Anda di halaman 1dari 9

Journal of Purchasing & Supply Management 18 (2012) 113–121

Contents lists available at SciVerse ScienceDirect

Journal of Purchasing & Supply Management


journal homepage: www.elsevier.com/locate/pursup

The interplay of governance mechanisms in complex procurement projects


Marjolein C.J. Caniëls a,1, Cees J. Gelderman a,n, Nicole P. Vermeulen b,2
a
Open University of the Netherlands (OUNL), Faculty of Management Sciences, P.O. Box 2960, 6401 DL Heerlen, The Netherlands
b
Open University of the Netherlands (OUNL), Faculty of Management Sciences, c/o Rue du 31-Décembre 26, 1207 Gene ve, Switzerland

a r t i c l e i n f o abstract

Available online 2 June 2012 Although many studies have investigated governance in inter-firm relationships, little is known about
Keywords: the simultaneous use of several governance mechanisms in complex procurement projects and their
Governance mechanisms impact on project outcomes. In a case study about a complex procurement project in the Norwegian oil
Contract theory and gas industry, we investigate the interplay of contractual incentives, authority and relational
Complex procurements governance. The project faced many problems with cost overruns and schedule delays. The study
Buyer–supplier relationships clearly illustrates the interrelationships between governance mechanisms and their effect on project
Authority outcomes. The findings suggest that relational governance (trust) is only beneficial for project outcomes
Trust when it is accompanied by contractual incentives and control systems (authority). Relational govern-
Contractual incentives
ance in itself does not guarantee an effective and beneficial interplay of all three mechanisms in a way
that positive project outcomes are generated.
& 2012 Elsevier Ltd. All rights reserved.

1. Introduction complementary (e.g., Poppo and Zenger, 2002; Ness and Haugland,
2005). Even though many studies have investigated the operation of
Complex procurement projects are characterized by a high isolated governance mechanisms (e.g. Gassenheimer et al., 1996;
degree of uncertainty and technological complexity, the involve- Hawkins et al., 2008; Jap and Anderson, 2003; Joshi and Stump,
ment of a large number of actors, and a time span of several years 1996; Poppo and Zenger, 2002; Wathne and Heide, 2000), only few
(Olsen et al., 2005). The complexity usually prevents the buyer studies investigate the simultaneous use of several governance
from simply buying discrete components and combining these. mechanisms (exceptions are Caniëls and Gelderman, 2010; Olsen
Therefore, the buying process does not follow the serial and et al., 2005; Liu et al., 2009).
sequential transaction mode of traditional procurement (Caldwell This paper contributes to current understanding of governance
et al., 2009). Hence, it is a managerial challenge to design contracts mechanisms in different ways. First, we investigate the simulta-
and employ governance mechanisms that can cope with the pitfalls neous use of contractual incentives, authority and relational
associated with uncertainty, transaction costs and opportunism governance. Hence, we specifically focus on the interplay of
that are typically involved in these complex procurement projects governance mechanisms, something that has not been addressed
(cf. Williamson, 1985, 1991). very often in academic studies. Second, the paper takes a dynamic
Governance mechanisms are safeguards against opportunism perspective on the development of governance mechanisms in
that firms employ to govern inter-organizational exchange (Jap inter-firm relationships, by studying the changes in the interplay
and Ganesan, 2000). Companies use formal governance mechanisms of different mechanisms over time.Inter-firm relationships are
such as market contracts and authority (Yu et al., 2006), as well as intrinsically unstable, because the costs and the benefits of the
relational governance mechanisms such as relational norms and relationship may change for each party after a while. In the
trust (Zaheer and Venkatraman, 1995). In managerial practice these beginning, benefits of the cooperation outweigh the costs. How-
mechanisms are often applied in combination. However, in aca- ever, as the cooperation continues circumstances might cause
demic literature there exist opposing views on whether or not costs to overshadow the benefits for one of the parties, while the
governance mechanisms act as substitutes (e.g., Reve, 1990; Wuyts other party may still gain from the relationship. This situation
and Geyskens, 2005; Williamson, 1985) or whether they are may induce opportunistic behavior of one party. Several govern-
ance mechanisms can safeguard against this opportunistic beha-
vior. However, the accents on each of the isolated mechanisms in
n
Corresponding author. Tel.: þ31 45 5762590; fax: þ31 45 5762103. the constellation of all mechanisms may have to shift over time as
E-mail addresses: Marjolein.Caniels@ou.nl (M.C.J. Caniëls), well, in order to attend to the changing circumstances and
Kees.Gelderman@ou.nl (C.J. Gelderman), changing behavior of business parties. Since it is hard to carry
nicolevermeulen@hotmail.com (N.P. Vermeulen).
1 out longitudinal studies, adaptations in the mix of governance
Tel.: þ31 45 5762724; fax: þ31 45 5762103.
2
Tel.: þ41 77 4622963. mechanisms over time are hardly ever investigated. Yet, they are

1478-4092/$ - see front matter & 2012 Elsevier Ltd. All rights reserved.
http://dx.doi.org/10.1016/j.pursup.2012.04.007
114 M.C.J. Caniëls et al. / Journal of Purchasing & Supply Management 18 (2012) 113–121

