Joint mapping to be done for the portion where Rigid pavement to be laid
on Rigid pavement for correct positioning of the joints.
Material-
Cement OPC 43 Grade, min 402 Kg grade as per design mix
approved.
Coarse aggregate- Coarse aggregate as per PS clause 9.2.1.4 will be
used.
Fine aggregate- Fine Aggregate as per PS Clause 9.2.1.3.
Recron- Non circular / Triangular fibre @ 0.25 % by weight of
cement i.e 1 kg /cum as per design mix.
Water-As per design mix.
Admixture @1.5 kg/cum as per design mix.
Curing compound @ 3-5 sqm/litre or as per manufacturer instruction.
Water : As per design mix.
Mix Design
Mix design has been carried out from IIT Roorkee. Trial mix has
been carried out at site lab.
Transporting of Concrete.
Freshly mixed concrete will be transported to the laying site without
segregation.
Sufficient delivering vehicles will be used to maintain a continuous
supply of concrete to the paving plant.
Initial Curing
Immediately after the brooming, initial curing of the exposed
concrete surfaces will begin with the application of the approved
curing compound
Rate of application is to be adopted as per CA or manufacturer
instructions. The curing compound will be applied by a approved
mechanical sprayer attached to slip form paver.
After 24 hours of casting of slab bund prepared and cured with water
for 14-21 days.
Construction Joints
Construction joints will be straight and vertically true 25mm depth
all as per CA.
Dummy Joints
Dummy joints will be straight and vertically true 25mm depth all as
per CA.
Deployment of manpower: The following staff will be deputed for
laying site operation