Anda di halaman 1dari 2

concrete concepts

CONCRETE – THE RESPONSIBLE CHOICE


09
thermal mass

impact-resistance

durability

strength

fire-resistance

flexibility

fast build-times

low-risk

energy-efficient
above and left: New concrete Adelong Bridge
low-maintenance bottom: Old timber bridge

non-toxic
Concrete meets the
termite-proof
challenge of replacing
cost-effective old infrastructure with
new, Adelong, NSW
Although relatively small in scale, the Adelong Bridge
Replacement Project is an example of how modern
concrete construction techniques can be cost
effectively adopted to replace aging or obsolescent
infrastructure, particularly in regional Australia.
In this case, a new 62-metre reinforced concrete
Adelong Bridge Replacement Project bridge – four spans of 15.5 metres each – has
been constructed in the southern NSW township of
client: NSW Roads and Maritime Services (formerly RTA)
Adelong, replacing the existing Adelong Creek and
principal contractor: Nelmac
Adelong Flood Channel timber bridges built at the
n Total project cost $8 million turn of the last century.
n Completed December 2010
The timber bridges had well and truly passed their
n 62 metre-long, four-span, reinforced concrete bridge
serviceable life, particularly in terms of the increasing
(replacing two adjoining century old timber bridges)
freight task on the corridor. In short, they no longer
n Designed for 1 in 50 year flood event, with a 100-year
met community expectations in terms of safety or
design life
performance.
For the new Adelong Bridge, section of the old bridges. Once
voided PSC planks with sacrificial the upstream half was completed,
formwork were used in preference the process was reversed.
to inverted Tee PSC planks. This The PSC planks were erected on
meant fewer units were required the bridge with minimal double-
overall and even less maintenance handling and traffic disruption.
in the longer term. Trucks delivered two planks at a
The new bridge was designed time, with the planks typically lifted

www.ccaa.com.au/sustainability
for submergence during flood. It and erected on the headstocks
included holding down brackets within a 10-minute timeframe.
tying the PSC planks to the The use of a concrete wall (instead
headstocks. of sheet piling) for shoring was
During construction, the new effective in preventing the vertical
bridge stood up to a 1 in 100 edge of the existing abutments
year flood, with water overtopping from collapsing during excavation
A simple, effective the bridge deck. Once the of the first half of these abutments.
and environmentally water subsided, the then newly In addition, concrete injection
sensitive concrete solution constructed southbound half between rock boulders at the
of the bridge was opened for bridge abutments has improved
The new bridge comprises a
traffic across the creek when the erosion protection from future flood
substructure of reinforced
fill between the existing timber events.
concrete pier columns and
bridges was destroyed by the
headstocks, and a superstructure
flood. Key features of the construction
of reinforced concrete deck slab
solution:
supported by pre-stressed An efficient construction
methodology n Substructure – reinforced
concrete (PSC) plank girders.
concrete pier columns and
The bridge deck has an asphalt The contractor, Nelmac, adopted a
headstocks
wearing course, and a concrete piling methodology
that saw holes drilled through n Superstructure – reinforced
walkway with street lighting. The
lighting columns are supported the existing bridge decks before concrete deck slab on voided
in elegant concrete pedestals demolition. Driving of steel casings pre-stressed concrete plank
situated on the outside facade of and pile excavation was then girders
the bridge. carried out to sub-surface rock n Two-metre wide concrete
The replacement bridge was through these holes in the decks, walkway
designed to sit low within the the holes capped and the bridges n New bridge completed in two
creek corridor. The continuous reopened to traffic. halves, allowing continued
refined edge of the bridge was With the piling in place, the new (restricted) traffic access during
emphasised as the main visual bridge was constructed in two construction.
form, providing an elegant halves – the first stage involving
horizontal line across the creek closure of the upstream half of the
landscape. existing timber bridges to traffic,
The bridge substructure was then demolishing this old section
designed as an integrated and constructing the upstream half left to right:

squared pier and headstock so as of the new. This enabled traffic to Piling through existing bridge deck

not to distract from the simple yet continue using the downstream Deck slab construction
Exclusion net installation
refined line of the outside edge of
the bridge.

Economy and performance of


concrete
One of the fundamental drivers for
replacing old timber bridges with
concrete is the cost and difficulty
of sourcing suitable hardwood.
Additionally, timber bridges
have a not insignificant ongoing
maintenance requirement.

SYDNEY [61 2] 9437 9711 Since the information provided is intended for general guidance
BRISBANE [61 7] 3227 5200 only and in no way replaces the services of professional
consultants on particular projects, no legal liability can be accepted
MELBOURNE [61 3] 9825 0200 by Cement Concrete & Aggregates Australia for its use.
ADELAIDE [61 8] 8274 3758
© Cement Concrete & Aggregates Australia
PERTH [61 8] 9389 4452
TASMANIA [61 3] 6491 1509

Anda mungkin juga menyukai