CONSTRUCTION OF 2 NO.

3-STOREY LECTURE HALL BLOCK AT GIMPA CAMPUS


(LOT 1 & 2)

MINUTES OF MEETING

MEETING PRELIMINARIES
Project : Construction of 2 No. 3-Storey Lecture hall blocks at GIMPA
Subject : 19th General meeting.
Place : GIMPA site Date : 11/10/18
Time : 10:00 am Pages : 2

MEETING ATTENDANCE:
Client: GIMPA

Consultant: Alberta Essamuah and Associates

EPC Contractor: Mr. Lui


China State Hualong Mr. Lu Vei
Construction Ghana Limited Mr. Mao
Emmanuel Siaw

APPROVAL:
Minutes By : Emmanuel Siaw Date : 11/10/18
Vetted By : Mr. Lui wey Date : 11/10/18
Approved By : Date : 11/10/18

No. Subject Matter Remark

1 General introduction and distribution of the Attendance Sign in forms

The meeting began at 10:00 am a n d attendees of the meeting were given the
1.1
platform to introduce themselves making it known to the members their
designations and with which team they represented.

2 Review of Meeting No. 4 Minutes

The meeting minutes for the 18th site meeting was not affirmed since the
2.1
Chairman couldn’t present the right minutes for the 18th General meeting.

Matters Arising.
3

Page 1 of 3
CONSTRUCTION OF 2 NO. 3-STOREY LECTURE HALL BLOCK AT GIMPA CAMPUS
(LOT 1 & 2)

i) Sound transmission on the Second floors


3.1 The Chairman proposed a mechanism to cater for sound transmission
within the room spaces on the second floors but the Client representative
indicated that the proposed structural arrangement will counter for the
sound echoing and transmission on the second floors.

ii) Issue on window specifications raised by Contractor


The Contractor enquired the type of windows to be used for all windows
3.2
and the Chairman indicated should be the same specification of existing
windows of the Yale building located in the school.

iii) Issue on washroom windows


3.3 The Chairman indicated that Fixed Top hung Aluminum is to be used for
the washroom windows.

iv) Issue on affirming MEP related works:


The chairman indicated that the consent of all MEP related issues is to be
sorted out from the MEP Consultant.

4 Comments on Progress report by Contractor


The Chairman and the house was convinced about the current progress of
4.1
works hence indicated the Contractor was on course.
5 Closure
The meeting was moved and adjourned to October 25th,2018 for a technical
5.1
meeting by the Chairman and the Clients representative.