 162,970.00 40,253,590.00
6 Dinding WC - Granit Tile 30 x 60 Garuda/setara M 2
78 303,160.00 23,646,480.00
7 Granite tile tangga dan stepnosing M2 42 390,000.00 16,380,000.00
8 Plin kayu (Finishing Melamic) M 440 22,000.00 9,680,000.00
Kelengkapan
9 lain-lain ls 1 7,000,000.00 7,000,000.00 Penunjang
Lembur
JUMLAH 226,510,830.00
D. PEKERJAAN PLAFOND EXPOSE DAN PENGECATAN
1 Pasangan panel kaca Décoratif sekat kaca r.Kasi/Kabid M2 114.6 270,000.00 30,942,000.00
2 Pasangan Plafond Gypsum Akustik Setara Jayaboard M2 195 190,000.00 37,050,000.00
3 Pengecatan Dinding Cat Weathershield (Outdoor) M 2
950 38,530.00 36,603,500.00 Outdoor
4 Pengecatan Dinding Panel (Indoor) M 2
1050 21,770.00 22,858,500.00
5 Perapihan Pelapisan plafon beton M 2
1200 24,000.00 28,800,000.00 Indoor
6 Pasangan List Plafond ,perapihan Pinggir Tembok balok lantai M' 808 27,660.00 22,349,280.00
Kelengkapan
7 lain-lain ls 1 7,000,000.00 7,000,000.00 Penunjang
Lembur
JUMLAH 185,603,280.00
E PEKERJAAN DEKORATIF DAN SOUNDPROFING
1 Peredam Suara Instalasi Glasswool Density 80 M2 90 185,000.00 16,650,000.00
2 Peredam Suara Diffuser Multipleks 9 mm M 2
45 180,000.00 8,100,000.00
3 Verticalblind/roll M2 72 390,000.00 28,080,000.00
4 Rak Gudang/Kitchen Set/Meja Wastafel M' 20 2,750,000.00 55,000,000.00
5 Wallsystem Unit Gypsum 9 mm, akustik Unit 77 210,000.00 16,170,000.00
6 Tangga ke lt Dak/baja Hollow unit 2 9,200,000.00 18,400,000.00
7 Hand rail tangga Stailess kaca M' 32 2,698,755.00 86,360,160.00
Kelengkapan
8 lain-lain ls 1 7,000,000.00 7,000,000.00 Penunjang
Lembur
JUMLAH 235,760,160.00
PEKERJAAN ARSITEKTUR 1,181,914,808.66
JUMLAH GEDUNG B 1,433,749,772.66
RENCANA ANGGARAN BIAYA
(ENGINERING ESTIMATE)
I PEKERJAAN PERSIAPAN
1 Pek bonkaran area Ground tank,pengolah grey water m3 380 68,000.00 25,840,000.00
2 Bongkaran Bangunan ex P U Bina Marga m2 380 35,000.00 13,300,000.00
3 Pembersihan dan Pembuangan m2 620 48,000.00 29,760,000.00
4 Pengukuran/Blowplank m2 450 9,000.00 4,050,000.00
5 pek Perataan Urugan koridor Bina Marga ls 1 18,000,000.00 18,000,000.00
Kelengkapan
6 Lain-lain 1 24,000,000.00 24,000,000.00 Penunjang
Lembur
TOTAL PEKERJAAN PERSIAPAN JUMLAH 114,950,000.00
II PEKERJAAN STRUKTUR (GEDUNG C & PARKIR)
1 Pekerjaan Pondasi
a. Pekerjaan Tanah m3 330 148,000.00 48,840,000.00
b. Pondasi Straus Pal/lift( 2x 6 m1) titik 19 14,350,000.00 272,650,000.00
c. balok sloof gantung 30/45/ pile Cap m3 12 3,600,000.00 43,200,000.00
c. Pekerjaan Ground Tank m3 34 4,200,000.00 142,800,000.00
2 Struktur Baja IWF(ged.C ,parkir dan R pompa)
a. Kolom IWF kg 21,000 21,000.00 441,000,000.00
b. Balok IWF kg 29,000 21,000.00 609,000,000.00
c. Expansion Joint titik 2 15,500,000.00 31,000,000.00
3 Cor Plat Lantai 1,2,3,4,gd Parkir m3 152 3,650,000.00 554,800,000.00
6 Dudukan ,jalur /selubung lift/shaft ls 1 68,000,000.00 68,000,000.00
Kelengkapan
7 Lain-lain ls 1 20,500,000.00 20,500,000.00 Penunjang
Lembur
TOTAL PEKERJAAN STRUKTUR 2,231,790,000.00
III PEKERJAAN ARSITEKTUR
A. PEKERJAAN PASANGAN DINDING CON BLOCK DAN ATAP
1 Pasangan Dinding Panel Beton Ringan M2 260 221,880.00 57,688,800.00
2 Plin Profil Kayu M 580 22,000.00 12,760,000.00
3 Acian Ramp parkir motordan dinding/ r.Pompa M2 1,400 17,750.00 24,850,000.00
4 Pekerjaan Rangka Atap Baja Ringan t = 0.75 mm M2 226 168,042.00 37,977,492.00
5 Pekerjaan Atap tutup unit AC Zincalume t = 0.3 mm M2 98 235,220.00 23,051,560.00
6 Pek, Talang Beton Waterproofing M' 320 115,000.00 36,800,000.00
7 Pek Panel alumunium Comp0site' M' 210 274,020.00 57,544,200.00
8 Peredam panas Instalasi Glasswool /alumunium M2 235 285,000.00 66,975,000.00
9 Kap Lt3 Galvalume m2 110 237,800.00 26,158,000.00
Kelengkapan
10 Lain-lain ls 1 18,000,000.00 18,000,000.00 Penunjang
Lembur
JUMLAH 361,805,052.00
IV PEKERJAAN PINTU DAN JENDELA
1 Pasangan Kusen Pintu Dan Jendela Almunium 4'' M' 380 127,940.00 48,617,200.00 Annodice
2 Pasangan Daun Pintu Panil (teak wood finishing melamic) buah 9 1,764,820.00 15,883,380.00
3 Pasangan Rangka daun Jendela Almunium (kaca 5 mm) M2 14 706,820.00 9,895,480.00
4 Pasangan Engsel Pintu Bh 16 59,680.00 954,880.00
5 Pasangan Engsel Jendela Bh 11 56,566.00 622,226.00
6 Pasangan Kunci pintar SAMSUNG bh 4 4,327,401.00 17,309,604.00 3,328,770.00
7 Pasangan Kunci Double Slag Bh 4 339,610.00 1,358,440.00
8 Pasangan Hak Angin Bh 8 62,310.00 498,480.00
9 Pasangan Sekat Kaca Bening t = 8 mm M2 94 327,184.00 30,755,296.00 251,680.00
10 Pasangan Kaca tempered lengkung Bening t = 10 mm M2 148 1,198,652.00 177,400,496.00 922,040.00
11 Pasangan Spring Knip Bh 6 46,180.00 277,080.00
Kelengkapan
12 Lain-lain ls 1 9,000,000.00 9,000,000.00 Penunjang
Lembur
JUMLAH 312,572,562.00
V PEKERJAAN LANTAI
1 Lantai Dasar - trap tangga Granit Tile 60 x 60 Garuda/setara M2 40 303,160.00 12,126,400.00 Outdoor
2 Lantai 1 - Granit Tile 60 x 60 Garuda/setara M2 139 303,160.00 42,139,240.00 Indoor
3 Lantai 2 dan 3 - Granit Tile 60 x 60 Garuda/setara M2 367 303,160.00 111,259,720.00
4 lantai 1 dan 2 - mosaic Granit Tile M2 77 951,120.00 73,236,240.00
Kelengkapan
5 Lain-lain ls 1 9,000,000.00 9,000,000.00 Penunjang
Lembur
JUMLAH 247,761,600.00
VI PEKERJAAN PLAFOND DAN PENGECATAN (Tanpa Fix Interior)
1 Pasangan Rangka Panel Besi Hollow 40 x 40 t = 1.2 mm M2 214.6 147,556.00 31,665,517.60
2 Pasangan olah plafon track kabel M2 314.6 168,000.00 52,852,800.00
3 Pengecatan Dinding Cat Weathershield (Outdoor) M2 346.5 38,530.00 13,350,645.00
4 Pengecatan Dinding Panel (Indoor) M2 540 21,770.00 11,755,800.00
Kelengkapan
5 lain-lain ls 1 12,000,000.00 12,000,000.00 Penunjang
Lembur
JUMLAH 121,624,762.60
VII PEKERJAAN (Fasad)
1 Sirip panel pipa tembaga 20 mm(termasuk Dudukan) M2 217 1,200,000.00 260,820,000.00
2 Alcobond m2 89 270,000.00 24,030,000.00
Kelengkapan
3 lain-lain ls 1 7,000,000.00 7,000,000.00 Penunjang
Lembur
JUMLAH 291,850,000.00
TOTAL PEKERJAAN ARSITEKTUR 1,335,613,976.60
JUMLAH GEDUNG C 3,682,353,976.60 4,091,504.42
RENCANA ANGGARAN BIAYA
(taman- halaman Parkir)
640,000.00
I PEKERJAAN MEKANIKAL - AIR BERSIH
setara
memanjang
toto std
toto std
lokal
China
toto std
III INSTALASI HVAC
Total
No Item Pekerjaan Volume Sat. Unit Price Keterangan
Rp.
