DAFTAR HARGA SATUAN UPAH DAN BAHAN

###
U P A H:

1 Pekerja = Rp. 46,000.00 /oh


2 Pekerja listrik/telepon = Rp. 69,575.00 /oh
3 Pengawas Akhli = Rp. 160,080.00 /oh
4 Pengawas las = Rp. 123,740.00 /oh
5 Pembantu tenaga akhli/tehnisi/juru ukur = Rp. 108,790.00 /oh
6 Pembantu operator = Rp. 34,500.00 /oh
7 Operator / Masinis = Rp. 80,500.00 /oh
8 Penjaga malam / semboyan = Rp. 46,000.00 /oh
9 Pengawal KA = Rp. 87,285.00 /oh
10 Mandor = Rp. 69,000.00 /oh
11 Tukang = Rp. 61,525.00 /oh
12 Tenaga akhli = Rp. 152,835.00 /oh
13 Tenaga Pelaksana = Rp. 63,250.00 /oh
14 Kepala Tukang = Rp. 63,250.00 /oh

B A H A N:

1 Amplas = Rp. 4,600.00 /lbr


2 Angker dia. 12 - 70 cm = Rp. 43,585.00 /bh
3 Angkutan wesel lengkap = Rp. 13,567,125.00 /unit
4 Alat bantu susun bantalan beton (kayu, tali, kawat ikat dll ) = Rp. 3,450.00 /ls
5 Alat bantu (bantalan kayu luncur, ban bekas) = Rp. 3,450.00 /ls
6 Alat bantu (steger pengecatan) = Rp. 230,000.00 /ls
7 Angkut bantalan beton dari pabrik dan siap muat = Rp. 8,625.00 /btg
8 Angkut bantalan beton lengkap penambat di site = Rp. 5,750.00 /btg
9 Alat bantu muat dan angkut rel = Rp. 4,025.00 /ls
10 Bahan las + mould R.54/42 (belum termasuk pengerjaan) = Rp. 1,818,495.00 /set
11 Bahan habis terpakai HTT (bensin + olie) = Rp. 2,990.00 /ls
12 Bak cucian piring (stainless) uk. 46 x 102 cm = Rp. 869,975.00 /btg
13 Bambu dia. 8 - 10 cm panjang 6 m = Rp. 49,220.00 /btg
14 Bantalan beton lengkap dgn alat penambat elastis di Quary = Rp. 287,500.00 /btg
15 Batu balas uk. 2/6 di dipo balas = Rp. 228,580.00 /m3
16 Batu bata (kecil) = Rp. 345.00 /bh
17 Batu bata (lubang/besar) = Rp. 2,875.00 /bh
18 Batu kali/belah uk. 15 - 25 cm = Rp. 253,000.00 /m3
19 Baut beugle penyanggaan jembatan = Rp. 43,585.00 /bh
20 Baut klos dia. 16 - 600 mm = Rp. 174,110.00 /bh
21 Baut klos dia. 16 - 1300 mm = Rp. 283,820.00 /bh
22 Baut sambung rel R.54/42 = Rp. 97,865.00 /bh
23 Baut dia. 19 mm - 60 cm = Rp. 62,445.00 /bh
24 Baut dia. 1/2" x 30 mm = Rp. 7,590.00 /bh
25 Baut isolator = Rp. 103,500.00 /bh
26 Baut mur dia. 25 x 100 mm = Rp. 75,670.00 /bh
27 Bensin = Rp. 4,500.00 /ltr
28 Besi beton ulir U.24 = Rp. 19,126.80 /kg
29 Besi L 50x50x5 - 6 m = Rp. 382,087.50 /btg
30 Besi siku ( 70x70x7mm ) panj.6m = Rp. 590,812.50 /bh
31 Besi siku penahan = Rp. 225,400.00 /bh
32 Besi plat uk. 12 x 200 x 3.200 mm = Rp. 15,525.00 /kg
33 Biaya langsir rel R. 54 = Rp. 55,200.00 /ton
34 Biaya pembongkaran bedeng = Rp. 172,500.00 /ls
35 Biaya pemeliharaan alat mesin gilas = Rp. 316,250.00 /bln
36 Biaya muat bongkar tanah (PT.KA. A.54) = Rp. 34,500.00 /m3
37 Biaya pengamanan operasional KA = Rp. 575,575.00 /ls
38 Biaya pengamanan operasional penggantian bantalan = Rp. 5,750.00 /ls
39 Biaya pengujian tanah = Rp. 9,200,000.00 /ls
40 Biaya pengujian dan peralatan listrik = Rp. 115,000.00 /ls
41 Biaya pengujian dan perawatan beton = Rp. 172,500.00 /ls
42 Biaya angkut perancah (truk) = Rp. 57,500.00 /ls
43 Biaya transportasi wesel sampai posisi baru = Rp. 747,500.00 /ls
44 Biaya memasukkan balas, pecok dan profil wesel = Rp. 672,750.00 /ls
45 Biaya operasi MTT wesel 3 x pecok = Rp. 27,600.00 /ls
(sampai kecepatan normal)
46 Biaya operasi PBR = Rp. 8,625.00 /ls
47 Biaya profil balas manual sampai sempurna = Rp. 1,495.00 /ls
48 Biaya pengamanan operasional,persinyalan = Rp. 805.00 /ls
49 Biaya operasi MTT, 3 x pecok track = Rp. 17,825.00 /ls
50 Biaya operasi PBR track = Rp. 13,800.00 /ls
51 Bongkar, pasang kembali saluran kawat tarik ganda (sinyal ) = Rp. 10,950,300.00 /ls
52 Bongkar, setel dan pasang kembali box roda wesel ISS = Rp. 2,616,250.00 /unit
53 Cat dasar = Rp. 40,250.00 /kg
54 Cat tembok setara ICI / Dulux / Mowilex = Rp. 34,500.00 /kg
63 Cat kayu setara FTALIT/ Dana Gloss = Rp. 36,800.00 /kg
64 Clip rel R.54 (bantalan beton/kayu) = Rp. 31,625.00 /bh
65 Closet jongkok (KIA/TOTO) standart = Rp. 220,800.00 /bh
66 Dempul besi (setara Sanpolax) = Rp. 14,950.00 /ltr
67 Demobilisasi alat = Rp. 11,500,000.00 /ls
68 Dokumentasi dan gambar akhir = Rp. 10,465,000.00 /ls
69 Elpiji 46 kg = Rp. 340,285.00 /tbg
70 Engsel pintu kuningan 4" = Rp. 60,490.00 /bh
71 Engsel pintu kuningan 3" = Rp. 47,840.00 /bh
72 Gebalan rumput (rumput embun) = Rp. 23,000.00 /m2
73 Geotextile (non woven) = Rp. 65,205.00 /m2
74 Grease (pelumas) = Rp. 47,725.00 /ltr
75 Grendel uk. 2,5" (kuningan) = Rp. 39,905.00 /bh
76 Genteng beton bubungan warna = Rp. 11,385.00 /bh
77 Genteng beton warna (monier) = Rp. 21,850.00 /bh
78 Ijuk = Rp. 17,250.00 /ikat
79 Insulator R.54 = Rp. 9,775.00 /bh
80 Isolator = Rp. 8,855.00 /bh
81 Jendela kawat raam dan naco = Rp. 207,000.00 /bh
82 Kabel tanah NYY (0,6/1 kv) 3x2x1,5mm2 = Rp. 21,850.00 /m
83 Kabel instalasi NYY (0,6/1 kv) 3 x 6 mm2 = Rp. 26,220.00 /m
84 Kaca polos/bening tebal 5 mm = Rp. 126,500.00 /m2
85 Kaca ribben / warna tebal 5 mm = Rp. 143,750.00 /m2
86 Kain lap = Rp. 8,740.00 /lbr
87 Kait Angin uk. 10" (kuningan) = Rp. 45,425.00 /bh
88 Karung plastik = Rp. 6,670.00 /bh
89 Kawat beton = Rp. 14,375.00 /kg
90 Kawat telepon = Rp. 34,845.00 /kg
91 Kawat ikat dia. 5 mm = Rp. 23,920.00 /kg
92 Kayu dolken dia. 6 - 8 cm panjang 4m = Rp. 47,840.00 /btg
93 Kayu Klas I = Rp. 8,150,625.00 /m3
94 Kayu Klas II = Rp. 3,199,875.00 /m3
95 Kayu Klas III = Rp. 2,233,875.00 /m3
96 Kayu Klas IV (campur) = Rp. 3,565,001.15 /m3
97 Keramik plint uk. 10x30 cm (corak / warna ) = Rp. 5,750.00 /bh
98 Keramik uk. 20x20 cm (corak / warna setara Roman, Milano, Kobin) = Rp. 51,750.00 /bh
100 Keramik uk. 30x30 cm (corak / warna setara Roman, Milano, Kobin) = Rp. 54,050.00 /bh
101 Kertas gambar kalkir = Rp. 20,125.00 /m'
102 Klem + baut = Rp. 189,750.00 /bh
103 Klem besi plat 5 mm (lemari kabel dsb) = Rp. 16,445.00 /bh
104 Kran air dia. 1/2" = Rp. 51,750.00 /bh
105 Kran air dia. 3/4" = Rp. 54,050.00 /bh
106 Kuas 2" = Rp. 16,905.00 /bh
107 Kunci tanam Alpha (lapis, satu slag) = Rp. 250,470.00 /bh
108 Kunci tanam Double Slag (Yale besar) = Rp. 315,330.00 /bh
109 Kunci tanam (KM/WC) Alpha = Rp. 206,655.00 /bh
110 Lantai semen camp. 1 : 3 : 6 = Rp. 44,275.00 /m2
111 Lis profil uk. 2/5 cm kayu klas II = Rp. 16,215.00 /m'
112 Mata bor kayu dia 14 - 16 mm = Rp. 85,445.00 /bh
113 Mata bor rel dia 22 - 25 mm = Rp. 487,025.00 /bh
114 Mata Gergaji besi (p = 12") = Rp. 82,225.00 /bh
115 Mata gerinda (resibon dia. 6") = Rp. 130,295.00 /bh
116 Meni kayu = Rp. 43,700.00 /kg
117 Menggorek, memasukkan balas termasuk pecok = Rp. 6,095.00 /ls
118 Mengumpulkan bantalan bekas, susun di gudang = Rp. 3,680.00 /ls
119 Menyiram dengan air = Rp. 5,060.00 /ls
120 Melengkapi alat penambat wesel, perapihan bantalan kayu = Rp. 8,625.00 /ls
121 Micawood uk.550x350x2,5mm = Rp. 71,875.00 /bh
122 Minyak cat = Rp. 17,250.00 /ltr
123 Mistar panjang 2.140 mm = Rp. 208,725.00 /bh
124 Mistar pelurus rel 1 m = Rp. 130,295.00 /bh
125 Mistar poros = Rp. 120,175.00 /bh
126 Mobilisasi peralatan kerja = Rp. 11,500,000.00 /ls
127 Muat, angkut, ecer patok rel / beton panjang 1.2 m ke lokasi = Rp. 14,950.00 /bh
128 Muat, angkut, ecer patok rel panjang 3.5 m ke lokasi = Rp. 17,250.00 /bh
129 Muat bantalan , susun dan ganjal kayu 6/6 cm = Rp. 12,650.00 /btg
130 Oksigen (46 kg) = Rp. 326,370.00 /tbg
131 Olie SAE 40 = Rp. 47,840.00 /ltr
132 Ongkos angkut sirtu dari quary ke site = Rp. 37,950.00 /m3
133 Ongkos angkut balas dari quary ke dipo balas/tempat muat = Rp. 46,000.00 /m3
134 Ongkos muat balas ke gerbong dengan loader = Rp. 20,930.00 /m3
135 Ongkos angkut balas ke lokasi = Rp. 15,870.00 /m3
136 Paku macam-macam ukuran ( 1,5 - 6" ) = Rp. 13,800.00 /kg
137 Paku maskram = Rp. 10,810.00 /bh
138 Paku seng = Rp. 20,700.00 /kg
139 Pasir beton = Rp. 220,800.00 /m3
140 Pasir pasang = Rp. 198,260.00 /m3
141 Pasir urug = Rp. 197,685.00 /m3
142 Patok beton (tanda kabel) = Rp. 103,500.00 /bh
143 Patok/papan penahan balas = Rp. 5,750.00 /ls
144 Pemasangan patok rel panjang 1.2 m, cor beton = Rp. 18,975.00 /bh
145 Pemasangan patok rel panjang 3.5 m, cor beton = Rp. 31,625.00 /bh
146 Pembersihan lapangan = Rp. 8,625,000.00 /ls
147 Pembuatan dan pemasangan papan nama proyek = Rp. 1,150,000.00 /bh
148 Penerangan lengkap peralatan Direksi Keet = Rp. 8,625,000.00 /ls
149 Penggantian bangunan permanen = Rp. 1,725,000.00 /m2
150 Penggantian bangunan semi permanen = Rp. 1,150,000.00 /m2
151 Penggantian lahan pertanian ( musimam ) = Rp. 3,450.00 /m2
152 Penggantian lahan perkebunan ( tahunan ) = Rp. 5,750.00 /m2
153 Penggantian tanaman tahun ( hutan ) = Rp. 201,250.00 /btg
154 Penjagaan keamanan lingkungan kerja = Rp. 13,800,000.00 /ls
155 Pemadatan / menimbris pasir urug = Rp. 3,450.00 /m3
156 Pembongkaran pagar kawat duri dan susun rel bekas = Rp. 4,600,000.00 /ls
157 Pengaman operasional pengelasan = Rp. 163,185.00 /unit
158 Pengelasan patok rel boog board = Rp. 72,967.50 /bh
159 Pemeriksaan las dengan ultrasonic = Rp. 44,275.00 /ttk
160 Pengecatan dinding dan plafond = Rp. 448,500.00 /unit
161 Pengecatan patok rel panjang 1.2 m (1 x dasar 2 x cat) termasuk tulisan = Rp. 138,000.00 /bh
162 Pengecatan patok rel panjang 3.5 m (1 x dasar 2 x cat) termasuk tulisan = Rp. 127,075.00 /bh
163 Pengecatan beton (1 x dasar 2 x cat) termasuk tulisan angka = Rp. 34,500.00 /bh
164 Pengikatan bantalan untuk keamanan angkutan = Rp. 5,750.00 /btg
165 Peralatan gambar lengkap = Rp. 258,750.00 /set
166 Perkerasan perlintasan sementara = Rp. 8,050,000.00 /unit
167 Perlengkapan alat kerja las termit = Rp. 172,500.00 /unit
168 Pintu Triplex lengkap gembok = Rp. 287,500.00 /bh
169 Pipa PVC dia.1/2" (type AW) 4 m = Rp. 29,900.00 /btg
170 Pipa PVC dia.3/4" (type AW) 4 m = Rp. 35,650.00 /btg
171 Pipa PVC dia.1,5" (type AW) 4 m = Rp. 141,680.00 /btg
172 Pipa PVC dia. 2" (type AW) 4 m = Rp. 112,700.00 /btg
173 Pipa PVC dia. 3" (type AW) 4 m = Rp. 341,550.00 /btg
174 Pipa PVC dia. 4" (type AW) 4 m = Rp. 220,800.00 /btg
175 Plamur Kayu = Rp. 43,700.00 /kg
176 Plamur tembok = Rp. 39,215.00 /kg
177 Plat besi berbagai ukuran tebal = Rp. 47,725.00 /kg
178 Plat besi uk. 12 x 180 x 1800 mm = Rp. 158,125.00 /bh
179 Plat besi tebal 3 mm uk. 60 x 40 cm = Rp. 173,995.00 /bh
180 Plat sambung datar R.54/42 = Rp. 500,365.00 /bh
181 Rel penyangga flens H-beam termasuk pengelasan = Rp. 132,250.00 /btg
182 Regulator elpiji = Rp. 977,845.00 /bh
183 Regulator oksigen = Rp. 1,087,900.00 /bh
184 Rail pad R.54 = Rp. 13,340.00 /bh
185 Rol cat = Rp. 30,475.00 /bh
186 Sabuk pengaman = Rp. 184,690.00 /bh
187 Saluran air dan aksesories = Rp. 80,500.00 /set
188 Saringan air stainless = Rp. 36,110.00 /bh
189 Semboyan (2A, 2B, 2C dan 3) dari plat seng BWG 28
termasuk tiang ( 2 unit ) = Rp. 402,500.00 /unit
190 Penerangan / lampu semboyan ( unit ) = Rp. 287,500.00 /unit
191 Semen Grouting = Rp. 43,700.00 /kg
192 Semen Portland / sejenis (50 kg) = Rp. 63,250.00 /zak
193 Semen Putih (50 kg) = Rp. 101,200.00 /zak
194 Seng aluminium t = 0,5 mm uk. 100 x 200 cm = Rp. 217,580.00 /lbr
195 Seng gelombang 180x90x0,05 BJLS 28 = Rp. 44,850.00 /lbr
196 Seng plat aluminium t = 0,3 mm uk. 100 x 200 cm = Rp. 173,995.00 /lbr
197 Sewa mesin gerinda MP 12 = Rp. 206,655.00 /hr
198 Sewa mesin gerinda tangan = Rp. 206,655.00 /hr
199 Sewa mesin Weldshear manual = Rp. 195,730.00 /hr
200 Sewa mesin Gilas ( Vibrator 12 ton ) = Rp. 31,204,400.00 /bln
201 Shoulders R.54/42 = Rp. 32,315.00 /bh
202 Sirtu (balas pasir + kerikil) = Rp. 201,250.00 /m3
203 Solar = Rp. 6,300.00 /ltr
204 Stapling bantalan lengkap rel geseran = Rp. 104,650.00 /btg
205 Steling bambu = Rp. 151,340.00 /stel
206 Susun bantalan beton = Rp. 9,200.00 /btg
207 Tambang manila = Rp. 65,205.00 /kg
208 Tarikan daun jendela 5" kuningan = Rp. 35,995.00 /bh
209 Tenda plastik 4 x 6 = Rp. 261,050.00 /lbr
210 Ter = Rp. 8,510.00 /kg
211 Terminal bok kabel tanah = Rp. 3,780,050.00 /unit
212 Tiang telepon 7 m (pipa besi) = Rp. 1,739,950.00 /btg
213 Tirepon TN = Rp. 47,840.00 /bh
214 Transportasi peralatan las = Rp. 325,910.00 /unit
215 Trak stang penguat = Rp. 9,430.00 /bh
216 Trak stang penguat tiang listrik = Rp. 172,500.00 /bh
217 Triplek 3mm (1,22x2,44 m) = Rp. 64,975.00 /lbr
218 Triplek 5mm (1,22x2,44 m) = Rp. 89,125.00 /lbr
219 Upah pekerjaan besi beton = Rp. 10,695.00 /kg
220 Upah, pasang, setel, bor / potong besi = Rp. 296,010.00 /ls

Bandar Lampung, 7 Februari 2011


Satkerbangka Lampung,
Ka Satker,

WICAKSONO INDARTO, ST
NIP.19800115 200604 1 002
RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN BOX CULVERT 1X1.5m DAN DRAINASE BETON


LOKASI :

Volume Harga Satuan


No Uraian Pekerjaan Satuan
Pekerjaan (Rp)
1 2 3 4 5
A PELAKSANAAN PEKERJAAN :
I. Persiapan

Jumlah A. I
II PEKERJAAN BOX CULVERT ( 1x1.5 m)

Jumlah A. II

III PEKERJAAN DRAINASE BETON TYPE 1.50 m (Saluran tertutup)


1
2
3
4
Jumlah A. III

IV PEKERJAAN DRAINASE BETON TYPE 1.50 m (Saluran terbuka)


0.00
0.00
0.00
0.00
Jumlah A. IV
V PEKERJAAN DRAINASE BETON TYPE 0.90 m
0.00
0.00
0.00
0.00
Jumlah A. V
B PEKERJAAN PENYELESAIAN

JUMLAH B
REKAPITULASI :
A. PELAKSANAAN PEKERJAAN = Rp.
B. PEKERJAAN PENYELESAIAN = Rp.
JUMLAH = Rp.
PPN 10% = Rp.
JUMLAH = Rp.
DIBULATKAN = Rp.
SUPERVISI = Rp.
TOTAL 13.90
PERHITUNGAN VOLUME
VOLUME DRAINASE BETON TYPE 1,5 M tertutup
Panjang pasangan m
luas penampang beton m2
vol m3
luas penampang galian m2
vol m3
luas penampang pasir m2
vol m3
luas penampang lantai kerja m2
vol m3

VOLUME DRAINASE BETON TYPE 1,5 M terbuka vol total


Panjang pasangan m2
luas penampang beton m2
vol m3 8.81
luas penampang galian m2
vol m3 27.92
luas penampang pasir m2
vol m3 0.83
luas penampang lantai kerja m2
vol m3 0.83

VOLUME DRAINASE BETON TYPE 0,90 M


L m
luas penampang beton m2
vol m3
luas penampang galian m2
vol m3
luas penampang pasir m2
vol m3
luas penampang lantai kerja m2
vol m3

DRAIN TYPE 90 0.00 #DIV/0! M


DIA PJG JUMLAH
16 9.28 #DIV/0!
8 #DIV/0! 56

NO DIA PJG JARAK


1 16 2.5 0.125
2 10 1.95 0.125

DRAIN TYPE 1.50 TERTUTUP 1.53 0.7 M


DIA PJG JUMLAH
19 10.76 2.00
10 0.7 60
10 14.5 3

VOLUME BOX BETON


KETERANGAN Panjang pas. luas penampang (m2) vol (m3)
BALIAN 21.5 5 107.5
Mini pile 6 M 90
COBLE STONE 21.5 0.3 6.45
lantai kerja 21.5 0.1 2.5
beton box 21.5 2.145 46.1175
beton leneng 0.2 5.35 2.14
48.2575

HITUNG BESI
vol beton 48.26 0.0 M

NO DIA PJG JARAK


1 16
2 13
3 16
4 13
5 13
6 13
7 13
8 13
9 12
10 12
11 12
12 12
13 12
14 12

NO DIA PJG JARAK


1 16 2.5 0.125
2 10 1.95 0.125

515.7142857143
9 6
box

Panjang pasangan 8.31 m2


luas penampang beton 1.06 m2
vol 8.81 m3
luas penampang galian 3.36 m2
vol 27.92 m3
luas penampang pasir 0.10 m2
vol 0.83 m3
luas penampang lantai kerja 0.10 m2
vol 0.83 m3

KOEF BERAT
0.888 #DIV/0!
0.394 #DIV/0!

JML #DIV/0! kg/m3

JUMLAH UNIT KOEF BERAT


129.00 2 1.57824 1,017.96
121.00 4 0.6165 581.85

KOEF BERAT
2.226 47.89
0.617 24.18
0.617 26.85
JML 98.93 kg/m3

Sat
m3
bh 540 m
m3
m3

m3

JUMLAH UNIT KOEF BERAT


#DIV/0! 2 1.57824 #DIV/0!
#DIV/0! 4 1.041885 #DIV/0!
#DIV/0! 2 1.57824 #DIV/0!
61.00 2 1.041885
2 1.041885
2 1.041885
4 1.041885
2 1.041885
2 0.88776
2 0.88776
2 0.88776
2 0.88776
2 0.88776
2 0.88776
JML #DIV/0! kg
#DIV/0! kg/m3
Double #DIV/0! kg/m3

JUMLAH UNIT KOEF BERAT


129.00 2 1.57824 1,017.96
121.00 4 0.6165 581.85
54
21
75 100000 7500000
ANALISA HARGA SATUAN

PEKERJAAN : PEMBANGUNAN JALAN KA PARTIAL DOUBLE TRACK ANTARA TTTLY-BBU ( LANJUTAN )


BLAMBANGANUMPU ( LANJUTAN )KM. 149+350 S/D KM. 165+000 NGN - BBU

A. PENGADAAN MATERIAL :
1. Bantalan beton lengkap dengan alat penambat elastis rel R.54 per btg
- Bantalan beton di pabrik @ Rp. 287,500.00 = Rp. 287,500.00
- Angkut dari pabrik dan siap muat = Rp. 8,625.00
- Muat, susun, ganjal kayu 6/6 cm = Rp. 12,650.00
- Pengikatan untuk keamanan angkutan = Rp. 5,000.00
- Alat penambat / bantalan terdiri dari
2.0000 bh Rail pad @ Rp. 13,340.00 = Rp. 26,680.00
4.0000 bh Clip rel @ Rp. 31,625.00 = Rp. 126,500.00
4.0000 bh Insulator @ Rp. 9,775.00 = Rp. 39,100.00
4.0000 bh Shoulders @ Rp. 32,315.00 = Rp. 129,260.00
Jumlah = Rp. 635,315.00
Dibulatkan = Rp. 635,300.00 /btg

2 Bantalan beton wesel R. 54 lengkap dengan alat penambat elastis per btg
- Bantalan beton di pabrik uk. 22x26x400 @ Rp. 850,267.00 = Rp. 850,267.00
- Angkut dari pabrik dan siap muat = Rp. 24,150.00
- Muat, susun, ganjal kayu 6/6 cm = Rp. 25,300.00
- Pengikatan untuk keamanan angkutan = Rp. 5,000.00
- Alat penambat / bantalan terdiri dari
4.0000 bh Rail pad @ Rp. 26,680.00 = Rp. 106,720.00
8.0000 bh Clip rel @ Rp. 31,625.00 = Rp. 253,000.00
8.0000 bh Insulator @ Rp. 9,775.00 = Rp. 78,200.00
8.0000 bh Shoulders @ Rp. 32,315.00 = Rp. 258,520.00
4.0000 bh Base plat 25x200x450 @ Rp. 287,212.50 = Rp. 1,148,850.00
8.0000 bh Baut dia. 25x100 mm @ Rp. 75,670.00 = Rp. 605,360.00
Jumlah = Rp. 3,355,367.00
Dibulatkan = Rp. 3,355,300.00 /btg

3 Bantalan beton wesel R. 54 lengkap dengan alat penambat elastis per btg
- Bantalan beton di pabrik uk. 22x26x300 @ Rp. 637,670.00 = Rp. 637,670.00
- Angkut dari pabrik dan siap muat = Rp. 10,500.00
- Muat, susun, ganjal kayu 6/6 cm = Rp. 18,975.00
- Pengikatan untuk keamanan angkutan = Rp. 5,000.00
- Alat penambat / bantalan terdiri dari
4.0000 bh Rail pad @ Rp. 26,680.00 = Rp. 106,720.00
8.0000 bh Clip rel @ Rp. 31,625.00 = Rp. 253,000.00
8.0000 bh Insulator @ Rp. 9,775.00 = Rp. 78,200.00
8.0000 bh Shoulders @ Rp. 32,315.00 = Rp. 258,520.00
4.0000 bh Base plat 25x200x450 @ Rp. 287,212.50 = Rp. 1,148,850.00
8.0000 bh Baut dia. 25x100 mm @ Rp. 75,670.00 = Rp. 605,360.00
Jumlah = Rp. 3,122,795.00
Dibulatkan = Rp. 3,122,700.00 /btg

1 Balas batu pecah uk. 2 - 6 cm / m3


1.0000 m3 batu balas di quary @ Rp. 207,800.00 = Rp. 207,800.00
Ongkos angkut dari quary ke dipo balas/tempat muat = Rp. 44,000.00
Ongkos muat ke gerbong dengan loader = Rp. 20,000.00
Ongkos angkut ke lokasi = Rp. 15,100.00
Ongkos bongkar, ecer di lokasi
0.3500 oh Pekerja @ Rp. 50,600.00 17,710.00
0.0090 oh Mandor @ Rp. 75,900.00 683.10
Jumlah = Rp. 305,293.10
Dibulatkan = Rp. 305,200.00 /m3

2 Balas Sirtu di site / m3


1.0000 m3 Sirtu (balas pasir + kerikil) uk. 0,1 x 0,5 c @ Rp. 175,500.00 = Rp. 175,500.00
Ongkos Angkut dari quarry ke site = Rp. 36,300.00
Ongkos bongkar, ecer di site
0.3500 oh Pekerja @ Rp. 50,600.00 = Rp. 17,710.00
0.0090 oh Mandor @ Rp. 75,900.00 = Rp. 683.10
Jumlah = Rp. 230,193.10
Dibulatkan = Rp. 230,100.00 /m3

3 Batu kali belah ( untuk banket )/m3


1.0000 m3 Batu kali bela uk. 0,5 x 0,2 cm @ Rp. 254,100.00 = Rp. 254,100.00
Ongkos Angkut dari quarry ke site = Rp. 36,300.00
Ongkos bongkar, ecer di site
0.3500 oh Pekerja @ Rp. 50,600.00 = Rp. 17,710.00
0.0090 oh Mandor @ Rp. 75,900.00 = Rp. 683.10
Jumlah = Rp. 308,793.10
Dibulatkan = Rp. 308,700.00 /m3

B. PELAKSANAAN PEKERJAAN :
I. Pekerjaan Persiapan :
1. Mobilisasi peralatan kerja = Rp. 11,000,000.00 /ls
10.00 ton Pengepakan Peralatan Mesin
2.00 ton Pengepakan Peralatan Manual
10.00 unit Barang Pendukung peralatan mesin
11.00 unit Alat dan Bahan pendukung peralatan mesin
Biaya muat - bongkar dan angkut dari gudang ke lokasi pekerjaan
2. Pengukuran, pasang patok profil track dan gambar / m'
Bahan
0.048 m3 Kayu kelas IV @ Rp 1,732,500.00 = Rp. 82,293.75
0.450 kg Paku biasa @ Rp 12,300.00 = Rp. 5,535.00

Upah
2.000 oh Pekerja @ Rp 50,600.00 = Rp. 101,200.00
1.000 oh Juru ukur @ Rp 108,000.00 = Rp. 108,000.00

Gambar
0.250 m' Kertas gambar kalkir @ Rp 11,000.00 = Rp. 2,750.00
1.000 set Peralatan gambar lengkap @ Rp 245,300.00 = Rp. 245,300.00
1.000 oh Juru gambar @ Rp 108,000.00 = Rp. 108,000.00
Jumlah 653,078.75
Untuk tiap 1,00 m' = 1 / 25 x Rp. 653,078.75 = Rp. 26,123.15
Dibulatkan = Rp. 26,100.00 /m'

3. Pembuatan direksi keet dan gudang material / m2


Dihitung berdasarkan pembuatan bangunan sementara dengan lantai
semen campuran 1 : 3 : 6 tebal 7,00 cm, seluas 40 m2
1.8500 m3 Kayu klas IV (campur) @ Rp. 1,732,500.00 = Rp. 3,205,125.00
30.0000 lbr Triplek 3 mm @ Rp. 69,300.00 = Rp. 2,079,000.00
46.0000 lbr Seng gelombang BJLS 28 @ Rp. 36,200.00 = Rp. 1,665,200.00
7.0000 kg Paku campur @ Rp. 12,300.00 = Rp. 86,100.00
3.0000 kg Paku seng @ Rp. 16,400.00 = Rp. 49,200.00
2.0000 bh Pintu Triplex lengkap gembok @ Rp. 275,000.00 = Rp. 550,000.00
2.0000 bh Jendela kawat raam dan naco @ Rp. 198,000.00 = Rp. 396,000.00
1.0000 unit Pengecatan dinding dan plafond @ Rp. 416,300.00 = Rp. 416,300.00
40.0000 m2 Lantai semen camp. 1 : 3 : 6 @ Rp. 42,300.00 = Rp. 1,692,000.00
6.0000 oh Mandor @ Rp. 75,900.00 = Rp. 455,400.00
24.0000 oh Pekerja @ Rp. 50,600.00 = Rp. 1,214,400.00
Biaya pembongkaran kembali = Rp. 150,000.00
Jumlah = Rp. 11,958,725.00
Untuk tiap 1,00 m2 = 1 / 40 x Rp. 11,958,725.00 = Rp. 298,968.13
Dibulatkan = Rp. 298,900.00 /m2

4. Pembuatan dan pemasangan papan nama proyek / bh


uk. 1 x 1,5 m dari micawood tebal 3 mm lengkap = Rp. 1,100,000.00 /bh

5. Penerangan lengkap peralatan Direksi Keet / ls


Biaya lampu penerangan, meja kursi tamu, meja-kursi kerja = Rp. 8,250,000.00 /ls'
Lemari/rak buku alat tulis-gambar, White Board-papan gambar/grafik

6. Angkut, bongkar, ecer bantalan beton lengkap penambat di site (An.59 PT.KA)
Angkut bantalan beton lengkap penambat di site = Rp. 5,500.00
0.3700 oh Pekerja @ Rp. 50,600.00 = Rp. 18,722.00
Alat bantu (bantalan kayu luncur, ban bekas) = Rp. 4,200.00
Jumlah = Rp. 28,422.00
Dibulatkan = Rp. 28,400.00 /btg

7. Penjagaan keamanan lingkungan kerja = Rp. 13,200,000.00 /ls

II. SANTUNAN
1. Santunan, penggantian nilai bangunan :
a. Permanen / m2 = Rp. 1,650,000.00 /m2
b. Semi Permanen / m2 = Rp. 1,100,000.00 /m2
c. Bongkar pagar kawat duri emplasemen berikut susun rel-rel bekas / ls = Rp. 4,400,000.00 /ls

2. Santunan, penggantian nilai tanam tumbuh :


a. Lahan pertanian (musiman) / m2 = Rp. 3,300.00 /m2
b. Lahan perkebunan (tahunan) / m2 = Rp. 5,500.00 /m2
c. Tanaman tahun (hutan) / btg = Rp. 192,500.00 /btg

III. PEKERJAAN BADAN JALAN KA


1 Menebang/membabat tanaman termasuk buang untuk lokasi tubuh baan / m2
0.1875 oh Pekerja @ Rp. 50,600.00 = Rp. 9,487.50
0.0063 oh Mandor @ Rp. 75,900.00 = Rp. 478.17
Jumlah = Rp. 9,965.67
Dibulatkan = Rp. 9,900.00 /m2

2 Pekerjaan Bongkar Pasangan Batu Kali / Beton / m3


4.0000 oh Pekerja @ Rp. 50,600.00 = Rp. 202,400.00
0.4000 oh Mandor @ Rp. 75,900.00 = Rp. 30,360.00
0.1000 ls Peralatan @ Rp. 55,000.00 = Rp. 5,500.00
Jumlah = Rp. 238,260.00
Dibulatkan = Rp. 238,200.00 /m3

3 Pekerjaan Bongkar Jalan paving / rabat beton / m2


0.1000 oh Pekerja @ Rp. 50,600.00 = Rp. 5,060.00
0.0100 oh Mandor @ Rp. 75,900.00 = Rp. 759.00
Jumlah = Rp. 5,819.00
Dibulatkan = Rp. 5,800.00 /m2

4 Mengupas permukaan tanah humus(striping) pada lokasi timbunan dan membuat trap / m2 (1/5 An Bow A 1)
0.0100 oh Mandor @ Rp. 75,900.00 = Rp. 759.00
0.2500 oh Pekerja @ Rp. 50,600.00 = Rp. 12,650.00
0.4000 jam Sewa Dump Truck @ Rp. 208,500.00 = Rp. 83,400.00
0.0900 oh Excavator @ Rp. 357,500.00 = Rp. 32,175.00
Jumlah untuk 8 m2 = Rp. 128,984.00
Harga per m2 = Rp. 16,123.00
Dibulatkan = Rp. 16,100.00 /m2

1 Pasangan batu kosong dibawah konstruksi / Coble Stone tiap 1 m3


Upah
2.3 oh Pekerja @ Rp. 50,600.00 = Rp. 116,380.00
0.085 oh Mandor @ Rp. 75,900.00 = Rp. 6,451.50
Bahan
1.2 m3 Batu belah @ Rp. 231,000.00 = Rp. 277,200.00
Jumlah 400,031.50
Dibulatkan 400,000.00 /m3

IV. PEKERJAAN BANGUNAN HIKMAT (BH), GORONG - GORONG


a. Penyanggaan / jembatan dadrurat untuk BH 18A anderpass
1 Muat, angkut, bongkar material kerja/penyanggaan dari gudang ke site
a. Rel bekas ( R.33/ R.25 ) /ton
Muat dan angkut /m'
0.0368 oh Pekerja @ Rp. 50,600.00 = Rp. 1,862.08
0.0260 oh Mandor @ Rp. 75,900.00 = Rp. 1,973.40
0.0500 kg Kawat ikat 5mm @ Rp. 23,920.00 = Rp. 1,196.00
1.0000 unit Alat bantu @ Rp. 4,025.00 = Rp. 4,025.00
0.0330 ton Biaya angkut KA @ Rp. 34,500.00 = Rp. 1,138.50
Jumlah = Rp. 10,194.98 a)
Ecer serta susun/m' :
0.0368 oh Pekerja @ Rp. 50,600.00 = Rp. 1,862.08
0.0260 oh Mandor @ Rp. 75,900.00 = Rp. 1,973.40
Jumlah = Rp. 3,835.48 b)
Jumlah (a+b) = Rp. 14,030.46 /m'
Untuk 1ton rel R.33 = 1000 / 33 = Rp. 14,030.46 = Rp. 425,165.45
Dibulatkan = Rp. 425,100.00 /ton

b. Perancah tipe I, II, III termasuk sewa /unit


Sewa perancah / unit untuk per bulan @ Rp. 300,000.00 a)
Muat
2.0000 oh Pekerja @ Rp. 50,600.00 = Rp. 101,200.00
0.2000 oh Mandor @ Rp. 75,900.00 = Rp. 15,180.00
0.7500 kg Kawat ikat 5mm @ Rp. 23,920.00 = Rp. 17,940.00
1.0000 ton Biaya angkut (truk) @ Rp. 57,500.00 = Rp. 57,500.00
Jumlah = Rp. 191,820.00 b)
Bongkar
2.0000 oh Pekerja @ Rp. 50,600.00 = Rp. 101,200.00
0.2000 oh Mandor @ Rp. 75,900.00 = Rp. 15,180.00
Jumlah = Rp. 116,380.00 c)
Jumlah (a+b+c) = Rp. 608,200.00
Dibulatkan = Rp. 608,200.00 /unit

c. Baja H-Beam (WF,INP,DIH) termasuk sewa /ton


Sewa H beam / ton untuk per bulan @ Rp. 400,000.00 a)
Muat
5.0000 oh Pekerja @ Rp. 50,600.00 = Rp. 253,000.00
0.5000 oh Mandor @ Rp. 75,900.00 = Rp. 37,950.00
2.0000 kg Kawat ikat 5mm @ Rp. 23,920.00 = Rp. 47,840.00
1.0000 ton Biaya angkut (truk) @ Rp. 57,500.00 = Rp. 57,500.00
Jumlah = Rp. 396,290.00 b)
Bongkar
5.0000 oh Pekerja @ Rp. 50,600.00 = Rp. 253,000.00
0.5000 oh Mandor @ Rp. 75,900.00 = Rp. 37,950.00
Jumlah = Rp. 290,950.00 c)
Jumlah (a+b+c) = Rp. 1,087,240.00
Dibulatkan = Rp. 1,087,200.00 /ton

2 Menyetel dan pasang rel bendel (3 atau 5 rel) / jalur


Untuk tiap 1 jalur
Upah :
5.0000 oh Tenaga Pelaksana @ Rp. 63,250.00 = Rp. 316,250.00
Jumlah a) = Rp. 316,250.00
Bahan :
5.0000 set beugel rel bendel dia 19 mm @ Rp. 0.00 = Rp. 0.00
Jumlah b) = Rp. 0.00
Jumlah (a+b) = Rp. 316,250.00 /jalur
Membongkar rel bendel (3 atau 5 rel) / jalur
Untuk tiap 1 jalur
Upah :
5.0000 oh Tenaga Pelaksana @ Rp. 63,250.00 = Rp. 316,250.00
Jumlah = Rp. 316,250.00
Biaya Stel dan bongkar rel bendel = Rp. 632,500.00 /jalur
Dibulatkan = Rp. 632,500.00 /jalur

3 Menyetel dan pasang stapling darurat tinggi 1 m


Upah :
15.0000 oh Tenaga Pelaksana @ Rp. 63,250.00 = Rp. 948,750.00
12.0000 oh Maskram @ Rp. 86,000.00 = Rp. 1,032,000.00
Jumlah = Rp. 1,980,750.00 /unit

Membongkar stapling darurat tinggi 1 m


Upah :
20.0000 oh Tenaga Pelaksana @ Rp. 63,250.00 = Rp. 1,265,000.00
Jumlah = Rp. 1,265,000.00 /unit

Biaya Stel dan bongkar stapling = Rp. 3,245,750.00 /unit


Dibulatkan = Rp. 3,245,700.00 /unit

4 Menyetel dan pasang perancah lengkap / jalur


Pasang Perancah type II
Untuk tiap 1 stel
### Membuat dan membongkar konstruksi penyanggaan sementara

Uraian Unit Kuantitas Harga Satuan

a Pekerjaan Angkutan Rel


Menyusun Rel di Lokasi
Muat/bongkar rel R.42 tiap m' rel (42 kg)

Pekerja oh 0.042 Rp. 60,000.00 Rp.


Mandor oh 0.026 Rp. 72,500.00 Rp.
Kawat diameter 4 mm kg 0.050 Rp. 22,800.00 Rp.

Biaya untuk 1 ton = 1000/42 x 5533

Upah Angkut rel per ton

Pekerja oh 5.000 Rp. 60,000.00 Rp.


Mandor oh 0.500 Rp. 72,500.00 Rp.
Biaya pengawalan (pekerja) oh 5.000 Rp. 60,000.00 Rp.
kayu ganjal bh 5.000 Rp. 74,690.00 Rp.
Muat bongkar ton 0.050 Rp. 131,738.10 Rp.

Angkutan Rel per ton

b Sewa Perancah/ Unit


Estimasi harga perancah kg 700.000 Rp. 27,500.00 Rp.
Penyusutan / hari = 17.500.000/(10 hari 1.000 Rp.

Sewa selama 60 hari hari 60.000 Rp. 5,347.22 Rp.

c Memancang Glugu / Batang

Upah
Pelaksana OH 11.000 Rp. 59,100.00 Rp.

