PEKERJAAN INTERIOR LOBBY & INTERIOR TOILET

PROYEK AEON SENTUL


REKAP

JUMLAH HARGA JUMLAH HARGA


NO. URAIAN PEKERJAAN
Basic +/-

I. PEKERJAAN PERSIAPAN 191,500,000

II. PEKERJAAN INTERIOR LOBBY 1,567,662,014 519,992,315


A. Lantai Basement 3 95,949,354 45,897,300
B. Lantai Basement 2 249,837,997 196,568,720
C. Lantai Basement 1 303,242,259 157,793,200
D. Lantai Ground 274,136,337 22,447,460
E. Lantai 1 262,378,029 32,209,150
F. Lantai 2 267,454,902 50,103,685
G. Lantai 3 114,663,136 14,972,800

III. PEKERJAAN INTERIOR TOILET 3,358,617,282 -


A. Lantai Basement 3 88,937,000 -
B. Lantai Basement 2 547,601,377 -
C. Lantai Basement 1 472,824,875 -
D. Lantai Ground 769,154,452 -
E. Lantai 1 789,901,852 -
F. Lantai 2 636,481,152 -
G. Lantai 3 53,716,575 -

TOTAL 5,117,779,296 519,992,315

Sub Penjumlahan Rp. 5,117,779,296 519,992,315


PPn 10 % 511,777,930 51,999,232
TOTAL 5,629,557,226 571,991,547
ROUNDUP 5,629,600,000 572,000,000

PROYEK AEON MIX USED - SENTUL CITY Hal (1/1) REKAP INTERIOR