A. GEDUNG A
a. Lantai Dasar
1 Instalasi Air Conditioning pindahan eks G. A
a IN Unit 7.00 Bh 4,500,000 31,500,000 Teknologi VRV IV
b Pipa Refrigerant - -
Gas : 15,88 mm 108.00 m' 92,727 10,014,545
Liquid : 6,35 mm 108.00 m' 57,818 6,244,364
c Pipa Drain PVC AW (10 Kg/Cm2) + Isolasi - -
Dia. 15 mm 150.00 m' 18,091 2,713,636
2 Instalasi Air Conditioning
a IN Unit Kecil 0.00 Bh - -
b Pipa Refrigerant - -
Gas : 9,5 mm 90.00 m' 92,727 8,345,455
Liquid : 6,35 mm 90.00 m' 57,818 5,203,636
c Pipa Drain PVC AW (10 Kg/Cm2) + Isolasi - -
Dia. 15 mm 75.00 m' 18,091 1,356,818
2 Exhaust Fan Mushola dan Toilet - -
a EF 4.00 Bh 320,727 1,282,909
Merk CKE - -
Type Ceiling Propeler - -
b CME 2.00 Bh 691,091 1,382,182
Merk CKE - -
Type Ceiling Propeler - -
5 Instalasi Ventilasi Exhaust - -
Duct PVC D Dia. 100 mm (4") 60.00 m' 62,182 3,730,909
Exhaust Grill 20 cm x 20 cm 3.00 Bh 376,364 1,129,091
Fiting 1.00 Lot 437,455 437,455
Support & Hanger 1.00 Lot 364,545 364,545
Consumable Material 1.00 Lot 291,545 291,545
TESTING & COMMISIONING 1.00 Ls 1,003,636 1,003,636
SUB TOTAL Lantai Dasar 75,000,727
b. Lantai Satu
1 Instalasi Air Conditioning
a IU 4.00 Bh 32,000,000 128,000,000 Teknologi VRV IV
b Pipa Refrigerant - -
Gas : 15,88 mm 108.00 m' 92,727 10,014,545
Liquid : 6,35 mm 108.00 m' 57,818 6,244,364
c Pipa Drain PVC AW (10 Kg/Cm2) + Isolasi - -
Dia. 15 mm 60.00 m' 18,091 1,085,455
2 Instalasi Air Conditioning
a IU kecil 4.00 Bh 12,000,000 48,000,000 Teknologi VRV IV
b Pipa Refrigerant - -
Gas : 9,5 mm 126.00 m' 92,727 11,683,636
Liquid : 6,35 mm 126.00 m' 57,818 7,285,091
c Pipa Drain PVC AW (10 Kg/Cm2) + Isolasi - -
Dia. 15 mm 60.00 m' 18,091 1,085,455
2 Exhaust Fan Toilet dan Pantry - -
a EF 4.00 Bh 320,727 1,282,909
Merk CKE - -
Type Ceiling Propeler - -
b CME 2.00 Bh 691,091 1,382,182
Merk CKE - -
Type Ceiling Propeler - -
5 Instalasi Ventilasi Exhaust - -
Duct PVC D Dia. 100 mm (4") 60.00 m' 62,182 3,730,909
Exhaust Grill 20 cm x 20 cm 3.00 Bh 376,364 1,129,091
Fiting 1.00 Lot 437,455 437,455
Support & Hanger 1.00 Lot 364,545 364,545
Consumable Material 1.00 Lot 291,545 291,545
TESTING & COMMISIONING 1.00 Ls 1,003,636 1,003,636
SUB TOTAL Lantai Satu 223,020,818
c. Lantai Dua
1 Instalasi Air Conditioning
a IU 4.00 Bh 32,000,000 128,000,000 Teknologi VRV IV
b Pipa Refrigerant - -
Gas : 15,88 mm 126.00 m' 92,727 11,683,636
Liquid : 6,35 mm 126.00 m' 57,818 7,285,091
c Pipa Drain PVC AW (10 Kg/Cm2) + Isolasi - -
Dia. 15 mm 75.00 m' 18,091 1,356,818
2 Instalasi Air Conditioning
a IU Unit Kecil 4.00 Bh 12,000,000 48,000,000 Teknologi VRV IV
b Pipa Refrigerant - -
Gas : 9,5 mm 108.00 m' 92,727 10,014,545
Liquid : 6,35 mm 108.00 m' 57,818 6,244,364
c Pipa Drain PVC AW (10 Kg/Cm2) + Isolasi - -
Dia. 15 mm 75.00 m' 18,091 1,356,818
3 Exhaust Fan Toilet & Pantry - -
a EF 4.00 Bh 320,727 1,282,909
Merk CKE - -
Type Ceiling Propeler - -
b CME 2.00 Bh 691,091 1,382,182
Merk CKE - -
Type Ceiling Propeler - -
4 OU 15 PK 5.00 unit 42,000,000 210,000,000 Teknologi VRV IV
5 Instalasi Ventilasi Exhaust - -
Duct PVC D Dia. 100 mm (4") 60.00 m' 62,182 3,730,909
Exhaust Grill 20 cm x 20 cm 3.00 Bh 376,364 1,129,091
Fiting 1.00 Lot 437,455 437,455
Support & Hanger 1.00 Lot 364,545 364,545
Consumable Material 1.00 Lot 291,545 291,545
TESTING & COMMISIONING 1.00 Ls 1,003,636 1,003,636
SUB TOTAL Lantai Dua 433,563,545
TOTAL HVAC Gedung A 731,585,091
B. GEDUNG B
a. Lantai Dasar
1 Exhaust Fan Toilet Staff - -
a EF 4.00 Bh 320,727 1,282,909
Merk CKE - -
Type Ceiling Propeler - -
b CME 2.00 Bh 691,091 1,382,182
Merk CKE - -
Type Ceiling Propeler - -
2 Instalasi Ventilasi Exhaust - -
Duct PVC D Dia. 100 mm (4") 40.00 m' 62,182 2,487,273
Exhaust Grill 20 cm x 20 cm 3.00 Bh 376,364 1,129,091
Fiting 1.00 Lot 437,455 437,455
Support & Hanger 1.00 Lot 364,545 364,545
Consumable Material 1.00 Lot 291,545 291,545
TESTING & COMMISIONING 1.00 Ls 1,003,636 1,003,636
SUB TOTAL Lantai Dasar 8,378,636
