Anda di halaman 1dari 312

QUANTITY TAKE-OFF FORM

Project :
Location
Date received:22 October 2018
Date of submission:

ITEM, DESCRIPTION AND LOCATION LEVELS SET L/A/P W/B/t

Area Computation

1 WALLS & PARTITION & WALL FINISHES


GROUND FLOOR GF
W1 Gypsum Drywall GF
at electrical rm 1 6.00
W2 12mm Ficem board Drywall GF
W3 Wall Tile GF
W4 6" Concrete PF-PF GF

SECOND FLOOR 2F
W1 Gypsum Drywall 2F
at electrical rm 1 6.00
W2 12mm Ficem board Drywall 2F
at changing rm 1 14.30
at office 1 & 2 1 23.20
at lounge rm 1 11.70
at management office 1 18.30
at hallway 1 11.00

W3 Wall Tile 2F

W4 6" Concrete PF-PF 2F


at T&B in management office 1 11.80
at T&B in common area 1 21.00

PI 6" Concrete PF-PF 2F


at T&B in management office 2 11.80
at T&B in common area 2 21.00

THIRD FLOOR 3F
W1 Gypsum Drywall 3F
at pantry, accounting,testing rm 1&2,HR office & Clinic 1 88.70
at electrical rm 1 6.20

W2 12mm Ficem board Drywall 3F


at lab, micro rm, hot rm 1 36.30
at qc office , R& D (kitchen) 1 22.40
at open area 1 22.20

W3 Wall Tile 3F

W4 6" Concrete PF-PF 3F

FOURTH FLOOR 4F
W1 Gypsum Drywall 4F
W2 12mm Ficem board Drywall 4F
W3 Wall Tile 4F
W4 6" Concrete PF-PF 4F

2 WALL FINISHES
GROUND FLOOR GF
WF2 baseboard GF
along panel walls 1 999.90
at stairs at grid A-B/5-5b 1 7.20 8.88
at stairs at grid A-B/5-5b 1 7.10 8.88

SECOND FLOOR 2F
WF1 60x30 wall tiles 2F
toilet @ management office 1 9.80
toilet @ hallway office 1 31.60

WF2 baseboard 2F
along panel walls 1 174.10
at stairs at grid A-B/5-5b 1 8.50 8.88
at stairs at grid A-B/5-5b 1 8.50 8.88

WF3 concrete mould (exterior) 2F


along panel walls 1 192.00

THIRD FLOOR 3F
WF2 baseboard 3F
along panel walls 1 139.70
at stairs at grid A-B/5-5b 1 8.50 4.08
at stairs at grid A-B/5-5b 1 8.50 4.08

WF3 concrete mould (exterior) 3F


along panel walls 1 197.50

FOURTH FLOOR 4F
WF2 baseboard 4F
along panel walls 1 156.10

WF3 concrete mould (exterior) 4F


along panel walls 1 171.20

3 FLOORS & CEILING FINISHES


GROUND FLOOR GF

SECOND FLOOR 2F
C1 10mm gypsum bd ceiling 2F
at hallway 1 99.00
at office 1 & 2 1 17.40

C1a 1" shadow line 2F


at hallway 1 81.20
at office 1 & 2 1 26.40

C2a 1/2" Plywood ceiling painted finish (main lobby) 2F


horizontal layout
plywood section 1150 x 400mm 105 1.15 0.40
plywood section 1220 x 400mm 14 1.22 0.40
plywood section 660 x 400mm 14 0.66 0.40
plywood section 830 x 400mm 1 0.83 0.40
plywood section 300 x 400mm 1 0.30 0.40

vertical layout (trapezoidal section) b1 b2


at plywood section 1150 x 400mm 210 0.13 0.25
at plywood section 1220 x 400mm 28 0.13 0.25
at plywood section 660 x 400mm 28 0.13 0.25
at plywood section 830 x 400mm 2 0.13 0.25
at plywood section 300 x 400mm 2 0.13 0.25

at edges horizontal layout


total area 1 69.40
at plywood section 1150 x 400mm
at plywood section 1220 x 400mm
at plywood section 660 x 400mm
at plywood section 830 x 400mm
at plywood section 300 x 400mm
at wood frame 1 126.60 0.05
at edges vertical layout 1 32.00

C2b 2x2" solid wood frame 2F


@ 9.1m length 13 9.10
@ 8.3m length 1 8.30
C3 10mm gypsum bd ceiling 2F
at management office 1 47.40
at lounge rm 1 16.20
offset at 60mm (both vertical & horizontal) 1 13.30

C4a 1/2" Plywood w/ laminated formica finish 2F


at management office 1 43.90
offset at 100mm (vertical) 1 13.30
at cove1 300mm (horizontal) 2 9.90
at cove1 50mm (vertical) 2 20.40
at cove 2 200mm (horizontal) 1 17.20
at cove2 330mm (vertical) 1 17.60

C4b 3 x 2" material at ends (for query) 2F 1 17.20

C5a 1/2" Plywood painted finish 2F


at conference rm 1 1 26.00
at conference rm 1 (vertical of cove) 1 4.90
at conference rm 2 1 39.70
at conference rm 2 (vertical of cove) 1 7.10

C5b 1 x 6" solid wood frame 2F


at conference rm 1 2 3.35 0.85
at conference rm 2 2 5.00 1.00

C5c 2 x 6" solid wood spaced @ 4"(100mm) O.C 2F


at conference rm 1, at 4.81m length 2 4.81 8.00
at conference rm 1, at 1.98m length 2 1.98 34.00
at conference rm 2, at 4.81m length 2 4.81 13.00
at conference rm 2, at 1.905m length 2 1.91 51.00

C5d 3 x 2" material at ends (for query) 2F


at conference rm 1 1 4.90
at conference rm 2 1 7.10

C6a 10mm Moisture resistan Gypsum board on Metal framing Sy 2F


toilet at management office 1 5.10
toilet at office hallway 1 15.90

C6b 10mm Moisture resistan Gypsum board on Metal framing Sy 2F


toilet at management office 1 9.80
toilet at office hallway 1 31.60

mh 600mm x 600mm celing manhole 2F


at hallway 1 1.00
at office 1 & 2 2 1.00
at management office 1 1.00
at lounge rm 1 1.00
at T&B at management office 1 1.00
at T&B at office hallway 2 1.00

tp 10mm Moisture resistan Gypsum board on Metal framing Sy 2F


toilet at management office 1
toilet at office hallway 1 4.70
THIRD FLOOR 3F
C1 10mm gypsum bd ceiling 3F
at laboratory 1 23.50
at qc office 1 21.50
at micro rm 1 7.00
at hot rm 1 11.30
at R&D (kitchen) 1 17.20
at elec. Rm 1 8.10
at pantry 1 20.10
at accounting 1 24.20
at testing rm1 1 23.80
at testing rm2 1 24.20
at hr office & clinic 1 39.90
at hallway 1 82.20

C1a 1" shadow line 3F


at laboratory 1 19.40
at qc office 1 18.60
at micro rm 1 11.40
at hot rm 1 13.60
at R&D (kitchen) 1 16.60
at pantry 1 18.90
at accounting 1 20.20
at testing rm1 1 20.20
at testing rm2 1 20.20
at hr office & clinic 1 34.80
at hallway 1 80.70

mh 600mm x 600mm celing manhole 3F


at laboratory 1 1.00
at qc office 1 1.00
at micro rm 1 1.00
at hot rm 1 1.00
at R&D (kitchen) 1 1.00
at elec. Rm 1 1.00
at pantry 1 1.00
at accounting 1 1.00
at testing rm1 1 1.00
at testing rm2 1 1.00
at hr offcie & clinic 1 1.00
at hallway 3 1.00

FOURTH FLOOR 4F
C7 Insulation NFR2 (exposed truss) 4F
at 4th floor MID 1 27.90 54.30
at 4th floor LEFT SIDE 1 27.90 19.30
at 4th floor RIGHT SIDE 1 27.90 19.00
at grid 5b-7/A-C 1 9.00 9.35
at grid 5b-7/A-C 1 9.00 13.75
at stairs 2 8.40 3.84
at office area 1 294.00 1.00

R1 0.6mm THK Pre-painted Rib Type Roof sheet RF


at 4th floor MID 1 27.90 54.30
at 4th floor LEFT SIDE 1 27.90 19.30
at 4th floor RIGHT SIDE 1 27.90 19.00
at grid 5b-7/A-C 1 9.00 9.35
at grid 5b-7/A-C 1 9.00 13.75
at stairs 2 8.40 3.84
at office area 1 294.00 1.00
additional 1 294.00 1.00

R2 0.6mm THK Pre-Painted Gutter RF


at 4th floor MID 1 161.50 1.00
at 4th floor LEFT SIDE 1 64.60 1.00
at 4th floor RIGHT SIDE 1 64.60 1.00
at grid 5b-7/A-C 1 45.00 1.00
at office area 1 57.20 1.00

R3 0.6mm THK Ridge Roll RF


at 4th floor MID 1 54.30 1.00
at 4th floor LEFT SIDE 1 19.30 1.00
at 4th floor RIGHT SIDE 1 19.00 1.00
at grid 5b-7/A-C 1 23.40 1.00
at stairs 2 1.00
at office area 1 37.90 1.00

R4 Fascia board (300mm high) RF


at 4th floor MID 1 161.50 1.00
at 4th floor LEFT SIDE 1 64.60 1.00
at 4th floor RIGHT SIDE 1 64.60 1.00
at grid 5b-7/A-C 1 45.00 1.00
at office area 1 57.20 1.00

WATERPROOFING 4F
WP TOILET T
at management office toilet 5.10
at office hallway toilet 15.90

PLUMBING FIXTURES PB
A Water closet PB
at main building 1 4.00
at motorpool 1 5.00

B Lavatory with faucet PB


at main building 1 3.00
at motorpool 1 3.00

C Shower head with faucet PB


at main building 1 1.00
at motorpool 1

D Urinal with push button PB


at main building 1 2.00
at motorpool 1 3.00

E Floor Drain PB
at main building 1 3.00
at motorpool 1

F Paper Holder PB
at main building 1 4.00
at motorpool 1

G Towel Bar PB
at main building 1 1.00
at motorpool 1

H Soap Basket PB
at main building 1 1.00
at motorpool 1

I Bidet PB
at main building 1 4.00
at motorpool 1 5.00

J Vanity Mirror PB
at main building 1 2.00
at motorpool 1

K Ball strainer at canopy and roof deck PB


at main building 1
at motorpool 1

Painting works
CPF SECOND FLOOR C
at main building
at motorpool
QUANTITY TAKE-OFF FORM

DEDUCTIONS
H/D QTY
AREA REMARKS

30.60
5.10 30.60

24.00
4.00 24.00
314.00
4.00 57.20
4.00 92.80
4.00 46.80
4.00 73.20
4.00 44.00

131.20
4.00 47.20
4.00 84.00

262.40
4.00 94.40
4.00 168.00

379.60
4.00 354.80
4.00 24.80

323.60
4.00 145.20
4.00 89.60
4.00 88.80

1,031.96
999.90
16.08
15.98

111.78
2.70 less door & window openings 26.46
2.70 less door & window openings 85.32

208.86
174.10
17.38
17.38

192.00
192.00

164.86
139.70
12.58
12.58

197.50
197.50

156.10
156.10

171.20
171.20

115.68
99.00
0.72 2 sets of 600 x 600mm ceiling manhole 16.68

107.60
81.20
26.40

122.83

48.30
6.83
3.70
0.33
0.12

h
1.06 42.39
1.14 6.04
0.56 2.97
0.74 0.28
0.16 0.06

60.79 less areas at section above & 2 x 2" wood frame 8.61
44.63
6.36
3.12
0.29
0.06
6.33
0.10 3.20

126.60
118.30
8.30
65.20
47.40
16.20
0.12 1.60

61.74
0.72 les 2 sets of ceiling manhole 43.18
0.10 1.33
0.30 5.94
0.05 2.04
0.20 3.44
0.33 5.81

17.20

68.94
26.00
0.27 1.32
39.70
0.27 1.92

20.40
8.40
12.00

530.97
76.96
134.64
125.06
194.31

12.00
4.90
7.10

21.00
5.10
15.90

41.40
9.80
31.60

8.00
1.00
2.00
1.00
1.00
1.00
2.00

12.69
-
2.70 12.69
299.40
0.36 less 600 x 600mm ceiling manhole 23.14
0.36 less 600 x 600mm ceiling manhole 21.14
7.00
0.36 less 600 x 600mm ceiling manhole 10.94
0.36 less 600 x 600mm ceiling manhole 16.84
8.10
0.36 less 600 x 600mm ceiling manhole 19.74
0.36 less 600 x 600mm ceiling manhole 23.84
0.36 less 600 x 600mm ceiling manhole 23.44
0.36 less 600 x 600mm ceiling manhole 23.84
0.36 less 600 x 600mm ceiling manhole 39.54
0.36 less 600 x 600mm ceiling manhole 81.84

274.60
19.40
18.60
11.40
13.60
16.60
18.90
20.20
20.20
20.20
34.80
80.70

14.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
3.00

3,149.95
1,514.97
538.47
530.10
84.15
123.75
64.51
294.00

3,443.95
1,514.97
538.47
530.10
84.15
123.75
64.51
294.00
294.00

392.90
161.50
64.60
64.60
45.00
57.20

153.90
54.30
19.30
19.00
23.40
-
37.90

392.90
161.50
64.60
64.60
45.00
57.20

21.00
5.10
15.90
9.00
4.00
5.00

6.00
3.00
3.00

1.00
1.00
-

5.00
2.00
3.00

3.00
3.00
-

4.00
4.00
-

1.00
1.00
-

1.00
1.00
-

9.00
4.00
5.00

2.00
2.00
-

-
-
-
-
Reference No.:
Date Started: 22 October 2018
Date Finished:

Tender No:

TOTAL QTY (adj. By %)


UNIT
2%

31.21 m2

- m2
- m2
- m2

24.48 m2

320.28 m2

- m2

133.82 m2

267.65 m2

387.19 m2
330.07 m2

- m2

- m2

- m2
- m2
- m2
- m2

1,052.60 l.m

114.02 m2

213.04 l.m

195.84 l.m

168.16 l.m

201.45 l.m
159.22 l.m

174.62 l.m

117.99 m2

109.75 lm

125.28 m2
129.13 lm
66.50 m2

62.97 m2

17.54 lm

70.32 m2

20.81 lm

541.59 lm

12.24 lm

21.42 m2

42.23 lm

8.00 set
12.94 m2
305.39 m2

280.09 lm

14.00 set

3,149.95 sq.m
3,443.95 sq.m

392.90 lm

153.90 lm

392.90 lm

21.00 sq.m
9.00 pc

6.00 pc

1.00 pc

5.00 pc

3.00 pc

4.00 pc

1.00 pc

1.00 pc

9.00 pc

2.00 pc

- pc
- sq.m
Reference No.:
WALLS, PARTITION & FINISHES TAKE- OFF SUMMARY Date Started:
Date Finished:

Project : Proposed Processing Plant Project No:


Location Malabon
Date received: 22 October 2018

CODE/
ITEM DESCRIPTION TOTAL QTY
TAG

WALLS & PARTITION


GF GROUND FLOOR
W1 Gypsum Drywall 31.21
W2 12mm Ficem board Drywall -
W3 Wall Tile -
W4 6" CHB -

2F SECOND FLOOR
W1 Gypsum Drywall 24.48
W2 12mm Ficem board Drywall 320.28
W3 Wall Tile -
W4 6" CHB 133.82
PI 25mm thk plastering interior 267.65

3F THIRD FLOOR
W1 Gypsum Drywall 387.19
W2 12mm Ficem board Drywall 330.07
W3 Wall Tile -
W4 6" CHB -

4F FOURTH FLOOR
W1 Gypsum Drywall -
W2 12mm Ficem board Drywall -
W3 Wall Tile -
W4 6" CHB -

FINISHES
WALL FINISHES
GF GROUND FLOOR
3" thk Concrete Baseboard Cladding (along insulated panel
WF2 wall by others), tapered on top (ref. Detail A dwg.no. 1,052.60
AR.273.15)@ 200mm high

2F SECOND FLOOR
WF1 60x30 wall tiles 114.02
3" thk Concrete Baseboard Cladding (along insulated panel
WF2 wall by others), tapered on top (ref. Detail A dwg.no. 213.04
AR.273.15)@ 200mm high

4" thk Concrete mould(along insulated panel wall by


WF3 others), tapered on top (ref. Detail A dwg.no. AR.273.15)@ 195.84
195mm high
3F THIRD FLOOR
3" thk Concrete Baseboard Cladding (along insulated panel
WF2 wall by others), tapered on top (ref. Detail A dwg.no. 168.16
AR.273.15)@ 200mm high

4" thk Concrete mould(along insulated panel wall by


WF3 others), tapered on top (ref. Detail A dwg.no. AR.273.15)@ 201.45
195mm high

4F FOURTH FLOOR
3" thk Concrete Baseboard Cladding (along insulated panel
WF2 wall by others), tapered on top (ref. Detail A dwg.no. 159.22
AR.273.15)@ 200mm high

4" thk Concrete mould(along insulated panel wall by


WF3 others), tapered on top (ref. Detail A dwg.no. AR.273.15)@ 174.62
195mm high

FLOOR FINISHES
CEILING FINISHES
GF GROUND FLOOR

2F SECOND FLOOR
10mm Gypsum board w/ Metal framing System w/ 1"
C1 117.99
shadow line (Measured separately)
C1a 1" shadow line 109.75
C2a 1/2" thk Plywood ceiling painted finish (main lobby) 125.28
C2b 2 x 2" Solid wood frame 129.13
C3 10mm Gypsum board on Metal framing System 66.50
C4a 1/2" thk Plywood w/ wood laminated formica finish 62.97
C4b 3 x 2" material at ends (for query) 17.54
C5a 1/2" Plywood painted finish 70.32
C5b 1 x 6" solid wood frame 20.81
2 x 2" solid wood spaced @ 4" (100mm) O.C in varnish
C5c 541.59
finish
C5d 3 x 2" material at ends (for query) 12.24
C6a 6mm Ficem Board on Metal framing System 21.42
C6b 1" shadow line 42.23
MH 600 x 600MM ceiling manhole 8.00
TP Toilet modular partition 12.94

3F THIRD FLOOR
10mm Gypsum board w/ Metal framing System w/ 1"
C1 305.39
shadow line (Measured separately)
C1a 1" shadow line 280.09
MH 600 x 600MM ceiling manhole 14.00

4F FOURTH FLOOR
C7 Insulation NFR2 (exposed truss) 3,149.95

WATERPROOFING
WP Waterproofing 21.00
ROOFING
R1 0.6mm THK Pre-painted Rib Type Roof sheet 3,443.95
R2 0.6mm THK Pre-Painted Gutter 392.90
R3 0.6mm THK Ridge Roll 153.90
R4 Fascia board (300mm high) 392.90

PLUMBING
A Water closet 9.00
B Lavatory with faucet 6.00
C Shower head with faucet 1.00
D Urinal with push button 5.00
E Floor Drain 3.00
F Paper Holder 4.00
G Towel Bar 1.00
H Soap Basket 1.00
I Bidet 9.00
J Vanity Mirror 2.00
K Ball strainer at canopy and roof deck -
PAINTING WORKS
CPF Ceiling Paint finish 852.97
10mm Gypsum board w/ Metal framing System w/ 1" shadow
C1 423.38
line (Measured separately)
C2a 1/2" thk Plywood ceiling painted finish (main lobby) 125.28
C2b 2 x 2" Solid wood frame 129.13
C3 10mm Gypsum board on Metal framing System 66.50
C4b 3 x 2" material at ends (for query) 17.54
C5a 1/2" Plywood painted finish 70.32
C5b 1 x 6" solid wood frame 20.81
22 October 2018

UNIT

sq.m
sq.m
sq.m
sq.m

sq.m
sq.m
sq.m
sq.m
sq.m

sq.m
sq.m
sq.m
sq.m

sq.m
sq.m
sq.m
sq.m

l.m

sq.m

l.m

l.m
l.m

l.m

l.m

l.m

sq.m

l.m
sq.m
l.m
sq.m
sq.m
l.m
sq.m
l.m

l.m

l.m
sq.m
l.m
pcs
sq.m

sq.m

l.m
pcs

sq.m

sq.m
sq.m
l.m
l.m
l.m

PC
PC
PC
PC
PC
PC
PC
PC
PC
PC
PC
sq.m
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

10.0 CHB (CONCRETE HOLLOW BLOCK) LAYING WORKS


10.03 Second to Third Floor
10.03.01 6" Chb Laying, (Use 700 psi) - Toilet pc/s 4,389.00
10.03.02 Cement bag/s 351.00
10.03.03 Sand cu.m. 30.00
SUB-TOTAL (CHB LAYING WORKS)

B ARCHITECTURAL WORKS

1.0 MASONRY WORKS


1.01 Ground Floor
1.01.01Plastering of Exterior Wall (25mm thick)
Cement bag/s 338.10
Sand cu.m. 19.60

1.01.02 Straight Finished Concrete


(All interior areas except: Shoe Change & Handwash Lobby/
Cement bag/s 1,047.62
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

Sand cu.m. 58.80

1.01.03 Floor Concrete Topping (50mm)


Shoe Change & Handwash Lobby/Reception, exterior entranc
Cement bag/s 21.56
Sand cu.m. 1.96

1.01.04Installation of Tiles at Reception/Shoe Change And Handw


60 x 90 cm Granite Tiles pc/s 68.60
Cement bag/s 30.38
Adhesive (20kg/bag) kg 98.00
Grout (2kg/bag) kg 19.60

1.01.05Installation of Tiles at Entrance Outdoor Tiles


60 x 60 cm Outdoor Tiles pc/s 29.40
Cement bag/s 8.82
Adhesive (20kg/bag) kg 39.20
Grout (2kg/bag) kg 5.88
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

