DAILY PRODUCTIVITY REPORT

DATE: 12/09/19

MANPOWER WORK DONE QUANTITY WORK


LABOUR
S.NO NATURE OF WORK CONTRACTOR AMOUNT RATE DONE REMARKS
M/S M/C F/C L B H QTY AMOUNT

RATE WORK
(PRODUCTIVITY
1 MATERIAL SHIFTING WORK AMUTHA 2 3 0 3200 0 0 0 CANNOT BE SHOWN
BECAUSE OF MATERIAL
SHIFTING WORK )

RATE WORK
(PRODUCTIVITY
CLUB HOUSE 3RD FLOOR MATERIAL CANNOT BE SHOWN
2 SHIFTING WORK
THIRUNAVUKARASU 1 0 1 1050 0 0 0 BECAUSE OF MATERIAL
SHIFTING WORK )

CLUB HOUSE 2ND FLOOR EAST WALL


3 PLASTERING WORK GOURI 2 2 0 2350 23.8 200 4760 RATE WORK

A4 BLOCK 805,806 FLOOR TOILET


FLOORING WORK 2 2 2300 156 16 2496 RATE WORK (A4
BLOCK 7TH FLOOR
4 RADHACHARAN RECTIFICATION WORK
CLUB HOUSE STILT FLOOR SPORTS M/S-1, M/C-2)
HALL GRANITE FLOOR TILE LAYING 4 4 4600 167.86 30 5036
WORK

A4 BLOCK STAIRCASE NO 1
4TH,5TH,6TH FLOOR SKIRTING TILE 125.95 15 1889
LAYING WORK FOR (RFT )

A4 BLOCK STAIRCASE NO 2 10TH TO


8TH LANDING FLOOR TILE LAYING 149.13 15 2237
WORK RATE WORK
5 AMINUL SHA 7 14 11200
A4 BLOCK STAIRCASE NO 2 10TH TO
8TH FLOOR TREAD AND RISER TILE 147.6 17 2509
LAYING WORK (RFT)

A5 BLOCK 204 HALL TILE LAYING WORK 352 17 5984

MEDITATION INTERNAL PLASTERING


WORK AND CLUB HOUSE STILT FLOOR RATE WORK
6 DILIP KUMAR YADAV 2 2 2200 215.2 16 3443
FINISHING WORK