REKAPITULASI RENCANA ANGGARAN BIAYA

DESA SOPA KECAMATAN KINDANG


TAHUN ANGGARAN 2017

NO. RAB : 02
BIDANG : PELAKSANAAN PEMBANGUNAN DESA
KEGIATAN : PEMBANGUNAN/REHABILITASI JALAN RABAT BETON
LOKASI : DUSUN CAMBANG BOKO DESA SOPA
UKURAN : 275m x 3,50m x 0,15m
WAKTU PELAKSANAAN : 22 HARI KERJA
PERINCIAN PENDANAAN :
HARGA SATUAN JUMLAH
KODE REKENING URAIAN VOLUME
(Rp.) (Rp.)
1 2 3 4 5
2 BELANJA
2 2 Bidang Pelaksanaan Pembangunan Desa
2 2 3 Pembangunan Jalan Rabat Beton 139,589,500
2 2 3 2 Belanja Barang dan Jasa 21,164,000
Belanja Upah Kerja 18,980,000
- Upah Pekerja 238.00 HOK 65,000 15,470,000
- Upah Tukang 39.00 HOK 90,000 3,510,000

Belanja Alat Kerja 2,184,000

- Papan Mall 0.5 m2 2,000,000 1,000,000

- Paku 6 Kg 14,000 84,000

- Sekop Pasir 3 Buah 55,000 165,000

- Gerobak 2 Buah 400,000 800,000

- Ember 9 Buah 15,000 135,000

2 2 3 3 Belanja Modal 118,425,500


- Semen Tonasa 50 Kg 941.33 Zak 65,000 61,186,125
- Pasir 77.96 m3
200,000 15,592,500
- Batu Pecah / Cipping 109.72 m3 375,000 41,146,875

- Prasasti 1 Buah 500,000 500,000

JUMLAH 139,589,500

Terbilang : " Seratus Tiga Puluh Sembilan Juta Lima Ratus Delapan Puluh Sembilan Ribu Lima Ratus Rupiah Rupiah "

Sopa, …………………………. 2017


DISETUJUI / MENGESAHKAN : PELAKSANA KEGIATAN :
KEPALA DESA

SALEH, SKM. H. AMBO


1
RENCANA ANGGARAN BIAYA (RAB)

DESA : Sopa, Dusun Cambang Boko No.RAB : 01


KECAMATAN : Kindang Bidang : Pembangunan Desa
KABUPATEN : Bulukumba Kegiatan : Jalan Rabat Beton
PROVINSI : Sulawesi Selatan Volume : 275m x 3,50m x 0,15m = 144.38 m3
Sumber Dana : Dana Desa Tahap I

URAIAN Volume Satuan Harga Satuan (Rp) Jumlah Total (Rp)

a b c d e=bxd Semen Pasir Batu Pecah Papan Mal Paku Sekop Gerobak Ember Pekerja Tukang Batu Kepala Tukang Jumlah
1. BAHAN
1.1 Portland Semen 50 Kg 941.33 Zak 65,000.00 61,186,125.00 941.33
1.2 Pasir 77.96 m3 200,000.00 15,592,500.00 77.96
1.3 Batu Pecah (Cipping) 109.73 m3 375,000.00 41,146,875.00 109.73
Sub Total 1) 117,925,500.00
2. ALAT
2.1. Papan Mall 0.5 m2 2,000,000.00 1,000,000.00 0.5
2.2. Paku 6 Kg 14,000.00 84,000.00 6
2.3. Sekop Pasir 3 Buah 55,000.00 165,000.00 3
2.4. Gerobak 2 Buah 400,000.00 800,000.00 2
2.5. Ember 10 Buah 15,000.00 150,000.00
Sub Total 2) 2,199,000.00
3. UPAH
3.1 Pekerja 238.22 HOK 65,000.00 15,484,218.75 238.22
3.2 Tukang Batu 39.70 HOK 90,000.00 3,573,281.25 39.70
Sub Total 3 ) 19,057,500.00 65,000 200,000 375,000 2,000,000 14,000 55,000 400,000 #REF! 65,000 90,000 #REF!
4. LAINNYA
4.1. Prasasti 1 Buah 500,000.00 500,000.00
Sub Total 4 ) 500,000.00
JUMLAH RAB 139,682,000.00 61,186,125 15,592,500 41,146,875 1,000,000 84,000 165,000 800,000 #REF! 15,484,219 3,573,281 #REF! #REF!
Terbilang : " Seratus Lima Puluh Dua Juta Dua Puluh Empat Ribu Rupiah "

Mengetahui : Sopa, 15 Maret 2017


KEPALA DESA SOPA PELAKSANA KEGIATAN :

SALEH, SKM. H. AMBO

2
PEKERJAAN : PEMBANGUNAN JALAN RABAT BETON
VOLUME : 275 m x 3,50 m x 0,15 m = 144.38 m3
LOKASI : DUSUN CAMBANG BOKO DESA SOPA KEC. KINDANG KAB. BULUKUMBA
SUMBER DANA : BDD DESA SOPA TAHUN 2017

ANALISA HARGA SATUAN PEKERJAAN

1. Pekerjaan Rabat Beton tiap m3 campuran 1:2:3 (K.175)

HARGA SATUAN
NO. URAIAN SAT KOEFISIEN JUMLAH (Rp.)
(Rp.)

A TENAGA
1 Pekerja OH 1.65 65,000 107,250 144.375 238.22 15,484,219
2 Tukang Batu OH 0.28 90,000 24,750 144.375 39.70 3,573,281
3 Mandor OH 0.08 100,000 8,000 144.375 11.55 1,155,000
JUMLAH TENAGA KERJA 140,000 20,212,500
B BAHAN
1 Portland Semen Zak 6.52 65,000 423,800 144.375 941.33 61,186,125
2 Pasir Pasang m3 0.54 200,000 108,000 144.375 77.96 15,592,500
2 Batu Pecah (Cipping) m3 0.76 375,000 285,000 144.375 109.73 41,146,875
JUMLAH HARGA BAHAN 816,800 117,925,500
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 956,800 - 138,138,000
PEKERJAAN : PEMBANGUNAN JALAN RABAT BETON
VOLUME : 275 m x 3,50 m x 0,15 m = 144.38 m3
LOKASI : DUSUN CAMBANG BOKO DESA SOPA KEC. KINDANG KAB. BULUKUMBA 270
SUMBER DANA : BDD DESA SOPA TAHUN 2017

DAFTAR HARGA SATUAN BAHAN DAN UPAH

HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

A BAHAN :
1 Semen Tonasa 50 Kg Zak 65,000
2 Pasir Pasang m3 200,000 800,000
3 Batu Pecah (Split/Cipping) m3 375,000 1,875,000
4 Paku Kg 14,000
5 Papan Mall m3 2,000,000

B UPAH :
1 Pekerja Org/Hari 65,000
2 Tukang Batu Org/Hari 90,000
3 Kepala Tukang Org/Hari 100,000
4 Mandor Org/Hari 100,000