PERHITUNGAN KUANTITAS REALISASI PEKERJAAN

DIVISI 1. UMUM

1.2 Mobilisasi

V = 1 Ls

DIVISI 3. PEKERJAAN TANAH

3.3(a) Penyiapan Badan Jalan Pada Galian Biasa atau Perk. Lama Rusak

V = 22,621.20 M2

DIVISI 5. PERKERASAN BERBUTIR

5.1(1) Lapisan Pondasi Agregat Kelas A

V = 4,524 x 0.15
= 678.64 M3

DIVISI 6. PERKERASAN ASPAL

6.1(1) Lapis resap Pengikat

V = 22,621 x 0.60
= 13,572.72 Ltr

6.3(4) Asphalt Treated Base ( ATB )

V = 22,621 x 0.05
= 1,131.06 M3

V = 4,524 x 0.05
= 226.21 M3

V = 1,131.06 + 226.21
= 1,357.27 M3
BACK UP PERHITUNGAN VOLUME

LUASAN AREA PENGURANGAN JUMLAH LUASAN


NO SECTION
( M2 ) ( M2 ) ( M2 )
1 SC 1 4,708.97 1,187.57 3,521.40

2 SC 2 2,159.51

3 SC 3 1,244.19

4 SC 4 2,227.68

5 SC 5 1,529.51

6 SC 6 2,659.09 131.60 2,527.49

7 SC 7 1,340.50

8 SC 8 2,878.32

9 SC 9 1,380.15

10 SC 10 1,221.93

11 SC 11 844.74

12 SC 12 1,745.77

22,621.20
ITEM PEMBAYARAN NO. : 5.1 (1) Analisa EI-511
JENIS PEKERJAAN : Lps. Pond. Ag. Kls. A, CBR Min 80%
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 8.7 KM
5 Tebal lapis agregat padat t 0.15 M
6 Faktor kembang material (Padat-Lepas) Fk 1.20 -
7 Jam kerja efektif per-hari Tk 7.00 jam
8 Proporsi Campuran : - Agregat Kasar Ak 55.00 % Gradasi harus
- Agregat Halus Ah 45.00 % memenuhi Spec.
II. URUTAN KERJA
1 Wheel Loader mencampur dan memuat Agregat ke
dalam Dump Truck di Base Camp
2 Dump Truck mengangkut Agregat ke lokasi
pekerjaan dan dihampar dengan Motor Grader
3 Hamparan Agregat dibasahi dengan Water Tank
Truck sebelum dipadatkan dengan Tandem
Roller dan Pneumatic Tire Roller
4 Selama pemadatan, sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan Alat Bantu
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
- Agregat Kasar = Ak x 1 M3 x Fk M03 0.6600 M3
- Agregat Halus = Ah x 1 M3 x Fk M04 0.5400 M3

2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu Siklus : Ts1
- Mencampur T1 1.50 menit
- Memuat dan lain-lain T2 0.50 menit
Ts1 2.00 menit

Kap. Prod. / jam = V x Fb x Fa x 60 Q1 28.01 M3


Fk x Ts1
Koefisien Alat / M3 = 1 : Q1 (E15) 0.0357 jam

2.b. DUMP TRUCK (E09)


Kapasitas bak V 6.00 M3
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 45.00 KM/jam
Kecepatan rata-rata kosong v2 60.00 KM/jam
Waktu Siklus : - Waktu memuat = V : Q1 x 60 T1 12.85 menit
- Waktu tempuh isi = (L : v1) x 60 menit T2 11.63 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T3 8.73 menit
- Dump dan lain-lain T4 3.00 menit
Ts2 36.21 menit

Berlanjut ke hal. berikut

File : 441670607.xls
Analisa EI-511

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK : Dinas Kimprasda Kabupaten Tanah Laut


No. PAKET KONTRAK :
NAMA PAKET
PROP / KAB / KODYA : Propinsi Kalimantan Selatan / Tanah Laut
ITEM PEMBAYARAN NO. : 5.1 (1) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Lps. Pond. Ag. Kls. A, CBR Min 80% TOTAL HARGA : 0.00
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 0.2499 5,000.00 1,249.44


2. Mandor (L03) jam 0.0357 7,142.86 254.99

JUMLAH HARGA TENAGA 1,504.43

B. BAHAN

1. Agregat Kasar (M03) M3 0.6600 200,999.00 132,659.34


2. Agregat Halus (M04) M3 0.5400 181,085.15 97,785.98

JUMLAH HARGA BAHAN 230,445.32

C. PERALATAN
1. Wheel Loader (E15) jam 0.0357 203,578.57 7,267.42
2. Dump Truck (E09) jam 0.1454 179,313.08 26,075.82
3. Motor Grader (E13) jam 0.0117 208,970.90 2,447.78
4. Vibratory Roller (E19) jam 0.0178 116,587.26 2,080.99
5. P. Tyre Roller (E18) jam 0.0043 111,676.35 478.40
6. Water Tanker (E23) jam 0.0211 140,668.04 2,965.89
7. Alat Bantu Ls 1.0000 75.00 75.00

JUMLAH HARGA PERALATAN 41,391.30

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 273,341.05


E. OVERHEAD & PROFIT 0.0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 273,341.05
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 441670607.xls
ITEM PEMBAYARAN NO. : 5.1 (1) Analisa EI-511
JENIS PEKERJAAN : Lps. Pond. Ag. Kls. A, CBR Min 80%
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

Kap. Prod. / jam = V x Fa x 60 Q2 6.88 M3


Fk x Ts2
Koefisien Alat / M3 = 1 : Q2 (E09) 0.1454 jam

2.c. MOTOR GRADER (E13)


Panjang hamparan Lh 50.00 M
Lebar efektif kerja blade b 2.40 M
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata alat v 4.00 KM/jam
Jumlah lintasan n 6.00 lintasan 3 x pp
Waktu Siklus : Ts3
- Perataan 1 lintasan = Lh : (v x 1000) x 60 T1 0.75 menit
- Lain-lain T2 1.00 menit
Ts3 1.75 menit

Kap. Prod. / jam = Lh x b x t x Fa x 60 Q3 85.37 M3


n x Ts3
Koefisien Alat / M3 = 1 : Q3 (E13) 0.0117 jam

2.d. VIBRATORY ROLLER (E19)


Kecepatan rata-rata alat v 3.00 KM/jam
Lebar efektif pemadatan b 1.20 M
Jumlah lintasan n 8.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap. Prod. / jam = (v x 1000) x b x t x Fa Q4 56.03 M3


n
Koefisien Alat / M3 = 1 : Q4 (E19) 0.0178 jam

2.e. PNEUMATIC TIRE ROLLER (E18)


Kecepatan rata-rata alat v 5.00 KM/jam
Lebar efektif pemadatan b 1.50 M
Jumlah lintasan n 4.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap. Prod. / jam = (v x 1000) x b x t x Fa Q5 233.44 M3


n
Koefisien Alat / M3 = 1 : Q5 (E18) 0.0043 jam

2.f. WATER TANK TRUCK (E23)


Volume tanki air V 4.00 M3
Kebutuhan air / M3 agregat padat Wc 0.07 M3
Pengisian tanki / jam n 1.00 kali
Faktor Efisiensi alat Fa 0.83 -

Kap. Prod. / jam = V x n x Fa Q6 47.43 M3


Wc
Koefisien Alat / M3 = 1 : Q6 (E23) 0.0211 jam

Berlanjut ke hal. berikut

File : 441670607.xls
ITEM PEMBAYARAN NO. : 5.1 (1) Analisa EI-511
JENIS PEKERJAAN : Lps. Pond. Ag. Kls. A, CBR Min 80%
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

2.g. ALAT BANTU Lump Sum


Diperlukan :
- Kereta dorong = 2 buah.
- Sekop = 3 buah.
- Garpu = 2 buah.

3. TENAGA
Produksi menentukan : WHEEL LOADER Q1 28.01 M3/jam
Produksi agregat / hari = Tk x Q1 Qt 196.09 M3
Kebutuhan tenaga :
- Pekerja P 7.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.2499 jam
- Mandor = (Tk x M) : Qt (L03) 0.0357 jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 273,341.05 / M3.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3

File : 441670607.xls
ITEM PEMBAYARAN NO. : 5.1 (2) Analisa EI-512
JENIS PEKERJAAN : Lps. Pond. Ag. Kls. B, CBR Min 35%
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 8.7 KM
5 Tebal lapis agregat padat t 0.15 M
6 Faktor kembang material (Padat-Lepas) Fk 1.20 -
7 Jam kerja efektif per-hari Tk 7.00 jam
8 Proporsi Campuran : - Agregat Kasar Ak 35.00 % Gradasi harus
- Agregat Halus Ah 20.00 % memenuhi
- Sirtu St 45.00 % Spesifikasi
II. URUTAN KERJA
1 Wheel Loader mencampur dan memuat Agregat ke
dalam Dump Truck di Base Camp
2 Dump Truck mengangkut Agregat ke lokasi
pekerjaan dan dihampar dengan Motor Grader
3 Hamparan Agregat dibasahi dengan Water Tank
Truck sebelum dipadatkan dengan Tandem
Roller dan Pneumatic Tire Roller
4 Selama pemadatan, sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan Alat Bantu
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
1. BAHAN
- Agregat Kasar = Ak x 1 M3 x Fk M03 0.4200 M3
- Agregat Halus = Ah x 1 M3 x Fk M04 0.2400 M3
- Sirtu = St x 1 M3 x Fk M16 0.5400 M3
2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu Siklus : Ts1
- Mencampur T1 1.50 menit
- Memuat dan lain-lain T2 0.50 menit
Ts1 2.00 menit

Kap. Prod. / jam = V x Fb x Fa x 60 Q1 28.01 M3


Fk x Ts1
Koefisien Alat / M3 = 1 : Q1 (E15) 0.0357 jam

2.b. DUMP TRUCK (E09)


Kapasitas bak V 6.00 M3
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 45.00 KM/jam
Kecepatan rata-rata kosong v2 60.00 KM/jam
Waktu Siklus : - Waktu memuat = V : Q1 x 60 T1 12.85 menit
- Waktu tempuh isi = (L : v1) x 60 menit T2 11.63 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T3 8.73 menit
- Dump dan lain-lain T4 3.00 menit
Ts2 36.21 menit

Berlanjut ke hal. berikut

File : 441670607.xls
Analisa EI-512

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK : Dinas Kimprasda Kabupaten Tanah Laut


No. PAKET KONTRAK :
NAMA PAKET 0
PROP / KAB / KODYA : Propinsi Kalimantan Selatan / Tanah Laut
ITEM PEMBAYARAN NO. : 5.1 (2) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Lps. Pond. Ag. Kls. B, CBR Min 35% TOTAL HARGA : 0.00
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 0.2499 5,000.00 1,249.44


2. Mandor (L03) jam 0.0357 7,142.86 254.99

JUMLAH HARGA TENAGA 1,504.43

B. BAHAN

1. Agregat Kasar (M03) M3 0.4200 200,999.00 84,419.58


2. Agregat Halus (M04) M3 0.2400 181,085.15 43,460.44
3. Sirtu (M16) M3 0.5400 79,500.00 42,930.00

JUMLAH HARGA BAHAN 170,810.01

C. PERALATAN
1. Wheel Loader (E15) jam 0.0357 203,578.57 7,267.42
2. Dump Truck (E09) jam 0.1454 179,313.08 26,075.82
3. Motor Grader (E13) jam 0.0117 208,970.90 2,447.78
4. Vibratory Roller (E19) jam 0.0178 116,587.26 2,080.99
5. P. Tyre Roller (E18) jam 0.0043 111,676.35 478.40
6. Water Tanker (E23) jam 0.0211 140,668.04 2,965.89
7. Alat Bantu Ls 1.0000 75.00 75.00

JUMLAH HARGA PERALATAN 41,391.30

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 213,705.75


E. OVERHEAD & PROFIT 0.0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 213,705.75
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 441670607.xls
ITEM PEMBAYARAN NO. : 5.1 (2) Analisa EI-512
JENIS PEKERJAAN : Lps. Pond. Ag. Kls. B, CBR Min 35%
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

Kap. Prod. / jam = V x Fa x 60 Q2 6.88 M3


Fk x Ts2
Koefisien Alat / M3 = 1 : Q2 - 0.1454 jam

2.c. MOTOR GRADER (E13)


Panjang hamparan Lh 50.00 M
Lebar efektif kerja blade b 2.40 M
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata alat v 4.00 KM/jam
Jumlah lintasan n 6.00 lintasan 3 x pp
Waktu Siklus : Ts3
- Perataan 1 lintasan = Lh : (v x 1000) x 60 T1 0.75 menit
- Lain-lain T2 1.00 menit
Ts3 1.75 menit

Kap. Prod. / jam = Lh x b x t x Fa x 60 Q3 85.37 M3


n x Ts3
Koefisien Alat / M3 = 1 : Q3 (E13) 0.0117 jam

2.d. VIBRATORY ROLLER (E19)


Kecepatan rata-rata alat v 3.00 KM/jam
Lebar efektif pemadatan b 1.20 M
Jumlah lintasan n 8.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap. Prod. / jam = (v x 1000) x b x t x Fa Q4 56.03 M3


n
Koefisien Alat / M3 = 1 : Q4 (E19) 0.0178 jam

2.e. PNEUMATIC TIRE ROLLER (E18)


Kecepatan rata-rata alat v 5.00 KM/jam
Lebar efektif pemadatan b 1.50 M
Jumlah lintasan n 4.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap. Prod. / jam = (v x 1000) x b x t x Fa Q5 233.44 M3


n
Koefisien Alat / M3 = 1 : Q5 (E18) 0.0043 jam

2.f. WATER TANK TRUCK (E23)


Volume tanki air V 4.00 M3
Kebutuhan air / M3 agregat padat Wc 0.07 M3
Pengisian tanki / jam n 1.00 kali
Faktor Efisiensi alat Fa 0.83 -

Kap. Prod. / jam = V x n x Fa Q6 47.43 M3


Wc
Koefisien Alat / M3 = 1 : Q6 (E23) 0.0211 jam

Berlanjut ke hal. berikut

File : 441670607.xls
ITEM PEMBAYARAN NO. : 5.1 (2) Analisa EI-512
JENIS PEKERJAAN : Lps. Pond. Ag. Kls. B, CBR Min 35%
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

2.g. ALAT BANTU Lump Sum


Diperlukan :
- Kereta dorong = 2 buah.
- Sekop = 3 buah.
- Garpu = 2 buah.

3. TENAGA
Produksi menentukan : WHEEL LOADER Q1 28.01 M3/jam
Produksi agregat / hari = Tk x Q1 Qt 196.09 M3
Kebutuhan tenaga :
- Pekerja P 7.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt - 0.2499 jam
- Mandor = (Tk x M) : Qt - 0.0357 jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 213,705.75 / M3.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3

File : 441670607.xls
ITEM PEMBAYARAN NO. : 5.2 (1) Analisa EI-521
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas C
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 8.7 KM
5 Tebal lapis Agregat padat t 0.15 M
6 Faktor kembang material (Padat-Lepas) Fk 1.35 -
7 Jam kerja efektif per-hari Tk 7.00 Jam
Proporsi Campuran : - Agregat Kasar Ak 38.00 % Gradasi harus
- Pasir Ps 47.00 % memenuhi
- Tanah Tn 15.00 % Spesifikasi

II. URUTAN KERJA


1 Wheel Loader memuat Agregat ke dalam Dump
Tuck di Base Camp
2 Dump Truck mengangkut Agregat ke lokasi
pekerjaandan dihampar dengan Motor Grader
3 Hamparan Agregat dibasahi dengan Water Tank
Truck sebelum dipadatkan dengan Tandem
Roller dan Pneumatic Tire Roller
4 Selama pemadatan sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
- Agregat Kasar = Ak x 1 M3 x Fk M03 0.5130 M3
- Pasir = Ps x 1 M3 x Fk M01 0.6345 M3
- Tanah = Tn x 1 M3 x Fk M08 0.2025 M3
2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.90 - Pemuatan ringan
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Muat T1 0.25 menit
- Lain-lain T2 0.25 menit
Ts1 0.50 menit

Kap. Prod. / jam = V x Fb x Fa x 60 Q1 99.60 M3


Fk x Ts1
Koefisien Alat / M3 = 1 : Q1 (E15) 0.0100 Jam

2.b. DUMP TRUCK (E08)


Kapasitas bak V 4.00 M3
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 45.00 KM / Jam
Kecepatan rata-rata kosong v2 60.00 KM / Jam
Waktu Siklus : - Waktu memuat = V : Q1 x 60 T1 2.41 menit
- Waktu tempuh isi = (L : v1) x 60 menit T2 11.63 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T3 8.73 menit
- Dump dan lain-lain T4 3.00 menit
Ts2 25.77 menit

File : 441670607.xls
Analisa EI-521

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 5.2 (1) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas C TOTAL HARGA : 0.00
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0703 5,000.00 351.41


2. Mandor (L03) Jam 0.0100 7,142.86 71.72

JUMLAH HARGA TENAGA 423.12

B. BAHAN

1. - Agregat Kasar (M03) M3 0.5130 200,999.00 103,112.48


- Pasir (M01) M3 0.6345 67,500.00 42,828.75
- Tanah (M08) M3 0.2025 45,000.00 9,112.50

JUMLAH HARGA BAHAN 155,053.73

C. PERALATAN

1. Wheel Loader (E15) Jam 0.0100 203,578.57 2,043.96


2. Dump Truck (E08) Jam 0.1746 119,331.88 20,839.21
3. Motor Grader (E13) Jam 0.0117 208,970.90 2,447.78
4. Vibratory Roller (E19) Jam 0.0214 116,587.26 2,497.18
5. P. Tyre Roller (E18) Jam 0.0043 111,676.35 478.40
6. Water Tanker (E23) Jam 0.0211 140,668.04 2,965.89
7. Alat Bantu Ls 1.0000 40.00 40.00

JUMLAH HARGA PERALATAN 31,312.43

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 186,789.28


E. OVERHEAD & PROFIT 0.0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 186,789.28
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 441670607.xls
Berlanjut ke hal. berikut
ITEM PEMBAYARAN NO. : 5.2 (1) Analisa EI-521
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas C
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

Kap. Prod./jam = V x Fa x 60 Q2 5.73 M3


Fk x Ts2
Koefisien Alat / M3 = 1 : Q2 (E08) 0.1746 Jam

2.c. MOTOR GRADER (E13)


Panjang hamparan Lh 50.00 M
Lebar efektif kerja blade b 2.40 M
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata alat v 4.00 KM / Jam
Jumlah lintasan n 6.00 lintasan 3 x pp
Waktu Siklus Ts3
- Perataan 1 lintasan = (Lh x 60) : (v x 1000) T1 0.75 menit
- Lain-lain T2 1.00 menit
Ts3 1.75 menit

Kap.Prod. / jam = Lh x b x t x Fa x 60 Q3 85.37 M3


n x Ts3
Koefisien Alat / M3 = 1 : Q3 (E13) 0.0117 Jam

2.d. VIBRATORY ROLLER (E19)


Kecepatan rata-rata v 2.50 KM / Jam
Lebar efektif pemadatan b 1.20 M
Jumlah lintasan n 8.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod. / jam = (v x 1000) x b x t x Fa Q4 46.69 M3


n
Koefisien Alat / M3 = 1 : Q4 (E19) 0.0214 Jam

2.e. PNEUMATIC TIRE ROLLER (E18)


Kecepatan rata-rata alat v 5.00 KM / Jam
Lebar efektif pemadatan b 1.50 M
Jumlah lintasan n 4.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod. / jam = (v x 1000) x b x t x Fa Q5 233.44 M3


n
Koefisien Alat / M3 = 1 : Q5 (E18) 0.0043 Jam

2.f. WATERTANK TRUCK (E23)


Volume tangki air V 4.00 M3
Kebutuhan air / M3 agregat padat Wc 0.07 M3
Pengisian tangki / jam n 1.00 kali
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod. / jam = V x n x Fa Q6 47.43 M3


Wc
Koefisien Alat / M3 = 1 : Q6 (E23) 0.0211 Jam

File : 441670607.xls
Berlanjut ke hal. berikut
ITEM PEMBAYARAN NO. : 5.2 (1) Analisa EI-521
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas C
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

2.g. ALAT BANTU


diperlukan : Lump Sum
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah

3. TENAGA
Produksi menentukan : WHEEL LOADER Q1 99.60 M3 / Jam
Produksi Agregat / hari = Tk x Q1 Qt 697.20 M3
Kebutuhan tenaga :
- Pekerja P 7.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0703 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0100 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 186,789.28 / M3.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3

File : 441670607.xls
Analisa EI-522

File : 441670607.xls
ITEM PEMBAYARAN NO. : 5.2 (2) Analisa EI-522
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas C2
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 8.73 KM
5 Tebal lapis Agregat padat t 0.15 M
6 Faktor kembang material (Padat-Lepas) Fk 1.20 -
7 Jam kerja efektif per-hari Tk 7.00 Jam

II. URUTAN KERJA


1 Wheel Loader memuat Agregat ke dalam Dump
Tuck di Base Camp
2 Dump Truck mengangkut Agregat ke lokasi
pekerjaandan dihampar dengan Motor Grader
3 Hamparaan Agregat dibasahi dengan Water Tank
Truck sebelum dipadatkan dengan Tandem
Roller dan Pneumatic Tire Roller
4 Selama pemadatan sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Material Agregat Kelas C2 hasil produksi di Base Camp
Setiap 1 M3 Agregat padat diperlukan : 1 x Fk (M29) 1.20 M3 Agregat lepas

2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.90 - Pemuatan ringan
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Muat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit

Kap. Prod. / jam = V x Fb x Fa x 60 Q1 56.03 M3


Fk x Ts1
Koefisien Alat / M3 = 1 : Q1 (E15) 0.0178 Jam

2.b. DUMP TRUCK (E08)


Kapasitas bak V 4.00 M3
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 45.00 KM / Jam
Kecepatan rata-rata kosong v2 60.00 KM / Jam
Waktu Siklus Ts2
- Waktu tempuh isi = (L : v1) x 60 menit T1 11.63 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T2 8.73 menit
- Lain-lain T3 5.00 menit

File : 441670607.xls
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 5.2 (2) PERKIRAAN VOL. PEK. : #REF!
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas C2 TOTAL HARGA : #REF!
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : #REF!

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.1249 5,000.00 624.72


2. Mandor (L03) Jam 0.0178 7,142.86 127.49

JUMLAH HARGA TENAGA 752.22

B. BAHAN

1. Agregat Kelas C2 (M29) M3 1.2000 - #VALUE!

JUMLAH HARGA BAHAN #VALUE!

C. PERALATAN

1 Wheel Loader (E15) Jam 0.0178 203,578.57 3,633.71


2 Dump Truck (E08) Jam 0.1528 119,331.88 18,229.26
3 Motor Grader (E13) Jam 0.0117 208,970.90 2,447.78
4 Vibratory Roller (E19) Jam 0.0214 116,587.26 2,497.18
5 P. Tyre Roller (E18) Jam 0.0043 111,676.35 478.40
6 Water Tanker (E23) Jam 0.0211 140,668.04 2,965.89
7 Alat Bantu Ls 1.0000 800.00 800.00

JUMLAH HARGA PERALATAN 31,052.23

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) #VALUE!


E. OVERHEAD & PROFIT 0.0 % x D #VALUE!
F. HARGA SATUAN PEKERJAAN ( D + E ) #VALUE!
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 441670607.xls
Ts2 25.36 menit

Berlanjut ke hal. berikut


ITEM PEMBAYARAN NO. : 5.2 (2) Analisa EI-522
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas C2
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

Kap. Prod./jam = V x Fa x 60 Q2 6.55 M3


Fk x Ts2
Koefisien Alat / M3 = 1 : Q2 (E08) 0.1528 Jam

2.c. MOTOR GRADER (E13)


Panjang hamparan Lh 50.00 M
Lebar efektif kerja blade b 2.40 M
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata alat v 4.00 KM / Jam
Jumlah lintasan n 6.00 lintasan 3 x pp
Waktu Siklus Ts3
- Perataan 1 lintasan = (Lh x 60) : (v x 1000) T1 0.75 menit
- Lain-lain T2 1.00 menit
Ts3 1.75 menit

Kap.Prod. / jam = Lh x b x t x Fa x 60 Q3 85.37 M3


n x Ts3
Koefisien Alat / M3 = 1 : Q3 (E13) 0.0117 Jam

2.d. VIBRATORY ROLLER (E19)


Kecepatan rata-rata v 2.50 KM / Jam
Lebar efektif pemadatan b 1.20 M
Jumlah lintasan n 8.00 lintasan 4 x pp
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod. / jam = (v x 1000) x b x t x Fa Q4 46.69 M3


n
Koefisien Alat / M3 = 1 : Q4 (E19) 0.0214 Jam

2.e. PNEUMATIC TIRE ROLLER (E18)


Kecepatan rata-rata alat v 5.00 KM / Jam
Lebar efektif pemadatan b 1.50 M
Jumlah lintasan n 4.00 lintasan 2 x pp
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod. / jam = (v x 1000) x b x t x Fa Q5 233.44 M3


n
Koefisien Alat / M3 = 1 : Q5 (E18) 0.0043 Jam

2.f. WATERTANK TRUCK (E23)


Volume tangki air V 4.00 M3
Kebutuhan air / M3 agregat padat Wc 0.07 M3
Pengisian tangki / jam n 1.00 kali
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod. / jam = V x n x Fa Q6 47.43 M3


Wc
Koefisien Alat / M3 = 1 : Q6 (E23) 0.0211 Jam

File : 441670607.xls
Berlanjut ke hal. berikut
ITEM PEMBAYARAN NO. : 5.2 (2) Analisa EI-522
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas C2
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

2.g. ALAT BANTU


diperlukan : Lump Sum
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah

3. TENAGA
Produksi menentukan : WHEEL LOADER Q1 56.03 M3 / Jam
Produksi Agregat / hari = Tk x Q1 Qt 392.18 M3
Kebutuhan tenaga :
- Pekerja P 7.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.1249 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0178 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. #VALUE! / M3.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : #REF! M3

File : 441670607.xls
ITEM PEMBAYARAN NO. : 5.4(1) Analisa EI-541
JENIS PEKERJAAN : Semen Untuk Pond. Semen Tnh.
SATUAN PEMBAYARAN : TON URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 8.73 Km
5 Jam kerja efektif per-hari Tk 7.00 Jam
6 Semen diangkut dari Base Camp ke lapangan
dengan menggunakan Dump Truck
7 Satu hari dapat diselesaikan hamparan Soil Cement
sepanjang Ls 400.00 M
8 Faktor hilang Material Fh 1.05 -
9 Tebal hamparan t 0.15 M

II. URUTAN KERJA


1 Dump Truck mengangkut semen dari Base Camp
ke lokasi Pekerjaan
2 Semen diatur/disusun di tempat hamparan
soil/tanah oleh tenaga manusia

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
Bahan yang diperlukan / ton = (1 x Fh x 1000) (M12) 1,050.00 Kg

2. ALAT
2.a. DUMP TRUCK (E08)
Kapasitas bak V 6.00 Ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 45.00 Km / Jam
Kecepatan rata-rata kosong v2 60.00 Km / Jam
Waktu siklus Ts1
- Waktu tempuh isi = (L : v1) x 60 T1 11.63 menit
- Waktu tempuh kosong = (L : v2) x 60 T2 8.73 menit
- Waktu mengisi T3 40.00 menit
- Waktu bongkar T4 30.00 menit
- Lain-lain T5 10.00 menit
Ts1 100.36 menit

Kapasitas Prod. / jam = V x Fa x 60 Q1 2.84 Ton/Jam


Fh x Ts1

Koefisien Alat/Ton = 1 / Q1 (E08) 0.3527 Jam

3. TENAGA
Lebar Soil Cement b 6.00 M
Kadar semen : Spesifikasi 5.4.3 (1) = ( 3 - 12 ) % s 7.50 %
Berat jenis tanah Bj 1.60 ton / M3
Setiap hari dengan produksi = {(s : 100) x t x b x Ls} x Bj Qt 43.20 Ton

Kebutuhan tenaga :
- Pekerja P 15.00 orang

File : 441670607.xls
Analisa EI-541

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 5.4(1) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Semen Untuk Pond. Semen Tnh. TOTAL HARGA : 0.00
SATUAN PEMBAYARAN : TON % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 2.4306 5,000.00 12,152.78


2. Mandor (L03) Jam 0.1620 7,142.86 1,157.41

JUMLAH HARGA TENAGA 13,310.19

B. BAHAN
1. Semen (M12) Kg 1,050.0000 940.00 987,000.00

JUMLAH HARGA BAHAN 987,000.00

C. PERALATAN
1. Dump Truck (E08) Jam 0.3527 119,331.88 42,084.16

JUMLAH HARGA PERALATAN 42,084.16

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,042,394.34


E. OVERHEAD & PROFIT 0.0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,042,394.34
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 441670607.xls
- Mandor M 1.00 orang

Berlanjut ke hal. berikut


ITEM PEMBAYARAN NO. : 5.4(1) Analisa EI-541
JENIS PEKERJAAN : Semen Untuk Pond. Semen Tnh.
SATUAN PEMBAYARAN : TON URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

Koefisien tenaga / Ton :


- Pekerja = (Tk x P) : Qt (L01) 2.4306 Jam
- Mandor = (Tk x M) : Qt (L03) 0.1620 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 1,042,394.34 / Ton

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 Ton

File : 441670607.xls
ITEM PEMBAYARAN NO. : 5.4(2) Analisa EI-542
JENIS PEKERJAAN : Lapis Pondasi Semen Tanah
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Pekerjaan dilakukan secara mekanik
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jarak rata-rata sumber material ke lokasi pekerjaan L 8.73 Km
5 Jam kerja efektif per-hari Tk 7.00 Jam
6 Harga pembayaran tidak termasuk semen ( semen
dibayar dalam item tersendiri)
7 Satu hari dapat diselesaikan hamparan Soil Cement
sepanjang Ls 400.00 M
8 Faktor kembang material (padat - lepas) Fk 1.20 -
9 Tebal hamparan padat t 0.15 M

II. URUTAN KERJA


1 Whell Loader memuat tanah/material ke dalam
Dump Truck di lokasi sumber bahan
2 Dump Truck mengangkut material ke lokasi pekerjaan
3 Motor Grader menghampar material di lokasi pekerjaan
4 Semen dan material tanah diaduk ditempat dengan
menggunakan Vulvi Mixer
5 Sebelum pemadatan material dibasahi dengan
menggunakan Water Tank Truck
6 Pemadatan dilakukan dengan menggunakan
Vibrator Roller dan Pneumatic Tire Roller
7 Selama pelaksanaan pekerjaan sekelompok pekerja
akan merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Setiap M3 Soil Cement padat diperlukan = 1 x Fk (M08) 1.20 M3

2. ALAT
2.a. WHELL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.90 - Pemuatan ringan
Faktor efisiensi alat Fa 0.83 -
Waktu siklus : Ts1
- Muat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit

Kap. Prod. / Jam = V x Fb x Fa x 60 Q1 56.03 M3


Fk x Ts1

Koefisien Alat / M3 = 1 / Q1 (E15) 0.0178 Jam

File : 441670607.xls
Analisa EI-542

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 5.4(2) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Lapis Pondasi Semen Tanah TOTAL HARGA : 0.00
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.1499 5,000.00 749.67


2. Mandor (L03) Jam 0.0214 7,142.86 152.99

JUMLAH HARGA TENAGA 902.66

B. BAHAN

1. Tanah Timbunan (M08) M3 1.2000 45,000.00 54,000.00

JUMLAH HARGA BAHAN 54,000.00

C. PERALATAN
1. Wheel Loader (E15) Jam 0.0178 203,578.57 3,633.71
2. Dump Truck (E08) Jam 0.1665 119,331.88 19,871.01
3. Motor Grader (E13) Jam 0.0084 208,970.90 1,748.42
4. Vibrator Roller (E19) Jam 0.0214 116,587.26 2,497.18
5. P. Tyre Roller (E18) Jam 0.0086 111,676.35 956.80
6. Water Tanker (E23) Jam 0.0070 140,668.04 988.63
7. Fulvi Mixer (E27) Jam 0.0193 90,762.66 1,749.64
8. Alat Bantu Ls 1.0000 90.00 90.00

JUMLAH HARGA PERALATAN 31,535.39

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 86,438.05


E. OVERHEAD & PROFIT 0.0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 86,438.05
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 441670607.xls
Berlanjut ke hal. berikut
ITEM PEMBAYARAN NO. : 5.4(2) Analisa EI-542
JENIS PEKERJAAN : Lapis Pondasi Semen Tanah
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

2.b. DUMP TRUCK (E08)


Kapasitas bak V 4.00 M3
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 45.00 Km / Jam
Kecepatan rata-rata kosong v2 60.00 Km / Jam
Waktu Siklus : - Waktu memuat = V : Q1 x 60 T1 4.28 menit
- Waktu tempuh isi = (L : v1) x 60 T2 11.63 menit
- Waktu tempuh kosong = (L : v2) x 60 T3 8.73 menit
- Dump dan lain-lain T4 3.00 menit
Ts2 27.64 menit

Kapasitas Prod. / jam = V x Fa x 60 Q2 6.01


Fk x Ts2

Koefisien Alat / M3 = 1 / Q2 (E08) 0.1665 Jam

2.c. MOTOR GRADER (E13)


Panjang hamparan Lh 100.00 M
Lebar efektif kerja blade b 2.40 M
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata alat v 4.00 Km / Jam
Jumlah lintasan n 6.00 lintasan 3 x pp
Waktu siklus Ts3
- Perataan 1 lintasan = Lh : (v x 1000) x 60 T1 1.50 menit
- Lain-lain T2 1.00 menit
Ts3 2.50 menit

Kap. Prod. / Jam = Lh x b x t x Fa x 60 Q3 119.52 M3


n x Ts3

Koefisien Alat / M3 = 1 / Q3 (E13) 0.0084 Jam

2.d. VIBRATOR ROLLER (E19)


Kecepatan rata-rata alat v 2.50 Km / Jam
Lebar efektif pemadatan b 1.20 M
Jumlah lintasan n 8.00 lintasan 3 x pp
Faktor efisiensi alat Fa 0.83 -

Kap. Prod. / Jam = (v x 1000) x b x t x Fa Q4 46.69 M3


n

Koefisien Alat / M3 = 1 / Q4 (E19) 0.0214 Jam

2.e. PNEUMATIC TIRE ROLLER (E18)


Kecepatan rata-rata alat v 5.00 Km / Jam
Lebar efektif pemadatan b 1.50 M
Jumlah lintasan n 8.00 lintasan 4 x pp
Faktor efisiensi alat Fa 0.83 -

File : 441670607.xls
Berlanjut ke hal. berikut
ITEM PEMBAYARAN NO. : 5.4(2) Analisa EI-542
JENIS PEKERJAAN : Lapis Pondasi Semen Tanah
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

Kap. Prod. / Jam = (v x 1000) x b x t x Fa Q5 116.72 M3


n

Koefisien Alat / M3 = 1 / Q5 (E18) 0.0086 Jam

2.e. WATER TANK TRUCK (E23)


Volume Tangki air V 4.00 M3
Kebutuhan air / M3 material padat Wc 0.07 M3
Pengisian tanhgki / jam n 3.00 kali
Faktor efisiensi alat Fa 0.83 -

Kap. Prod. / Jam = V x n x Fa Q6 142.29 M3


Wc

Koefisien Alat / M3 = 1 / Q6 (E23) 0.0070 Jam

2.f. FULVI MIXER (E27)


Kecepatan rata-rata alat v 2.50 Km / Jam
Lebar efektif pemadatan b 1.00 M
Jumlah lintasan n 6.00 lintasan 3 x pp
Faktor efisiensi alat Fa 0.83 -

Kap. Prod. / Jam = (v x 1000) x b x t x Fa Q7 51.88 M3


n

Koefisien Alat / M3 = 1 / Q7 (E27) 0.0193 Jam

2.g. ALAT BANTU


Diperlukan : Lump Sump
- Kereta dorong = 2 buah
- Sekop = 3 buah

3. TENAGA
Produksi menetukan : VIBRATOR ROLLER Q4 46.69 M3/Jam
Produksi Soil Cement / hari = Tk x Q4 Qt 326.81 M3
Kebutuhan tenaga :
- Pekerja P 7.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.1499 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0214 Jam

File : 441670607.xls
Berlanjut ke hal. berikut
ITEM PEMBAYARAN NO. : 5.4(2) Analisa EI-542
JENIS PEKERJAAN : Lapis Pondasi Semen Tanah
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 86,438.05 / M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3

File : 441670607.xls
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK : Dinas Kimprasda Kabupaten Tanah Laut


No. PAKET KONTRAK :
NAMA PAKET
PROP / KAB / KODYA : Propinsi Kalimantan Selatan / Tanah Laut
ITEM PEMBAYARAN NO. : 6.3 (2) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Latasir (SS) Kelas B TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : M2 % THD. BIAYA PROYEK : 0.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0074 5,000.00 37.11


2. Mandor (L03) Jam 0.0011 7,142.86 7.57

JUMLAH HARGA TENAGA 44.68

B. BAHAN

1. Agregat Kasar (M03) M3 0.0039 200,999.00 773.85


2. Agregat Halus (M04) M3 0.0190 181,085.15 3,439.41
3 Filler (M05) Kg 0.9240 1,600.00 1,478.40
4 Aspal (M10) Kg 4.0788 6,307.50 25,727.03

JUMLAH HARGA BAHAN 31,418.69

C. PERALATAN
1. Wheel Loader (E15) Jam 0.0007 203,578.57 148.04
2. AMP (E01) Jam 0.0011 2,347,142.66 2,488.54
3. Genset (E12) Jam 0.0011 215,993.65 229.01
4. Dump Truck (E09) Jam 0.0060 179,313.08 1,080.44
5. Asphalt Finisher (E02) Jam 0.0013 0.00 0.00
6. Tandem Roller (E17) Jam 0.0017 102,988.71 177.26
7 P. Tyre Roller (E18) Jam 0.0013 0.00 0.00
8 Alat Bantu Ls 1.0000 100.00 100.00

JUMLAH HARGA PERALATAN 4,223.28

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 35,686.65


E. OVERHEAD & PROFIT 0.0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 35,686.65
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 441670607.xls
RENCANA BIAYA PEKERJAAN
Kegiatan :
No. Paket Kontrak :
Nama Paket :
Panjang Jalan :
Panjang Jalan Addendum :
Prop / Kab / Kodya :

Jumlah Harga
No Devisi Uraian
( Rp )

1 UMUM 18,291,500.00

2 DRAINASE -

3 PEKERJAAN TANAH 39,181,498.42

5 PERKERASAN BERBUTIR 185,499,062.47

6 PERKERASAN ASPAL 2,136,626,099.46

7 STRUKTUR -

JUMLAH TOTAL ( I + II + III + IV + V + VI ) 2,379,598,160.35

Pajak Pertambahan Nilai ( PPn ) = 10 % x ( A ) 237,959,816.04

Jumlah Total Harga Pekerjaan = ( A ) + ( B ) 2,617,557,976.39

Dibulatkan 2,617,557,000.00
DAFTAR KUANTITAS DAN HARGA
Kegiatan :
No. Paket Kontrak :
Nama Paket :
Panjang Jalan :
Panjang Jalan Addendum :
Prop / Kab / Kodya :

Volume Rencana
No. Mata Harga Satuan Jumlah Harga
Uraian
Pembayaran Perkiraan ( Rp ) ( Rp )
Satuan
Kuantitas