part of daily business practice and as such a relevant and impact of the following governance mechanisms (cf. Wang et al.,
interesting area of research that can offer important managerial 2008; Olsen et al., 2005):
insights. Third, the study links the co-evolvement of governance
mechanisms to project outcomes, assessed in terms of cost, timely 1. Price agreements and incentives anchored in contracts;
delivery and achieved quality. The specific focus on project out- 2. Hierarchical mechanisms, based on control and authority;
comes is original, because most studies in this field focus on the 3. Relational governance mechanisms, based on trust.
use or working of governance mechanisms in buyer–supplier
relationships, but not so much on the impact of these mechan- Contractual agreements are tied to the functioning of the
isms in a project management context. market mechanism in which behavior is induced by economic
In order to explore the interplay of governance mechanisms a rationales and prices. Contracts ensure relationship governance
case study has been conducted on a complex procurement project by imposing explicit, legally enforceable contractual terms (cf.
in the Norwegian offshore oil and gas industry. Companies in the Williamson, 1991).
oil and gas industry generally spend around 80% to 90% of their Hierarchical control is primarily used to governance relation-
costs on contractors (Raymond and Leffler, 2006). Procurement ships with a strong hierarchical structure, and is generally labeled
projects in this sector are generally complex, inducing companies as authority (e.g. Olsen et al., 2005). Authority implies the reliance
to explore the simultaneous use of contracts and other governance on governance mechanisms such as rules and procedures, and it
mechanisms (Olsen et al., 2005). The case study involved semi- involves exercising control and power strategies (Haugland and
structured interviews with key respondents, which were employed Reve, 1994; Ness and Haugland, 2005). Authority is applied by the
by an initial operator, a second operator and an integrator. party who has the (legitimate) right to make decisions. This party
Furthermore, this study draws on the available documentation is then using its power to control the activities of the other party
and archival records such as contracts and project monthly reports. (Wang et al., 2008).
This article is organized as follows. First, we present the In contrast to contracts and authority that can be classified as
theoretical background of the study, resulting in a conceptual formal governance mechanisms, trust is a typical example of
model. Then, we discuss the research methodology, followed by a relational governance (cf. Yu et al., 2006). Relational governance
presentation of the results of the case study. Subsequently, we assumes a shared set of norms and values between exchange
discuss the results by analyzing our empirical observations and partners (Wang et al., 2008). Important relational norms are
comparing them to what is known from previous studies. The flexibility, solidarity, and information exchange (Heide and John,
final section presents conclusions and recommendations for 1992), and mutuality, role integrity, and harmonization of rela-
further research. tions conflict (Ness and Haugland, 2005). These relational norms
can provide an important safeguard against opportunistic beha-
vior (Caniëls and Gelderman, 2010; Macneil, 1980; Dwyer et al.,
2. Theoretical background 1987). Relational governance (trust) implies that transactions are
monitored while relying on social norms and personal relation-
2.1. Governance mechanisms ships (Haugland and Reve, 1994). It refers to the willingness
to rely on exchange partners in whom one has confidence
Building or rebuilding an offshore oil platform is a typical (Moorman et al., 1992). Sako (1992) emphasized that trust refers
example of a complex procurement project, involving several to an expectation that a trading partner behaves in a predictable
contractors and subcontractors for a number of years (Olsen and acceptable manner. Basically, the most important aspect of
et al., 2005), and requiring extensive coordination between parties. trust is a positive belief, an affective sentiment about an exchange
Complex procurements are often associated with uncertainty and partner. One has confidence in the partner’s reliability and
(technological) complexity. The financial risks are likely to be integrity (Morgan and Hunt, 1994). It is widely acknowledged
enormous. The complexity of such projects makes it very hard to that trust is of key importance in projects that involve multiple
plan and achieve project outcomes in terms of time, costs and project partners (e.g., Maurer, 2010).
functioning according to specifications. Furthermore, since compa- The literature on governance mechanisms distinguishes many
nies are in a constant struggle to achieve competitive advantage other potential safeguards such as reducing information asym-
and financial performance, there is potential for opportunistic metry (monitoring), promoting goal convergence and values
behavior (Hawkins et al., 2008). Williamson (1975, p. 6) defined (socialization), and to excluding less reliable partners (selection)
opportunism as ‘‘self interest seeking with guile’’. Opportunism (e.g. Wathne and Heide, 2000). We adopt the classification into
includes the incomplete or distorted disclosure of information. It contracts, authority, and relational governance (trust), because it
refers to calculated efforts to mislead, distort, disguise or otherwise covers a broad area of measures that can be employed when
confuse the other party (Williamson, 1985). Many studies have dealing with opportunistic behaviors. Moreover, each of the three
demonstrated the destructive and devastating impact of opportu- mechanisms operates in a different way, therefore it may have a
nism on the performance of a strategic alliance (Parkhe, 1993), unique impact on performance outcomes (cf. Jap and Anderson,
satisfaction (Gassenheimer et al., 1996), trust (Morgan and Hunt, 2003). The theoretical underpinning of this classification lies in
1994), and its potential to generate conflict (Joshi and Stump, contract theory, which considers contracts as a structural dimen-
1996). Hence, opportunistic behavior can be expected to have sion in relationships (Ness and Haugland, 2005).
a detrimental impact on cooperation in complex procurement
projects. 2.2. Interplay of governance mechanisms
Companies can utilize a variety of governance mechanisms in
order to cope with exchange hazards and to reduce or prevent The current literature on governance mechanisms has not yet
opportunism. Governance mechanisms are safeguards that firms reached consensus on whether governance mechanisms substi-
employ to govern inter-organizational exchange, minimize expo- tute, or rather complement each other. Various studies have
sure to opportunism and protect transaction specific investments emphasized the complementary characteristics of using different
(Jap and Ganesan, 2002). These mechanisms are used in several governance mechanisms (e.g., Das and Teng, 1998; Larson, 1992;
interorganizational exchanges, also in procurement. In this study Poppo and Zenger, 2002; Zucker, 1986; Klein Woolthuis et al.,
we seek to expand the knowledge of the isolated and combined 2005; North, 1990; Hoetker and Mellewigt, 2008; Bradach and
M.C.J. Caniëls et al. / Journal of Purchasing & Supply Management 18 (2012) 113–121 115

Eccles,1989). Haugland and Reve (1994) found that governance


Incentives/contract
by contractual agreements, authority and trust can be used in
different combinations for safeguarding against opportunism. One
important reason for arguing that different governance mechan-
Project outcomes:
isms should be combined, is the presence of a large number of - cost
governance challenges in most inter-firm relationships, and the Trust - time
application of only one mechanism is therefore not sufficient - quality
(Bradach and Eccles, 1989). Contractual governance mechanisms
and relational governance mechanisms serve different goals and
have different functionalities, and could therefore be complemen-
Authority
tary in their roles in facilitating exchange performance (Das and
Teng, 1998; Ferguson et al., 2005; Haugland and Reve, 1994). A
well-tailored contract might stimulate collaborative behaviors Fig. 1. Research model.
and create a restraint on opportunism. Furthermore, relational
governance and trust might be useful in overcoming the adaptive project success is by determining whether the project stayed
limits of contracts (Poppo and Zenger, 2002). Stinchcombe (1985) within budget, delivered on time, and delivered conform specifi-
documents how price incentives (contracts) and authority can be cations (Munns and Bjeirmi, 1996). That is, the project has to
combined, arguing that control mechanisms have to be explicitly perform within the cost, time, and quality constraints as identi-
addressed in contracts. fied by the Iron Triangle of project management (Oisen, 1971; De
An alternative view argues that relational norms and trust are Wit, 1988). The triangle illustrates the notion that the different
substitutes for contracts and authority (Granovetter, 1985). Especially constraints are interconnected. For example, not adhering to time
in collaborative relationships drawing up formal contracts may be schedules can lead to high costs and therefore to overruns of the
interpreted as an act of distrust in the exchange partner. Apparently project budget.
the exchange partner is not willing to risk cooperation without Fig. 1 presents the conceptual research model that is adopted
having a contract that explicitly states the terms of interaction. In in this study. The model connects the three governance mechan-
such a situation a formal contract might encourage (rather than isms directly to the project outcomes. In general, we expect
discourage) opportunistic behavior (Ghoshal and Moran, 1996). In positive relationships between each governance mechanisms
this line of reasoning, a contract is considered to have a counter- and the identified project outcomes. In addition, the model shows
productive impact in the presence of relational governance. the interrelationships between the three governance mechan-
Although, there is a reasonable body of evidence to support an isms. The isolated mechanisms are mutually dependent, and their
integrative view of contractual and relational governance as simultaneous application affects the project outcomes. It is
complementary mechanisms (e.g., Das and Teng, 1998), there is expected that the interplay between each governance mechanism
still little understanding about the specific ways in which govern- has an effect on the other mechanisms, as well as on the project
ance mechanisms interact, and the impact of their inter-relation- process and outcome. The empirical part of the study elaborates
ship (Poppo and Zenger, 2002; Zheng et al., 2008; Caniëls and on the interplay of mechanisms.
Gelderman, 2010). Exceptions are the studies of Olsen et al. (2005),
Caniëls and Gelderman (2010), and Liu et al. (2009). Based on two
case studies concerning system delivery projects, Olsen et al. 3. Methodology
(2005) reported that contacts, authority and trust are complemen-
tary. Moreover, they found a complex interplay between the We conducted a case study in the Norwegian offshore oil and
specific use of the different mechanisms, which was denoted as a gas industry. A case study approach is best suited for an
‘multiplier effect’. It was concluded that using one mechanism explorative study that contains the in-depth investigation of the
supports the use of other mechanisms. However, Olsen et al. specific interactions between the governance mechanisms and its
(2005) have no explicit focus on preventing and remedying impact on the project outcomes (Yin, 2009). In order to enhance
opportunistic behavior. Furthermore, they explicitly call for more the validity and reliability of our study, we followed the phases
empirical work to further validate the idea of complementarity. for conducting case study research as described by Noor (2008).
Caniëls and Gelderman (2010) and Liu et al. (2009) adopted a The selected case consists of a complex procurement project for a
survey approach when studying the simultaneous use of several very innovative construction pilot project. The selection of the case
safeguards against opportunism. Both studies find interaction was based on the consideration that we explicitly wanted to
effects between different safeguards. However, these studies adopt investigate a complex procurement project that involved multiple
a slightly different categorization of safeguards than is proposed in actors. The complexity of the chosen project stemmed from its high
the underlying study. Furthermore, by using cross-sectional data, technological difficulty, the vast number of actors involved, the high
these studies cannot investigate the dynamics of the interplay. budgetary implications, the long lead time and the high level of
We conclude that there is ample room for additional empirical uncertainty at the start of the project with regards to the expected
studies that investigate the interplay of governance mechanisms outcomes and precise technical specifications.
as a way to safeguard against opportunism. In addition, there is Different sources of evidence are used to complement each
opportunity for research that takes a dynamic perspective. Except other and to ensure the validity of the study (Yin, 2009). The case
for the longitudinal case study of Ness and Haugland (2005), little study involved in-depth semi-structured interviews with key
research has been undertaken on relationship development and respondents, as well as an analysis of documentation and archival
the change over time in the reliance on certain (combinations of) records, including contracts, project kick-off documents, project
governance mechanisms. strategy reports, and monthly progress reports.
The case study was performed in retrospect. Due to the long
2.3. Project outcomes and research model duration of the project (6 years), the analysis of supporting
evidence such as the project documents and other archival
In our study we explicitly focus on the influence of governance records were critical in order to validate interview outcomes.
mechanisms in project management. A common way to measure Another reason why triangulation was important for enhancing
116 M.C.J. Caniëls et al. / Journal of Purchasing & Supply Management 18 (2012) 113–121

the validity of the study is that some informants might have making a contribution to our understanding of the interplay of
difficulties recalling certain events, leading to response bias. In a governance mechanisms in complex procurement projects.
complex project like the one in this study it is difficult and nearly
impossible to find one person with a complete overview of the
project. 4. Results
We conducted interviews within the organizations of the
internal operator, a second operator and the integrator. An inter- 4.1. Case description
view typically lasted 60–90 min. All interviews were recorded and
transcribed. We have interviewed employees of different levels The innovative character of the project implied the need for
within the organizations to collect a great variety of information. joint technical development of parts and processes. Therefore, it
The respondents included project managers, contract managers, was necessary for the parties involved in the project to engage in
technical managers and more hands-on (technical) employees long term relationships with supplying partners. Supplying par-
whose combined insights gave a full spectrum view on the ties were expected to design and produce components for a major
project, ranging from top-level management activities to more construction project in the offshore industry. The size of the
down-to-earth day to day action on the work floor. project was initially estimated at 850 million Norwegian Krone,
Memoing was used to facilitate the qualitative analysis and the project was allowed to last 6 years. The main character-
(Babbie, 2001). This technique includes writing memos and notes istics of the project are shown in Table 1.
in order to refine and keep track of ideas about the investigated The project was executed in a way that is typical for projects in
phenomena. The use of memoing enhanced data collection the oil and gas industry, namely involving an operator, an
and data exploration by making it easy to compare information integrator and subcontractors. In the selected case the complexity
about key issues and facilitate communication with respondents was increased by the switch to another operator after a few years.
(Glaser, 1998). The collected data (archival as well as interview The second operator was already involved in the project from the
data) was coded and classified (Ghauri and Gronhaug, 2002). The start in an observing role, and later gained full responsibility (see
content of each of the contracts was categorized in a table which Fig. 2). The executing parties remained the same throughout the
made it easy to compare and to have a clear overview of the key entire project.
elements of each contract. Progress reports were processed into a The involvement of a large number of subcontractors was
timeline to understand the chronology of events. The timeline another complexity. This generated a long supply chain with
was also very useful in showing the key problems that occurred sub-subcontractors, which did not support communication, and
during the project. generated difficulties in the alignment of tasks between the
For the conceptualization and the operationalization of the sequential sub contractors. To increase complexity even more,
variables in our interviews and in the research model we drew on some parties held multiple roles simultaneously, for example the
existing studies: integrator was also a subcontractor for some deliverables.
Contract/incentives refer to a market mode of exchange. In the Operator A and the integrator had already been cooperating in
interviews we specifically paid attention to agreements on the previous projects. In the beginning, the project was mainly based
sharing of risks and rewards in the contracts, since these are on a trustful relationship between operator A and the integrator.
expected to function as key incentives that determine behavior These parties displayed much openness in communication and
and therefore performance of parties in the project. We also a high level of integration. The integrator and operator A were
gathered information on the perceived clarity of the specifications even located in the same building. The relationship between the
of the expected deliverables, as well as the feasibility of being able integrator and the subcontractors was of another nature. The
to deliver them in time and within budget (Olsen et al., 2005). subcontractors had many different nationalities which limited the
Authority refers to the hierarchical mode of exchange, i.e. quality and openness of communication. There were also differ-
reliance on administrative procedures and control systems. Since ences in perception of correct working procedures. During the
authority requires power to control the activities of others, project the staff of the integrator had to travel much to visit the
authority is indicated by the extent to which one party has the subcontractors on site.
ability to determine terms of trade, and the extent to which
standard operating procedures for supervision are implemented 4.2. Project outcomes
(Wang et al., 2008).
Trust refers to a social mode of exchange, and was assessed by The project outcomes with respect to the adherence to budget
investigating the relational norms that govern the relationships and time constraints were unsatisfactory. Problems at the origin
as well as the perceived importance of personal relationships
(Bradach and Eccles, 1989).
Table 1
Project outcomes refer to the results of the project. Project Case specifications.
success is generally assessed by determining whether the deliver-
ables are on time, within budget, and fulfill specified quality Criteria Case specifications
norms (Munns and Bjeirmi, 1996; De Wit, 1988).
Purpose Qualification of components for a major construction
The observed patterns and relationships in our case study have project in the offshore industry
been compared with the ones in the research model (pattern Budget Initially estimated at 850 million Norwegian Krone
matching, e.g. Eisenhardt, 1989). Since the impact of additional Length 6 years
factors outside of our model cannot be completely excluded, the Contract form Reimbursable contract
Organizational Co-location with main contractor/integrator. Strongly
internal validation is limited. However, the research framework
form integrated team at the start, but over the course of the
for the case study was derived from the literature, identifying project the teams became more separated
(potential relationships between) key variables and outcomes. Number of main 1 integrator, 5 subcontractors
Obviously, the results of a single case study do not allow for any partners
statistical generalization to other complex procurement projects. End result  Cost increased to 2 billion Norwegian Krone
 Delays
Still, the findings will be related to the current body of knowledge,  Deliverable were according to technical specifications
allowing for some analytical generalization (Yin, 2009) and
M.C.J. Caniëls et al. / Journal of Purchasing & Supply Management 18 (2012) 113–121 117

Fig. 2. Main stakeholders in project—change of responsibilities.

of the chain caused a negative effect all the way up the chain. technological complexity of the project led to unforeseen technical
Since activities and planning schedules were closely linked across difficulties. Subcontractors lacked technical expertise and had to
parties, delays by one actor in the chain resulted in a ‘chain enter entire new fields of know-how for which they were insuffi-
reaction’ and led to difficulties for subsequent actors. Often, the ciently prepared. Second, partners did not allocate sufficient
focus of sub(sub)contractors was not on timely delivery, but resources to the project, because in the beginning phases of the
rather on technology development and technical quality. The project the incentive structure did not support the envisioned
main problems in the project that caused the cost increases and outcomes. For example, there were no penalties installed for late
schedule delays are discussed below. deliveries. A related third reason for delays was that an adequate
The project had many problems with cost overruns. In the end the time control system was absent. There was a lack of adequate
project doubled the estimated costs. The client had to pay all the cost documentation. The monthly reports provided an overview of
incurred by the contractors, since the project was governed by a fully project highlights. However, the overviews did not show who was
reimbursable contract. This means that all cost that are made by responsible for deviations and what the expected impact would be
contractors will be fully compensated and paid back by the initiator on the project in terms of cost and time delays. Fourth, there was no
of the project. Because parties worked with open financial books, it planning manager appointed by the integrator. A lack of focus on
was clear how, when and by whom the money was spent. Several planning and scheduling occurred already from the start of the
reasons were given for the unforeseen cost increase. The first reason project. The operators were very involved in and concerned with the
is associated with the nature of the project. Projects in which new technology development and they had a narrow focus on technical
technology is developed are difficult to oversee in terms of time, issues, while project management aspects were neglected.
budget and specification of deliverables. It was not clear from the In a later phase during the project, specific incentives were
start of the project what the project would exactly entail and included in contracts in order to reduce the number of delays.
therefore non-accurate estimates had been given with respect to Penalties were given when delivery deadlines were not met. Not
time, cost and quality. Even though the deliverables were described in meeting specified deadlines would reduce the percentage that
the technical requirements section in the contracts, several subcon- would be compensated by the project initiator. However, these
tractors were faced with unclarities about the exact specification incentives did not entirely generate the desired results. The
concerning the deliverables. Second, the responsibilities and roles of envisioned end date for the project did not improve. Furthermore,
the different parties were unclear, and proper interface management delayed deliverables stayed delayed, although no additional
was missing. Consequently, there was a lack of cost control, since slippage of time was reported. The fact that the contractual
adequate control systems were absent, such as procedures for cost incentives did not have the desired effects has probably to do
and time monitoring and control. Third, the contractual agreements with the specific nature of the project. Projects that involve
in the first phase of the project did not provide an incentive structure research and development of new technology are highly uncer-
for the parties involved that was likely to lead to desirable behavior. tain and difficult to schedule and speed up. Still, the incentives
Initially, the contract was fully cost reimbursable, without penalties did direct the attention of the parties involved towards the
for non-performance or incentives for meeting specific objectives, importance of cost and time efficiency.
such as keeping activities within a certain budget or meeting a During the run of the project, quality requirements were put
particular time schedule. Hence, no incentives existed for the inte- center stage. Meeting quality requirements was perceived as the
grator or for the subcontractors to stay within cost limits. most important aspect of the project, which caused the neglect of
With regard to the dynamics of the project, we found that budget and time constraints. Despite the usual quality problems
during the run of the project certain incentives were deployed, during a project and the associated interventions to remedy those,
which led to a reduction in the number of cost overruns and their the project end result achieved the envisioned quality levels.
severity. For example, midway the project bonuses were intro-
duced if certain milestones were achieved, furthermore costs 4.3. Governance mechanisms
were only paid back up to a certain maximum.
Whether a project is finished within the allocated time is another Operator A and the integrator had frequently cooperated in
measure of project performance. In the underlying case many delays previous projects and were highly integrated. The contract was seen
occurred: 60–90% of the deliverables did not arrive on schedule, as a way to write up the intention to undertake a joint effort in order
causing a chain-reaction of delays in subsequent activities. The to deliver the required technology. The contract stated among others
following factors were found to cause these delays. First, the that all costs made by the integrator and subcontractors would be
118 M.C.J. Caniëls et al. / Journal of Purchasing & Supply Management 18 (2012) 113–121

fully reimbursed. However, the fact that the contract included no the contract was changed. The unlimited reimbursability was
additional rewards if the parties achieved positive outcomes and over and operator A now had to justify each and every expendi-
contained very limited penalties, resulted in low motivation to keep ture. One of the respondents at the side of the operator said: ‘‘We
costs within budget and to stay within time limits. The following were afraid to ask for specific tasks to be executed as it would
statement from a respondent illustrates the problem of having a increase the costs. Every item we asked for, would be written
reimbursable contract without incentives: ‘‘The contract we had down and we would have to pay for it’’. The role of operator B
between the operator and the integrator was a suicide contract. All became more prominent in the execution of the project up to a
costs charged by the integrator were immediately paid without point that operator B gained full responsibility.
questions asked’’. Our case study effectively illustrates the interplay of contractual
The lack of incentives for the contractors made that the incentives, authority and trust and the effect of the use of these
contractors occasionally prioritized other projects when allocat- governance mechanisms on the final project outcomes. Governance
ing their resources. When resources were needed in another mechanisms of contractual incentives, authority and relational
project which provided higher incentives, subcontractors shifted norms (trust) affected each other to a great extent. When at the
resources to that particular project, while leaving this project start of the project a high level of trust existed between operator A
with a shortage of resources. This obviously had a negative impact and the integrator, they decided that there was not much need for
on the progress of the project. Again the absence of clear rewards contractual incentives or an adequate control system. Hence, little
and penalties in the contract was mentioned by respondents as to no effort was made to ensure that the contract contained
one of the problems leading to a lack of project outcomes. incentives, which would generate the desired behavior of parties.
The initial high level of trust between operator A and the Additionally, there were no systems installed to monitor each
integrator may have been one of the reasons that an inadequate party’s behavior in order to verify progress and outcomes. This
incentive scheme was implemented in the first place, and that prevented the parties involved to be able to intervene in a timely
parties completely relied on common goals and objectives. The manner. High trust together with a lack of clear contractual
respondents indicated that the high level of trust and the incentives and low hierarchical governance (authority) had a very
presence of common interests made it acceptable not to have negative impact on project outcomes. The case illustrates a clear
rewards and penalties in the contract. interaction between the three governance mechanisms. Whereas at
With respect to mechanisms of hierarchical governance we the outset of the project trust is leading to informal agreements (no
find that a steering committee was installed already from the contractual incentives) and little use of authority, later on the
start of the project. However, its existence was barely noticed by absence of contractual incentives combined with a low level
the project members. The high level of integration between the of authority became the source of the decline in the level of trust
integrator and operator A induced a high reliance on relational between parties.
norms and trust within the relationship. As a consequence, parties At the time that the poor interim project outcomes were
did not use hierarchical mechanisms to enforce control. Formal announced, the amount of trust between parties severely decreased,
procedures were not installed and the neither party used their which resulted in the instalment and use of more formal governance
power position to enforce agreements or expectations. mechanisms, namely contractual incentives and control systems.
The use of authority as a way to govern the relationships was This particular constellation of governance mechanisms ultimately
also hindered by the incompleteness of the contract. Since the had a positive effect on the project outcomes, since the incentives
contract between operators mainly consisted of a two page generated awareness of parties to focus more on budgetary aspects
cooperation agreement and did not encompass clear responsibil- and the importance of adhering to time schedules.
ities and expectations of deliverables, parties were unable to refer
to contractual agreements about costs and time schedules. Respon-
dents representing operator B claim that they were unable to use 5. Discussion
any authority since there were no adequate procedures or control
systems identified in the contract that allowed them to do so. Our results complement and nuance the findings of the com-
Over time, as the project progressed, this way of working parable study of Olsen et al. (2005) on two cases in the Norwegian
resulted in a decrease of trust between operator A and the oil and gas industry. The first case of Olsen et al. (2005) was
integrator. During the course of the project, subcontractors characterized by trust at the outset, which made it possible to
started to behave opportunistically and misused the budgetary implement an effective incentive scheme in the contract and to
freedom provided by the contract. Operator A was unable to meet design an authority structure conducive to timely progress within
deadlines, because of the bad performance of its subcontractors. budget and conform specifications. In the interplay between
After a while operator A noticed the opportunistic attitude and governance mechanisms, the formal governance mechanisms
behavior of the subcontractors and started to mistrust them. Also (incentives and authority) were believed to positively reinforce
the confidence and trust between operator A and the integrator trust between parties, resulting in positive project outcomes. The
subsided. All this time, employees from operator B felt powerless. second case analyzed in Olsen et al. (2005) described a project
They saw that there was no control on what was going on in the which was characterized by a low level of trust at the start-up. This
project. Respondents representing operator B indicated that they made it difficult to implement contractual incentives and author-
were very concerned about whether the project goals would be ity. As a result, parties were not bound by shared goals, and this led
achieved within a reasonable time frame and within budget. to opportunistic behavior and poor project outcomes. One of the
In contrast, respondents representing operator A indicated that conclusions of Olsen et al. (2005) from these two cases is that that
their decisions were questioned more and more as the project trust might drive the interactions among governance mechanisms,
advanced. They felt that they were continuously being checked. and therefore might be key to explaining project outcomes. Trust
The following statement of a respondent working at operator A seems to facilitate the implementation of the other mechanisms.
illustrates the spiraling negative impact on trust between parties: High trust at the outset is beneficial for project outcomes, the
‘‘We avoided giving too much information, as this would lead to absence of trust is associated with bad project results.
even more questions’’ and ‘‘Obviously, a 100% openness is not This finding is supported by other contributions. For example,
possible in a commercial project like this’’. As became clear by an in a study about safeguards against opportunism Caniëls and
interim progress report that the project progress was under par, Gelderman (2010) found that trust (relational norms) is the most
M.C.J. Caniëls et al. / Journal of Purchasing & Supply Management 18 (2012) 113–121 119

