Chairperson Apologies
Kesia Chigwida Mrs Maposa
Nhlanhla Sibambo
1. Evacuation Procedure
1.1 Ms Chairperson explained the evacuation procedure Info
1
MINUTES FOR PROJECTS PROGRESS
SOLIDUS ENGINEERING SOLUTIONS:
MEETINGS
Minutes for Projects Progress Meetings
5.1 The safety file and documents requested were submitted to SM 23/07/15 24/07/15
the client and they are happy with them.
5.2 The site Manager will be meeting the Client tomorrow to
discuss the Launders and the acceptance of the scope 24/07/15
SM/Safety 23/07/15
(24/07/14).
5.3 We will be replacing all the Launders according to the Info 23/07/15 31/07/15
scope.
5.6 We are waiting for the access permit from the client. SM 23/07/15 31/07/15
5.7 Fabrication of ESP bypass in progress at the workshop.