SEGUNDO EXAMEN PARCIAL DE PROYECTOS Y VALUACIONES

1. CALCULAR EL INTERES A PAGAR AL CONTRATISTA (INC. IGV) POR EL NO PAGO DE LA


VALORIZACION SIGUIENTE

V(ABRIL-09) = 180,356.00 (SIN IGV)

D= 4,820.00 (SIN IGV)

A= 7,000.00 (SIN IGV)

DIA DE PAGO= 30.06.09

TILE: 30.04.09 = 3.30000 KABRIL-09 = 1.010

TILE: 31.05.09 = 3.78000 KMAY-09 = 1.022

TILE: 30.06.09 = 3.98600 KJUN-09 = 1.030

2. CALCULAR EL PORCENTAJE DEL ADICIONAL DE LA OBRA SIGUIENTE:

MC = 380,000.00 (SIN IGV)

AD-1 = 37,000.00 (SIN IGV)

D-1 = 3,250.00 (SIN IGV)

AD-2 = 15,000.00 (SIN IGV)

D-2 = 7,350.00 (SIN IGV)

3. CALCULAR EL REAJUSTE DE LA VALORIZACION SIGUIENTE:

FEB. MAR. ABR. MAY.


AVANCE
PROGRAMADO 10,000.00 20,000.00 30,000.00 0.00
MENSUAL

AVANCE
PROGRAMADO
ACOMULADO

K 1.005 1.010 1.015 1.020


FEB. MAR. ABR. MAY. JUN

AVANCE REAL
8,000.00 20,000.00 20,000.00 12,000.00 0.00
MENSUAL

AVANCE REAL
ACOMULADO

K 1.005 1.010 1.015 1.020 1.025

VALORIZACION VALORIZACION REAJUSTE REAUSTE POR VALORIZACION


VALORIZACION REAJUSTE REAJUSTE REAL
REAL PROGRAMADA PRGRAMADO RECONOCER REAJUSTE