influential safeguard against opportunistic behavior of exchange was low, the relational governance mechanism was substituted
partners. In addition, this study found that trust plays a key role by the more formal mechanisms of authority and contractual
on implementing other governance mechanisms. Thus, trust incentives. However, these findings have to be interpreted with
affects the application of other safeguards. In the field of project great caution, since the cases of Olsen et al. (2005) suggested the
management, Pinto et al. (2009) showed that trust is an important opposite, namely that low trust led to low formal governance.
factor to enhance the project outcomes and reduce opportunism These seemingly conflicting findings might be explained by the
in projects. Hence, the general view from the literature seems to interplay of governance mechanisms. It might not be the case that
be that trust drives other governance mechanisms. trust determines whether there will be high or low formal
The findings from our case show the need to nuance and refine governance, with an associated positive or negative impact on
these conclusions. Our case indicates that trust based on shared a project results. Rather it is much more likely that the constella-
common history and positive past experiences do not automati- tion of the three governance mechanisms at one moment in time
cally drive other governance mechanisms towards an interplay has a direct effect on project outcomes. The interaction between
that results in positive project outcomes. We found that trust in governance mechanisms is of paramount importance in deter-
absence of contractual incentives and control (authority) leads to mining project progress and outcomes in terms of time and cost
bad project outcomes. Hence, the role of trust is less straightfor- efficiency and quality.
ward than would be expected from the literature in general, and Our case is particularly interesting because we can clearly see
Olsen et al. (2005) in particular. the dynamics of the interaction effects between different govern-
The high level of trust between operator A and the integrator ance mechanisms. We find that some governance mechanisms
can be identified as competence trust, i.e., the belief in the ability lose importance over time, i.e. trust; while other mechanisms
of an exchange partner to perform tasks according to agreements become essential, i.e. contractual incentives and authority. In this
(Nooteboom, 1996), as opposed to benevolent trust in which sense our case also differs from Olsen et al. (2005) in which the
partners are truly interested in the other’s welfare (Anderson and change in accents on particular governance mechanisms over
Narus, 1990). The latter form of trust can be associated to time is not that prominent. Our study adds to previous studies in
common goal setting and shared intentions. Partners watch each this respect, by not only focusing on the interplay of government
other’s back and really put in effort to jointly reach a commonly mechanisms but also illustrating the dynamics.
shared goal. When one party makes an honest mistake, it is Hence, our study contributes to the discussion on whether
forgiven by the other party. Although in our case at the start of formal and relational governance can be both substitutes and
the project parties might indeed have had benevolent trust in complements (cf. Huemer et al., 2009). Our empirical findings
each other as they seemed to be focused on shared goals, this suggest that one should look at the mix of governance mechan-
slowly changed over time. At first some level of competence trust isms at one point in time to determine chances and risks for
remained, which might have been the reason that the project project progress and outcomes. In that sense governance mechan-
could carry on for quite some time before the bad results became isms are complementary and support each other. Our case also
visible. However, over time the competence trust disappeared as demonstrates that accents on different mechanisms in the mix
well, especially when it became clear by the interim evaluation can change during the run of a project. The shifting accents could
that the project results were below par. be interpreted as substitution effects.
Moreover, little team building activities had been taking place The results of this study should be interpreted in the light of
between both operators and the integrator during the project. the specific mix of governance mechanisms (high trust – low
Trust is believed to serve an important role in the beginning of a incentives – low authority) and in the light of a poor (interim)
project to enhance a common focus on joint goals, however, during project performance. Other mixes and other circumstances are
the run of the project it is important to keep communication lines likely to result in other developmental patterns of governance
open and to continue to invest in maintaining a close relationship. mechanisms, as was shown by the study of Olsen et al. (2005).
The socialization literature suggests that socializing is needed to
build inter-personal relationships and trust (e.g. Cousins et al.,
2008). Socializing forges bonds and ties that facilitate the exchange 6. Conclusions and recommendations
of communication and information (Cousins and Menguc, 2006)
and has a positive impact on business performance (Cousins et al., Although many studies have investigated governance in inter-
2008). Lawson et al. (2009) found that informal socialization firm relationships, little is known about the simultaneous use and
mechanisms are the most important means of facilitating the impact of several governance mechanisms, particularly in com-
sharing of knowledge. The lack of social events, joint workshops, plex procurement projects. In complex and hazardous projects
and team building exercises could explain why the communication that require an extensive coordination between different parties,
between operator A and the integrator failed, why the problems the impact and interplay of governance mechanisms are espe-
were not properly handled, and why trust dwindled. cially important. The investigated project in the Norwegian oil
The case nicely shows that at the time that trust levels became and gas industry is a typical example of such a complex procure-
quite low, the parties resorted to more formal governance mechan- ment project. Significant interplay effects were found in the
isms. These findings are in line with the duality perspective of study, not just among governance mechanisms, but also between
Möllering (2005), in which is claimed that trust and control are these mechanisms and project outcomes.
always present simultaneously and cannot be analyzed in isolation. With respect to the interplay of governance mechanisms and
In this respect, Caniëls and Gelderman (2010) found that high its impact on project outcomes we find that the role of trust is less
administrative control (contracts) was significantly and negatively straightforward than would be expected from the literature.
associated with relational governance (trust). However, the study Existing studies (e.g. Olsen et al., 2005) suggest that trust drives
of Caniëls and Gelderman (2010) relied on multiple regression other governance mechanisms and ultimately leads to desirable
analysis, hence causality could not be established. Thus, all we can project outcomes. The absence of trust is generally associated
conclude from their study is the negative relationship between with bad collaboration between project partners, resulting in
trust and control. The findings of our case study seem to elaborate bad project outcomes. Our study shows the need to refine this
on this evidence by suggesting a causal relationship from trust reasoning. We found that trust in absence of contractual incen-
towards contractual incentives and authority. At the time that trust tives and control leads to bad project outcomes. In contrast, trust
120 M.C.J. Caniëls et al. / Journal of Purchasing & Supply Management 18 (2012) 113–121