b. Lantai Satu
1 Instalasi Air Conditioning
a IU besar 4.00 Bh 32,000,000 128,000,000 Teknologi VRV IV
b Pipa Refrigerant - -
Gas : 15,88 mm 90.00 m' 92,727 8,345,455
Liquid : 6,35 mm 90.00 m' 57,818 5,203,636
c Pipa Drain PVC AW (10 Kg/Cm2) + Isolasi - -
Dia. 15 mm 75.00 m' 18,091 1,356,818
2 Instalasi Air Conditioning
a IU Unit Kecil 6.00 Bh 12,000,000 72,000,000 Teknologi VRV IV
b Pipa Refrigerant - -
Gas : 9,5 mm 72.00 m' 92,727 6,676,364
Liquid : 6,35 mm 72.00 m' 57,818 4,162,909
c Pipa Drain PVC AW (10 Kg/Cm2) + Isolasi - -
Dia. 15 mm 45.00 m' 18,091 814,091
2 Exhaust Fan Toilet Staff - -
a EF 6.00 Bh 320,727 1,924,364
Merk CKE - -
Type Ceiling Propeler - -
b CME 2.00 Bh 691,091 1,382,182
Merk CKE - -
Type Ceiling Propeler - -
5 Instalasi Ventilasi Exhaust - -
Duct PVC D Dia. 100 mm (4") 40.00 m' 62,182 2,487,273
Exhaust Grill 20 cm x 20 cm 3.00 Bh 376,364 1,129,091
Fiting 1.00 Lot 437,455 437,455
Support & Hanger 1.00 Lot 364,545 364,545
Consumable Material 1.00 Lot 291,545 291,545
TESTING & COMMISIONING 1.00 Ls 1,003,636 1,003,636
SUB TOTAL Lantai Satu 235,579,364
c. Lantai Dua
1 Instalasi Air Conditioning
a IU Unit 4.00 Bh 32,000,000 128,000,000 Teknologi VRV IV
b Pipa Refrigerant - -
Gas : 15,88 mm 90.00 m' 92,727 8,345,455
Liquid : 6,35 mm 90.00 m' 57,818 5,203,636
c Pipa Drain PVC AW (10 Kg/Cm2) + Isolasi - -
Dia. 15 mm 75.00 m' 18,091 1,356,818
2 Instalasi Air Conditioning
a IU Kecil 4.00 Bh 12,000,000 48,000,000 Teknologi VRV IV
b Pipa Refrigerant - -
Gas : 9,5 mm 36.00 m' 92,727 3,338,182
Liquid : 6,35 mm 36.00 m' 57,818 2,081,455
c Pipa Drain PVC AW (10 Kg/Cm2) + Isolasi - -
Dia. 15 mm 45.00 m' 18,091 814,091
2 Exhaust Fan Toilet Staff - -
a EF 6.00 Bh 320,727 1,924,364
Merk CKE - -
Type Ceiling Propeler - -
b CME 2.00 Bh 691,091 1,382,182
Merk CKE - -
Type Ceiling Propeler - -
3 OU 15 PK 5.00 unit 42,000,000 210,000,000 Teknologi VRV IV
4 Instalasi Ventilasi Exhaust 5.00 unit 800,000 4,000,000
Duct PVC D Dia. 100 mm (4") 40.00 m' 62,182 2,487,273
Exhaust Grill 20 cm x 20 cm 3.00 Bh 376,364 1,129,091
Fiting 1.00 Lot 437,455 437,455
Support & Hanger 1.00 Lot 364,545 364,545
Consumable Material 1.00 Lot 291,545 291,545
SUB TOTAL Lantai Dua 419,156,091
TOTAL HVAC Gedung B 663,114,091
C. GEDUNG C
a. Lantai Satu
1 Instalasi Air Conditioning
a IU 3.00 Bh 32,000,000 96,000,000
b Pipa Refrigerant - -
Gas : 15,88 mm 24.00 m' 92,727 2,225,455
Liquid : 6,35 mm 24.00 m' 57,818 1,387,636
c Pipa Drain PVC AW (10 Kg/Cm2) + Isolasi - -
Dia. 15 mm 20.00 m' 18,091 361,818
Fiting 1.00 Lot 437,455 437,455
Support & Hanger 1.00 Lot 364,545 364,545
Consumable Material 1.00 Lot 291,545 291,545
TESTING & COMMISIONING 1.00 Ls 1,003,636 1,003,636
SUB TOTAL Lantai Satu 102,072,091
b. Lantai Dua
1 Instalasi Air Conditioning
a IU Unit Besar 2.00 Bh 32,000,000 64,000,000 Teknologi VRV IV
b Pipa Refrigerant - -
Gas : 15,88 mm 24.00 m' 92,727 2,225,455
Liquid : 6,35 mm 24.00 m' 57,818 1,387,636
c Pipa Drain PVC AW (10 Kg/Cm2) + Isolasi - -
Dia. 15 mm 20.00 m' 18,091 361,818
Fiting 1.00 Lot 437,455 437,455
Support & Hanger 1.00 Lot 364,545 364,545
Consumable Material 1.00 Lot 291,545 291,545
TESTING & COMMISIONING 1.00 Ls 1,003,636 1,003,636
SUB TOTAL Lantai Dua 70,072,091
c. Lantai Tiga
1 Instalasi Air Conditioning
a IU Unit Kecil 3.00 Bh 12,000,000 36,000,000 Teknologi VRV IV
b Pipa Refrigerant - -
Gas : 15,88 mm 24.00 m' 92,727 2,225,455
Liquid : 6,35 mm 24.00 m' 57,818 1,387,636
c Pipa Drain PVC AW (10 Kg/Cm2) + Isolasi - -
Dia. 15 mm 20.00 m' 18,091 361,818
Fiting 1.00 Lot 437,455 437,455
Support & Hanger 1.00 Lot 364,545 364,545
Consumable Material 1.00 Lot 291,545 291,545
TESTING & COMMISIONING 1.00 Ls 1,003,636 1,003,636
SUB TOTAL Lantai Tiga 42,072,091
TOTAL HVAC Gedung C 214,216,273
TESTING & COMMISIONING 1.00 Ls 1,003,636 1,003,636
SUB TOTAL Testing & Comissioning 1,003,636
Harga satuan
Total
No. Item Pekerjaan Volume Sat. Material Upah KETERANGAN
Rp. Rp. Rp.