DIVISI 1. UMUM

1.2 Mobilisasi LS 1.00 18,291,500.00 18,291,500.00

1.8 ( 1 ) Pemeliharaan dan Perlindungan Lalu Lintas LS


1.8 ( 1 ) Pemasangan dan Pemeliharaan Jembatan Sementara At coast

Sub Total I 18,291,500.00

DIVISI 2. DRAINASE

2.1 Galian untuk Selokan Drainase dan Saluran Air M3

2.2 Pasangan Batu dengan Mortar M3

2.3 (1) Gorong-gorong Pipa Beton Bertulang, Diameter Dalam < 45 cm M1


2.3 (2) Gorong-gorong Pipa Beton Bertulang, Diameter Dalam 45 - <75 cm M1
2.3 (3) Gorong-gorong Pipa Beton Bertulang, Diameter Dalam 75 - <95 cm M1
2.3 (4) Gorong-gorong Pipa Beton Bertulang, Diameter Dalam 95 - 120 cm M1
2.3 (5) Gorong-gorong Beton Tanpa tulang Diameter Dalam 20 - 30 M1
2.3 (6) Gorong-gorong Pipa Baja Bergelombang Ton

2.4 (1) Timbunan Porus atau Bahan Penyaring M3


2.4 (2) Anyaman Filter Plastik M2
2.4 (2)a Geotekstil M2
2.4 (3) Pipa Berlubang Banyak untuk Pek. Drainase di Bawah Permukaan M1

Sub Total II -

DIVISI 3. PEKERJAAN TANAH

3.1 ( 1) Galian Biasa M3


3.2 ( 2 ) Galian Batu M3
3.2 (3) Galian Struktur dengan Kedalaman 0-2 meter M3
3.2 (4) Galian Struktur dengan Kedalaman 2-4 meter M3
3.2 (5) Galian Struktur dengan Kedalaman 4-6 meter M3
3.2 (6) Cofferdam, Penyokong, Pengaku dan Pekerjaan yng Berkaitan Ls
3.2 (7) Galian Pekerasan Beraspal dengan cold Miling Machine M3
3.2 (8) Galian Pekerasan Beraspal tanpa cold Miling Machine M3
3.2 (9) Biaya Tambahan untuk Pengangkutan yang Melebihi 5 Km M3/Km

3.2 (1) Timbunan Biasa dari Selain Galian Sumber Bahan M3


3.2 (1)a Timbunan Biasa dari Galian Sumber Bahan M3
3.2 (2) Timbunan Pilihan M3
3.2 (3) Timbunan Pilihan di Atas Tanah Rawa (diukur di atas bak truk) M3

3.3a Penyiapan Badan Jalan pada Galian Biasa atau Perk. Lama rusak M2 22,621.20 1,732.07 39,181,498.42
3.3b Penyiapan Badan Jalan pada Galian Batu

3.4 (1) Pemotongan Pohon Dia. <10 cm Buah


3.4 (2) Pemotongan Pohon Dia. 10 - <30 cm Buah
3.4 (3) Pemotongan Pohon Dia. 30 - <50 cm Buah
3.4 (4) Pemotongan Pohon Dia. 50 - <75 cm Buah
3.4 (5) Pemotongan Pohon Dia. >75 cm Buah
3.4 (6) Stabilitas Lereng dengan Gebelan Rumput M2
3.4 (7) Penanaman Perdu M2
3.4 (8) Penanaman Pohon Buah

Sub Total III 39,181,498.42


Volume Rencana
No. Mata Harga Satuan Jumlah Harga
Uraian
Pembayaran Perkiraan ( Rp ) ( Rp )
Satuan
Kuantitas

DIVISI 5. PERKERASAN BERBUTIR

5.1(1) Lapisan Pondasi Agregat Kelas A M3 678.64 273,341.05 185,499,062.47


5.1(2) Lapisan Pondasi Agregat Kelas B M3

5.2 (1) Lapis Pondasi Agregat Kelas C M3

5.3 (1) Cement Treated Base (CTB) M3


5.3 (2) Cement Treated Sub Base (CTSB) M3

5.4 (1) Semen untuk Pondasi Semen Tanah Ton


5.4 (2) Lapis Pondasi Semen Tanah M3

5.5 Pekerjaan Beton M3

Sub Total V 185,499,062.47

DIVISI 6. PERKERASAN ASPAL

6.1 ( 1 ) Lapis resap Pengikat Ltr 13,572.72 6,464.09 87,735,278.44


6.2 ( 2 ) Lapis perekat Ltr

6.2 (1) Agregat Penutup BURTU M2


6.2 (2) Agreat Penutup BURDA M2
6.2 (3) Bahan aspal untuk Pekerjaan Laburann Ltr

6.3 (1) Latasir (SS) Kelas A M2


6.3 (2) Latasir (SS) Kelas B ( Manual ) M2
6.3 (3) Lataston (HRS) M2
6.3 (4) Asphalt Treated Base (ATB) M3 1,357.27 1,509,565.51 2,048,890,821.02
6.3 (5) Lapis Aus Aspal Beton (AC-WC) t = 3 cm M2
6.3 (6) Lapis Pengikat aspal beton (AC-BC) t = 5 cm M3

6.4 (1) Lasbutag M2


6.4 (2) Lasbutag kelas A M2
6.4(3) Lasbutag kelas B M2
6.4 (4) Bitumen Asbuton Ton
6.4 (5) Bitumen Bahan Peremaja Ton
6.4 (6) Bahan Anti-Stripping Ltr

6.5 (1) Campuran Aspal Dingin untuk Pelapisan Kembali M3

6.6 Lapis Penetrasi Macadam (permukaan) M3

Sub Total VI 2,136,626,099.46

JUMLAH TOTAL ( I + II + III + IV + V + VI ) 2,379,598,160.35

Pajak Pertambahan Nilai ( PPn ) = 10 % x ( A ) 237,959,816.04

Jumlah Total Harga Pekerjaan = ( A ) + ( B ) 2,617,557,976.39

Dibulatkan 2,617,557,000.00