Bahan
Glugu (10 m) btg 1.000 Rp. 482,700.00 Rp.
Beugel glugu bh 1.000 Rp. 109,000.00 Rp.
Sepatu glugu bh 1.000 Rp. 77,000.00 Rp.
Cincin glugu bh 0.200 Rp. 77,000.00 Rp.
Baud glugu bh 3.000 Rp. 36,300.00 Rp.
Paku Tirpon bh 3.000 Rp. 43,500.00 Rp.
Tambang manila kg 2.000 Rp. 44,000.00 Rp.
Senteleng bambu bh 0.080 Rp. 101,600.00 Rp.
Solar ltr 4.000 Rp. 8,500.00 Rp.
Olie SAE 30-40 ltr 0.160 Rp. 42,700.00 Rp.
LPG 12 kg bh 0.010 Rp. 138,000.00 Rp.
Zat asam btl 0.050 Rp. 193,800.00 Rp.

d Membongkar Glugu / Batang

Upah
Pelaksana OH 2.000 Rp. 70,000.00 Rp.

e Pasang Perancah/ Unit

Upah
Pelaksana OH 4.000 Rp. 70,000.00 Rp.

Bahan
Baud stel 19-50 mm kg 12.000 Rp. 69,600.00 Rp.
Tambang Manila kg 0.500 Rp. 44,000.00 Rp.

f Bongkar Perancah/ Unit

Upah
Pelaksana OH 2.000 Rp. 70,000.00 Rp.

g Memasang Stapling Tunggal / m tinggi

Upah
Pelaksana OH 1.500 Rp. 70,000.00 Rp.

Bahan
Maskaram kg 1.5 Rp. 18,000.00 Rp.

h Bongkar Stapling Tunggal / m tinggi

Upah
Pelaksana OH 1.000 Rp. 70,000.00 Rp.

i Memasang Rel Bendel/ jalur

Upah
Pelaksana OH 5.000 Rp. 70,000.00 Rp.
Bahan
Begel Rel bendel 19 mm (besi siku set 5 Rp. 290,700.00 Rp.

j Membongkar Rel Bendel/ jalur

Upah
Pelaksana OH 2.000 Rp. 70,000.00 Rp.

k Pasang Gambangan Lengkap Dengan Rel Bendel Untuk Dasar Perancah / m2

Upah
Pelaksana OH 0.750 Rp. 70,000.00 Rp.

Bahan
Baud Kopel 19-50 mm pj 400 mm bh 2.000 Rp. 42,350.00 Rp.
Bor kayu bh 0.200 Rp. 58,000.00 Rp.

l Bongkar Gambangan / m2

Upah
Pelaksana OH 0.350 Rp. 70,000.00 Rp.

m Memasang Bracing Pada Glugu/ton

Upah
Pelaksana OH 5.000 Rp. 70,000.00 Rp.

Bahan
Baud Kopel dia 19 mm panjang 70 bh 4.000 Rp. 67,350.00 Rp.
Tambang Manila kg 2.000 Rp. 44,000.00 Rp.

Untuk Bentang 40 Meter diperlukan


Bantalan kayu 0.18x0.22x200 m btg 52 Rp. 1,199,700.00 Rp.
Angkutan Rel ton 53.760 Rp. 1,148,025.00 Rp.
Sewa Perancah Type II unit 10.000 Rp. 320,833.33 Rp.
Memancang Glugu / Batang btg 72.000 Rp. 1,721,630.00 Rp.
Membongkar Glugu / Batang btg 72.000 Rp. 140,000.00 Rp.
Pasang Perancah unit 10.000 Rp. 1,137,200.00 Rp.
Bongkar Perancah unit 10.000 Rp. 140,000.00 Rp.
Memasang Stapling Tunggal m 12.000 Rp. 132,000.00 Rp.
Bongkar Stapling Tunggal m 12.000 Rp. 70,000.00 Rp.
Memasang Rel Bendel jalur 8.000 Rp. 1,803,500.00 Rp.
Membongkar Rel Bendel jalur 8.000 Rp. 140,000.00 Rp.
Pasang Gambangan Lengkap m2 70.600 Rp. 148,800.00 Rp.
Bongkar Gambangan m2 70.600 Rp. 24,500.00 Rp.
Memasang Bracing Pada Glugu ton 13.440 Rp. 707,400.00 Rp.

Untuk per meter bentang:


313,834,353.33 / 40 Rp.

Harga Satuan m 1.000


Pembulatan m 1.000 Dibulatkan Rp.
jumlah (unit)
Stapling m 2 2
Jumlah

2,508.00
1,885.00
1,140.00
5,533.00
131,738.10

300,000.00
36,250.00
300,000.00
373,450.00
6,586.90
1,016,286.90

1,148,025.00

19,250,000.00
5,347.22

320,833.33

650,100.00

482,700.00
109,000.00
77,000.00
15,400.00
108,900.00
130,500.00
88,000.00
8,128.00
34,000.00
6,832.00
1,380.00
9,690.00
1,721,630.00

140,000.00

280,000.00

835,200.00
22,000.00
1,137,200.00

140,000.00

105,000.00

27,000.00
132,000.00

70,000.00

350,000.00
1,453,500.00
1,803,500.00

140,000.00

52,500.00

84,700.00
11,600.00
148,800.00

24,500.00

350,000.00

269,400.00
88,000.00
707,400.00

62,384,400.00
61,717,824.00
3,208,333.33
123,957,360.00
10,080,000.00
11,372,000.00
1,400,000.00
1,584,000.00
840,000.00
14,428,000.00
1,120,000.00
10,505,280.00
1,729,700.00
9,507,456.00
313,834,353.33

7,845,858.83

7,845,858.83
7,845,800.00

31,383,200.00
DAFTAR HARGA SATUAN UPAH DAN BAHAN

###
U P A H:

1 Pekerja = Rp. 60,000.00 /oh


2 Pekerja listrik/telepon = Rp. 69,500.00 /oh
3 Pengawas Akhli = Rp. 155,000.00 /oh
4 Pengawas las = Rp. 120,000.00 /oh
5 Pembantu tenaga akhli/tehnisi/juru ukur = Rp. 108,000.00 /oh
6 Pembantu operator = Rp. 75,000.00 /oh
7 Operator / Masinis = Rp. 100,000.00 /oh
8 Penjaga malam / semboyan = Rp. 48,400.00 /oh
9 Pengawal KA = Rp. 86,600.00 /oh
10 Mandor = Rp. 72,500.00 /oh
11 Tukang = Rp. 75,000.00 /oh
12 Tenaga akhli = Rp. 152,300.00 /oh
13 Tenaga Pelaksana = Rp. 70,000.00 /oh
14 Kepala Tukang = Rp. 85,000.00 /oh

B A H A N:

1 Amplas = Rp. 4,600.00 /lbr


2 Angker dia. 12 - 70 cm = Rp. 41,600.00 bh
3 Angkutan wesel lengkap = Rp. 12,977,200.00 /unit
4 Angkutan tanah urug = Rp. 28,600.00 /m3
5 Alat bantu susun bantalan beton (kayu, tali, kawat ikat dll ) = Rp. 3,300.00 /ls
6 Alat bantu (bantalan kayu luncur, ban bekas) = Rp. 3,850.00 /ls
7 Angkut bantalan beton dari pabrik dan siap muat = Rp. 8,200.00 /btg
8 Angkut bantalan beton lengkap penambat di site = Rp. 5,000.00 /btg
9 Alat bantu muat dan angkut rel = Rp. 3,800.00 /ls
10 Bahan las + mould R.54/42 (belum termasuk pengerjaan) = Rp. 1,739,400.00 /set
11 Bahan habis terpakai HTT (bensin + olie) = Rp. 2,800.00 /ls
12 Bambu dia. 8 - 10 cm panjang 6 m = Rp. 42,800.00 /btg
13 Bantalan beton lengkap dgn alat penambat elastis di Quary = Rp. 275,000.00 /btg
14 Bantalan kayu klas II uk 13x22x200 cm = Rp. 626,200.00 /btg
15 Batu balas uk. 2/6 di dipo balas = Rp. 207,800.00 /m3
16 Batu pecah (1/2) cm (Split) = Rp. 236,500.00 /m3
17 Batu bata (lubang/besar) = Rp. 1,200.00 /bh
18 Batu kali/belah uk. 15 - 25 cm = Rp. 231,000.00 /m3
19 Baut beugle penyanggaan jembatan = Rp. 41,600.00 /bh
20 Baut klos dia. 16 - 600 mm = Rp. 166,500.00 /bh
21 Baut klos dia. 16 - 1300 mm = Rp. 271,400.00 /bh
22 Baut sambung rel R.54/42 = Rp. 93,600.00 /bh
23 Baut dia. 19 mm - 60 cm = Rp. 59,700.00 /bh
24 Baut dia. 1/2" x 30 mm = Rp. 7,200.00 /bh
25 Baut isolator = Rp. 90,000.00 /bh
26 Baut mur dia. 25 x 100 mm = Rp. 72,300.00 /bh
27 Bensin = Rp. 4,500.00 /ltr
33 Besi beton (polos) U.24 = Rp. 17,500.00 /kg
28 Besi beton ulir U.24 = Rp. 20,500.00 /kg
29 Besi beton ulir U.32 = Rp. 22,500.00 /kg
###
U P A H:

30 Besi L 50x50x5 - 6 m = Rp. 365,400.00 /btg


31 Besi siku ( 70x70x7mm ) panj.6m = Rp. 565,100.00 /bh
32 Besi siku penahan = Rp. 196,000.00 /bh
33 Besi plat uk. 12 x 200 x 3.200 mm = Rp. 13,500.00 /kg
34 Beugel rel bendel dia 19mm = Rp. 241,400.00 /set
35 Biaya langsir rel R. 54 = Rp. 48,000.00 /ton
36 Biaya pembongkaran bedeng = Rp. 165,000.00 /ls
37 Biaya pemeliharaan alat mesin gilas = Rp. 302,500.00 /bln
38 Biaya muat bongkar tanah (PT.KA. A.54) = Rp. 33,000.00 /m3
39 Biaya pengamanan operasional KA = Rp. 550,500.00 /ls
40 Biaya pengamanan operasional penggantian bantalan = Rp. 5,500.00 /ls
41 Biaya pengujian tanah = Rp. 8,800,000.00 /ls
42 Biaya pengujian dan peralatan listrik = Rp. 110,000.00 /ls
43 Biaya pengujian dan perawatan beton = Rp. 165,000.00 /ls
44 Biaya angkut perancah (truk) = Rp. 55,000.00 /ls
45 Biaya transportasi wesel sampai posisi baru = Rp. 715,000.00 /ls
46 Biaya memasukkan balas, pecok dan profil wesel = Rp. 643,500.00 /ls
47 Biaya operasi MTT wesel 3 x pecok = Rp. 24,000.00 /ls
(sampai kecepatan normal)
48 Biaya operasi PBR = Rp. 7,500.00 /ls
49 Biaya profil balas manual sampai sempurna = Rp. 1,400.00 /ls
50 Biaya pengamanan operasional,persinyalan = Rp. 700.00 /ls
51 Biaya operasi MTT, 3 x pecok track = Rp. 16,500.00 /ls
52 Biaya operasi PBR track = Rp. 13,000.00 /ls
53 Bongkar, pasang kembali saluran kawat tarik ganda (sinyal ) = Rp. 10,474,200.00 /ls
54 Bongkar, setel dan pasang kembali box roda wesel ISS = Rp. 2,502,500.00 /unit
55 Cat dasar = Rp. 33,600.00 /kg
56 Cat tembok setara ICI / Dulux / Mowilex = Rp. 18,500.00 /kg
57 Clip rel R.54 (bantalan beton/kayu) = Rp. 30,200.00 /bh
58 Demobilisasi alat = Rp. 11,000,000.00 /ls
59 Dokumentasi dan gambar akhir = Rp. 10,010,000.00 /ls
60 Elpiji 46 kg = Rp. 325,400.00 /tbg
61 Gebalan rumput (rumput embun) = Rp. 17,300.00 /m2
62 Geotextile (non woven) = Rp. 49,500.00 /m2
63 Grease (pelumas) = Rp. 30,200.00 /ltr
64 Insulator R.54 = Rp. 9,300.00 /bh
65 Isolator = Rp. 7,700.00 /bh
66 Jendela kawat raam dan naco = Rp. 180,000.00 /bh
67 Kabel tanah NYY (0,6/1 kv) 3x2x1,5mm2 = Rp. 20,900.00 /m
68 Kabel instalasi NYY (0,6/1 kv) 3 x 6 mm2 = Rp. 25,000.00 /m
69 Kain lap = Rp. 8,300.00 /lbr
70 Karung plastik = Rp. 5,800.00 /bh
71 Kawat beton = Rp. 13,000.00 /kg
72 Kawat telepon = Rp. 30,300.00 /kg
73 Kawat ikat dia. 5 mm = Rp. 22,800.00 /kg
74 Kayu dolken dia. 6 - 8 cm panjang 4m = Rp. 17,600.00 /btg
###
U P A H:

75 Kayu dolken dia. 8 - 10 cm panjang 4m = Rp. 21,100.00 /btg


73 Kayu Klas III = Rp. 2,136,700.00 /m3
74 Kayu Klas IV (campur) = Rp. 1,732,500.00 /m3
75 Kertas gambar kalkir = Rp. 11,000.00 /m'
76 Klem + baut = Rp. 165,000.00 /bh
77 Klem besi plat 5 mm (lemari kabel dsb) = Rp. 15,700.00 /bh
78 Kuas 2" = Rp. 14,000.00 /bh
79 Lantai semen camp. 1 : 3 : 6 = Rp. 40,000.00 /m2
80 Mata bor kayu dia 14 - 16 mm = Rp. 81,700.00 /bh
81 Mata bor rel dia 22 - 25 mm = Rp. 465,800.00 /bh
82 Mata Gergaji besi (p = 12") = Rp. 78,600.00 /bh
83 Mata gerinda (resibon dia. 6") = Rp. 124,600.00 /bh
84 Memindahkan Bok kontrol kabel tanah termasuk lasmop. = Rp. 3,615,700.00 /ls
85 Menggorek, memasukkan balas termasuk pecok = Rp. 5,800.00 /ls
86 Mengumpulkan bantalan bekas, susun di gudang = Rp. 3,500.00 /ls
87 Menyiram dengan air = Rp. 4,800.00 /ls
88 Melengkapi alat penambat wesel, perapihan bantalan kayu = Rp. 8,200.00 /ls
89 Mobilisasi peralatan kerja = Rp. 11,000,000.00 /ls
90 Muat, angkut, ecer patok rel / beton panjang 1.2 m ke lokasi = Rp. 14,300.00 /bh
91 Muat, angkut, ecer patok rel panjang 3.5 m ke lokasi = Rp. 16,500.00 /bh
92 Muat bantalan , susun dan ganjal kayu 6/6 cm = Rp. 12,100.00 /btg
93 Oksigen (46 kg) = Rp. 312,100.00 /tbg
94 Olie SAE 40 = Rp. 33,000.00 /ltr
95 Ongkos angkut sirtu dari quary ke site = Rp. 36,300.00 /m3
96 Ongkos angkut balas dari quary ke dipo balas/tempat muat = Rp. 44,000.00 /m3
97 Ongkos muat balas ke gerbong dengan loader = Rp. 20,000.00 /m3
98 Ongkos angkut balas ke lokasi = Rp. 15,100.00 /m3
99 Paku macam-macam ukuran ( 1,5 - 6" ) = Rp. 12,300.00 /kg
100 Paku maskram = Rp. 10,300.00 /bh
101 Paku seng = Rp. 14,900.00 /kg
102 Pasir beton = Rp. 201,600.00 /m3
103 Pasir pasang = Rp. 181,000.00 /m3
104 Pasir urug = Rp. 180,500.00 /m3
105 Patok beton (tanda kabel) = Rp. 90,000.00 /bh
106 Patok/papan penahan balas = Rp. 5,500.00 /ls
107 Pemasangan patok rel panjang 1.2 m, cor beton = Rp. 18,100.00 /bh
108 Pemasangan patok rel panjang 3.5 m, cor beton = Rp. 30,200.00 /bh
109 Pembersihan lapangan = Rp. 8,250,000.00 /ls
110 Pembuatan dan pemasangan papan nama proyek = Rp. 1,000,000.00 /bh
111 Penerangan lengkap peralatan Direksi Keet = Rp. 7,500,000.00 /ls
112 Penggantian bangunan permanen = Rp. 1,650,000.00 /m2
113 Penggantian bangunan semi permanen = Rp. 1,100,000.00 /m2
114 Penggantian lahan pertanian ( musimam ) = Rp. 3,300.00 /m2
115 Penggantian lahan perkebunan ( tahunan ) = Rp. 5,500.00 /m2
116 Penggantian tanaman tahun ( hutan ) = Rp. 192,500.00 /btg
###
U P A H:

117 Penjagaan keamanan lingkungan kerja = Rp. 12,000,000.00 /ls


118 Pemadatan / menimbris pasir urug = Rp. 3,300.00 /m3
119 Pembongkaran pagar kawat duri dan susun rel bekas = Rp. 4,400,000.00 /ls
120 Pengaman operasional pengelasan = Rp. 156,000.00 /unit
121 Pengelasan patok rel boog board = Rp. 69,700.00 /bh
122 Pemeriksaan las dengan ultrasonic = Rp. 42,300.00 /ttk
123 Pengecatan dinding dan plafond = Rp. 378,500.00 /unit
124 Pengecatan patok rel panjang 1.2 m (1 x dasar 2 x cat) termasuk = Rp. 132,000.00 /bh
125 Pengecatan patok rel panjang 3.5 m (1 x dasar 2 x cat) termasuk = Rp. 121,500.00 /bh
126 Pengecatan beton (1 x dasar 2 x cat) termasuk tulisan angka = Rp. 33,000.00 /bh
127 Pengikatan bantalan untuk keamanan angkutan = Rp. 5,500.00 /btg
128 Peralatan gambar lengkap = Rp. 223,000.00 /set
129 Perkerasan perlintasan sementara = Rp. 7,700,000.00 /unit
130 Perlengkapan alat kerja las termit = Rp. 165,000.00 /unit
131 Pintu Triplex lengkap gembok = Rp. 250,000.00 /bh
132 Pipa PVC dia.3/4" (type AW) 4 m = Rp. 28,100.00 /btg
133 Plamur tembok = Rp. 11,750.00 /kg
134 Plat besi berbagai ukuran tebal = Rp. 14,800.00 /kg
135 Plat besi uk. 12 x 180 x 1800 mm = Rp. 151,200.00 /bh
136 Plat besi tebal 3 mm uk. 60 x 40 cm = Rp. 166,400.00 /bh
137 Plat sambung datar R.54/42 = Rp. 478,600.00 /bh
138 Rel penyangga flens H-beam termasuk pengelasan = Rp. 126,500.00 /btg
139 Regulator elpiji = Rp. 935,300.00 /bh
140 Regulator oksigen = Rp. 1,040,600.00 /bh
141 Rail pad R.54 = Rp. 12,700.00 /bh
142 Sabuk pengaman = Rp. 160,600.00 /bh
143 Semboyan (2A, 2B, 2C dan 3) dari plat seng BWG 28
termasuk tiang ( 2 unit ) = Rp. 385,000.00 /unit
144 Penerangan / lampu semboyan ( unit ) = Rp. 275,000.00 /unit
145 Semen Grouting = Rp. 41,800.00 /kg
146 Semen Portland / sejenis (50 kg) = Rp. 65,000.00 /zak
147 Seng gelombang 180x90x0,05 BJLS 28 = Rp. 33,000.00 /lbr
147 Seng gelombang 180x90x0,05 BJLS 30 = Rp. 42,200.00 /lbr
148 Sewa mesin gerinda MP 12 = Rp. 197,600.00 /hr
149 Sewa mesin gerinda tangan = Rp. 197,600.00 /hr
150 Sewa mesin Weldshear manual = Rp. 187,200.00 /hr
151 Sewa Buldozer = Rp. 225,000.00 /jam
152 Sewa Dump Truck = Rp. 190,000.00 /hr
153 Sewa Excavator = Rp. 325,000.00 /jam
154 Sewa Vibro roller = Rp. 220,000.00 /jam
155 Sewa mesin Gilas ( Vibrator 12 ton ) = Rp. 34,324,800.00 /bln
156 Shoulders R.54/42 = Rp. 30,900.00 /bh
157 Sirtu (balas pasir + kerikil) = Rp. 165,000.00 /m3
158 Solar = Rp. 4,500.00 /ltr
159 Stapling bantalan lengkap rel geseran = Rp. 100,100.00 /btg
160 Steling bambu = Rp. 132,000.00 /stel
161 Susun bantalan beton = Rp. 8,800.00 /btg
162 Tanah urug / timbunan ( merah ) padat = Rp. 52,200.00 /m3
163 Tambang manila = Rp. 48,500.00 /kg
164 Tenda plastik 4 x 6 = Rp. 249,700.00 /lbr
###
U P A H:

165 Ter = Rp. 7,500.00 /kg


166 Terminal bok kabel tanah = Rp. 3,287,000.00 /unit
167 Tiang listrik 9 m (beton) = Rp. 3,580,000.00 /btg
168 Tiang telepon 7 m (pipa besi) = Rp. 1,513,000.00 /btg
169 Tirepon TN = Rp. 41,600.00 /bh
170 Transportasi peralatan las = Rp. 283,400.00 /unit
171 Trak stang penguat = Rp. 8,200.00 /bh
172 Trak stang penguat tiang listrik = Rp. 150,000.00 /bh
173 Triplek 3mm (1,22x2,44 m) = Rp. 63,000.00 /lbr
174 Upah, pasang, setel, bor / potong besi = Rp. 283,100.00 /ls
ANALISA HARGA SATUAN

PEKERJAAN : PEMBANGUNAN JALAN KA PARTIAL DOUBLE TRACK ANTARA TTTLY-BBU ( LANJUTAN )


BLAMBANGANUMPU ( LANJUTAN )KM. 149+350 S/D KM. 165+000 NGN - BBU

A. PENGADAAN MATERIAL :

1 Balas Sirtu di site / m3


1.0000 m3 Sirtu (balas pasir + kerikil) uk. 0,1 x 0,5 c @ Rp. 165,000.00 = Rp. 165,000.00
Ongkos Angkut dari quarry ke site = Rp. 36,300.00
Ongkos bongkar, ecer di site
0.3500 oh Pekerja @ Rp. 60,000.00 = Rp. 21,000.00
0.0090 oh Mandor @ Rp. 72,500.00 = Rp. 652.50
Jumlah = Rp. 222,952.50
Dibulatkan = Rp. 222,900.00 /m3

2 Batu kali belah ( untuk banket )/m3


1.0000 m3 Batu kali bela uk. 0,5 x 0,2 cm @ Rp. 231,000.00 = Rp. 231,000.00
Ongkos Angkut dari quarry ke site = Rp. 36,300.00
Ongkos bongkar, ecer di site
0.3500 oh Pekerja @ Rp. 60,000.00 = Rp. 21,000.00
0.0090 oh Mandor @ Rp. 72,500.00 = Rp. 652.50
Jumlah = Rp. 288,952.50
Dibulatkan = Rp. 288,900.00 /m3

B. PELAKSANAAN PEKERJAAN :
I. Pekerjaan Persiapan :
1. Mobilisasi peralatan kerja = Rp. 11,000,000.00 /ls
10.00 ton Pengepakan Peralatan Mesin
2.00 ton Pengepakan Peralatan Manual
10.00 unit Barang Pendukung peralatan mesin
11.00 unit Alat dan Bahan pendukung peralatan mesin
Biaya muat - bongkar dan angkut dari gudang ke lokasi pekerjaan

2. Pengukuran, pasang patok profil track dan gambar / m'


Bahan
0.048 m3 Kayu kelas IV @ Rp 1,732,500.00 = Rp. 82,293.75
0.450 kg Paku biasa @ Rp 12,300.00 = Rp. 5,535.00

Upah
2.000 oh Pekerja @ Rp 60,000.00 = Rp. 120,000.00
2.000 oh Juru ukur @ Rp 108,000.00 = Rp. 216,000.00

Gambar
0.250 m' Kertas gambar kalkir @ Rp 11,000.00 = Rp. 2,750.00
1.000 set Peralatan gambar lengkap @ Rp 223,000.00 = Rp. 223,000.00
2.000 oh Juru gambar @ Rp 108,000.00 = Rp. 216,000.00
Jumlah 865,578.75
Untuk tiap 1,00 m' = 1 / 25 x Rp. 865,578.75 = Rp. 34,623.15
Dibulatkan = Rp. 34,600.00 /m'

3. Pembuatan direksi keet dan gudang material / m2


Dihitung berdasarkan pembuatan bangunan sementara dengan lantai
semen campuran 1 : 3 : 6 tebal 7,00 cm, seluas 40 m2
1.8500 m3 Kayu klas IV (campur) @ Rp. 1,732,500.00 = Rp. 3,205,125.00
30.0000 lbr Triplek 3 mm @ Rp. 63,000.00 = Rp. 1,890,000.00
46.0000 lbr Seng gelombang BJLS 28 @ Rp. 33,000.00 = Rp. 1,518,000.00
7.0000 kg Paku campur @ Rp. 12,300.00 = Rp. 86,100.00
3.0000 kg Paku seng @ Rp. 14,900.00 = Rp. 44,700.00
2.0000 bh Pintu Triplex lengkap gembok @ Rp. 250,000.00 = Rp. 500,000.00
2.0000 bh Jendela kawat raam dan naco @ Rp. 180,000.00 = Rp. 360,000.00
1.0000 unit Pengecatan dinding dan plafond @ Rp. 378,500.00= Rp. 378,500.00
40.0000 m2 Lantai semen camp. 1 : 3 : 6 @ Rp. 40,000.00= Rp. 1,600,000.00
6.0000 oh Mandor @ Rp. 72,500.00= Rp. 435,000.00
24.0000 oh Pekerja @ Rp. 60,000.00= Rp. 1,440,000.00
Biaya pembongkaran kembali = Rp. 150,000.00
Jumlah = Rp. 11,607,425.00
Untuk tiap 1,00 m2 = 1 / 40 x Rp. 11,607,425.00 = Rp. 290,185.63
Dibulatkan = Rp. 290,100.00 /m2

4. Pembuatan dan pemasangan papan nama proyek / bh


uk. 1 x 1,5 m dari micawood tebal 3 mm lengkap = Rp. 1,000,000.00 /bh

5. Penerangan lengkap peralatan Direksi Keet / ls


Biaya lampu penerangan, meja kursi tamu, meja-kursi kerja = Rp. 7,500,000.00 /ls'
Lemari/rak buku alat tulis-gambar, White Board-papan gambar/grafik

6. Angkut, bongkar, ecer bantalan beton lengkap penambat di site (An.59 PT.KA)
Angkut bantalan beton lengkap penambat di site = Rp. 5,000.00
0.3700 oh Pekerja @ Rp. 60,000.00 = Rp. 22,200.00
Alat bantu (bantalan kayu luncur, ban bekas) = Rp. 3,850.00
Jumlah = Rp. 31,050.00
Dibulatkan = Rp. 31,000.00 /btg

7. Penjagaan keamanan lingkungan kerja = Rp. 12,000,000.00 /ls

II. SANTUNAN
1. Santunan, penggantian nilai bangunan :
a. Permanen / m2 = Rp. 1,650,000.00 /m2
b. Semi Permanen / m2 = Rp. 1,100,000.00 /m2
c. Bongkar pagar kawat duri emplasemen berikut susun rel-rel bekas / ls = Rp. 4,400,000.00 /ls

2. Santunan, penggantian nilai tanam tumbuh :


a. Lahan pertanian (musiman) / m2 = Rp. 3,300.00 /m2
b. Lahan perkebunan (tahunan) / m2 = Rp. 5,500.00 /m2
c. Tanaman tahun (hutan) / btg = Rp. 192,500.00 /btg

III. PEKERJAAN BADAN JALAN KA


1 Menebang/membabat tanaman termasuk buang untuk lokasi tubuh baan / m2
0.1875 oh Pekerja @ Rp. 60,000.00 = Rp. 11,250.00
0.0063 oh Mandor @ Rp. 72,500.00 = Rp. 456.75
Jumlah = Rp. 11,706.75
Dibulatkan = Rp. 11,700.00 /m2

2 Pekerjaan Bongkar Pasangan Batu Kali / Beton / m3


4.0000 oh Pekerja @ Rp. 60,000.00 = Rp. 240,000.00
0.4000 oh Mandor @ Rp. 72,500.00 = Rp. 29,000.00
0.1000 ls Peralatan @ Rp. 55,000.00 = Rp. 5,500.00
Jumlah = Rp. 274,500.00
Dibulatkan = Rp. 274,500.00 /m3

3 Pekerjaan Bongkar Jalan paving / rabat beton / m2


0.1000 oh Pekerja @ Rp. 60,000.00 = Rp. 6,000.00
0.0100 oh Mandor @ Rp. 72,500.00 = Rp. 725.00
Jumlah = Rp. 6,725.00
Dibulatkan = Rp. 6,700.00 /m2

4 Mengupas permukaan tanah humus(striping) pada lokasi timbunan dan membuat trap / m2 (1/5 An Bow A 1)
0.0100 oh Mandor @ Rp. 72,500.00 = Rp. 725.00
0.2500 oh Pekerja @ Rp. 60,000.00 = Rp. 15,000.00
0.4000 jam Sewa Dump Truck @ Rp. 190,000.00 = Rp. 76,000.00
0.0900 oh Excavator @ Rp. 325,000.00 = Rp. 29,250.00
Jumlah untuk 8 m2 = Rp. 120,975.00
Harga per m2 = Rp. 15,121.88
Dibulatkan = Rp. 15,700.00 /m2

5 Pembuatan jalan sementara lebar 3 meter, lapis sirtu digilas padat / m'
Bahan + upah :
4.5000 m3 Sirtu (balas pasir + kerikil) @ Rp. 165,000.00 = Rp. 905,625.00
1.0000 jam Buldozer @ Rp. 225,000.00 = Rp. 258,750.00
0.3000 oh Mandor @ Rp. 72,500.00 = Rp. 20,700.00
4.0000 oh Pekerja @ Rp. 60,000.00 = Rp. 184,000.00
1.0000 ls Alat bantu @ Rp. 50,000.00 = Rp. 50,000.00
Jumlah untuk 10 m' j = Rp. 1,419,075.00
Harga 1 m' jalan se = Rp. 141,907.50
Dibulatkan = Rp. 141,900.00 /m'
6 Galian/keprasan tebing sesuai kemiringan lereng / m3
Menggali tanah (Bow A.1) :
0.7500 oh Pekerja @ Rp. 60,000.00 = Rp. 45,000.00
0.0250 oh Mandor @ Rp. 72,500.00 = Rp. 1,812.50
Jumlah a) = Rp. 46,812.50
Membuang tanah (Bow A.10) :
0.3300 oh Pekerja @ Rp. 60,000.00 = Rp. 19,800.00
0.0100 oh Mandor @ Rp. 72,500.00 = Rp. 725.00
Jumlah b) = Rp. 20,525.00
Jumlah (a+b) = Rp. 67,337.50
Dibulatkan = Rp. 67,300.00 /m3

7 Perataan dan Pemadatan Tanah Dasar / m2


Perataan tanah dengan buldozer
0.0270 jam Sewa Buldozer @ Rp. 225,000.00 = Rp. 6,075.00
Pemadatan tanah pakai mesin
0.0260 jam Sewa Vibro roller @ Rp. 220,000.00 = Rp. 5,720.00
Jumlah = Rp. 11,795.00
Dibulatkan = Rp. 11,700.00 /m2

8 Mengurug tanah (tubuh baan) sesuai normalisasi jalan KA / m3


Untuk tiap 1,00 m3 tanah timbunan
a. Dari tanah (merah) di luar lokasi / badan jalan KA per m3
1). Tanah timbunan termasuk menggali
0.6000 oh Pekerja @ Rp. 60,000.00 = Rp. 36,000.00
0.0250 oh Mandor @ Rp. 72,500.00 = Rp. 1,812.50
2). Biaya muat bongkar tanah (PT.KA. A.54) = Rp. 34,500.00
3). Biaya mengangkut tanah sampai lokasi (jarak angkut 100 m) (Bow A.7)
a 60,000
k= (L + 75) = (100+75) = Rp. 38,181.82
275 275
Jumlah = Rp. 110,494.32
Dibulatkan = Rp. 110,400.00 /m3

9 Menggilas, memadatkan tanah lapis demi lapis dengan mesin berat/gilas/handy stamper per m3 (Bow W.4)
- Biaya operasional 1,00 mesin gilas per bulan ( 25 hari kerja, @ 8 jam/hari)
1,025.00 ltr Solar @ Rp. 4,500.00 = Rp. 4,612,500.00
20.0000 ltr Olie/pelumas mesin @ Rp. 33,000.00 = Rp. 660,000.00
1.0000 bln Biaya pemeliharaan @ Rp. 302,500.00 = Rp. 302,500.00
1.0000 bln Sewa mesin gilas / vibro @ Rp. 34,324,800.00 = Rp. 34,324,800.00
1.0000 bln Operator / Masinis @ Rp. 100,000.00 = Rp. 100,000.00
1.0000 bln Pembantu operator / Penjaga api @ Rp. 75,000.00 = Rp. 75,000.00
150.0000 oh Pekerja @ Rp. 60,000.00 = Rp. 9,000,000.00
30.0000 oh Penjaga malam @ Rp. 60,000.00 = Rp. 1,800,000.00
Jumlah = Rp. 50,874,800.00 /bln
- Biaya gilas untuk 100 m2 = 2/75 x biaya gilas 1 bulan
= 2/75 x Rp. 50,874,800.00 = Rp. 1,356,661.33
Dibulatkan = Rp. 1,356,600.00 /100 m2

Untuk tiap 1,00 m3 dengan ketebalan 0,40 m menjadi 0,30 m tanah padat =
1 : ( 100 x 0,40 ) x biaya gilas = 1 : ( 100 x 0,40 ) x Rp. 1,356,600.00 = Rp. 33,915.00
per 100m2 Dibulatkan = Rp. 33,900.00 /m3

10 Timbunan dan pemadatan tanah tubuh jalan rel lapis demi lapis
dengan menggunakan alat berat / m3
a. Pengurugan tanah untuk tubuh jalan rel / m3
1.2000 m3 Bahan tanah urug @ Rp. 52,200.00 = Rp. 57,000.00
1.0000 m3 Angkutan tanah @ Rp. 28,600.00 = Rp. 29,900.00
Jumlah = Rp. 86,900.00 /m3
b. Perataan dan pemadatan tanah lapis demi lapis
Peralatan
1.0000 m3 Perataan dengan Buldozer @ Rp. 17,200.00 = Rp. 17,200.00
1.0000 m3 Pemadatan dengan Vibro Roller @ Rp. 12,300.00 = Rp. 12,300.00
(10-20 ton)
Upah Perataan dan Pemadatan tanah urug / m3 = Rp. 29,500.00 /m3
c. Pemadatan tanah di belakang tembok penahan
Peralatan
1.0000 m3 Perataan dengan manual @ Rp. 15,780.00 = Rp. 15,780.00
1.0000 m3 Pemadatan dengan Stemper @ Rp. 12,000.00 = Rp. 12,000.00

Upah Perataan dan Pemadatan tanah urug / m3 = Rp. 27,780.00 /m3

d. Test kepadatan DCP dan CBR / m3


1.0000 m3 Test Kepadatan @ Rp. 110.00 = Rp. 110.00
Jumlah = Rp. 110.00
Jumlah ( b+c ) = Rp. 29,610.00
Dibulatkan = Rp. 29,600.00 /m3

11 Biaya pengujian tanah = Rp. 8,800,000.00 /ls

IV. PEKERJAAN BANGUNAN HIKMAT (BH), GORONG - GORONG


a. Memperpanjang BH 18
1. Galian tanah (sama dengan di B.III.4)
- Menggali tanah (Bow A.1) :
0.7500 oh Pekerja @ Rp. 60,000.00 = Rp. 45,000.00
0.0250 oh Mandor @ Rp. 72,500.00 = Rp. 1,812.50

- Membuang tanah (Bow A.6) :


0.3300 oh Pekerja @ Rp. 60,000.00 = Rp. 19,800.00
0.0100 oh Mandor @ Rp. 72,500.00 = Rp. 725.00
Jumlah = Rp. 67,337.50
Dibulatkan = Rp. 67,300.00 /m3

2 Pembuatan kisdam termasuk bongkar / m'


2.5000 btg Kayu dolken dia 6 - 8 cm panjang 4 m @ Rp. 17,600.00 = Rp. 44,000.00
16.0000 bh Karung plastik @ Rp. 5,800.00 = Rp. 92,800.00
1.1000 oh Pekerja @ Rp. 60,000.00 = Rp. 66,000.00
0.0600 oh Mandor @ Rp. 72,500.00 = Rp. 4,350.00
0.2400 oh Pekerja (bongkar) @ Rp. 60,000.00 = Rp. 14,400.00
Jumlah = Rp. 221,550.00
Dibulatkan = Rp. 221,500.00 /m'

3 Pasir urug pemadatan berikut bahan / m3


Bahan + Upah :
1.2000 m3 Pasir urug @ Rp. 180,500.00 = Rp. 216,600.00
0.3000 oh Pekerja @ Rp. 60,000.00 = Rp. 18,000.00
0.0100 oh Mandor @ Rp. 72,500.00 = Rp. 725.00
Pemadatan/menimbris = Rp. 3,450.00
Jumlah = Rp. 238,775.00
Dibulatkan = Rp. 238,700.00 /m3

4 Pekerjaan beton
a. Campuran / adukan beton
Upah kerja membuat campuran beton / m3
1.0000 oh Tukang batu @ Rp. 75,000.00 = Rp. 75,000.00
0.1000 oh Kepala tukang batu @ Rp. 85,000.00 = Rp. 8,500.00
6.0000 oh Pekerja @ Rp. 60,000.00 = Rp. 360,000.00
0.3000 oh Mandor @ Rp. 72,500.00 = Rp. 21,750.00
Jumlah = Rp. 465,250.00 /m3
Dibulatkan = Rp. 465,200.00 /m3

b. Campuran beton dengan batu pecah


1) Beton campuran 1 Pc : 3 Psr : 6 bt pch
Untuk tiap 1,00 m3 beton
Bahan + Upah
1.0000 m3 Batu pecah / split (0,5 - 2,0 cm) @ Rp. 236,500.00 = Rp. 236,500.00
0.5400 m3 Pasir beton @ Rp. 201,600.00 = Rp. 108,864.00
4.2360 zak Semen Portland (kantong @ 50 kg) @ Rp. 65,000.00 = Rp. 275,340.00
1.0000 m3 Upah membuat campuran beton @ Rp. 465,200.00 = Rp. 465,200.00
Jumlah = Rp. 1,085,904.00 /m3
Dibulatkan = Rp. 1,085,900.00 /m3

2) Beton campuran 1 Pc : 2 Psr : 3 bt pch


Untuk tiap 1,00 m3 beton
Bahan + Upah
0.8200 m3 Batu pecah / split (0,5 - 2,0 cm) @ Rp. 236,500.00 = Rp. 193,930.00
0.5400 m3 Pasir beton @ Rp. 201,600.00 = Rp. 108,864.00
6.8000 zak Semen Portland (kantong @ 50 kg) @ Rp. 65,000.00 = Rp. 442,000.00
1.0000 m3 Upah membuat campuran beton @ Rp. 465,200.00 = Rp. 465,200.00
Jumlah = Rp. 1,209,994.00 /m3
Dibulatkan = Rp. 1,209,900.00 /m3

c. Penulangan / Pembesian
Upah : mengerjakan besi beton untuk setiap 1,00 kg besi beton
0.0675 oh Tukang besi @ Rp. 75,000.00 = Rp. 5,062.50
0.0225 oh Kepala tukang besi @ Rp. 85,000.00 = Rp. 1,912.50
0.0675 oh Pekerja @ Rp. 60,000.00 = Rp. 4,050.00
Jumlah = Rp. 11,025.00
Dibulatkan = Rp. 11,000.00 /kg

d. Bekisting/Cetakan Beton.
Bekisting untuk Kolom Utama, Balok Utama, Plat Lantai dan konstruksi berat lainnya
1) Upah kerja membuat, memasang bekisting/cetakan beton dan membongkar kembali
Upah : untuk tiap 1,00 m3 beton bertulang
5.0000 oh Tukang kayu @ Rp. 75,000.00 = Rp. 375,000.00
0.5000 oh Kepala tukang kayu @ Rp. 85,000.00 = Rp. 42,500.00
2.0000 oh Pekerja @ Rp. 60,000.00 = Rp. 120,000.00
0.1000 oh Mandor @ Rp. 72,500.00 = Rp. 7,250.00
2.0000 oh Pekerja bongkar @ Rp. 60,000.00 = Rp. 120,000.00
Jumlah = Rp. 664,750.00 /m3

2) Upah untuk tiap 1,00 m2 cetakan =1/ 10.00 x Rp. 664,750.00 = Rp. 66,475.00 /m2
beton/bekisting Dibulatkan = Rp. 66,400.00 /m2

3) Membuat, memasang bekisting/cetakan beton


Untuk tiap 1,00 m2 cetakan beton
Bahan + Upah
0.0280 m3 Kayu kls IV + papan @ Rp. 1,732,500.00 = Rp. 48,510.00
0.3000 kg Paku campur @ Rp. 12,300.00 = Rp. 3,690.00
0.3500 lbr Triplek tebal 3mm @ Rp. 63,000.00 = Rp. 22,050.00
1.0000 m2 Upah kerja bekisting @ Rp. 66,400.00 = Rp. 66,400.00
Jumlah = Rp. 140,650.00
Dibulatkan = Rp. 140,600.00 /m2

4) Membuat-memasang Stoot Werk


Bahan + Upah untuk tiap 1,00 m3 beton terpasang
10.0000 btg Kayu dolken dia. 6 - 8 cm, Pj. 4 m' @ Rp. 17,600.00 = Rp. 176,000.00
0.1500 m3 Kayu kls IV @ Rp. 1,732,500.00 = Rp. 259,875.00
1.5000 kg Paku campur @ Rp. 12,300.00 = Rp. 18,450.00
7.8750 oh Tukang kayu @ Rp. 75,000.00 = Rp. 590,625.00
0.7875 oh Kepala tukang @ Rp. 85,000.00 = Rp. 66,937.50
2.6250 oh Pekerja @ Rp. 60,000.00 = Rp. 157,500.00
0.1313 oh Mandor @ Rp. 72,500.00 = Rp. 9,519.25
Jumlah = Rp. 1,278,906.75
Dibulatkan = Rp. 1,278,900.00 /m3

- Beton bertulang ad. 1pc : 2ps : 3bt pch (U.24=140kg besi beton/m3)
1.0000 m3 Beton campuran 1 pc : 2 ps : 3 bt pch @ Rp. 1,209,900.00 = Rp. 1,209,900.00
140.0000 kg Besi beton ulir U.24 @ Rp. 20,500.00 = Rp. 2,870,000.00
2.5000 kg Kawat beton @ Rp. 13,000.00 = Rp. 32,500.00
6.0000 m2 Membuat,memasang catakan beton @ Rp. 140,600.00 = Rp. 843,600.00
0.0550 m3 Membuat,memasang Stoot Werk @ Rp. 1,278,900.00 = Rp. 70,339.50
140.0000 kg Upah pekerjaan besi beton @ Rp. 11,000.00 = Rp. 1,540,000.00
Jumlah = Rp. 6,566,339.50
Dibulatkan = Rp. 6,566,300.00 /m3
5 Acian semen dan pengecatan tembok / m2
Bahan :
0.0600 zak Semen Portland (50 kg) @ Rp. 65,000.00 = Rp. 3,900.00
0.1320 kg Cat tembok setara ICI / Mowilex @ Rp. 18,500.00 = Rp. 2,442.00
0.0160 kg Plamur cat tembok @ Rp. 11,750.00 = Rp. 188.00
0.0119 kg Cat Dasar @ Rp. 33,600.00 = Rp. 399.84
0.2500 lbr Amplas @ Rp. 4,600.00 = Rp. 1,150.00
0.0200 bh Kuas 2" @ Rp. 14,000.00 = Rp. 280.00
Jumlah = Rp. 8,359.84 a)
Upah :
0.0750 oh Tukang Cat @ Rp. 75,000.00 = Rp. 5,625.00
0.0080 oh Kepala tukang @ Rp. 85,000.00 = Rp. 680.00
0.0500 oh Pekerja @ Rp. 60,000.00 = Rp. 3,000.00
0.0025 oh Mandor @ Rp. 72,500.00 = Rp. 181.25
Jumlah = Rp. 9,486.25 b)
Jumlah (a+b) = Rp. 17,846.09
Dibulatkan = Rp. 17,800.00 /m2

6 Membuat pondasi/tembok pengaman tanah/balas dari pasangan batu kali/belah ad. 1pc : 3ps
termasuk bahan / m3 (Bow G.31 m + G.26)
Bahan + Upah :
1.2000 m3 Batu kali/belah uk. 15 - 25 cm @ Rp. 231,000.00 = Rp. 277,200.00
3.4000 zak Semen Portland (@ 50 kg) @ Rp. 65,000.00 = Rp. 221,000.00
0.4560 m3 Pasir pasang @ Rp. 181,000.00 = Rp. 82,536.00
1.2000 oh Tukang @ Rp. 75,000.00 = Rp. 90,000.00
0.1200 oh Kepala Tukang @ Rp. 85,000.00 = Rp. 10,200.00
3.6000 oh Pekerja @ Rp. 60,000.00 = Rp. 216,000.00
0.1800 oh Mandor @ Rp. 72,500.00 = Rp. 13,050.00
0.2500 m3 Galian, timbun tanah kembali @ Rp. 67,300.00 = Rp. 16,825.00
Jumlah = Rp. 926,811.00
Dibulatkan = Rp. 926,800.00 /m3

7 Plesteran dengan siar timbul ad. 1:2 / m2 (Bow G.51c)


Bahan + Upah :
0.1050 zak Semen Portland (@ 50 kg) @ Rp. 65,000.00 = Rp. 6,825.00
0.0085 m3 Pasir pasang @ Rp. 181,000.00 = Rp. 1,538.50
0.1200 oh Tukang @ Rp. 75,000.00 = Rp. 9,000.00
0.0120 oh Kepala Tukang @ Rp. 85,000.00 = Rp. 1,020.00
0.3600 oh Pekerja @ Rp. 60,000.00 = Rp. 21,600.00
0.0180 oh Mandor @ Rp. 72,500.00 = Rp. 1,305.00
Jumlah = Rp. 41,288.50
Dibulatkan = Rp. 41,200.00 /m2

Plesteran pasangan batu dengan ad. 1:3 tebal 15 mm termasuk acian / m2


Bahan + Upah :
0.1630 zak Semen Portland (@ 50 kg) @ Rp. 65,000.00 = Rp. 10,595.00
0.0194 m3 Pasir pasang @ Rp. 181,000.00 = Rp. 3,511.40
0.2000 oh Tukang @ Rp. 75,000.00 = Rp. 15,000.00
0.0200 oh Kepala Tukang @ Rp. 85,000.00 = Rp. 1,700.00
0.4000 oh Pekerja @ Rp. 60,000.00 = Rp. 24,000.00
0.0200 oh Mandor @ Rp. 72,500.00 = Rp. 1,450.00
Jumlah = Rp. 56,256.40
Dibulatkan = Rp. 56,200.00 /m2

8 Plesteran pasangan batu dengan ad. 1:3 tebal 15 mm, untuk perbaikan
lantai dinding BH lama / m2 (Bow G.50.i)
Bahan + Upah :
0.1630 zak Semen Portland (@ 50 kg) @ Rp. 65,000.00 = Rp. 10,595.00
0.0194 m3 Pasir pasang @ Rp. 181,000.00 = Rp. 3,511.40
0.2000 oh Tukang @ Rp. 75,000.00 = Rp. 15,000.00
0.0200 oh Kepala Tukang @ Rp. 85,000.00 = Rp. 1,700.00
0.4000 oh Pekerja @ Rp. 60,000.00 = Rp. 24,000.00
0.0200 oh Mandor @ Rp. 72,500.00 = Rp. 1,450.00
Jumlah = Rp. 56,256.40
Dibulatkan = Rp. 56,200.00 /m2
V PEKERJAAN DRAINASE, SALURAN :
1. Membuat saluran air dari pasangan batu kali/belah ad. 1pc : 3ps termasuk pengecatan / m'
Untuk per m' ......................................... = 0,2850 m3 x Rp. Pasangan batu kali/belah
0.285 x Rp. 926,800.00 = Rp. 264,138.00
Pengecatan (topi) saluran =0,60m2/m' 0.6 x Rp. 17,800.00 = Rp. 10,680.00
Jumlah = Rp. 10,680.00 /m'
Dibulatkan = Rp. 10,600.00 /m'

pasangan batu 0.6 m3 x Rp. 926,800.00 = Rp. 556,080.00


Per meter lari (m') Rp. 556,080.00 + 10,600.00 = Rp. 566,680.00
Dibulatkan = Rp. 566,600.00

VI PEKERJAAN JALAN REL :

1. Menguras balas
Menggorek balas lama
1.2500 oh Pekerja @ Rp. 60,000.00 = Rp. 75,000.00
0.0500 oh Mandor @ Rp. 72,500.00 = Rp. 3,625.00
Jumlah = Rp. 78,625.00 a)

Mengayak balas lama


0.7500 oh Pekerja @ Rp. 60,000.00 = Rp. 45,000.00
0.0250 oh Mandor @ Rp. 72,500.00 = Rp. 1,812.50
Jumlah = Rp. 46,812.50 b)

Membuang balas kotor


0.3200 oh Pekerja @ Rp. 60,000.00 = Rp. 19,200.00
0.0110 oh Mandor @ Rp. 72,500.00 = Rp. 797.50
Alat bantu @ Rp. 900.00
Jumlah = Rp. 20,897.50 c)
Jumlah (a+b+c) = Rp. 146,335.00
Dibulatkan = Rp. 146,300.00

2 Menyusun bantalan beton lengkap penambat elastis di site / btg


a. Melangsir, bongkar/menurunkan bantalan
0.3700 oh Pekerja @ Rp. 60,000.00 = Rp. 22,200.00
b. Susun = Rp. 8,800.00
Alat bantu (kayu, tali, kawat ikat dll ) = Rp. 3,300.00
Jumlah = Rp. 34,300.00
Dibulatkan = Rp. 34,300.00 /btg

3 Pengelasan rel R.54 dengan alluminothermit termasuk bahan / ttk (A.61.c PT. KA)
a. Bahan las rel R.54
1.0000 set Bahan las + mould lengkap @ Rp. 1,739,400.00 = Rp. 1,739,400.00 a)

b. Bahan pendukung (habis terpakai) :


0.1500 tbg Oksigen (46 kg) @ Rp. 312,100.00 = Rp. 46,815.00
0.0300 tbg Elpiji 46 kg @ Rp. 325,400.00 = Rp. 9,762.00
1.5000 ltr Bensin @ Rp. 4,500.00 = Rp. 6,750.00
0.0600 ltr Olie SAE 40 @ Rp. 47,840.00 = Rp. 2,870.40
0.0200 lbr Kain lap @ Rp. 8,300.00 = Rp. 166.00
0.0100 lbr Tenda plastik 4 x 6 m @ Rp. 249,700.00 = Rp. 2,497.00
0.1500 bh Mata gerinda dia. 6" @ Rp. 124,600.00 = Rp. 18,690.00
0.0050 bh Regulator oksigen @ Rp. 1,040,600.00 = Rp. 5,203.00
0.0050 bh Regulator elpiji @ Rp. 935,300.00 = Rp. 4,676.50
Jumlah = Rp. 97,429.90 b)
c. Sewa mesin :
0.2500 hr Sewa mesin gerinda MP 12 @ Rp. 197,600.00 = Rp. 49,400.00
0.2500 hr Sewa mesin gerinda tangan @ Rp. 197,600.00 = Rp. 49,400.00
0.2500 hr Sewa mesin Weldshear manual @ Rp. 187,200.00 = Rp. 46,800.00
0.2500 unit Perlengkapan (alat kerja) @ Rp. 165,000.00 = Rp. 41,250.00
Jumlah = Rp. 186,850.00 c)

d. Upah kerja siang hari :


0.7500 oh Pekerja @ Rp. 60,000.00 = Rp. 45,000.00
0.5000 oh Tukang las @ Rp. 75,000.00 = Rp. 37,500.00
0.5000 oh Tukang gerinda @ Rp. 60,000.00 = Rp. 30,000.00
0.2500 oh Pengawas las @ Rp. 120,000.00 = Rp. 30,000.00
Jumlah = Rp. 142,500.00 d)

e. Lain-lain :
0.2000 unit Transportasi peralatan las @ Rp. 283,400.00 = Rp. 56,680.00
0.6000 unit Pengamanan operasional @ Rp. 156,000.00 = Rp. 93,600.00
1.0000 ttk Pemeriksaan las dengan ultrasonic @ Rp. 42,300.00 = Rp. 42,300.00
Jumlah = Rp. 192,580.00 e)

- Pengelasan rel R.54 = Jumlah (a+b+c+d+e) = Rp. 2,358,759.90


Dibulatkan = Rp. 2,358,700.00 /ttk

4 Memasang track baru bantalan beton rel R.54 per m'

a. Memotong rel :
0.1250 oh Pekerja @ Rp. 60,000.00 = Rp. 7,500.00
0.0037 oh Mandor @ Rp. 72,500.00 = Rp. 268.25
1.0000 bh Mata Gergaji besi (p = 12") @ Rp. 82,225.00 = Rp. 82,225.00
0.7000 ltr Bensin @ Rp. 4,500.00 = Rp. 3,150.00
0.0200 ltr Olie SAE 40 @ Rp. 47,840.00 = Rp. 956.80
Jumlah = Rp. 94,100.05 /ttk
Dibulatkan = Rp. 94,100.00 /ttk

Untuk 1 m'track .. 4 x 17.00 x Rp. 94,100.00 = Rp. 22,141.18 /m' a)

b. Menyetel sepur bantalan beton rel R.54


2.2620 oh Pekerja @ Rp. 60,000.00 = Rp. 135,720.00
0.0836 oh Mandor @ Rp. 72,500.00 = Rp. 6,061.00
Jumlah = Rp. 141,781.00 /m' b)
Harga memasang track ...............................
Jumlah (a+b) = Rp. 163,922.18
Dibulatkan = Rp. 163,900.00 /m'

5 Perbaikan geometris jalan rel pada busur lengkap pasang patok lengkung / m'
a. Pasang patok lengkung / m'
Untuk setiap 10 m' sepur
1.0000 bh Patok lengkung dari beton @ Rp. 90,000.00 = Rp. 90,000.00
uk. 0,15 x 0,15 x 1,25 m'
Muat, angkut, ecer ke lokasi = Rp. 14,300.00
Pemasangan patok lengkung, termasuk gambar grafik busur = Rp. 25,740.00
Pengecetan 1 x dasar 2 x cat = Rp. 33,000.00
Jumlah = Rp. 163,040.00
Untuk 1,00 msp = 1/ 10.00 x Rp. 163,040.00 = Rp. 16,304.00 /m' a)

b. Menggorek dan memasukkan balast kembali kedalam


track, profil dan memecok / m'
0.0200 oh Mandor @ Rp. 72,500.00 = Rp. 1,450.00
0.6500 oh Pekerja @ Rp. 60,000.00 = Rp. 39,000.00
Jumlah = Rp. 40,450.00 /m' b)

c. Mengeser arah melintang track bantalan beton / m'


0.0356 oh Mandor @ Rp. 72,500.00 = Rp. 2,581.00
0.4810 oh Pekerja @ Rp. 60,000.00 = Rp. 28,860.00
Jumlah = Rp. 31,441.00
Untuk tiap 1 msp hidup (lintas raya) = 1, x Rp. 31,441.00 = Rp. 41,910.85 /m' c)
Jumlah (a+b+c) = Rp. 98,664.85
Dibulatkan = Rp. 98,600.00 / m
6 Pembuatan skip semboyan dan penerangan
2 unit semboyan (2A, 2B, 2C dan 3) dari plat seng BWG 28 termasuk tiang = Rp. 385,000.00
2 unit penerangan / lampu semboyan = Rp. 275,000.00
Jumlah = Rp. 660,000.00 /unit

7 Penjagaan track, keamanan perjalanan KA = Rp. 48,400.00 /oh

VII PEKERJAAN WESEL :


1. Muat, angkut, bongkar, langsir wesel R.54 dari tempat penyimpanan sampai ke posisi wesel baru / unit
Untuk tiap 1,00 unit wesel R.54 ( 1 : 12 ) lengkap sampai ke posisi baru
a. Muat, memilih dan memilah wesel R.54 bantalan kayu
29.2000 oh Pekerja @ Rp. 60,000.00 = Rp. 1,752,000.00
0.9250 oh Mandor @ Rp. 72,500.00 = Rp. 67,062.50
10.0000 kg Kawat ikat dia 5 mm @ Rp. 22,800.00 = Rp. 228,000.00
1.0000 unit Angkutan wesel lengkap = Rp. 12,977,200.00
Jumlah a) = Rp. 15,024,262.50
b. Bongkar di emplasemen
29.2000 oh Pekerja @ Rp. 60,000.00 = Rp. 1,752,000.00
0.9250 oh Mandor @ Rp. 72,500.00 = Rp. 67,062.50
Jumlah b) = Rp. 1,819,062.50
c. Langsir wesel ke posisi pemasangan
30.000 oh Pekerja @ Rp. 60,000.00 = Rp. 1,800,000.00
0.9250 oh Mandor @ Rp. 72,500.00 = Rp. 67,062.50
Biaya pengamanan operasional KA = Rp. 575,575.00
Jumlah c) = Rp. 2,442,637.50
Jumlah [ a) + b) + c) ] = Rp. 19,285,962.50
Dibulatkan = Rp. 19,285,900.00 /unit

2 Menyetel wesel R.54/42 termasuk pembuatan stapling dan rel penggeser / unit
a. Menyetel wesel baru / bekas :
33.000 oh Pekerja @ Rp. 60,000.00 = Rp. 1,980,000.00
1.9000 oh Mandor @ Rp. 72,500.00 = Rp. 137,750.00
Jumlah a) = Rp. 2,117,750.00

b. Membuat stapling dan rel geseran lengkap :


30.000 btg Stapling bantalan lengkap rel geseran @ Rp. 104,650.00 = Rp. 3,139,500.00
1.500 ltr Grease (pelumas) @ Rp. 30,200.00 = Rp. 45,300.00
7.500 ltr Solar @ Rp. 4,500.00 = Rp. 33,750.00
Jumlah b) = Rp. 3,218,550.00

c. Membuat, pasang plat besi dudukan roda wesel ISS :


2.0000 bh Plat besi uk. 12 x 180 x 1800 mm @ Rp. 151,200.00 = Rp. 302,400.00
12.0000 bh Tirepon TN @ Rp. 41,600.00 = Rp. 499,200.00
1.0000 ls Upah, pasang, setel, bor / potong besi = Rp. 283,100.00
Jumlah c) = Rp. 1,084,700.00
Jml {a)+b)+c)} = Rp. 6,421,000.00
Dibulatkan = Rp. 6,421,000.00 /unit

3 Membongkar dan menggeser keluar track lama untuk kedudukan


wesel UIC.54 berikut potong/bor rel per m'
a. Membongkar track lama :
0.2000 oh Pekerja @ Rp. 60,000.00 = Rp. 12,000.00
0.0143 oh Mandor @ Rp. 72,500.00 = Rp. 1,036.75
Jumlah = Rp. 13,036.75 /m' a)

b. Memotong rel : = Rp. 94,100.00 /ttk


Untuk 1 m'track 4 / 17.00 x Rp. 94,100.00 = Rp. 22,141.18 /m' b)

c. Mengumpulkan bantalan :
0.0800 oh Pekerja @ Rp. 60,000.00 = Rp. 4,800.00 /btg
Untuk 1 m'track = 1.6700 x Rp. 4,800.00 = Rp. 8,016.00 /m' c)
d. Mengebor rel = Rp. 26,686.00 /ttk
Untuk 1 m'track = 18 / 30.00 x Rp. 26,686.00 = Rp. 16,011.60 /m' d)

e. Biaya menggali, menggorek, meratakan balas termasuk buang balas kotor = Rp. 146,300.00 e)
Jumlah[a)+b)+c)+d)+e)] = Rp. 205,505.53
Dibulatkan = Rp. 205,500.00 /m'

4 Memasukkan, pemasangan wesel ke sepur / unit


51.000 oh Pekerja @ Rp. 60,000.00 = Rp. 3,060,000.00
1.0000 oh Mandor @ Rp. 72,500.00 = Rp. 72,500.00
Biaya memasukkan balas, pecok dan profil = Rp. 672,750.00
Biaya pengamanan operasional KA = Rp. 575,575.00
Jumlah = Rp. 4,380,825.00 /unit

5 a. Penyetelan peralatan klauw pengaman persinyalan pada wesel / unit


1.1500 oh Kepala tukang besi @ Rp. 85,000.00 = Rp. 97,750.00
4.6000 oh Tukang besi @ Rp. 75,000.00 = Rp. 345,000.00
1.8000 oh Pekerja @ Rp. 60,000.00 = Rp. 108,000.00
0.2000 oh Mandor @ Rp. 72,500.00 = Rp. 14,500.00
1.500 ltr Grease (pelumas) @ Rp. 30,200.00 = Rp. 45,300.00
120.740 kg Besi plat uk. 12 x 200 x 3.200 mm @ Rp. 13,500.00 = Rp. 1,629,990.00
Jumlah = Rp. 2,240,540.00
Dibulatkan = Rp. 2,240,500.00 /unit

6 Mengganti bantalan kayu wesel termasuk melengkapi alat penambat / batang


Untuk bantalan kayu biasa di Emplasemen sepur utama / batang
0.0500 oh Mandor @ Rp. 72,500.00 = Rp. 3,625.00
0.2000 oh Pekerja @ Rp. 60,000.00 = Rp. 12,000.00
0.1000 bh Mata bor kayu (dia. 14 - 16 mm) @ Rp. 81,700.00 = Rp. 8,170.00
0.1000 kg Ter @ Rp. 7,500.00 = Rp. 750.00
Menggorek, memasukkan balas termasuk pecok = Rp. 5,800.00
Mengumpulkan bantalan bekas, susun di gudang = Rp. 3,500.00
Melengkapi alat penambat wesel, perapihan bantalan kayu = Rp. 8,200.00
Biaya pengamanan operasional = Rp. 550,500.00
Jumlah = Rp. 592,545.00
Untuk 1,00 batang bantalan kayu wesel ............ 2.00 x Rp. 592,545.00 = Rp. 1,185,090.00
Dibulatkan = Rp. 1,185,000.00 /btg

7 Angkat listring wesel dengan HTT/Manual /unit


Sesuai ketinggian KR baru dan kecepatan KA > 60 km/jam pada bantalan kayu/besi
Untuk tiap 1,00 m' sepur
a. Untuk kecepatan ka. 20 km/jam, dari kecepatan ka 5 km/jam
0.2800 oh Pekerja @ Rp. 60,000.00 = Rp. 16,800.00
0.0280 oh Mandor @ Rp. 72,500.00 = Rp. 2,030.00
Jumlah a) = Rp. 18,830.00 /m'

b. Untuk kecepatan ka. 40 km/jam, dari kecepatan ka 20 km/jam


0.4500 oh Pekerja @ Rp. 60,000.00 = Rp. 27,000.00
0.0500 oh Mandor @ Rp. 72,500.00 = Rp. 3,625.00
Jumlah b) = Rp. 30,625.00
c. Bahan habis terpakai HTT
0.7000 ltr Bensin @ Rp. 4,500.00 = Rp. 3,150.00
0.1000 ltr Olie SAE 40 @ Rp. 47,840.00 = Rp. 4,784.00
Jumlah d) = Rp. 7,934.00
Jumlah[a)+b)+c)+d)] = Rp. 57,389.00 /m'

Untuk tiap 1,00 unit wesel R.54 1:12 (= 140 msp 140.00 x Rp. 57,389.00 = Rp. 8,034,460.00
Dibulatkan = Rp. 8,034,400.00 /unit
8 Angkat listring wesel dengan MTT (sampai ketinggian dan kec. KA normal) / unit
Untuk tiap 1,00 m' panjang sepur
0.0350 oh Juru ukur (optik) @ Rp. 108,000.00 = Rp. 3,780.00
0.3500 oh Pekerja track(pembantu juru ukur) @ Rp. 60,000.00 = Rp. 21,000.00
2x Biaya operasi MTT wesel 3 x pecok @ Rp. 24,000.00 = Rp. 48,000.00
(sampai kecepatan normal)
1x Biaya operasi PBR @ Rp. 7,500.00 = Rp. 7,500.00
Biaya profil balas manual sampai sempurna = Rp. 1,300.00
Biaya pengamanan operasional,persinyalan = Rp. 650.00
Jumlah = Rp. 82,230.00 /m'
Untuk tiap 1,00 unit wesel R.54 1/12 (140 msp) 140.00 x Rp. 82,230.00 = Rp. 11,512,200.00 /unit
Dibulatkan = Rp. 11,512,200.00 /unit

VIII. PEKERJAAN BALAS


1. Menghampar, meratakan/memasukkan sub balas sirtu ke dalam track
berikut pemadatan dengan alat berat per m3 (A.4a PT.KA)
a. Menghampar, meratakan / memasukkan sub balas sirtu ke dalam track
0.2000 oh Pekerja @ Rp. 60,000.00 = Rp. 12,000.00
0.0100 oh Mandor @ Rp. 72,500.00 = Rp. 725.00
Jumlah = Rp. 12,725.00 a)
b. Pemadatan dengan mesin = Rp. 33,900.00 b)
Menyiramdengan air = Rp. 4,800.00 c)
Jumlah (a+b+c) = Rp. 51,425.00
Dibulatkan = Rp. 51,400.00 /m3

2. Memasang / Memasukkan batu kali belah baru ke tubuh baan baru / m3


0.8260 oh Pekerja @ Rp. 60,000.00 = Rp. 49,560.00
0.0270 oh Mandor @ Rp. 72,500.00 = Rp. 1,957.50
Jumlah = Rp. 51,517.50
Dibulatkan = Rp. 51,500.00 /m3

3. Angkat listring track dengan HTT/manual (sampai ketinggian KR Top dan kec.KA > 40 km/jam) per m'
a. Untuk kecepatan 20 km/jam dari kecepatan 5 km/jam
0.0380 oh Mandor @ Rp. 72,500.00 = Rp. 2,755.00
0.3800 oh Pekerja @ Rp. 60,000.00 = Rp. 22,800.00
Jumlah = Rp. 25,555.00 a)
b. Untuk kecepatan 40 km/jam dari kecepatan 20 km/jam
0.0750 oh Mandor @ Rp. 72,500.00 = Rp. 5,437.50
0.6800 oh Pekerja @ Rp. 60,000.00 = Rp. 40,800.00
Jumlah = Rp. 46,237.50 b)
c. Bahan habis terpakai HTT (bensin + olie) = Rp. 2,990.00 c)
Jumlah ( a + b + c ) = Rp. 74,782.50
Dibulatkan = Rp. 74,700.00 /m'

4. Angkat listring track dengan MTT (sampai kecepatan KA normal) dan PBR / m' (A.38 PT. KA)
0.0350 oh Juru ukur (optik) @ Rp. 108,000.00 = Rp. 3,780.00
0.3500 oh Pekerja (pembantu juru ukur) @ Rp. 60,000.00 = Rp. 21,000.00
3.0000 x Biaya operasi MTT, 3 x pecok @ Rp. 24,000.00 = Rp. 72,000.00
2.0000 x Biaya operasi PBR @ Rp. 7,500.00 = Rp. 15,000.00
Biaya pengaman operasional = Rp. 805.00
Jumlah = Rp. 112,585.00
Dibulatkan = Rp. 112,500.00 /m'
IX. PEKERJAAN KHUSUS
1. Pekerjaan lain :
a. Patok rel lengkung peralihan / preipal per bh
1.0000 ttk memotong rel (pj. 1.20m) @ Rp. 94,100.00 = Rp. 94,100.00
Muat, angkut, ecer ke lokasi = Rp. 14,300.00
Pemasangan patok rel, cor beton = Rp. 18,100.00
Pengecatan (1 x dasar 2 x cat) termasuk tulisan = Rp. 33,000.00
Jumlah = Rp. 159,500.00
Dibulatkan = Rp. 159,500.00 /bh
b. Patok beton km - hm / bh
1.0000 bh Patok beton km / hm @ Rp. 90,000.00 = Rp. 90,000.00
Muat, angkut, ecer ke lokasi = Rp. 14,300.00
Pemasangan patok = Rp. 18,100.00
Pengecatan (1 x dasar 2 x cat) termasuk tulisan angka = Rp. 33,000.00
Jumlah = Rp. 155,400.00
Dibulatkan = Rp. 155,400.00 /bh

c. Membongkar dan pasang kembali jaringan kabel/kawat, tiang telepon lengkap / m'
Bahan : untuk tiap jalur sepanjang 30 m'
0.2500 bh Tiang telepon @ Rp. 1,513,000.00 = Rp. 378,250.00
0.2500 bh Besi siku penahan @ Rp. 196,000.00 = Rp. 49,000.00
1.0000 bh Klem + baut @ Rp. 165,000.00 = Rp. 165,000.00
1.0000 bh Baut isolator @ Rp. 90,000.00 = Rp. 90,000.00
0.2500 bh Trak stang penguat @ Rp. 8,200.00 = Rp. 2,050.00
2.5000 bh Isolator @ Rp. 7,700.00 = Rp. 19,250.00
5.0000 kg Kawat telepon @ Rp. 30,300.00 = Rp. 151,500.00
4.8500 kg Tambang manila @ Rp. 48,500.00 = Rp. 235,225.00
0.4000 bh Senteleng bambu @ Rp. 132,000.00 = Rp. 52,800.00
0.1500 m3 Beton cor 1 : 2 : 3 @ Rp. 1,209,900.00 = Rp. 181,485.00
0.5000 bh Sabuk pengaman @ Rp. 160,600.00 = Rp. 80,300.00

Upah :
15.0000 oh Pekerja @ Rp. 60,000.00 = Rp. 900,000.00
3.0000 oh Tenaga akhli @ Rp. 152,300.00 = Rp. 456,900.00
0.1000 oh Pengawas Akhli @ Rp. 155,000.00 = Rp. 15,500.00
Biaya pengujian dan peralatan = Rp. 172,500.00
Jumlah = Rp. 2,949,760.00

Untuk tiap 1,00 m 1/ 30 x Rp. 2,949,760.00 = Rp. 98,325.33


Dibulatkan = Rp. 98,300.00 /m'

C. PEKERJAAN PENYELESAIAN

1. Demobilisasi = Rp. 11,000,000.00 /ls

2. Pembersihan lapangan = Rp. 8,250,000.00 /ls

3. Dokumentasi dan gambar akhir = Rp. 10,010,000.00 /ls

Bandar Lampung, 7 Maret 2011


Satkerbangka Lampung,
Ka Satker,

WICAKSONO INDARTO, ST
NIP.19800115 200604 1 002