A PRIME EQUITMENT HYDRANT PUMP
1 Electric Hydrant Pump (NFPA 20 Standard) 1 Unit 42,137,143 2,901,600 45,038,743
2 Diesel Hydrant Pump (NFPA 20 Standard) 1 Unit 48,256,000 3,230,300 51,486,300
3 Jockey Fire Hydrant Pump (NFPA 20 Standard) Ex. Groun 1 Unit 15,040,909 1,552,600 16,593,509
SUB TOTAL A 113,118,552
B ADDITIONAL EQUITMENT HYDRANT PUMP
1 Check Valve dia. 80 mm (3") 2 Bh 2,124,800 72,000 4,393,600
2 Gate Valve dia. 80 mm (3") 3 Bh 2,094,000 72,000 6,498,000
3 Flexibel Joint dia. 80 mm (3") 2 Bh 771,800 72,000 1,687,600
3 Gate Valve dia. 100 mm (4") 3 Bh 2,895,300 96,000 8,973,900
4 Flexibel Joint dia. 100 mm (4") 2 Bh 917,400 96,000 2,026,800
5 Strainer Valve dia. 100 mm (4") 2 Bh 2,372,600 96,000 4,937,200
6 Gate Valve dia. 40 mm (1.5") 2 Bh 1,219,200 36,000 2,510,400
7 Check Valve dia. 40 mm (1.5") 1 Bh 1,294,200 36,000 1,330,200
8 Flexibel Joint dia. 40 mm (1.5") 2 Bh 384,300 36,000 840,600
9 Strainer Valve dia. 40 mm (1.5") 1 Bh 703,800 36,000 739,800
10 Foot Valve dia. 40 mm (1.5") 1 Bh 1,847,700 36,000 1,883,700
11 Foot Valve dia. 80 mm (3") 1 Bh 1,786,500 72,000 1,858,500
12 Foot Valve dia. 100 mm (4") 1 Bh 2,034,300 96,000 2,130,300
13 Gate Valve dia. 150 mm (6") 1 Bh 5,048,400 144,000 5,192,400
14 Relief Valve dia. 80 mm (3") 1 Bh 8,105,400 96,000 8,201,400
15 Preesure Gauge + Ball Valve 5 Bh 423,000 48,000 2,355,000
16 Preesure Swtich + Ball Valve 3 Bh 1,083,000 24,000 3,321,000
17 Header 200 mm (8") 1 Lot 6,476,200 896,800 7,373,000
18 Gate Valve dia. 25 mm (1") (swrew) 2 Bh 211,800 24,000 471,600
19 Safety Valve dia 30 mm (1.25") 10 kg/cm2 1 Bh 4,606,500 18,000 4,624,500
Installation R. Pump Hydrant & Instalation Sprinkler
20 site Black Steel Pipe Schadule 40
Finish Red Painting Anti Corrosive
- dia. 25 mm ( 1" ) 35 m' 38,500 28,800 2,355,500
- dia. 40 mm ( 1.5" ) 35 m' 61,300 40,800 3,573,500
- dia. 80 mm ( 3" ) 35 m' 162,400 76,800 8,372,000
- dia. 100 mm ( 4" ) 35 m' 230,200 100,800 11,585,000
21 Fitting & Accessories 1 Lot 9,284,560 1,740,900 11,025,460
22 Consumable material 1 Lot 7,737,120 1,450,700 9,187,820
23 Support & Hanger 1 Lot 6,189,680 1,160,600 7,350,280
SUB TOTAL 124,799,060
C TESTING & COMMISIONING 1 Ls 840,000 8,400,000 9,240,000
SUB TOTAL 9,240,000
TOTAL POMPA HYDRANT 247,157,612
VI INSTALASI FIRE HYDRANT
A INSTALLASI HYDRANT AREA SITE
1 Outdoor Hydrant Box complete Type C with : 2 Unit 4,013,200 357,000 8,740,400
2 Hydrant Pillar 4 Unit 5,784,560 192,000 23,906,240
3 Seames Connection 1 Unit 5,154,320 192,000 5,346,320
4 Instalasi Hydrant Area Site Pipa A53 Schadule 40
Finish Red Painting Anti Corrosive Outdoor
- dia. 100 mm ( 4" ) 66 m' 230,200 100,800 21,846,000 Indoor
- dia. 150 mm ( 6" ) 50 m' 401,200 148,800 27,500,000
5 Master Control Valve Alarm Gong Dia 6" 1 Set 14,603,850 1,407,600 16,011,450
6 Check Valve dia. 100 mm (4") 1 Bh 3,092,100 96,000 3,188,100
7 Gate Valve dia. 150 mm (6") 3 Bh 5,048,400 144,000 15,577,200
B Instalasi Water Hammer
1 Check Valve dia. 150 mm (6") 2 Bh 6,370,700 144,000 13,029,400
2 Ball Valve Valve dia. 150 mm (6") 4 Bh 5,541,000 144,000 22,740,000
3 Wraping asphalt 31 m2 65,600 7,100 2,253,700
4 Fitting & Accessories 1 Lot 10,194,389 5,504,960 15,699,349
5 Consumable material 1 Lot 7,645,789 4,128,720 11,774,509
6 Support & Hanger 1 Lot 8,920,089 4,816,840 13,736,929
SUB TOTAL 201,349,597
GEDUNG A, B DAN C
B INSTALASI HYDRANT & FIRE EXTINGUISHER LANTAI DASAR
1 Indoor Hydrant Box complete Type B with : 4 Unit 4,823,400 595,000 21,673,600
2 Instalasi Hydrant Pipa A53 Schadule 40
Finish Red Painting Anti Corrosive
- dia. 100 mm ( 4" ) 71 m' 320,960 148,800 33,352,960
- dia. 80 mm ( 3" ) 52.5 m' 162,400 76,800 12,558,000
- dia. 65 mm ( 2.5" ) 14 m' 130,400 64,800 2,732,800
- dia. 40 mm ( 1.5" ) 4 m' 61,300 40,800 408,400
3 Gate Valve dia. 80 mm (3") 1 Bh 2,094,000 72,000 2,166,000
4 Gate Valve dia. 100 mm (4") 1 Bh 2,895,300 96,000 2,991,300
5 Fire Extinguisher Dry Chemical 3.5 kg Ex. Quick Fire 6 Bh 602,700 30,000 3,796,200
6 Fitting & Accessories 1 Lot 5,425,218 1,790,320 7,215,538
7 Consumable material 1 Lot 4,521,018 1,491,920 6,012,938
8 Support & Hanger 1 Lot 3,616,800 1,193,560 4,810,360
SUB TOTAL 97,718,096
C INSTALASI HYDRANT & FIRE EXTINGUISHER LANTAI SATU
1 Indoor Hydrant Box complete Type B with : 4 Unit 4,823,400 595,000 21,673,600
2 Instalasi Hydrant Pipa A53 Schadule 40
Finish Red Painting Anti Corrosive
- dia. 80 mm ( 3" ) 22 m' 162,400 76,800 5,262,400
- dia. 65 mm ( 2.5" ) 17 m' 130,400 64,800 3,318,400
- dia. 40 mm ( 1.5" ) 5 m' 61,300 40,800 510,500
3 Gate Valve dia. 80 mm (3") 3 Bh 2,094,000 72,000 6,498,000
4 Fire Extinguisher Dry Chemical 3.5 kg Ex. Quick Fire 6 Bh 602,700 30,000 3,796,200
5 Fitting & Accessories 1 Lot 3,877,300 581,600 4,458,900
6 Consumable material 1 Lot 3,231,100 484,700 3,715,800
7 Support & Hanger 1 Lot 2,584,900 387,700 2,972,600
SUB TOTAL 52,206,400
D INSTALASI HYDRANT & FIRE EXTINGUISHER LANTAI DUA
1 Indoor Hydrant Box complete Type B with : 4 Unit 4,823,400 595,000 21,673,600
2 Instalasi Hydrant Pipa A53 Schadule 40
Finish Red Painting Anti Corrosive
- dia. 80 mm ( 3" ) 3 m' 162,400 76,800 717,600
- dia. 65 mm ( 2.5" ) 11 m' 130,400 64,800 2,147,200
- dia. 40 mm ( 1.5" ) 3 m' 61,300 40,800 306,300
3 Gate Valve dia. 80 mm (3") 2 Bh 2,094,000 72,000 4,332,000
4 Fire Extinguisher Dry Chemical 3.5 kg Ex. Quick Fire 6 Bh 602,700 30,000 3,796,200
5 Fitting & Accessories 1 Lot 866,500 130,000 996,500
6 Consumable material 1 Lot 722,100 108,300 830,400
7 Support & Hanger 1 Lot 577,700 86,600 664,300
SUB TOTAL 35,464,100
E INSTALASI HYDRANT & FIRE EXTINGUISHER LANTAI TIGA
1 Fire Extinguisher Dry Chemical 3.5 kg Ex. Quick Fire 2 Bh 602,700 30,000 1,265,400
2 Fitting & Accessories 1 Lot 1,914,400 287,200 2,201,600
3 Consumable material 1 Lot 1,595,300 239,300 1,834,600
4 Support & Hanger 1 Lot 1,276,300 191,400 1,467,700
SUB TOTAL 6,769,300
F INSTALASI PIPA TEGAK MAIN LINE HYDRANT & SPRINKLER
1 Instalasi Pipa Tegak Main Line Hydrant & Sprinkler A53 Schadule 40
Finish Red Painting Anti Corrosive
- dia. 100 mm ( 4" ) 22 m' 320,960 148,800 10,334,720
2 Fitting & Accessories 1 Lot 4,124,700 618,700 4,743,400
3 Consumable material 1 Lot 5,499,600 824,900 6,324,500
4 Support & Hanger 1 Lot 2,749,800 412,500 3,162,300
SUB TOTAL 24,564,920
G TESTING & COMMISIONING 1 LS 1,200,000 12,000,000 13,200,000
SUB TOTAL 13,200,000
SUB TOTAL INSTALASI FIRE HYDRANT 678,430,025
V INSTALASI SPRINKLER
Harga satuan Total KETERANG
No. Item Pekerjaan Volume Sat.
