Answer these questions first and the formulas will be calculated for you.
0.90
0.80
0.70
0.60
0.50
Cost performance index
0.40
Schedule performance
0.30 index
0.20
0.10
0.00
Variances
-20,000
-40,000
-80,000
-100,000
-120,000
Formula
Predict how much more the remainder of the project will costs
Predicts likelihood of reaching BAC
EV-AC
EV-PV
BAC-EAC
EV/AC
EV/PV
BAC/CPI
AC + BAC – EV
AC + [BAC-EV/(CPI x SPI)]
EAC-AC
(BAC-EV)/(BAC-AC)
(BAC-EV)/(EAC-AC)
Indication
PV=FV/(1+ i)n
Present value of money You enter info here Formula components
Future value 625000 625000
Interest 0.06 1.06
Years 5 1.3382255776
Present value $ 467,036.36
Build Cost 100000
Monthly Build Cost 12000