UPS power point to be considered as fuse type for all IBMS equipments
In POD, 50mm Trunking/perforated trays need to consider on all cold aisle for detector & rodent fixing.
300mm Trays/Trunking with closure to be considered inside shafts & below DDC panel
SCADA system workstation with monitor, cat-6 cables, N/W switch to be considered
Completely one vendor is required for one floor to have single ownership.
In Tray line item, need to mention factory fabricated tray/joints/bends/covers to be supplied & installed
along with respective make name
RODENT:
VESDA:
Gray pipes are having more quality than Red pipes, even the red pipe accessories are not available due
to which painting to be done and it doesn’t look quality.
WLD:
Need Addressable WLD panel with In-built battery backup or we can consider 8 Zone panel which is
available in Star Make.
CCTV:
Model No for CCTV switch should be DGS 3120-48TC/24TC to avoid any BW issues and it’s been
recommended from N/W team.
BMS:
Required 10-15% points free space in each JACE controller to utilize for future.
Need to work out on SNMP communication instead of Modbus communication from UPS. At present
data fetching are getting delayed up to 2-3 mins.
Default design of each DDC panel should be 1 Spyder and 3 SIO modules along with relays & fuse for
sensors
IO summary to be considered of all equipment’s pertaining to all electrical and HVAC units.
Tagging for every 5 meters need to be mentioned in all IBMS cables as per client req.
From GSS gas release IO points to be considered for controlling the exhaust and FA fans.
ACS:
PAS:
After first knock, Need to have initial message from Main controller and if it’s not clear within 3 min
then evacuation message to be announced. (Respective inputs/relays to be considered)
FAS:
Required Smock detectors in each Hot Aisle as per client requirement.
Separate panel is required with 10 loops, since existing panel loops are over.
BOM53 is asking the FAS graphics in BMS so required communication card and points in JACE.
GSS:
3D drawing for 9th floor GSS system to be provided to have a clear view on installation
Design has to finalize immediately since the material delivery and logic panel will take min. of 1.5
months lead time.