Improvement of Cycle Working Bore pile Load Test

RECORD TIME :

Time
No. Item Description Hour Note
Start Finish

1 Preparation Inspection by QS 14:00 16:00 2.00

2 Drilling 1st stage (5M) 16:30 17:00 0.50

2nd stage (>5M) 17:00 17:30 0.50

3rd stage (8M) 17:30 20:30 3.00

4th stage (trial crusher


stone) 20:30 21:30 1.50

3 Others Rest Open fasting -1.00

Total Time 6.50

Note : only drilling time

Exclude : Install Reinforcement, Setting Equipment and Pouring concrete

IMPROVEMENT :

1. The plotting of the spacer line to the next line of zigzag placement should not be straight
line.

2. It is recommended to check the condition of the hole using a cage lamp.

Out door type


weather prof

Wire rop

2.a. – Volume of disposal not a little, need to handle / take care how to improved.
3. The wood of the base support fork for hanging rod (1) + auger does not use small wood
(5/7) replaced with replace WF steel.
1,5 M

1,5 M

4. Use scraper tool to make it easier to clean the head of the rod connection, and the stick
steel to clean the pen hole on the rod

Stick steel, 1” inch


Scraper

5. Availability of closing holes when drilling work is stopped due to rain (plywood and blue
sheets).
6. Availability pole (1.5 m) 4 pcs for safety line

1,5 M

7. Standing “ROD” auger (Drill Rod) using scafolding

Rod Auger

Scafolding /
Rack

Safety Rop

Base used Timber


8. Position of Excavator
Surveyor

Temporary
Rod

Drilling
Excavator Surveyor

Drilling
Point

9. Accessories
- Spare “pin” rod minimum 5pcs each location
- Asiba for inspection hole