Material Rp. Upah Rp. Rp. AN
GEDUNG A, B DAN C
A INSTALASI SPRINKLER LANTAI DASAR
1 Instalasi Sprinkler Pipa A53 Schadule 40
Finish Red Painting Anti Corrosive
- dia. 100 mm ( 4" ) 19.17 m' 230,200 100,800 6,344,167
- dia. 50 mm ( 2" ) 12.00 m' 81,100 52,800 1,606,800
- dia. 40 mm ( 1.5" ) 10.00 m' 61,300 40,800 1,021,000
- dia. 32 mm ( 1.25" ) 28.11 m' 51,700 34,800 2,431,611
- dia. 15 mm ( 1" ) 53.75 m' 38,500 28,800 3,617,375
2 Instalasi Dran (flushing) & Test Sprinkler Pipa A53 Schadule 40
Finish Red Painting Anti Corrosive
- dia. 50 mm ( 2" ) 18.00 m' 81,100 52,800 2,410,200
- Gate Valve dia. 50 mm ( 2" ) 1.00 Bh 348,000 48,000 396,000
3 BCV dia. 150 mm ( 6") (Branch Control Unit) lengkap dengan 1.00 Bh 7,918,000 572,400 8,490,400
Flow Swtich, Sligh Glass & Valve Test Sprinkler
4 Head Sprinkler 28.00 Bh 73,200 12,000 2,385,600
5 Fitting & Accessories 1.00 Lot 11,568,100 12,146,500 23,714,600
6 Consumable material 1.00 Lot 9,640,086 10,122,100 19,762,186
7 Support & Hanger 1.00 Lot 7,712,071 8,097,700 15,809,771
SUB TOTAL 87,989,710
B INSTALASI SPRINKLER LANTAI SATU
1 Instalasi Sprinkler Pipa A53 Schadule 40
Finish Red Painting Anti Corrosive
- dia. 100 mm ( 4" ) 9.25 m' 230,200 100,800 3,061,750
- dia. 80 mm ( 3" ) 18.00 m' 162,400 76,800 4,305,600
- dia. 50 mm ( 2" ) 17.50 m' 81,100 52,800 2,343,250
- dia. 40 mm ( 1.5" ) 34.00 m' 61,300 40,800 3,471,400
- dia. 32 mm ( 1.25" ) 34.50 m' 51,700 34,800 2,984,250
- dia. 15 mm ( 1" ) 72.00 m' 38,500 28,800 4,845,600
2 Instalasi Dran (flushing) & Test Sprinkler Pipa A53 Schadule 40
Finish Red Painting Anti Corrosive
- dia. 50 mm ( 2" ) 13.00 m' 81,100 52,800 1,740,700
- Gate Valve dia. 50 mm ( 2" ) 1.00 Bh 348,000 48,000 396,000
3 BCV dia. 150 mm ( 6") (Branch Control Unit) lengkap dengan 1.00 Bh 11,877,000 572,400 12,449,400
Flow Swtich, Sligh Glass & Valve Test Sprinkler
4 Head Sprinkler 58.00 Bh 73,200 12,000 4,941,600
5 Fitting & Accessories 1.00 Lot 5,611,375 3,366,800 8,978,175
6 Consumable material 1.00 Lot 4,676,150 2,805,700 7,481,850
7 Support & Hanger 1.00 Lot 4,987,900 2,244,500 7,232,400
SUB TOTAL 64,231,975
C INSTALASI SPRINKLER LANTAI DUA
1 Instalasi Sprinkler Pipa A53 Schadule 40
Finish Red Painting Anti Corrosive
- dia. 100 mm ( 4" ) 8.33 m' 230,200 100,800 2,758,333
- dia. 80 mm ( 3" ) 8.67 m' 162,400 76,800 2,073,067
- dia. 50 mm ( 2" ) 19.00 m' 81,100 52,800 2,544,100
- dia. 40 mm ( 1.5" ) 17.00 m' 61,300 40,800 1,735,700 Outdoor
- dia. 32 mm ( 1.25" ) 3.00 m' 51,700 34,800 259,500 Indoor
- dia. 15 mm ( 1" ) 84.25 m' 38,500 28,800 5,670,025
2 Instalasi Dran (flushing) & Test Sprinkler Pipa A53 Schadule 40
Finish Red Painting Anti Corrosive
- dia. 50 mm ( 2" ) 15.00 m' 81,100 52,800 2,008,500
- Gate Valve dia. 50 mm ( 2" ) 1.00 Bh 348,000 48,000 396,000
3 BCV dia. 150 mm ( 6") (Branch Control Unit) lengkap dengan 1.00 Bh 11,877,000 572,400 12,449,400
Flow Swtich, Sligh Glass & Valve Test Sprinkler
4 Head Sprinkler 49.00 Bh 73,200 12,000 4,174,800
5 Fitting & Accessories 1.00 Lot 6,305,550 1,891,700 8,197,250
6 Consumable material 1.00 Lot 5,254,600 1,576,400 6,831,000
7 Support & Hanger 1.00 Lot 4,203,700 1,261,100 5,464,800
SUB TOTAL 54,562,475
D INSTALASI SPRINKLER LANTAI TIGA
1 Instalasi Sprinkler Pipa A53 Schadule 40
Finish Red Painting Anti Corrosive
- dia. 100 mm ( 4" ) 12.50 m' 230,200 100,800 4,137,500
- dia. 80 mm ( 3" ) 13.00 m' 162,400 76,800 3,109,600
- dia. 50 mm ( 2" ) 19.00 m' 81,100 52,800 2,544,100
- dia. 40 mm ( 1.5" ) 8.50 m' 61,300 40,800 867,850
- dia. 32 mm ( 1.25" ) 3.00 m' 51,700 34,800 259,500
- dia. 15 mm ( 1" ) 67.40 m' 38,500 28,800 4,536,020
2 Instalasi Dran (flushing) & Test Sprinkler Pipa A53 Schadule 40
Finish Red Painting Anti Corrosive
- dia. 50 mm ( 2" ) 15.00 m' 81,100 52,800 2,008,500
- Gate Valve dia. 50 mm ( 2" ) 1.00 Bh 348,000 48,000 396,000
3 BCV dia. 150 mm ( 6") (Branch Control Unit) lengkap dengan 1.00 Bh 11,877,000 572,400 12,449,400
Flow Swtich, Sligh Glass & Valve Test Sprinkler
4 Head Sprinkler 69.00 Bh 73,200 12,000 5,878,800
5 Fitting & Accessories 1.00 Lot 12,611,100 1,891,700 14,502,800
6 Consumable material 1.00 Lot 10,509,200 1,576,400 12,085,600
7 Support & Hanger 1.00 Lot 8,407,400 1,261,100 9,668,500
SUB TOTAL 72,444,170
E INSTALASI PIPA TEGAK DRAIN & TEST DRAIN
1 Instalasi Pipa Tegak Dran (flushing) & Test Drain Sprinkler Pipa A53
Schadule 40
Finish Red Painting Anti Corrosive
- dia. 50 mm ( 2" ) 58.00 m' 81,100 52,800 7,766,200
2 Fitting & Accessories 1.00 Lot 2,109,200 316,400 2,425,600
3 Consumable material 1.00 Lot 3,515,400 527,300 4,042,700
4 Support & Hanger 1.00 Lot 1,406,200 210,900 1,617,100
SUB TOTAL 15,851,600
J TESTING & COMMISIONING 1.00 LS 1,200,000 12,000,000 13,200,000
SUB TOTAL 13,200,000
TOTAL INSTALASI SPRINKLER 308,279,930
VI INSTALASI FIRE ALARM
Total
No. Uraian Volume Sat. Unit Price Keterangan
Rp.
GEDUNG A
A. Instalasi Fire Alarm
a. Lantai Dasar
1 ROR Heat Detector 10.00 bh 318,181.82 3,181,818.18
2 Photo Elektrik Smoke Detector 28.00 bh 345,454.55 9,672,727.27
3 Break Glass Switch 8.00 bh 136,363.64 1,090,909.09
4 Alarm Bell 8.00 bh 145,454.55 1,163,636.36
5 Lampu Tanda 8.00 bh 113,636.36 909,090.91
6 Instalasi Detector 38.00 titik 136,363.64 5,181,818.18
7 Material Bantu 1.00 ls 909,090.91 909,090.91
SUB TOTAL - 22,109,090.91
b. Lantai Satu
1 ROR Heat Detector 10.00 bh 318,181.82 3,181,818.18
2 Photo Elektrik Smoke Detector 32.00 bh 345,454.55 11,054,545.45
3 Break Glass Switch 8.00 bh 136,363.64 1,090,909.09
4 Alarm Bell 8.00 bh 145,454.55 1,163,636.36
5 Lampu Tanda 8.00 bh 113,636.36 909,090.91
6 Instalasi Detector 42.00 titik 136,363.64 5,727,272.73
7 Material Bantu 1.00 ls 909,090.91 909,090.91
SUB TOTAL - 24,036,363.64
c. Lantai Dua
1 ROR Heat Detector 10.00 bh 318,181.82 3,181,818.18
2 Photo Elektrik Smoke Detector 32.00 bh 345,454.55 11,054,545.45
3 Break Glass Switch 8.00 bh 136,363.64 1,090,909.09
4 Alarm Bell 8.00 bh 145,454.55 1,163,636.36
5 Lampu Tanda 8.00 bh 113,636.36 909,090.91
6 Instalasi Detector 42.00 titik 136,363.64 5,727,272.73
7 Material Bantu 1.00 ls 909,090.91 909,090.91
SUB TOTAL - 24,036,363.64
TOTAL PEKERJAAN FIRE ALARM GEDUNG A 70,181,818.18
GEDUNG B
A. Instalasi Fire Alarm
a. Lantai Dasar
1 ROR Heat Detector 6.00 bh 318,181.82 1,909,090.91
2 Photo Elektrik Smoke Detector 18.00 bh 345,454.55 6,218,181.82
3 Break Glass Switch 12.00 bh 136,363.64 1,636,363.64
4 Alarm Bell 12.00 bh 145,454.55 1,745,454.55
5 Lampu Tanda 12.00 bh 113,636.36 1,363,636.36
6 Instalasi Detector 24.00 titik 136,363.64 3,272,727.27
7 Material Bantu 1.00 ls 909,090.91 909,090.91
SUB TOTAL - 17,054,545.45
b. Lantai Satu
1 ROR Heat Detector 6.00 bh 318,181.82 1,909,090.91
2 Photo Elektrik Smoke Detector 18.00 bh 345,454.55 6,218,181.82
3 Break Glass Switch 12.00 bh 136,363.64 1,636,363.64
4 Alarm Bell 12.00 bh 145,454.55 1,745,454.55
5 Lampu Tanda 12.00 bh 113,636.36 1,363,636.36
6 Instalasi Detector 24.00 titik 136,363.64 3,272,727.27
7 Material Bantu 1.00 ls 909,090.91 909,090.91
SUB TOTAL - 17,054,545.45
c. Lantai Dua
1 ROR Heat Detector 6.00 bh 318,181.82 1,909,090.91
2 Photo Elektrik Smoke Detector 18.00 bh 345,454.55 6,218,181.82
3 Break Glass Switch 12.00 bh 136,363.64 1,636,363.64
4 Alarm Bell 12.00 bh 145,454.55 1,745,454.55
5 Lampu Tanda 12.00 bh 113,636.36 1,363,636.36
6 Instalasi Detector 24.00 titik 136,363.64 3,272,727.27
7 Material Bantu 1.00 ls 909,090.91 909,090.91
SUB TOTAL - 17,054,545.45
TOTAL PEKERJAAN FIRE ALARM GEDUNG B 51,163,636.36
GEDUNG C -
A. Instalasi Fire Alarm
a. Lantai Dasar
1 ROR Heat Detector 4.00 bh 318,181.82 1,272,727.27
2 Photo Elektrik Smoke Detector 12.00 bh 345,454.55 4,145,454.55
3 Break Glass Switch 2.00 bh 136,363.64 272,727.27
4 Alarm Bell 2.00 bh 145,454.55 290,909.09
5 Lampu Tanda 2.00 bh 113,636.36 227,272.73
6 Instalasi Detector 16.00 titik 136,363.64 2,181,818.18
7 Material Bantu 1.00 ls 909,090.91 909,090.91
SUB TOTAL - 9,300,000.00
b. Lantai Satu
1 ROR Heat Detector 4.00 bh 318,181.82 1,272,727.27
2 Photo Elektrik Smoke Detector 12.00 bh 345,454.55 4,145,454.55
3 Break Glass Switch 2.00 bh 136,363.64 272,727.27
4 Alarm Bell 2.00 bh 145,454.55 290,909.09
5 Lampu Tanda 2.00 bh 113,636.36 227,272.73
6 Instalasi Detector 16.00 titik 136,363.64 2,181,818.18
7 Material Bantu 1.00 ls 909,090.91 909,090.91
SUB TOTAL - 9,300,000.00
c. Lantai Dua
1 ROR Heat Detector 4.00 bh 318,181.82 1,272,727.27
2 Photo Elektrik Smoke Detector 12.00 bh 345,454.55 4,145,454.55
3 Break Glass Switch 2.00 bh 136,363.64 272,727.27
4 Alarm Bell 2.00 bh 145,454.55 290,909.09
5 Lampu Tanda 2.00 bh 113,636.36 227,272.73
6 Instalasi Detector 16.00 titik 136,363.64 2,181,818.18
7 Material Bantu 1.00 ls 909,090.91 909,090.91
SUB TOTAL - 9,300,000.00
TOTAL PEKERJAAN FIRE ALARM GEDUNG C 27,900,000.00
E TESTING & COMMISIONING 4.00 Ls 2,090,909.09 8,363,636.36
SUB TOTAL 8,363,636.36
SUB TOTAL INSTALASI FIRE ALARM 157,609,090.91
VII. PEKERJAAN ELEKTRIKAL
Total
No. Uraian Pekerjaan Q'ty Unit Unit Price Keterangan
Harga
A INSTALASI GENSET
1 Dudukan Genset dan rumah pompa 6 titik 4,800,000 28,800,000
2 Tambah Daya 200.000 KVA dan Pemindahan Trafo 1 ls 122,000,000 122,000,000
3 Perbaikan Diesel Generator Set Lama 1 Set 70,877,778 70,877,778
4 Diesel Generator 1 set 120,000,000 120,000,000
5 Pekerjaan Plumbing untuk instalasi 1 ls 6,429,091 6,429,091
6 Support & Material Bantu 1 ls 8,181,818 8,181,818
SUB TOTAL A - 356,288,687
B PANEL TEGANGAN RENDAH -
1 OHM Saklar 2 set 4,243,636 8,487,273
2 PUTR ( Panel Utama Tegangan Rendah ) 2 set 13,462,727 26,925,455
2 PL-1 Penerangan Lantai 1 2 set 4,896,250 9,792,500
3 Support & Material Bantu 2 ls 467,273 934,545
SUB TOTAL B - 46,139,773
C PEKERJAAN KABEL FEEDER -
Kabel Feeder -
1 NYY 4C-10 mm2 ( Proporsional ) 32 m 99,091 3,170,909
2 l NYY 4C-6 mm2 20 m 72,222 1,444,444
+ NYA 6 mm2 - -
3 l NYY 4C-2,5 mm2 212 m 40,000 8,480,000
+ NYA 2,5 mm2 - -
4 Material bantu & terminasi 4 ls 786,364 3,145,455
SUB TOTAL C - 16,240,808
D INSTALASI PENTANAHAN -
1 Bak Kontrol & Grounding Point Panel PUTR Max. 2 Ohm 3 ttk 3,553,636 10,660,909
2 Kabel Pentanahan dengan kabel BC 50mm2 90 mtr 67,273 6,054,545
SUB TOTAL D 16,715,455
E INSTALASI SMART BUILDING -
1 Software 1 Lot 180,000,000 180,000,000
2 Hardware 1 Lot 350,000,000 350,000,000
SUB TOTAL E 530,000,000
F INSTALASI PENERANGAN DAN STOP KONTAK
1 PEKERJAAN INSTALASI
A. GEDUNG A
a. Lantai Dasar
1 Down Light LED 10 W 81 bh 216,364 17,525,455
2 Outbouw Down Light LED 10 W 19 bh 154,091 2,927,727
3 Stop Kontak 1 Ph, 13 A,220 V 7 bh 48,182 337,273
4 Stop Kontak AC 1 Ph, 220 V 8 bh 80,909 647,273
5 Saklar Tunggal 39 bh 43,636 1,712,727
6 Saklar Ganda 20 bh 55,455 1,088,295
7 Saklar Hotel Tunggal 2 bh 48,182 96,364
8 kabel NYM.3 x 2,5 mm² c/w PVC Konduit dia. 20 mm 68 ttk 291,667 19,833,333
9 Cable Ladder 75 m' 227,272.73 17,045,454.55
10 Material Bantu 4 ls 1,363,636 5,454,545
Sub Total Lantai Dasar 66,668,447
b. Lantai Satu
1 Down Light LED 11 W 62 bh 216,364 13,414,545
2 Outbouw Down Light LED 13 W 12 bh 188,333 2,260,000
3 Tl-LED gantung 16 W 24 ttik 282,500 6,780,000
4 Stop Kontak 1 Ph, 13 A,220 V 8 bh 48,182 385,455
6 Stop Kontak AC 1 Ph, 220 V 8 bh 80,909 647,273
7 Saklar Tunggal 28 bh 43,636 1,200,000
8 Saklar Ganda 14 bh 55,455 762,500
9 Saklar Hotel Tunggal 2 bh 48,182 96,364
10 kabel NYM.3 x 2,5 mm² c/w PVC Konduit dia. 20 mm 48 ttk 291,667 14,000,000
11 Cable Ladder 55 m' 227,272.73 12,500,000.00
12 Material Bantu 6 ls 1,363,636 8,181,818
Sub Total Lantai Satu 60,227,955
c. Lantai Dua
1 Down Light LED 11 W 67 bh 216,364 14,496,364
2 Outbouw Down Light LED 13 W 18 bh 282,500 5,085,000
3 TL -LED Gantung 16 W 24 bh 282,500 6,780,000
4 Stop Kontak 1 Ph, 13 A,220 V 8 bh 48,182 385,455
5 Stop Kontak AC 1 Ph, 220 V 8 bh 80,909 647,273
6 Saklar Tunggal 35 bh 43,636 1,516,364
7 Saklar Ganda 17 bh 55,455 963,523
8 Saklar Hotel Tunggal 2 bh 48,182 96,364
9 Kabel NYM.3 x 2,5 mm² c/w PVC Konduit dia. 20 mm 48 ttk 291,667 14,000,000
10 Cable Ladder 75 m' 227,272.73 17,045,454.55
11 Material Bantu 6 ls 1,363,636 8,181,818
Sub Total Lantai Dua 69,197,614
TOTAL Instalasi Penerangan & Stop Kontak Gedung A 196,094,015 -
B. GEDUNG B
a. Lantai Satu
1 Down Light LED 10 W 24 bh 216,364 5,192,727
2 Tl- LED Ganting 22 bh 282,500 6,215,000
3 Stop Kontak 1 Ph, 13 A,220 V 12 bh 48,182 578,182
4 Stop Kontak AC, 13 A,220 V 6 bh 80,909 485,455
5 Saklar Ganda 12 bh 55,455 665,455
6 kabel NYM.3 x 2,5 mm² c/w PVC Konduit dia. 20 mm 48 ttk 291,667 14,000,000
7 Cable Ladder 65 m' 227,272.73 14,772,727.27
8 Material Bantu 3 ls 1,363,636 4,090,909
Sub Total Lantai Satu 46,000,455
b. Lantai Dua
1 Down Light LED 10 W 15 bh 216,364 3,245,455
2 TL-LED Gantung 24 bh 282,500
3 Stop Kontak 1 Ph, 13 A,220 V 12 bh 48,182 578,182
4 Saklar Ganda 8 bh 55,455 415,909
5 kabel NYM.3 x 2,5 mm² c/w PVC Konduit dia. 20 mm 35 ttk 291,667 10,062,500
6 Cable Ladder 25 m' 227,272.73 5,681,818.18
7 Material Bantu 3 ls 1,363,636 4,090,909
Sub Total Lantai Dua 24,074,773
c. Lantai Tiga
1 Down Light LED 11 W 35 bh 216,364 7,572,727
2 Tl -LED Gantung 24 bh 282,500 6,780,000
3 Stop Kontak 1 Ph, 13 A,220 V 4 bh 176,667 706,667
4 Saklar Ganda 18 bh 101,667 1,779,167
5 kabel NYM.3 x 2,5 mm² c/w PVC Konduit dia. 20 mm 57 ttk 291,667 16,479,167
6 Cable Ladder 25 m' 227,272.73 5,681,818.18
7 Material Bantu 3 ls 1,363,636 4,090,909
Sub Total Lantai Tiga 43,090,455
TOTAL Instalasi Penerangan & Stop Kontak Gedung B 113,165,682 -
C. GEDUNG C
a. Lantai Dasar dan Bang Parkir
1 Outbouw Down Light LED 11 W 12 bh 216,364 2,596,364
2 Tl-LED gantung 16 W 12 bh 282,500 3,390,000
3 Stop Kontak AC 1 Ph, 220 V 2 bh 80,909 161,818
4 Saklar Tunggal 2 bh 160,000 384,000
5 Saklar Ganda 2 bh 203,333 488,000
6 Saklar Hotel Tunggal 2 bh 176,667 353,333
7 kabel NYM.3 x 2,5 mm² c/w PVC Konduit dia. 20 mm 19 ttk 291,667 5,483,333
8 Cable Ladder 50 m' 227,272.73 11,363,636.36
9 Material Bantu 4 ls 1,363,636 5,454,545
Sub Total Lantai Dasar 29,675,030
b. Lantai Satu
1 Outbouw Down Light LED 10 W 45 bh 216,364 9,736,364
2 TL-LED Gantung 16W 18 bh 282,500 5,085,000
3 Stop Kontak 1 Ph, 13 A,220 V 18 bh 48,182 867,273
4 Stop Kontak AC 1 Ph, 220 V 6 bh 80,909 485,455
5 Saklar Tunggal 9 bh 43,636 392,727
6 Saklar Ganda 9 bh 55,455 499,091
7 Saklar Hotel Tunggal 1 bh 176,667 176,667
8 kabel NYM.3 x 2,5 mm² c/w PVC Konduit dia. 20 mm 69 ttk 291,667 20,125,000
9 Cable Ladder 44 m' 227,272.73 10,000,000.00
10 Material Bantu 4 ls 1,363,636 5,454,545
Sub Total Lantai Satu 52,822,121
c. Lantai Dua
1 Outbouw Down Light LED 10 W 18 bh 216,364 3,894,545
2 TL-LED gantung 16 W 6 bh 282,500 1,695,000
3 Stop Kontak 1 Ph, 13 A,220 V 6 bh 48,182 289,091
4 Stop Kontak AC 1 Ph, 220 V 4 bh 80,909 323,636
5 Saklar Tunggal 4 bh 43,636 157,091
6 Saklar Ganda 4 bh 55,455 199,636
7 Saklar Hotel Tunggal 2 bh 48,182 96,364
8 kabel NYM.3 x 2,5 mm² c/w PVC Konduit dia. 20 mm 29 ttk 159,091 4,645,455
9 Hanger & Support 4 Lot 2,123,909.09 8,495,636.36
10 Cable Ladder 42 m' 227,272.73 9,545,454.55
11 Material Bantu 4 ls 1,363,636 5,454,545
Sub Total Lantai Dua 34,796,455
TOTAL Instalasi Penerangan & Stop Kontak Gedung C 117,293,606 -
F PENANGKAL PETIR -
1 Kepala Penangkal Petir 4 Unit 1,216,667 4,866,667
2 Kabel 50mm2 + Klem 60 m' 106,364 6,381,818
3 Bak Kontrol & Grounding Point Max.2 Ohm 4 ls 1,776,818 7,107,273
4 Material Bantu 4 ls 876,364 3,505,455
SUB TOTAL F - 21,861,212
G TESTING & COMMISSIONING -
1 Testing & Commissioning 2 ls 3,506,364 7,012,727
SUB TOTAL G 7,012,727
GEDUNG A
Harga Satuan
No Uraian Pekerjaan Satuan Vulume Jumlah Harga (Rp.)
(Rp.)
A PERALATAN UTAMA.
1 PABX 1 set 6,272,727 6,272,727.27
2 UPS 600 VA + Back up Battery 2 set 2,727,273 5,454,545.45
3 MDF-Telepon 2 set 917,273 1,834,545.45
4 Instalasi Peralatan Utama 2 ls 642,727 1,285,454.55
5 Material Bantu 1 ls 1,015,455 1,015,454.55
SUB TOTAL A - 15,862,727.27
B KABEL FEEDER -
1 TITC 20x2x0.6 mm2 15 m 170,000 2,550,000.00
2 TITC 10x2x0.6 mm2 20 m 110,000 2,200,000.00
( Proposional Sum ) - -
3 Material Bantu 1 ls 87,273 87,272.73
SUB TOTAL B - 4,837,272.73
C INSTALASI TELPON -
1 Single Line Telepon 20 bh 1,243,333 24,866,666.67
2 Outlet Telepon 20 bh 106,364 2,127,272.73
3 Instalasi titik Telepon dgn kabel ITC 2x2x0.6 mm2 20 ttk 173,636 3,472,727.27
c/w PVC conduit 20 mm - -
4 Material bantu 2 ls 80,000 160,000.00
SUB TOTAL C - 30,626,666.67
D TESTING & COMMISIONING -
1 Testing & Commissioning 1 ls 291,818 291,818.18
SUB TOTAL D 291,818.18
Total 51,618,484.85
GEDUNG B
Harga Satuan
No Uraian Pekerjaan Satuan Vulume Jumlah Harga (Rp.)
(Rp.)
II PEKERJAAN INSTALASI TELEPON
A PERALATAN UTAMA.
1 PABX (6 line 24 ext) 1 set 11,500,000 11,500,000.00
2 UPS 600 VA + Back up Battery 2 set 2,727,273 5,454,545.45
3 MDF-Telepon 2 set 917,273 1,834,545.45
4 Instalasi Peralatan Utama 2 ls 642,727 1,285,454.55
5 Material Bantu 1 ls 1,015,455 1,015,454.55
SUB TOTAL A - 21,090,000.00
B KABEL FEEDER -
1 TITC 20x2x0.6 mm2 15 m 46,364 695,454.55
2 TITC 10x2x0.6 mm2 20 m 36,667 733,333.33
( Proposional Sum ) - -
3 Material Bantu 1 ls 87,273 87,272.73
SUB TOTAL B - 1,516,060.61
C INSTALASI TELPON -
1 Single Line Telepon 20 bh 932,500 18,650,000.00
2 Outlet Telepon 20 bh 117,000 2,340,000.00
3 Instalasi titik Telepon dgn kabel ITC 2x2x0.6 mm2 20 ttk 191,000 3,820,000.00
c/w PVC conduit 20 mm - -
4 Material bantu 2 ls 60,000 120,000.00
SUB TOTAL C - 24,930,000.00
D TESTING & COMMISIONING -
1 Testing & Commissioning 1 ls 321,000 321,000.00
SUB TOTAL D 321,000.00
Total 47,857,060.61
GEDUNG C
Harga Satuan
No Uraian Pekerjaan Satuan Vulume (Rp.) Jumlah Harga (Rp.)
GEDUNG A
TOTAL 116,487,535
GEDUNG B
Total
No. Uraian Pekerjaan Q'ty Unit Unit Price
Harga
IIIPEKERJAAN INSTALASI TV
A PERALATAN UTAMA
1 Pemasangan TV Cable 1 set 2,500,000 2,500,000
2 Sound System 2 set 10,526,316 21,052,632
3 Pengabelan & pemasangan untuk 2 ls 7,143,333 14,286,667
peralatan utama lengkap dgn accessories - -
4 Penarikan Kabel 185 m 40,417 7,477,083
dgn kabel 2x RG c/w PVC conduit 20 mm - -
5 Material Bantu 1 ls 821,429 821,429
SUB TOTAL A 46,137,810
B. INSTALASI MATV
1 INSTALASI LANTAI DASAR DAN LT 1
1 Spliter 4 Way 8 bh 282,727 2,261,818
2 Outlet TV 14 bh 86,364 1,209,091
3 Instalasi Outlet TV 14 ttk 302,667 4,237,333
c/w PVC conduit 20 mm
4 Material bantu 1 ls 681,818 681,818
SUB TOTAL B 8,390,061
C. TESTING & COMMISIONING
1 Testing & Commissioning 2 ls 1,493,636 2,987,273
SUB TOTAL C 2,987,273
TOTAL 57,515,143
KETERANGAN