PROJECT
PROPOSED
: PROPOSED
BUNGALOW2-STOREY
RESIDENCE
RESIDENCE
LOCATION : VILLA JULITA CSFP
OWNER : MR. AND MRS RAMOS
BACK FILLING
F-1 (16-Sets) 15.24 cu.m. 175.00 2,667.70
F-2 (6-Sets) 3.61 cu.m. 175.00 631.75
WF-1 - cu.m. 175.00 -
REINFORCING BARS
A) Footings, Column-Tie-Beam, Wall Footing & Stair (See Cutting List)
F-1 (16-Sets) (12pcs-12Øx6.00m) 64.10 kgs 39.00 2,499.90 999.96
F-2 (6-Sets) (4pcs-12Øx6.00m) 21.36 kgs 39.00 833.04 333.22
WF1: (17pcs-10Øx6.00m) 63.24 kgs 39.00 2,466.36 986.54
CTB (80pcs-12Øx9.00m; 67pcs-10Øx7.5m) 950.91 kgs 39.00 37,085.49 14,834.20
STAIR 2, Footing, Slab, Riser, Thread: (4pcs-16Øx12.00m; 1.5pcs-12Øx12.00m; 5pcs-10Øx12.00m) - kgs 39.00 - -
B) Columns / Stiffener Columns (SC-1) / Lintel Beams Door, Window & Opening
Columns
(C1) : (16-Sets) (48pcs-12Øx9m; 48pcs-10Øx6m) 563.04 kgs 39.00 21,958.56 8,783.42
(C2) : (6-Sets) (12pcs-12Øx9m; 18pcs-10Øx6.00m) 163.08 kgs 39.00 6,360.12 2,544.05
Window
W1 (1-Set) : (3pcs-12Øx7.50m; 2pcs-10Øx6.00m) 27.50 kgs 39.00 1,072.50 429.00
W2 (2-Sets) : (4pcs-12Øx6.00m; 2pcs-10Øx7.50m) 30.66 kgs 39.00 1,195.74 478.30
W3 (2-Sets) : (4pcs-12Øx6.00m; 2pcs-10Øx7.50m) 30.66 kgs 39.00 1,195.74 478.30
W4a (3-Sets) : (8pcs-12Øx7.5m; 6pcs-10Øx6.00m) 81.18 kgs 39.00 3,166.02 1,266.41
W4b (1-Set) : (1pcs-12Øx7.5m; 1pcs-10Øx6.00m) 10.38 kgs 39.00 404.82 161.93
W5 (2-Sets) : (2pc-12Øx7.5m; 1pc-10Øx7.5m) 17.97 kgs 39.00 700.83 280.33
W6 (1-Set) : (2pcs-12Øx7.50m; 1pc-10Øx7.50m) 17.97 kgs 39.00 700.83 280.33
W7 (1-Set) : (3pcs-12Øx7.50m; 2pcs-10Øx6.00m) 27.24 kgs 39.00 1,062.36 424.94
Opening
-
C) Rear Roof Beams -
a) Roof Beams -
(RB-1): (47pcs-12Øx7.5m; 54pcs-10Øx6.00m) 513.90 kgs 39.00 20,042.10 8,016.84
(RB-2): (12pcs-12Øx7.5m; 18pcs-10Øx6.00m) 146.88 kgs 39.00 5,728.32 2,291.33
E) CHB Reinforcing-bars
(Vetical & Horizontal Bars) (187pcs-10Øx12m) ####### kgs 39.00 53,909.86 21,563.94
FORM WORKS
A) Footings, Column-Tie-Beam, Wall Footing & Stair
F-1 (16-Sets) 10.24 sq.m. 400.00 4,096.00 1,638.40
F-2 (6-Sets) 7.68 sq.m. 400.00 3,072.00 1,228.80
WF1 2.52 sq.m. 400.00 1,008.00 403.20
CTB 55.63 sq.m. 400.00 22,250.00 8,900.00
STAIR 2, Footing, Slab, Riser, Thread sq.m. 400.00 - -
B) Columns / Stiffener Columns (SC-1) / Lintel Beam: Door, Window & Opening
a) Columns
(C1) : (16-Sets) 60.80 sq.m. 400.00 24,320.00 9,728.00
(C2) : (6-Sets) 20.40 sq.m. 400.00 8,160.00 3,264.00
C) Roof Beams
b) Roof Beams
(RB-1) 26.04 sq.m. 400.00 10,416.00 4,166.40
(RB-2) 16.55 sq.m. 400.00 6,619.00 2,647.60
D) Slab-on-fill / Suspended Slab / Canopy
Slab-on-Grade 8.56 sq.m. 400.00 3,424.00 1,369.60
- -
CONCRETE WORKS (3,000psi @ 28days) w/ 3% Waste - -
A) Footings, Column-Tie-Beam, Wall Footing & Stair - -
F-1 (16-Sets) 2.05 cu.m. 3,050.00 6,252.50 2,501.00
F-2 (6-Sets) 1.60 cu.m. 3,050.00 4,880.00 1,952.00
WF1 6.40 cu.m. 3,050.00 19,520.00 7,808.00
STAIR 1, Slab, Riser, Thread:
STAIR 2, Footing, Slab, Riser, Thread
B) Columns / Stiffener Columns (SC-1) / Lintel Beams Door, Window & Opening
Columns
(C1) : (16-Sets) 3.36 cu.m. 3,050.00 10,248.00 4,099.20
(C2) : (6-Sets) 1.05 cu.m. 3,050.00 3,202.50 1,281.00
B. FLOORING
GROUND FLOOR
a) Ground Floor. 60 x 60 cm Simple Tiles Design 86.17 sq.m. 500.00 43,085.00 17,234.00