in combination with contractual incentives and authority leads to insights on whether trust acts as a driver for other governance
well defined contracts with clear roles of parties and specific mechanisms, or whether it is really the combination of trust with
agreements on deliverables that easily can be reinforced. the other mechanisms that generates a successful interplay and a
The main conclusion of our study is that trust and relational positive impact on project outcomes.
governance are only beneficial for project outcomes when they One of the limitations of our study pertains to the level of
are accompanied by contractual incentives and control systems. complexity of this project and its duration. Only few employees
Trust in itself does not guarantee an effective and beneficial were involved from the start of the project had could therefore
interplay of all three mechanisms in a way that automatically provide a complete overview of what had happened during the 6
generates project progress and desired outcomes. In order to years. Moreover, several employees had changed roles during the
achieve project performance, all three mechanisms must work run of the project. Some of the interview questions might have
together and support and stimulate each other. This does not been difficult to answer by respondents who were not in a project
happen automatically, it might be so, as was demonstrated by our management position, and were lacking a helicopter view. How-
case, that one mechanism leads to the neglect of another. ever, we feel that the analysis on basis of all the interviews
This study has several managerial implications. Management together, supplemented with the archival records, gave a com-
should understand the impact of governance mechanisms on the plete and comprehensive overview of the project.
project outcomes, their interplay, and the varying effects during Another limitation of our study concerns our use of a single
the run of complex (procurement) projects. From a managerial case that obviously limits the external validity of the results.
perspective it is importance to be aware that different governance Therefore it is clear that our results should be interpreted with
mechanisms are mutually dependent. In order to achieve optimal caution. Further research is needed to extend the knowledge in
project performance, proactive strategies are required on how to this field and to identify whether out findings can be generalized
employ the mix of various governance mechanisms, rather than to other complex procurement projects. To this end more cases of
applying each mechanism in isolation. It is a challenge to manage complex procurement projects should be studied and compared.
the entire mix of mechanisms simultaneously to generate a Moreover, future research should investigate the impact of
productive rather than counter-productive interplay between specific combinations of governance mechanisms, preferably in
mechanisms. A way to deal with this challenge could be to have a dynamic context.
a kick-off meeting with all stakeholders, in which governance
mechanisms are explicitly discussed (see also Liu et al., 2009).
Before the start of a project the parties involved could come to an
aligned plan about how to implement the mix of governance References
mechanisms. Parties should be aware that the design and execu-
tion of an optimal mix of governance is essential to reach Anderson, J.C., Narus, J.A., 1990. A model of distributor firm and manufacturer firm
common goals. Furthermore, parties should be willing to jointly working partnerships. Journal of Marketing 54 (1), 42–58.
Babbie, E., 2001. The Practice of Social Research, 9th ed. Wadsworth.
evaluate, discuss and possibly revise the mix of mechanisms on a Bradach, S., Eccles, R.G., 1989. Price, authority, and trust: from ideal types to plural
regular basis, to be able to adapt to changing circumstances forms. Annual Review of Sociology 15, 97–117.
during the run of a project. Branconi, C., Loch, C.H., 2004. Contracting for major projects: eight business levers
for top management. International Journal of Project Management 22,
The classical recommendation in project management litera- 119–130.
ture is to use cost reimbursable contracts when project uncer- Caldwell, N.D., Roehrich, J.K., Davies, A.C., 2009. Procuring complex performance in
tainty is high (e.g. Branconi and Loch, 2004). In the complex, risky construction: London Heathrow Terminal 5 and a private finance initiative
hospital. Journal of Purchasing & Supply Management 15, 178–186.
and highly uncertain project of our case a reimbursable contract Caniëls, M.C.J., Gelderman, C.J., 2010. Safeguarding effect of governance mechan-
was indeed used. However, this approach left all responsibility to isms in inter firm exchange: the decisive role of mutual opportunism. British
the client, while the contractors had no incentive to be cost and Journal of Management 21, 239–254.
Cousins, P.D., Menguc, B., 2006. The implications of socialization and integration in
time efficient. The findings of our case lead to the following supply chain management. Journal of Operations Management 24 (5),
managerial advice in this respect. Because of the many uncertain- 604–620.
ties about output specifications, it might still be wise to draw up Cousins, P.D., Lawson, B., Squirre, B., 2008. Performance measurement in strategic
buyer–supplier relationships. The mediating role of socialization mechanism.
reimbursable contracts, however, it is highly advisable to ensure
International Journal of Operations & Production Management 28 (3),
that the roles of parties are clearly stated in the contract and 238–258.
contractual incentives are designed in a way that they induce Das, T.K., Teng, B., 1998. Between trust and control: developing confidence in
desired behavior of parties. A trusting relationship in itself is not partner cooperation in alliances. Academy of Management Review 23,
491–512.
sufficient to induce good project performance. In addition, it is De Wit, A., 1988. Measurement of project success. International Journal of Project
sensible to develop clever ways in which interests of project Management 6 (3), 164–170.
parties become and remain aligned. This can be achieved for Dwyer, F.R., Schurr, P.H., Oh, S., 1987. Developing buyer–supplier relationships.
Journal of Marketing 52, 21–34.
instance by investing in socialization efforts, such as team build- Eisenhardt, K.M., 1989. Building theories from case study research. Academy of
ing events. Management Review 14, 532–550.
Several avenues for further research are opened by our study. Ferguson, R.J., Paulin, M., Bergeron, J., 2005. Contractual governance, relational
governance, and the performance of interfirm service exchanges: the influence
A next step could be to formulate a format for a mix of of boundary–spanner closeness. Journal of the Academy of Marketing Science
governance mechanisms with different accents that would gen- 33 (2), 217–234.
erate optimal project outcomes in different circumstances. It Gassenheimer, J.B., Baucus, D.B., Baucus, M.S., 1996. Cooperative arrangements
among entrepreneurs: an analysis of opportunism and communication in
would be worthwhile to investigate whether it is possible to franchise structures. Journal of Business Research 36, 67–79.
provide a ‘‘recipe’’ of constellations of mechanisms to use in Ghauri, P., Gronhaug, K., 2002. Research Methods in Business Studies: A Practical
various circumstances. This would be a valuable asset to man- Guide. Financial Times and Prentice-Hall, Harlow, UK.
Ghoshal, S., Moran, P., 1996. Bad for practice: a critique of the transaction cost
agers in complex procurement situations. Furthermore, research-
theory. Academy of Management Review 21, 13–47.
ers are encouraged to undertake further studies into socialization Glaser, B.G., 1998. Doing Grounded Theory—Issues and Discussions. Sociology
as a potentially effective governance mechanism that precedes Press.
and stimulates trust in buyer–supplier relationships. Additionally, Granovetter, M., 1985. Economic action and social structure: the problem of
embeddedness. American Journal of Sociology 91 (3), 481–510.
further research is recommended on the role of trust in relation to Haugland, S.A., Reve, T., 1994. Price, authority and trust in international distribu-
the other governance mechanisms to provide supplementary tion channel relationships. Scandinavian Journal of Management 10, 225–244.
M.C.J. Caniëls et al. / Journal of Purchasing & Supply Management 18 (2012) 113–121 121

Hawkins, T.G., Wittmann, C.M., Beyerlein, M.M., 2008. Antecedents and conse- North, D.C., 1990. Institutions, Institutional Change and Economic Performance.
quences of opportunism in buyer–supplier relations: research synthesis and University Press, Cambridge.
new frontiers. Industrial Marketing Management 37 (8), 895–909. Oisen, R.P., 1971. Can project management be defined? Project Management
Heide, J.B., John, G., 1992. Do norms matter in marketing relationships? Journal of Quarterly 2 (1), 12–14.
Marketing 56 (April), 32–44. Olsen, B.E., Haugland, S.A., Karlsen, E., Husoy, G.J., 2005. Governance of complex
Hoetker, G., Mellewigt, T., 2008. Choice and performance of governance mechan- procurements in the oil and gas industry. Journal of Purchasing and Supply
isms: matching alliance governance to asset type. Strategic Management Management 11, 1–13.
Journal 30 (10), 1025–1044. Parkhe, A., 1993. Understanding trust in international alliances. Journal of World
Huemer, L., Boström, G., Felzenstein, C., 2009. Control–trust interplays and the Business 33, 219–240.
influence paradox: a comparative study of MNC–subsidiary relationships. Pinto, J.K., Slevin, D.P., English, B., 2009. Trust in projects: an empirical assessment
Industrial Marketing Management 38, 520–528. of owner/contractor relationships. International Journal of Project Manage-
Jap, S.D., Ganesan, S., 2000. Control mechanisms and the relationship life cycle: ment 27, 638–648.
implications for safeguarding specific investments and developing commit- Poppo, L., Zenger, T., 2002. Do formal contracts and relational governance function
ment. Journal of Marketing Research 37, 227–245. as substitutes or complements? Strategic Management Journal 23, 707–725.
Jap, S.D., Anderson, E., 2003. Safeguarding interorganizational performance and Raymond, M.S., Leffler, W.L., 2006. Oil and Gas Production in Nontechnical
continuity under ex post opportunism. Management Science 49 (12), Language. PenWell.
1701–2684. Reve, T., 1990. The firm as a nexus of internal and external contracts. In: Aoki, M.,
Joshi, A.W., Stump, R.L., 1996. Supplier opportunism: antecedents and conse- Gustafsson, B., Williamson, O.E. (Eds.), The Firm as a Nexus of Treaties. Sage,
quences in buyer–supplier relationships. In: Droge, C., Calantone, R. (Eds.), London.
American Marketing Association Summer Educators’ Conference Proceedings, Sako, M., 1992. Prices, Quality and Trust—Inter-firm Relationships in Britain and
Japan. Cambridge University Press, Cambridge UK.
vol. 7. American Marketing Association, Chicago, IL, pp. 129–135.
Stinchcombe, A.L., 1985. Contracts as hierarchical documents. In: Stinchcombe, A.,
Klein Woolthuis, R., Hillebrand, B., Nooteboom, B., 2005. Trust, contract
Heimer, C. (Eds.), Organization Theory and Project Management. Norwegian
and relationship development. Organization Studies 26 (6), 813–840.
University Press, Bergen, Norway.
Larson, A., 1992. Network dyads in entrepreneurial settings—a study of the
Wang, Q., Xu, J., Weitz, B., 2008. Creativity in buyer–seller relationships: the role of
governance of exchange relationships. Administrative Science Quarterly
governance. International Journal of Research in Marketing 25, 109–118.
37 (1), 76–104.
Wathne, K.H., Heide, J.B., 2000. Opportunism in interfirm relationships: forms,
Lawson, B., Petersen, K.J., Cousins, P.D., Handfield, R.B., 2009. Knowledge sharing in
outcomes, and solutions. Journal of Marketing 64, 36–51.
interorganizational product development teams: the effect of formal and
Williamson, O.E., 1975. Markets and Hierarchies: Analysis and Antitrust Implica-
informal socialization mechanisms. Journal of Product Innovation Manage-
tions. Free Press, New York.
ment 26 (2), 156–172. Williamson, O.E., 1985. The Economic Institutions of Capitalism. Free Press,
Liu, Y., Luo, Y., Liu, T., 2009. Governing buyer–supplier relationships through New York.
transactional and relational mechanisms: evidence from China. Journal of Williamson, O.E., 1991. Comparative economic organisation: the analysis of
Operations Management 27, 294–309. discrete structural alternatives. Administrative Science Quarterly 36 (2),
Macneil, I.R., 1980. The New Social Contract: An Inquiry into Modern Contractual 269–296.
Relations. Yale University Press, New Haven and London. Wuyts, S., Geyskens, I., 2005. The formation of buyer–supplier relationships:
Maurer, I., 2010. How to build trust in inter-organizational projects: the impact of detailed contract drafting and close partner selection. Journal of Marketing 69,
project staffing and project rewards on the formation of trust, knowledge 103–117.
acquisition and product innovation. International Journal of Project Manage- Yin, R.K., 2009. Case Study Research: Design and Methods, 4th ed. Applied Social
ment 28, 629–637. Research Methods, vol. 5. Sage Publications Incorporated.
Möllering, G., 2005. The trust/control duality: an integrative perspective on Yu, C.M.J., Liao, T.J., Lin, Y.D., 2006. Formal governance mechanisms, relational
positive expectations of others. International Sociology 20 (3), 283–305. governance mechanisms, and transaction-specific investments in supplier-
Morgan, R.M., Hunt, S.D., 1994. The commitment–trust theory of relationship manufacturer relationships. Industrial Marketing Management 35, 128–139.
marketing. Journal of Marketing 58, 20–38. Zaheer, A., Venkatraman, N., 1995. Relational governance as an interorganizational
Munns, A.K., Bjeirmi, B.F., 1996. The role of project management in achieving strategy: an empirical test of the role of trust in economic exchange. Strategic
project success. International Journal of Project management 14, 81–87. Management Journal 16 (5), 373–392.
Ness, H., Haugland, S.A., 2005. The evolution of governance mechanisms and Zheng, J., Roehrich, J.K., Lewis, M.A., 2008. The dynamics of contractual and
negotiation strategies in fixed-duration interfirm relationships. Journal of relational governance: evidence from long-term public–private procurement
Business Research 58, 1226–1239. arrangements. Journal of Purchasing & Supply Management 14, 43–54.
Noor, K.B.M., 2008. Case study: a strategic methodology. American Journal of Zucker, L.G., 1986. Production of trust: institutional sources of economic structure.
Applied Sciences 5 (11), 1602–1604. Research in Organizational Behavior 8, 53–111.
Nooteboom, B., 1996. Trust, opportunism and governance: a process and control
model. Organization Studies 17 (6), 985–1010.

Anda mungkin juga menyukai