x PT PLN (PERSERO)

PENYALURAN DAN PUSAT PENGATUR BEBAN SUMATERA


UNIT PELAYANAN TRANSMISI JAMBI

HARGA PERKIRAAN ENJINIRING (HPE)


PENGADAAN SANITASI DAN SARANA PENGAMANAN GI SUNGAI PENUH
NOMOR : /REN.01.02/MRENEV/2019

NILAI TOTAL
No. Uraian VOL STN HARGA
Material Jasa
(Rp)
1 2 3 4 5 6 7 = (5X3)+(6X3)

I PEKERJAAN PEMBUATAN SUMUR BOR Err:522

a Pembuatan Sumur Bor 1 lot 16,350,000 16,350,000

b Material Pengeboran 1 lot 7,783,250 7,783,250

c Material Filter Air 1 lot Err:522 Err:522

II PEKERJAAN PEMBUATAN POS JAGA 40,876,661


a Pekerjaan Persiapan 1 lot 344,894 344,894
a Pekerjaan Pondasi 1 lot 1,518,059 1,518,059
c Pekerjaan Dinding
Dinding Masif 1 lot 19,420,300 19,420,300
Dinding Komponen 1 lot 3,289,890 3,289,890
Pekerjaan Lantai 1 lot 503,174 503,174
Pekerjaan Sanitair 1 lot 13,011,834 13,011,834
Pekerjaan Pengecatan 1 lot 1,609,530 1,609,530
Pekerjaan Instalasi Listrik 1 lot 867,460 867,460
d Water Proffing Atap 7.08 m2 44,000 311,520

III PEKERJAAN PEMBUATAN PAGAR 75,707,265


a Pekerjaan Galian Tanah 1 meter 1 m3 91,260 91,260
b Pekerjaan Pondasi 1m3 1PC : 4 PS 3.81 m3 765,500 311,460 4,103,218
c Pekerjaan 1m3 sloof beton bertulang (150kg+bekisting) 1.524 m3 6,141,874 886,376 10,711,054

d Pekerjaan 1m3 kolom beton bertulang (150 kg besi + bekisting) 8,186,042 1,069,376 11,106,502
1.2 m3
e Memasang 1 m2 Plesteran 1 PC : 3 PP. Tebal 15mm 152 m2 17,863 77,292 14,463,484
f Pemasangan dinding 1/2 bata 76 m2 137,335 230,688 27,969,748
g Pekerjaan Pengecatan 152 m2 33,554 14,222 7,262,001

Jumlah 150,886,606.00
PPN 10 % 15,088,661
Total 165,975,267

Terbilang : Err:511

Jambi, April 2019


Menyetujui, Yang Mengevaluasi
Manager Manager Bagian Renev

WEGIG AGUS TRIGOYO CANDRA SOLINAR


x PT PLN (PERSERO)
PENYALURAN DAN PUSAT PENGATUR BEBAN SUMATERA
UNIT PELAYANAN TRANSMISI JAMBI

ANALISA HARGA SATUAN (AHS)


PEKERJAAN SUMUR BOR GI SUNGAI PENUH

NILAI TOTAL
No. Uraian VOL STN HARGA
Material Jasa
(Rp)
1 2 3 4 5 6 7 = (5X3)+(6X3)

a Pembuatan Sumur Bor


1 Mobilisasi dan Demobilisasi alat kerja 1 ls 4,500,000 4,500,000

2 Kebersihan Lokasi (dari awal s/d selesai pekerjaan) 1 ls 4,500,000 4,500,000


3 Pengeboran 35 m 210,000 7,350,000
Jumlah 16,350,000

b Material Pengeboran
1 Pipa 4" 35 m 115,000 4,025,000
2 Pipa 2" 35 m 38,000 1,330,000
3 Pipa 3/4" 24 m 10,500 252,000
4 Accessories Pipa 1 ls 1,400,000 1,400,000
5 Ijuk 15 kg 51,750 776,250
Jumlah 7,783,250

c Material Filter Air


1 Fitler Air 1 bh 3,410,000 3,410,000
2 Pompa 1 ls 4,379,430 4,379,430
3 Toren air 1100 liter 1 bh 1,380,000 1,380,000
4 Rumah Pompa 1 bh 1,000,000 1,000,000
Jumlah Err:522

Jambi, April 2019


Yang Mengevaluasi
Manager Bagian Renev

CANDRA SOLINAR
x PT PLN (PERSERO)
PENYALURAN DAN PUSAT PENGATUR BEBAN SUMATERA
UNIT PELAYANAN TRANSMISI JAMBI

ANALISA HARGA SATUAN (AHS)


PEKERJAAN PEMBANGUNAN POS JAGA

NILAI TOTAL
No. Uraian VOL STN HARGA
Material Jasa
(Rp)
1 2 3 4 5 6 7 = (5X3)+(6X3)

a Pekerjaan Persiapan
1 Pengukuran&pembersihan lapangan kerja 1 ls 1,000,000 1,000,000

2 Pemasangan bouwplank 14 m' 8,110 113,540


Jumlah 1,113,540

b Pekerjaan Pondasi
1 Pekerjaan Galian Tanah 3.97 m3 18,200 72,254
2 Pekerjaan Urugan Kembali Bekas Galian 1.39 m3 4,180 5,810
3 Urugan tanah bawah lantai 1.454 m3 4,180 6,078
4 Urugan pasir bawah pondasi & lantai 0.364 m3 108,550 39,512
5 Pondasi Batu kali 1 pc : 4 ps 2.76 m3 455,600 1,257,456
Jumlah 1,381,110

Jambi, September 2019


Yang Mengevaluasi
Manager Bagian Renev

CANDARA SOLINAR
x PT PLN (PERSERO)
PENYALURAN DAN PUSAT PENGATUR BEBAN SUMATERA
UNIT PELAYANAN TRANSMISI JAMBI

ANALISA HARGA SATUAN (AHS)


PEKERJAAN PEMBANGUNAN POS JAGA

NILAI TOTAL

No. Uraian VOL STN HARGA


Material Jasa
(Rp)
1 2 3 4 5 6 7 = (5X3)+(6X3)

a Pekerjaan Galian Tanah 1 meter


1 Pekerja 0.7500 Oh 116,400 87,300
2 Mandor 0.0250 Oh 158,400 3,960

Jumlah 91,260
b Pekerjaan Pondasi 1m3 1PC : 4 PS
1 Batu belah 1.2 m3 328,000 393,600

2 Portland Cement 163 kg 1,500 244,500


3 Pasir pasang 0.52 m3 245,000 127,400
4 Pekerja 1.5000 Oh 116,400 174,600
5 Tukang Kayu 0.7500 Oh 150,000 112,500
6 kepala Tukang 0.0750 Oh 166,400 12,480
7 Mandor 0.0750 Oh 158,400 11,880
Jumlah 1,076,960
c Pekerjaan 1m3 sloof beton bertulang (150kg+bekisting)
1 Kayu Kelas III 0.27 m3 3,523,000 951,210
2 Paku 5 - 12 cm 2 kg 25,307 50,614
3 Minyak bekisting 0.6 ltr 25,000 15,000
4 Besi beton polos 157.5 kg 26,000 4,095,000
5 Kawat beton 2.25 kg 25,000 56,250
6 Semen Portland 336 kg 1,500 504,000
7 Pasir beton 0.54 m3 270,000 145,800
8 Kerikil 0.81 m3 400,000 324,000
9 Pekerja 3.65 Oh 116,400 424,860
10 Tukang Kayu 1.3 Oh 150,000 195,000
11 Tukang Batu 0.275 Oh 150,000 41,250
12 Tukang Besi 1.05 Oh 150,000 157,500
13 Kepala Tukang 0.234 Oh 166,400 38,938
14 Mandor 0.182 Oh 158,400 28,829
Jumlah 7,028,250
d Pekerjaan 1m3 kolom beton bertulang (150 kg besi + bekisting)
1 Kayu Kelas III 0.32 m3 3,523,000 1,127,360
2 Paku 5 - 12 cm 3.2 kg 25,307 80,982
3 Minyak bekisting 1.6 ltr 25,000 40,000
4 Besi beton polos 157.5 kg 26,000 4,095,000
5 Kawat beton 4.5 kg 25,000 112,500
6 Semen Portland 336 kg 1,500 504,000
7 Pasir beton 0.54 m3 270,000 145,800
8 Kerikil 0.81 m3 400,000 324,000
9 Dolken Kayu Galam, φ (8-10) cm, panjang 4 m 32 btg 25,000 800,000
10 Kayu Kelas II balok 0.12 m3 4,190,000 502,800
11 Plywood 9mm 2.8 lbr 162,000 453,600
12 Pekerja 3.65 Oh 166,400 607,360
13 Tukang Kayu 1.3 Oh 150,000 195,000
14 Tukang Batu 0.275 Oh 150,000 41,250
15 Tukang Besi 1.05 Oh 150,000 157,500
16 Kepala Tukang 0.237 Oh 166,400 39,437
17 Mandor 0.182 Oh 158,400 28,829
Jumlah 9,255,418
e Memasang 1 m2 Plesteran 1 PC : 3 PP. Tebal 15mm
1 Semen Portland 7.776 kg 1,500 11,664
2 Pasir Pasang 0.023 m3 269,500 6,199
3 Pekerja 0.3 Oh 166,400 49,920
4 Tukang Batu 0.15 Oh 150,000 22,500
5 Kepala Tukang 0.015 Oh 166,400 2,496
6 Mandor 0.015 Oh 158,400 2,376
Jumlah 95,155
f Pemasangan dinding 1/2 bata
1 Bata Merah 70 kg 1,500 105,000
2 Smen Portland 14.37 m3 1,500 21,555
3 Pasir Pasang 0.04 Oh 269,500 - 10,780
4 Pekerja 0.32 Oh 166,400 53,248
5 Tukang Batu 0.1 Oh 150,000 15,000
6 Kepala Tukang 0.01 Oh 166,400 1,664
7 Mandor 1.015 Oh 158,400 160,776
Jumlah 263,023
g Pekerjaan Pengecatan
1 Plamir tembok 0.1000 kg 65,000 6,500
2 Cat dasar 0.1000 m3 75,150 7,515
3 Cat Penutup 2x setara ICI 0.2600 Oh 75,150 - 19,539
4 Pekerja 0.0200 Oh 166,400 3,328
5 Tukang cat 0.0630 Oh 150,000 9,450
6 Kepala Tukang 0.0063 Oh 166,400 1,048
7 Mandor 0.0025 Oh 158,400 396
Jumlah 41,276

Jambi, September 2019


Yang Mengevaluasi
Manager Bagian Renev

CANDRA SOLINAR
x PT PLN (PERSERO)
PENYALURAN DAN PUSAT PENGATUR BEBAN SUMATERA
UNIT PELAYANAN TRANSMISI JAMBI

BILL OF QUANTITY (BOQ)


PEKERJAAN SUMUR BOR GI MUARA BULIAN

NILAI TOTAL
No. Uraian VOL STN HARGA
Material Jasa
(Rp)
1 2 3 4 5 6 7 = (5X3)+(6X3)

I Pembuatan Sumur Bor 1 lot -

II Material Pengeboran

1 Pipa 4" 50 m -

2 Pipa 2" 50 m -

3 Pipa 3/4" 24 m -

4 Accessories Pipa 1 ls -

5 Ijuk 15 kg -

III Material Filter Air

1 SAND FILTER 1 bh -

2 carbon filter 1 bh -

3 vero filter 1 bh -

4 Pompa 1 ls -

5 Tedmon 1 bh -

6 Bak Air 1 bh -

7 Rumah Pompa 1 bh -

Jumlah -
PPN 10 % -
Total -