b) Toilet. 60 x 60 cm Tiles 44.46 sq.m. 450.00 20,005.65 8,002.26
B. WALLS
INTERIOR WALLS
a) GROUND FLOOR 115.39 sq.m. 220.00 25,385.80 17,308.50
b) Gray Scale Skim Coat Light Color GROUND FLOOR 115.39 sq.m. 350.00 40,386.50 17,308.50
EXTERIOR WALLS
a) FRONT ELEVATION
Plain Cement Painted Finish 36.80 sq.m. 220.00 8,096.00 5,520.00
b) LEFT SIDE ELEVATION
Plain Cement Painted Finish 33.35 sq.m. 220.00 7,337.00 5,002.50
c) RIGHT SIDE ELEVATION
Plain Cement Painted Finish 29.00 sq.m. 220.00 6,380.00 4,350.00
d) REAR ELEVATION
Plain Cement Painted Finish 46.00 sq.m. 220.00 10,120.00 6,900.00
c) Glass Railing
10. Glass Railing 1/2" Thk. Clear Glass (7.69 X 1.10m) (3rd Floor)
ROOFING WORKS
Trusses
49pcs - 50 X 50 X 5mm Angle Bars ####### kgs 50.00 55,419.00 16,625.70
C-Purlins LC 50x100x4mm Thk. 35.00 pcs 595.00 20,825.00 6,247.50
Sag Rods; 12mmØ plain round bars (5pcs-12mm dia. X 6.00m) - kgs 39.00 - -
Roofing; Rib-Type 0.50mm Thk. Tek Screw, Sealant / Vulcaseal, Insulation 144.65 sq.m. 450.00 65,092.50 19,527.75
Gutter & Flushing ; 0.50 mm Thk. 50.38 l.m. 245.00 12,342.61 3,702.78
Painting : Angle Bar, C-Purlin, Sag Rod, Cross Bracing
Epoxy Paint w/ Catalyst: 2 Coats 8.00 gals 645.00 5,160.00 1,548.00
Epoxy Reducer 4.00 gals 470.00 1,880.00 564.00
Roller Brush 3.00 pcs 165.00 495.00 148.50
3" & 2" Paint Brush 4.00 pcs 110.00 440.00 132.00
CONSUMMABLES
Tie-Wire Gage #16 4.00 roll/s 1,750.00 7,000.00
Common Nail Wire 2",3" & 4" 3.00 boxes 1,250.00 3,750.00
Welding Rods (20 kgs/ Box) 6.00 boxes 3,400.00 20,400.00
14" Cutting Wheel 8.00 pcs 650.00 5,200.00
4" Grinding Wheel 4.00 pcs 100.00 400.00
Acetylene 1.00 cyl. 830.00 830.00
Oxygen 2.00 cyl. 380.00 760.00
EQUIPMENTS
Steel & Wood Scaffolding Erection & Dismantling 1.00 Lot 30,000.00
Backhoe - Lot 84,000.00 -
Concrete Pump (Rental) - set/s 20,000.00 -
SEPTIC TANK
Excavation 10.71 cu.m. 350.00 3,748.50
Backfill cu.m. 175.00
Volume of Concrete 1.43 cu.m. 3,050.00 4,361.50 1,308.45
Formworks 6.56 sq.m. 400.00 2,624.00 1,049.60
Reinforcing Bars: (12pcs-12Øx12.00m; 10pcs-10Øx12.00m) 201.79 kgs 39.00 7,869.89 1,967.47
Chb Laying Area 19.76 sq.m.
5" Chb Laying, 350psi w/ 3% Wastage 247.00 pc/s 26.00 6,422.00 3,161.60
Cement 24.26 bag/s 220.00 5,336.19
Sand 1.31 cu.m. 670.00 877.10
Plastering Works: Area 25.58 sq.m. 4,092.80
Cement 8.90 bag/s 220.00 1,958.40
Sand 0.48 cu.m. 670.00 318.78
Waterproofing 8.85 sq.m. 500.00 4,425.00
CATCH BASIN (6-Sets)
Excavation 1.88 cu.m. 350.00 656.25
Volume of Concrete 0.75 cu.m. 3,050.00 2,287.50 686.25
Formworks 15.00 sq.m. 550.00 8,250.00 3,300.00
Reinforcing Bars: (17pcs-10Øx12.00m) 125.66 kgs 39.00 4,900.90 1,225.22
Chb Laying Area 15.00 sq.m.
4" Chb Laying, 350psi w/ 3% Wastage 188.00 pc/s 12.00 2,256.00 2,400.00
Cement 18.46 bag/s 220.00 4,061.55
Sand 1.00 cu.m. 670.00 667.59
Plastering Works: Area 15.00 sq.m. 2,400.00
Cement 1.47 bag/s 220.00 324.06
Sand 0.08 cu.m. 670.00 53.27
Excavation of 2"/3" Pvc Connecting Pipe cu.m. 350.00 -
Backfill of 2"/3" Pvc Connecting Pipe cu.m. 175.00 -
CONTRACTOR SUPPLY
a) MATERIALS COST 1,231,157.25
b) LABOR COST 479,637.12
c) CONTINGENCIES 0
d) SUPERVISION, CONSULTATION, TOOLS & EQUIPMENT, PLUS PROFIT 0
PREPARED BY: