This document is an engineer's cost estimate for the construction of a 10-story teacher's dormitory building at Rajshahi University of Engineering Technology in Rajshahi, Bangladesh. It includes a grand summary that breaks down the total estimated costs into 9 bills - for general site facilities, civil works, plumbing and sanitary works, electrical works, substation equipment, diesel generator, lifts, fire hydrant system, and air conditioning system. The civil works section further breaks down costs for substructure, superstructure, painting, and windows/doors. The total estimated cost for the entire construction project is provided at the end in Bangladeshi Taka.
This document is an engineer's cost estimate for the construction of a 10-story teacher's dormitory building at Rajshahi University of Engineering Technology in Rajshahi, Bangladesh. It includes a grand summary that breaks down the total estimated costs into 9 bills - for general site facilities, civil works, plumbing and sanitary works, electrical works, substation equipment, diesel generator, lifts, fire hydrant system, and air conditioning system. The civil works section further breaks down costs for substructure, superstructure, painting, and windows/doors. The total estimated cost for the entire construction project is provided at the end in Bangladeshi Taka.
This document is an engineer's cost estimate for the construction of a 10-story teacher's dormitory building at Rajshahi University of Engineering Technology in Rajshahi, Bangladesh. It includes a grand summary that breaks down the total estimated costs into 9 bills - for general site facilities, civil works, plumbing and sanitary works, electrical works, substation equipment, diesel generator, lifts, fire hydrant system, and air conditioning system. The civil works section further breaks down costs for substructure, superstructure, painting, and windows/doors. The total estimated cost for the entire construction project is provided at the end in Bangladeshi Taka.
Construction of 10 Storied Teacher's Dormitory Building of Rajshahi University of
Engineering Technology (RUET) at Rajshahi
Engineer's Cost Estimate Grand Summary Bill No. Description Amount (BDT) Bill No. General and Site Facilities 1: Bill No. Civil Works 2: A-1 : Sub-structure (Below Ground Level) A-1.1 : General Sub Soil Investigation Works A-1.2 Pile Work A-1.3: Excavation, Filling, Site Development A-1.4 Brick Soling, Mass Concrete, Polythene Sheet & Water Stopper A-1.5 Reinforced Cement Concrete (RCC) Works, Admixture & M.S. Fabrication Works A-1.6 Brick Work, Paving Brick, Plaster ,Patent Stone Total (A-1) = A-2: Super-structure (Above Plinth Level) A-2.1: Reinforced Cement Concrete (RCC) Works, Admixture & M.S. Fabrication Works A-2.2: Brick Works A-2.3 Cement Plaster and Drip Course A-2.4: Patent Stone, Tiles, Marble Stone, Granite Stone, , A-2.5: Screeding on Roof A-2.6: Wood Work in Door Frame and Shutter, Clamp, Lock etc.
A-2.7: Stair Railing, Verandah Railing and window Grill works
Total (A-2) = A-3: Painting, Polishing A-4 : Aluminium sliding door, sliding window fixed composite window and glass Total (A-3 to A-4) = Total =
Bill No. Plumbing and Sanitary Works
3: Bill No. Electrical Works (Part-1) 4: Bill No. Electrical Works (Part-2) 4: Bill No. Sub-station Equipment, Bus-bar Trunking, H.T. and LT cable works. 5: Bill No. Diesel Generator and LT cable works. 6: Bill No. Installation of 7: Lifts: Bill No. Fire Hydrant System 8: Bill No. Air-conditioning System 9: Total (Package) = (A) Total of Bills = Amount in words: