Paper 0657
Paper 0657
238
232
switching was conducted in energization scenario I where
230
transformer T2 and T3 were energized together, with T1
Vr
Vy
228 Vb
220
based on the 3-phase rms voltage dips shown in Figure 4.
-100 0 100 200
Time (ms)
300 400 500
It can be seen that the simulation circuit is capable to
Figure 2 Measured phase to earth voltage dip of energization scenario II produce results very similar to the field measurement
results, both in terms of voltage dip magnitude and the
It can be seen that the voltage dips caused by the trend of voltage recovery.
transformer inrush is unsymmetrical and shallow in form.
Although transformer energization is a planned operation,
Measured phase A&B
the uncertainties contributed by switching angle, remnant
flux and system strength can still give rise to concerns
about the magnitude of possible voltage dips and the Simulation phase A&B
consequent impacts. To estimate all the possible scenarios, Measured phase C
a computer simulation exercise is used.
Simulation phase C
Paper 0657
duration according to the standards and grid codes. 0.99 2nd threshold
0.97
voltage (pu)
0.93
Vd
From the perspective of the power system operator, the 0.91
0.85
0.91
other than step changes may be allowed up to a level of 0.89
1st
3%, and ER-P28 also recommends that the voltage step- 0.87
0.83
energization. 0.81
voltage and the second one is set at 97% of reference Figure. 6 Signature of sympathetic interaction
voltage, which are labelled in Figure 5 for quantifying the
worst voltage dip scenario. The magnitude of the largest Impact of Numbers of already Energized
voltage dip is defined here as Vd; the duration measured Transformers
based on threshold one is defined as d1; the duration The case above considers only one adjacent already
measured based on threshold two is defined as d2. As can energized transformer. However, there are cases where
be seen, the largest dip magnitude is 14%, with the dip to more than one adjacent transformer can be engaged in
90% for duration of 0.23 s and the dip to 97% for sympathetic interaction. A particular case can be found in
duration of 2.85 s. a wind farm grid connection where a branch of wind
Paper 0657
turbine transformers is energized with other branches of Industry Applications Magazine, vol. 2, pp. 16-19.
wind turbine transformers already energized. [2] J. Lamoree, D. Mueller, P. Vinett, W. Jones, and M.
Simulation studies were carried out to consider such a Samotyj, 1994, "Voltage sag analysis case studies," IEEE
Transactions on Industry Applications, vol. 30, pp. 1083-
scenario based on the circuit shown in Figure 3. The
1089.
worst voltage dip scenario estimated above is chosen as [3] P. Heine and M. Lehtonen, 2003, "Voltage sag distributions
the base case, where the numbers of transformer T1 are caused by power system faults," IEEE Transactions on
varied from zero to five. The comparison of results is Power Systems, vol. 18, pp. 1367-1373.
shown in Figure 7. It is intuitive to know that increasing [4] J. V. Milanovic, A. Myo Thu, and C. P. Gupta, 2005, "The
the number of transformers can significantly prolong the influence of fault distribution on stochastic prediction of
duration of voltage dips, due to the increased sympathetic voltage sags," IEEE Transactions on Power Delivery, vol.
interaction. However, the largest voltage dip is always 20, pp. 278-285.
staying the same. [5] A. J. Williams and M. S. Griffith, 1978, "Evaluating the
Effects of Motor Starting on Industrial and Commercial
Power Systems," IEEE Transactions on Industry
1.02
0.98
Applications, vol. IA-14, pp. 292-305,.
2nd
0.96 [6] E. Styvaktakis and M. H. J. Bollen, 2003, "Signatures of
voltage dips: transformer saturation and multistage dips,"
voltage (pu)
0.94
0.92
IEEE Transactions on Power Delivery, vol. 18, pp. 265-
0.9 1st
0.88
270.
0.86 [7] M. Nagpal, T. G. Martinich, A. Moshref, K. Morison, and
0.84
no sym base case 2 trans P. Kundur, 2006, "Assessing and limiting impact of
0.82
3 trans 4 trans 5 trans transformer inrush current on power quality," IEEE
Transactions on Power Delivery, vol. 21, pp. 890-896.
0.8
0.1 0.4 0.7 1 1.3 1.6 1.9 2.2 2.5 2.8 3.1 3.4 3.7 4 4.3 4.6 4.9
Figure 7 Impacts of numbers of already energized transformers on the dips resulting from energisation of MV wind turbine
magnitude and recovery of voltage dips transformers," 18th International Conference and
Exhibition on Electricity Distribution, CIRED 2005, pp. 1-
CONCLUSIONS 5.
[9] G. Bathurst, 2009, "A simplified method for estimating
This paper presents voltage dip events caused by the voltage dips due to transformer inrush," 20th International
energization of generator step-up transformers from the Conference and Exhibition on Electricity Distribution,
main grid. This voltage dip event occurred in a CIRED 2009, pp. 1-4.
transmission system and was detected and reported by the [10] K.S. Smith, 2005, “Transformer inrush studies for wind
connected distribution utilities. Field measurement results farm grid connections”, International Conference on
are used to verify the simulation model developed in ATP Power System Transients, Paper NO. IPST05-026.
to enable detailed evaluation of the worst case scenario. [11] J. Prousalidis, E. Styvaktakis, E. Sofras, I. K. Hatzilau, and
D. Muthumuni, 2007, "Voltage dips in ship systems," in
It shows that a weak (low short-circuit fault level) system
Electric Ship Technologies Symposium, ESTS '07. IEEE,
is not only vulnerable to significant voltage dips but can pp. 309-314.
also present conditions favourable to initiating [12] K. S. Smith, L. Ran, and B. Leyman, 1999, "Analysis of
sympathetic inrush when there are previously energized transformer inrush transients in offshore electrical
transformers adjacent to the transformer being switched in. systems," IEE Proceedings-Generation, Transmission and
Impacts of such a sympathetic interaction are studied and Distribution, vol. 146, pp. 89-95.
the voltage dip is quantified using thresholds derived [13] H. Bronzeado and R. Yacamini, 1995, "Phenomenon of
from standards and grid codes. sympathetic interaction between transformers caused by
inrush transients," IEE Proceedings Science, Measurement
and Technology, vol. 142, pp. 323-329.
ACKNOWLEDGEMENTS [14] J.S. Peng, S.P. Ang, H.Y. Li, and Z.D. Wang, 2010
The authors would like to express their sincere gratitude "Comparisons of normal and sympathetic inrush and their
toward National Grid for the financial and technical implications toward system voltage depression", 45th
International Universities Power Engineering Conference
support; in particular a special thank-you is given to Mr. (UPEC), pp. 1-5.
Graham Stein and Dr. Forooz Ghassemi for their
technical inputs. The first author, Mr. Peng, would like to
thank the Alumni Research Impact Scholarship of the
University of Manchester for supporting his PhD study.
REFERENCES
[1] H. G. Sarmiento and E. Estrada, 1996, "A voltage sag study
in an industry with adjustable speed drives," IEEE