1.02 Second Floor


1.02.01Plastering of Interior Wall (25mm thick)
Cement bag/s 268.52
Sand cu.m. 15.68

1.01.02 Straight Finished Concrete


(All interior areas except: Shoe Change & Handwash Lobby/
Cement bag/s 349.86
Sand cu.m. 19.60

1.03 Floor Concrete topping (50mm) for Reception/Shoe Change


T&B, Testing Room, HR Office, Clinic, Waiting Area, Spare
1.03.01 Cement bag/s 294.00
1.03.02 Sand cu.m. 16.66

1.04 Installation of Wall and floor tiles at Toilet Female, Toilet


1.04.01 60 x 60 cm Granite Tiles - Floor pc/s 235.20
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

1.04.02 30 x 60 cm Tiles - Wall pc/s 2,528.40


1.04.03 Adhesive (20kg/bag) kg 803.60
1.04.04 Grout (2kg/bag) kg 158.76
1.04.05 Cement bag/s 250.88
1.04.06 Sand cu.m. 17.35

1.05 Installation of Tiles at Testing Room, HR Office, Clinic, Wa


1.05.0145 x 90 cm Granite Tiles pc/s 1097.60
1.05.02 Adhesive (20kg/bag) kg 1117.20
1.05.03 Grout (2kg/bag) kg 223.44
1.05.04 Cement bag/s 355.74
1.05.05 Sand cu.m. 24.70

1.06 Installation of Tiles at Stairs


1.06.01 300x1200mm Tiles pc/s 212.66
1.06.02 Adhesive (20kg/bag) kg 58.80
1.06.03 Grout (2kg/bag) kg 9.80
1.06.04 Cement bag/s 15.68
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

1.06.05 Sand cu.m. 1.08

Additionals
Ground floor
Drywall Partition
Gypsum Drywall sq.m
.6mm x 3m Metal Tracks
.6mm x 3m Metal Studs
Gypsum Board
Blind rivets 1/8" x 1/2"
Blind rivets 1/8" x 3/4"
Premium Jointing Powder Boral
Mesh Tape
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub
3" thk Concrete Baseboard
Cladding (along insulated panel
wall by others), tapered on top
(ref. Detail A dwg.no.
AR.273.15)@ 200mm high l.m
Cement bags
Sand cu.m
Gravel cu.m
6"x 6: wire mesh with 4.5mm dia. pcs

Second Floor
Drywall Partition
Gypsum Drywall sq.m
.6mm x 3m Metal Tracks
.6mm x 3m Metal Studs
Gypsum Board
Blind rivets 1/8" x 1/2"
Blind rivets 1/8" x 3/4"
Premium Jointing Powder Boral
Mesh Tape

12mm Ficem board Drywall sq.m


PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

.6mm x 3m Metal Tracks


.6mm x 3m Metal Studs
Ficem Board
Blind rivets 1/8" x 1/2"
Blind rivets 1/8" x 3/4"
3" Premium
thk Concrete Baseboard
Jointing Powder Boral
Cladding (along insulated panel
Mesh Tape
wall by others), tapered on top
(ref. Detail A dwg.no.
AR.273.15)@ 200mm high l.m
Cement bags
Sand cu.m
4"Gravel
thk Concrete mould(along cu.m
insulated panel wall by others),
6"x 6: wire mesh with 4.5mm dia. pcs
tapered on top (ref. Detail A
dwg.no. AR.273.15)@ 195mm
high l.m
Cement bags
Sand cu.m
Gravel cu.m
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

12mm Ø RSB (horizontal bar) kgs


10mm Ø RSB (stirrups) kgs

Armstrong Carpet Tiles (by barri sq.m

Third Floor
Straight Finished Concrete
Cement bag/s
Sand cu.m.

Floor Concrete topping (50mm)


Cement bag/s
Sand cu.m.

Drywall Partition
Gypsum Drywall sq.m
.6mm x 3m Metal Tracks
.6mm x 3m Metal Studs
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

Gypsum Board
Blind rivets 1/8" x 1/2"
Blind rivets 1/8" x 3/4"
Premium Jointing Powder Boral
Mesh Tape

12mm Ficem board Drywall sq.m


.6mm x 3m Metal Tracks
.6mm x 3m Metal Studs
Ficem Board
Blind rivets 1/8" x 1/2"
Blind rivets 1/8" x 3/4"
3" Premium
thk Concrete Baseboard
Jointing Powder Boral
Cladding (along insulated panel
Mesh Tape
wall by others), tapered on top
(ref. Detail A dwg.no.
AR.273.15)@ 200mm high l.m
Cement bags
Sand cu.m
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

4"Gravel
thk Concrete mould(along cu.m
insulated panel wall by others),
6"x 6: wire mesh with 4.5mm dia. pcs
tapered on top (ref. Detail A
dwg.no. AR.273.15)@ 195mm
high l.m
Cement bags
Sand cu.m
Gravel cu.m
12mm Ø RSB (horizontal bar) kgs
10mm Ø RSB (stirrups) kgs

Installation of Tiles
45 x 90 cm Granite Tiles pc/s
Adhesive (20kg/bag) kg
Grout (2kg/bag) kg
Cement bag/s
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

Sand cu.m.

Granite Counter Top (at T&B lavatory sq.m


Adhesive (20kg/bag) kg
Grout (2kg/bag) kg
Cement bag/s
Sand cu.m.

Fourth Floor
Straight Finished Concrete
3" thk Concrete Baseboard
Cement bag/s
Cladding (along insulated panel
Sand cu.m.
wall by others), tapered on top
(ref. Detail A dwg.no.
AR.273.15)@ 200mm high l.m
Cement bags
Sand cu.m
Gravel cu.m
6"x 6: wire mesh with 4.5mm dia. pcs
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

4" thk Concrete mould(along


insulated panel wall by others),
tapered on top (ref. Detail A
dwg.no. AR.273.15)@ 195mm
high l.m
Cement bags
Sand cu.m
Gravel cu.m
12mm Ø RSB (horizontal bar) kgs
10mm Ø RSB (stirrups) kgs

1.07 Others - MOTORPOOL


Plastering of Exterior Wall (25mm thick)
Cement bag/s 196.00
Sand cu.m. 11.76

Straight Finished Concrete


Cement bag/s 101.92
Sand cu.m. 5.88

Floor Concrete Topping (50mm)


PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

Cement bag/s 73.50


Sand cu.m. 4.90

Installation of Wall and floor tiles at Toilet Female, Toilet


60 x 60 cm Granite Tiles - Floor pc/s 450.80
30 x 60 cm Tiles - Wall pc/s 107.80
Adhesive (20kg/bag) kg 509.60
Grout (2kg/bag) kg 101.92
Cement bag/s 161.70
Sand cu.m. 11.17

1.10.03
SUB TOTAL (MASONRY WORKS)

3.0 CARPENTRY WORKS


3.01 Ground Floor
3.01.0110mm Gypsum Board on Metal Framing System (Handwash
3.01.02.5mm x 5m. Wall angle pcs 20.00
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

3.01.03.5mm x 5m. Double furring channel pcs 20.00


3.01.04.8mm x 5.0m Carrying Channel pcs 20.00
3.01.05Suspension rod # 6 pcs 50.00
3.01.06Suspension Clip 3 type pcs 50.00
3.01.07Double furring clip pcs 90.00
3.01.08Blind rivets 1/8" x 3/8" pcs 190.00
3.01.09Steel angle pcs 50.00
3.01.10Drive Pin 1" pcs 230.00
3.01.11Cartridge .27 cal red pcs 230.00
3.01.12Gypsum Board pcs 20.00
3.01.13Grabber Screw pcs 560.00
3.01.14UB88 boral powder bag/s 2.00
3.01.15Mesh tape pcs 30.00
sqm
3.01.161/2" Plywood with Wood Laminate/Formica 117.60
Finish (Manage
3.01.172"x2" Solid Wood Frame (Main Lobby)sqm 55.47
sqm Conference
3.01.181/2" Plywood Painted Finish (Main Lobby, 103.34 1, Conf
3.01.191"x6" Solid Wood Frame (Conference sqm
1, Conference
47.87 2)
sqm Varnish
3.01.202"x2" Solid Wood Spaced @ 4" on Center 49.31 Finish (C
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

3.02 Second Floor


3.02.0110mm Gypsum Board on Metal Framing System (Pantry, Lo
3.02.02Office, Meeting Room, R&D (Kitchen), Hot Room, Micro Room, Lab
3.02.03.5mm x 5m. Wall angle pcs 210.00
3.02.04.5mm x 5m. Double furring channel pcs 330.00
3.02.05.8mm x 5.0m Carrying Channel pcs 180.00
3.02.06Suspension rod # 6 pcs 780.00
3.02.07Suspension Clip 3 type pcs 780.00
3.02.08Double furring clip pcs 1520.00
3.02.09Blind rivets 1/8" x 3/8" pcs 3180.00
3.02.10Steel angle pcs 780.00
3.02.11Drive Pin 1" pcs 3,780.00
3.02.12Cartridge .27 cal red pcs 3,780.00
3.02.13Gypsum Board pcs 330.00
3.02.14Grabber Screw pcs 9450.00
3.02.15UB88 boral powder bag/s 21.00
3.02.16Mesh tape pcs 480.00
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

sqm
3.01.161/2" Plywood with Wood Laminate/Formica 117.60
Finish (Manage
3.01.172"x2" Solid Wood Frame (Main Lobby)sqm 55.47
sqm Conference
3.01.181/2" Plywood Painted Finish (Main Lobby, 103.34 1, Conf
3.01.191"x6" Solid Wood Frame (Conference sqm
1, Conference
47.87 2)
sqm Varnish
3.01.202"x2" Solid Wood Spaced @ 4" on Center 49.31 Finish (C

3.02 Third floor (additional)


3.02.0110mm Gypsum Board on Metal Framing System (Pantry, Lo
3.02.02Office, Meeting Room, R&D (Kitchen), Hot Room, Micro Room, Lab
3.02.03.5mm x 5m. Wall angle pcs
3.02.04.5mm x 5m. Double furring channel pcs
3.02.05.8mm x 5.0m Carrying Channel pcs
3.02.06Suspension rod # 6 pcs
3.02.07Suspension Clip 3 type pcs
3.02.08Double furring clip pcs
3.02.09Blind rivets 1/8" x 3/8" pcs
3.02.10Steel angle pcs
3.02.11Drive Pin 1" pcs
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

3.02.12Cartridge .27 cal red pcs


3.02.13Gypsum Board pcs
3.02.14Grabber Screw pcs
3.02.15UB88 boral powder bag/s
3.02.16Mesh tape pcs

3.03 6mm Ficem Board on Metal Framing System and Shadow


3.03.01.5mm x 5m. Wall angle pcs 30.00
3.03.02.5mm x 5m. Double furring channel pcs 40.00
3.03.03.8mm x 5.0m Carrying Channel pcs 30.00
3.03.04Suspension rod # 6 pcs 100.00
3.03.05Suspension Clip 3 type pcs 100.00
3.03.06Double furring clip pcs 190.00
3.03.07Blind rivets 1/8" x 3/8" pcs 380.00
3.03.08Steel angle pcs 100.00
3.03.09Drive Pin 1" pcs 460.00
3.03.10Cartridge .27 cal red pcs 460.00
3.03.11Hardiflex pcs 40.00
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

3.03.12Grabber Screw pcs 1130.00


3.03.13UB88 boral powder bag/s 3.00
3.03.14Mesh tape pcs 60.00

3.04 10mm Thk. Acoustic Board (Testing Room)


3.04.01.5mm x 5m. Wall angle pcs 20.00
3.04.02.5mm x 5m. Double furring channel pcs 20.00
3.04.03.8mm x 5.0m Carrying Channel pcs 20.00
3.04.04Suspension rod # 6 pcs 50.00
3.04.05Suspension Clip 3 type pcs 50.00
3.04.06Double furring clip pcs 90.00
3.04.07Blind rivets 1/8" x 3/8" pcs 190.00
3.04.08Steel angle pcs 50.00
3.04.09Drive Pin 1" pcs 220.00
3.04.10Cartridge .27 cal red pcs 220.00
3.04.11Acoustic Board pcs 160.00
3.04.12Grabber Screw pcs 550.00
3.04.13UB88 boral powder bag/s 2.00
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

3.04.14Mesh tape pcs 30.00

3.05 Toilet Partition


3.05.011" Laminated Phenolic Board sqm 102.66
3.05.02304 stainless Steel - Lock Front pcs 20.00
3.05.03304 stainless Steel - Lock Back pcs 20.00
3.05.04304 stainless Steel - Coat Hook pcs 20.00
3.05.05304 stainless Steel - L Bracket pcs 20.00

3.06 Stairs
3.06.012"x16" Solid Wood Planks lm 118.13
Others; Pls Specify
1"x6" Solid Wood Cladding lm
2"Ø Solid Wood Railing lm

3.07 Others; Please Specify


Ceiling manhole set
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

SUB-TOTAL (CARPENTRY WORKS)

4.0 SPECIALTY WORKS


4.01 DOORS (FLUSHED DOOR AS PER MICROTEL UP HUB)
4.01.01MD-A (1/2" THK Clear Tempered Glass Doset/s 1.00
4.01.02D1A-A (1/2" THK Tempered Glass on FD set/s 3.00
4.01.03D1B-B (Insulated Panel Door) set/s 5.00
4.01.04D1C-C (Solid Wood Door Hafele Stainlesset/s 3.00
4.01.05D1D-C (Solid Wood Door Hafele Stainlesset/s 1.00
4.01.06D2A-A (1/4" THK Glass Door on PVC Framset/s 7.00
4.01.07D2B-D (GI Plain Sheet Steel Door) set/s 1.00
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

4.01.08D2C-B (Panic Door) set/s 16.00


4.01.09D3A-A (1/4" THK Glass Door on PVC Fram set/s 20.00
4.01.10D3B-B (Insulated Panel Door) set/s 8.00
4.01.11D4A-B (Insulated Sliding Panel Door) set/s 4.00
4.01.12D4B-B (Insulated Sliding Panel Door w/ set/s 1.00
4.01.13D5A-D (G.I. Plain Sheet Steel Door) set/s 4.00
4.01.14D6A-E (Curtain Door) set/s 5.00
4.01.15D6B-E (Curtain Door) set/s 2.00
4.01.16D7A-E (Curtain Door) set/s 1.00
4.01.17D8A-E (Automatic Alternating Roll Up & set/s 5.00
4.01.18D9-F (Automatic Roll Up Door) set/s 5.00
4.01.19D10-A (1/2" THK Clear Tempered Glass set/s 1.00
4.01.20D11-A (1/2" THK Clear Tempered Glass set/s 1.00
D12-A (1/2" THK Clear Tempered Glass set/s 1.00
4.01.21D13-G (Solid Wood Panel Door w/ Formi set/s 1.00
4.01.22D14-G (Solid Wood Panel Door w/ Formi set/s 3.00
4.01.23D15A-B (Insulated Panel Door) set/s 1.00
4.01.24D16A (PVC Door) set/s 1.00
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

4.01.25D17A (PVC Door) set/s 1.00

4.02 Hardwares
4.02.01Dead bolt (metal doors) set/s 5.00
4.02.02Loose pin hinges for wooden doors set/s 24.00
4.02.03Panic Door Device set/s 16.00
4.02.04Door stopper set/s 76.00
4.02.05Door closer set/s 76.00
4.02.06Lever type door handle set/s 20.00
4.02.10Stainless kick plate set/s 37.00
4.02.11Stainless cladding set/s -
4.02.12Others; Pls Specify

4.03 WINDOWS (6mm THICK with tint on 1 side)


4.03.01W1 (1/4" THK Fixed Glass Window on P set/s 16.00
4.03.02W2 (1/4" THK Clear Glass Sliding Wind set/s 2.00
4.03.03W3 (1/4" THK Clear Glass Sliding Wind set/s 6.00
4.03.04W4 (1/4" THK Clear Glass Sliding Wind set/s 3.00
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

4.03.05W5 (1/2" THK Tempered Fixed Glass) set/s 1.00


4.03.07W6 (1/2" THK Tempered Fixed Glass) set/s 1.00
4.03.08W7 (1/2" THK Tempered Fixed Glass) set/s 1.00

SUB-TOTAL (SPECIALTY WORKS)

5.0 PAINTING WORKS


5.01 Materials lot 1.00
5.01.01Acrytex Paint gal/s
5.01.02Automotive lacquer gal/s
5.01.03Lacquer primer white gal/s
5.01.04Epoxy Primer Gray gal/s
5.01.05Lacquer Thinner gal/s
5.01.06Lacquer Flo gal/s
5.01.07Sanding Sealer
5.01.08Wood Stain
5.01.09Stofa Rug
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

5.01.10Clear dead flat


5.01.11Sanding paper # 120
5.01.12Sanding paper # 100
5.01.13Masking tape
5.01.14Adhesive tape #2
5.01.15Boral powder (25 bags)
5.01.16Polytuff with hardiner
5.01.17Spot putty
5.01.18Patching compound
5.01.19Gypsum putty
5.01.20
5.02 Others; Please Specify
consumables lot
Epoxy paint for trusses sq.m
Painting works to ceiling sq.m

SUB-TOTAL (PAINTING WORKS)


PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

6.0 PLUMBING WORKS


6.01 Fixtures & Accessories (Installation)
6.01.01Water closet unit 20.00
6.01.02Lavatory with faucet unit 12.00
6.01.03Shower head with faucet unit 1.00
6.01.04Urinal with push button unit 9.00
6.01.06 Floor Drain unit -
6.01.07 Paper Holder unit 20.00
6.01.08 Towel Bar unit 1.00
6.01.09 Soap Basket unit 20.00
6.01.10 Bidet unit 20.00
6.01.11 Vanity Mirror unit
6.01.12Ball strainer at canopy and roof deck unit

6.02 Others; Please Specify


PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

SUB-TOTAL (PLUMBING WORKS)

7.0 IRON WORKS


7.01 Electrical and Genset Room Cover sqm 242.10
7.01.012x4"x1/4" Tubular Frame kgs. -
7.01.021/4"x2" Wire Mesh with 1/4"x1" Flat Ba kgs. -

7.02 Stair Railing lm 70.00


7.02.01 1/4" dia. Stainless Steel Pipe Railing kgs.
7.02.02 16mm Round Bar kgs.
7.02.03 12mm Round Bar kgs.
7.02.04 1/2" x 2" Flat Bar kgs.
7.02.05 Welding Rod kgs.
7.02.06 Epoxy Primer Gray kgs.

7.03 Flatform for condensing units unit 18.00


7.03.01Angle bar 1 x 1 x 3mm kgs. -
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

7.03.02Flat bar 1 x 3mm kgs. -


7.03.03welding rod kgs. -
7.03.04Plastic mesh wire kgs. -

7.04 Trench Drain pc 192.00


7.04.01DH-WHG G305/30/100PG Zinc Coated D kgs.

7.05 Manhole Cover pc 11.00

7.06 Others; Please Specify

SUB-TOTAL (IRON WORKS)


7.0 MISCELLANEOUS WORKS
7.01 Waterproofing
7.01.01Toilets sq.m. 106.72
7.01.02Roof Deck sq.m. 277.99
7.01.03Cistern Tank sq.m. 32.56
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

7.02 Roofing
7.02.01 Insulation NFR2 sq.m. 2,311.53
7.02.02 Insulation tape
7.02.03 0.6mm THK Pre-painted Rib Type Roof sq.m. 2,311.53
7.02.04 0.6mm THK Pre-Painted Gutter lm 143.40
7.02.05 0.6mm THK Ridge Roll lm 86.70
7.02.06 0.6mm THK Wall Flashing lm -
7.02.07 Tekscrew
7.02.08 Rivets
7.02.09 Silicon

7.03 Glass Railing


7.03.01 1/2" Thk Tempered Glass Railing sqm 12.90
7.03.02 Fittings lot 1.00

Others; Please Specify


PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

Side Stair
3"x3"x¼" Angle Bar l.m.
C15x33.9 Steel Channel l.m.
10mmØ Bar kgs
Stair Concrete
Cement bag/s
Sand cu.m.
Gravel cu.m.

Side Stair
50mm Aluminum Nosing l.m.
50mmØ B.I. Pipe Railing l.m.
32mmØ B.I. Pipe Railing l.m.
28mmØ B.I. Pipe Railing l.m.
16mmØ Bar kgs
12mmØ Bar kgs
10mmØ Bar kgs
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

Stair Concrete
Cement bag/s
Sand cu.m.
Gravel cu.m.
Plain Leveled Concrete
Cement bag/s
Sand cu.m.

Main Stair
Granite/Tile Cladding sq.m.
3"x¼" Flat Bar Plate l.m.
½" THK Steel Plate pcs
10mmØ Bar kgs
Stair Reinforced Concrete
Cement bag/s
Sand cu.m.
Gravel cu.m.
Reinforcement kg/s
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

SUB-TOTAL (MISCELLANEOUS WORKS)


TOTAL DIRECT COST (ARCHITECTURAL)

Including CHB works (for T&B only)


PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

DEDUCTIVE ITEMS AS PER LATEST DESIGN

A STRUCTURAL WORKS
8.0 REINFORCING BARS (Use Garde 60 for 12mm dia. And above, Use Grade 40 for 10mm di

8.07 G) CHB Reinforcing-bars


8.07.01 Footing to Ground (Vetical & Horizontal Bars) 661.34 kgs
8.07.02 Ground to 2nd Storey (Vetical & Horizontal Bars) 591.97 kgs
8.07.03 2nd to 3rd Storey (Vetical & Horizontal Bars) ### kgs

3rd to 4th Storey (Vetical & Horizontal Bars) 591.97 kgs


8.07.04
4th to Upper Fourth Storey (Vetical & Horizontal 221.99 kgs
8.07.05
Others - MOTORPOOL
8.09
G) CHB Reinforcing-bars
528.87 kgs
SUB-TOTAL (REINFORCING BARS)
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

10.0 CHB (CONCRETE HOLLOW BLOCK) LAYING WORKS

10.01 Footing to Ground Floor

10.01.01 8" Chb Laying (Use 700 psi) - Elevator Wall ### pc/s

10.01.02 Cement 288.00 bag/s

10.01.03 Sand 24.00 cu.m.

10.02 Ground to Second Floor


4" Chb Laying, (Use 700 psi) - 40cm Ht Zocalo for I ### pc/s
Cement 156.00 bag/s
Sand 9.00 cu.m.

10.02.01 8" Chb Laying (Use 700 psi) - Elevator Wall ### pc/s

10.02.02 Cement 258.00 bag/s

10.02.03 Sand 22.00 cu.m.

10.03 Second to Third Floor


4" Chb Laying, (Use 700 psi) - 40cm Ht Zocalo for I ### pc/s
Cement 104.00 bag/s
Sand 6.00 cu.m.
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

10.03.01 6" Chb Laying, (Use 700 psi) - Toilets ### pc/s

10.03.02 Cement 351.00 bag/s

10.03.03 Sand 30.00 cu.m.

10.03.04 8" Chb Laying (Use 700 psi) - Elevator Wall ### pc/s

10.03.05 Cement 258.00 bag/s

10.03.06 Sand 22.00 cu.m.

10.04 Third to Fourth Floor


4" Chb Laying, (Use 700 psi) - 40cm Ht Zocalo for I ### pc/s
Cement 99.00 bag/s
Sand 6.00 cu.m.

10.04.01 8" Chb Laying (Use 700 psi) - Elevator Wall ### pc/s

10.04.02 Cement 258.00 bag/s

10.04.03 Sand 22.00 cu.m.

10.05 Fourth to Upper Fourth Floor


4" Chb Laying, (Use 700 psi) - 40cm Ht Zocalo for I ### pc/s
Cement 64.00 bag/s
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

Sand 4.00 cu.m.

10.05.01 8" Chb Laying (Use 700 psi) - Elevator Wall 804.00 pc/s

10.05.02 Cement 97.00 bag/s

10.05.03 Sand 9.00 cu.m.

10.06 Others - MOTORPOOL


Ground Floor
4" Chb Laying, (Use 700 psi) - 40cm Ht Zocalo for I 405.00 pc/s
Cement 26.00 bag/s
Sand 2.00 cu.m.

6" Chb Laying, (Use 700 psi) - Toilets ### pc/s


Cement 106.00 bag/s
Sand 9.00 cu.m.

8" Chb Laying (Use 700 psi) 355.00 pc/s


Cement 43.00 bag/s
Sand 4.00 cu.m.
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

Mezzanine
4" Chb Laying, (Use 700 psi) - 40cm Ht Zocalo for I 444.00 pc/s
Cement 29.00 bag/s
Sand 2.00 cu.m.

8" Chb Laying (Use 700 psi) 260.00 pc/s


Cement 32.00 bag/s
Sand 3.00 cu.m.

SUB-TOTAL (CHB LAYING WORKS)

B ARCHITECTURAL WORKS

1.0 MASONRY WORKS


1.01 Ground Floor
1.01.01 Plastering of Exterior Wall (25mm thick)
Cement 338.10 bag/s
Sand 19.60 cu.m.

1.02 Second Floor


1.02.01 Plastering of Interior Wall (25mm thick)
PROJECT : Proposed 4-Storey Processing Plant
OWNER : J2NS Property Development, Inc.
LOCATION: Sancingco St., Catmon, Malabon, Metro
SUBJECT : Change Order (Additives &
DATE : MAY 15, 2018
BOQ REF :051518-J2NSPDI.FINAL
BID
ITEM NO.

ITEM DESCRIPTION UNIT


QUANTITY
Main Sub

Cement 268.52 bag/s


Sand 15.68 cu.m.

1.07 Others - MOTORPOOL

Plastering of Exterior Wall (25mm thick)


Cement 196.00 bag/s
Sand 11.76 cu.m.

SUB TOTAL (MASONRY WORKS)

OTHERS
7.05 Perimeter CHB Wall
7.05.01 6" Non Load Bearing CHB ### sqm

7.05.02 Plastering ### sqm

7.05.03 Painting ### sqm


ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

164,038.88 1,672.80 62,520.90 1,672.80


128,562.53 204.22 74,799.00 204.22
42,900.00 11.43 16,350.68 11.43
335,501.40 153,670.58

123,837.58 338.10 123,837.58 -


28,028.00 19.60 28,028.00 -

& Handwash Lobby/Reception, exterior entrance stairs)


383,717.02 1,156.00 423,412.47 108.38
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

84,084.00 64.22 91,837.47 5.42

on, exterior entrance stairs


7,896.89 26.54 9,721.83 4.98
2,802.80 2.21 3,162.97 0.25

hange And Handwash Lobby


27,440.00 131.75 52,700.00 63.15
8,559.57 58.35 16,439.11 27.97
1,352.40 355.73 4,909.01 257.73
563.50 37.64 1,082.23 18.04

11,760.00 6.24 2,495.49 (23.16)


2,485.04 4.13 1,162.54 (4.69)
540.96 86.25 1,190.24 47.05
169.05 8.66 249.12 2.78
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

98,352.16 204.68 74,970.84 204.68


22,422.40 11.95 17,091.91 11.95

& Handwash Lobby/Reception, exterior entrance stairs)


128,144.97 709.29 259,794.50 359.43
28,028.00 39.40 56,349.00 19.80

ption/Shoe Change And Handwash Lobby, Entrance Outdoor Tiles, Toilet Female, Toile
Waiting Area, Spare Office, Pantry, Meeting Room, Hallway, Changing Area
107,684.85 54.13 19,824.74 (239.87)
23,823.80 3.01 4,299.95 (13.65)

let Female, Toilet Male, T&B


94,080.00 57.46 22,984.00 (177.74)
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

1,011,360.00 633.42 253,368.00 (1,894.98)


11,089.68 673.51 9,294.38 (130.09)
4,564.35 67.35 1,936.33 (91.41)
70,685.44 62.61 17,639.30 (188.27)
19,080.60 4.33 4,761.50 (13.02)

Office, Clinic, Waiting Area, Spare Office, Pantry, Meeting Room, Hallway, Ch
439,040.00 245.78 98,312.89 (851.82)
15,417.36 497.71 6,868.38 (619.49)
6,423.90 50.03 1,438.48 (173.41)
100,229.75 79.66 22,444.14 (276.08)
27,165.60 5.53 6,083.11 (19.17)

138,229.00 48.20 31,326.75 (164.47)


811.44 86.75 1,197.16 27.95
281.75 8.68 249.41 (1.12)
4,417.84 3.55 1,001.21 (12.13)
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

1,185.80 0.24 268.74 (0.83)

- 31.21 37,454.40 31.21


ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

189.47 69,397.34 189.47


7.89 11,289.13 7.89
15.79 25,657.11 15.79
73.10 297,505.47 73.10

- 24.48 29,376.00 24.48

- 320.28 432,378.00 320.28


ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

38.35 26,818.95 38.35


1.60 4,362.74 1.60
3.20 9,915.32 3.20
14.79 81,784.68 14.79

45.83 16,785.12 45.83


22.91 32,765.99 22.91
22.91 37,234.08 22.91
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

367.22 20,197.10 367.22


259.74 14,285.62 259.74

112.85 141,066.00 112.85

- 587.24 215,093.02 587.24


- 32.62 46,653.32 32.62

- 40.74 14,923.47 40.74


- 3.40 4,855.31 3.40

- 387.19 464,630.40 387.19


ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

- 330.07 445,597.20 330.07

30.27 24,542.86 30.27


1.26 3,992.48 1.26
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

2.52 9,073.82 2.52


11.68 70,253.01 11.68

47.14 17,265.95 47.14


23.57 33,704.60 23.57
23.57 38,300.68 23.57
378.40 20,811.80 378.40
267.17 14,694.19 267.17

- 55.00 22,001.71 55.00


- 679.07 9,371.10 679.07
- 67.91 1,952.31 67.91
- 11.68 3,290.82 11.68
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

- 8.15 8,963.46 8.15

- 3.61 1,444.56 3.61


18.06 249.19 18.06
1.81 51.91 1.81
0.31 87.51 0.31
0.22 238.35 0.22

- 710.52 200,188.51 710.52


- 39.47 43,420.56 39.47
- - -

28.66 24,089.71 28.66


1.19 3,918.76 1.19
2.39 8,906.28 2.39
11.06 67,957.16 11.06
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

-
- 174.62 - 174.62
40.86 14,966.73 40.86
20.43 29,216.34 20.43
20.43 33,200.39 20.43
328.33 3,283.27 328.33
231.62 2,316.16 231.62
- - -
- - -
- - -
71,789.90 196.00 71,789.90 -
16,816.80 11.76 16,816.80 -
- - -
- - -
37,330.75 101.92 37,330.75 -
8,408.40 5.88 8,408.40 -
- - -
- - -
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

26,921.21 73.50 26,921.21 -


7,007.00 4.90 7,007.00 -
- - -
let Female, Toilet Male, Of - - -
180,320.00 450.80 180,320.00 -
43,120.00 107.80 43,120.00 -
7,032.48 509.60 7,032.48 -
2,930.20 101.92 2,930.20 -
45,558.98 161.70 45,558.98 -
12,289.20 11.17 12,289.20 -
- -
- -
3,495,280.40 5,323,037.64

- -
System (Handwash Foot Bath Shoe Rack)
- -
882.05 - - (20.00)
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

2,960.10 - - (20.00)
2,242.50 - - (20.00)
4,858.75 - - (50.00)
747.50 - - (50.00)
1,345.50 - - (90.00)
86.35 - - (190.00)
47,092.50 - - (50.00)
932.88 - - (230.00)
2,344.16 - - (230.00)
12,506.00 - - (20.00)
217.67 - - (560.00)
1,509.95 - - (2.00)
4,260.75 - - (30.00)
298,116.00 - - (117.60)
37,316.10 - - (55.47)
33,988.85 - - (103.34)
32,206.56 - - (47.87)
37,964.38 - - (49.31)
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

- -
- -
System (Pantry, Lounge Room, Management
- Office, Hallway, Clinis, HR
- Office, Waitin
om, Micro Room, Laboratory, QC - -
9,261.53 26.07 1,149.83 (183.93)
48,841.65 66.08 9,779.64 (263.92)
20,182.50 48.38 5,424.31 (131.62)
75,796.50 306.78 29,811.67 (473.22)
11,661.00 306.78 4,586.41 (473.22)
22,724.00 471.97 7,056.02 (1,048.03)
1,445.25 394.80 179.43 (2,785.20)
734,643.00 96.84 91,207.04 (683.16)
15,331.68 469.29 1,903.45 (3,310.71)
38,525.76 469.29 4,783.03 (3,310.71)
206,349.00 41.30 25,823.49 (288.70)
3,673.22 1,173.23 456.04 (8,276.77)
15,854.48 2.61 1,968.36 (18.39)
68,172.00 59.59 8,463.66 (420.41)
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

298,116.00 117.60 298,116.00 -


37,316.10 55.47 37,316.10 -
33,988.85 103.34 33,988.85 -
32,206.56 47.87 32,206.56 -
37,964.38 49.31 37,964.38 -
-
-
System (Pantry, Lounge Room, Management
- Office, Hallway, Clinis, HR Office, Waitin
om, Micro Room, Laboratory, QC -
- 67.48 2,975.97 67.48
- 171.02 25,311.41 171.02
- 125.21 14,039.07 125.21
- 794.01 77,157.81 794.01
- 794.01 11,870.43 794.01
- 1,221.55 18,262.20 1,221.55
- 1,021.82 464.39 1,021.82
- 250.63 236,059.72 250.63
- 1,214.61 4,926.46 1,214.61
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

- 1,214.61 12,379.32 1,214.61


- 106.89 66,835.69 106.89
- 3,036.53 1,180.30 3,036.53
- 6.75 5,094.45 6.75
- 154.24 21,905.42 154.24
- -
- - - -
1,323.08 8.08 356.48 (21.92)
5,920.20 12.00 1,775.35 (28.00)
3,363.75 8.78 984.70 (21.22)
9,717.50 55.69 5,411.87 (44.31)
1,495.00 55.69 832.60 (44.31)
2,840.50 85.68 1,280.92 (104.32)
172.70 102.38 46.53 (277.62)
94,185.00 26.94 25,376.64 (73.06)
1,865.76 123.94 502.70 (336.06)
4,688.32 123.94 1,263.19 (336.06)
27,716.00 10.78 7,467.63 (29.22)
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

439.23 304.46 118.34 (825.54)


2,264.93 0.81 610.25 (2.19)
8,521.50 16.17 2,295.98 (43.83)
- - - -
- - - -
882.05 - - (20.00)
2,960.10 - - (20.00)
2,242.50 - - (20.00)
4,858.75 - - (50.00)
747.50 - - (50.00)
1,345.50 - - (90.00)
86.35 - - (190.00)
47,092.50 - - (50.00)
892.32 - - (220.00)
2,242.24 - - (220.00)
43,264.00 - - (160.00)
213.79 - - (550.00)
1,509.95 - - (2.00)
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

4,260.75 - - (30.00)
- - - -
- - - -
590,322.60 12.94 74,426.85 (89.72)
14,950.00 3.00 2,242.50 (17.00)
14,950.00 3.00 2,242.50 (17.00)
5,830.50 3.00 874.58 (17.00)
1,644.50 3.00 246.68 (17.00)
- - - -
- - - -
299,446.88 67.32 170,656.20 (50.81)
- - - -
47.43
25.88

- -
8.00 40,000.00 8.00
- -
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

- -
3,437,888.23 1,469,659.40
- -

EL UP HUB) - -
5,000.00 1.00 5,000.00 -
15,000.00 3.00 15,000.00 -
30,187.50 5.00 30,187.50 -
6,750.00 3.00 6,750.00 -
2,250.00 1.00 2,250.00 -
15,750.00 7.00 15,750.00 -
2,250.00 1.00 2,250.00 -
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

240,000.00 16.00 240,000.00 -


45,000.00 20.00 45,000.00 -
21,735.00 8.00 21,735.00 -
51,750.00 4.00 51,750.00 -
6,037.50 1.00 6,037.50 -
9,000.00 4.00 9,000.00 -
75,000.00 5.00 75,000.00 -
30,000.00 2.00 30,000.00 -
15,000.00 1.00 15,000.00 -
11,250.00 5.00 11,250.00 -
11,250.00 5.00 11,250.00 -
2,250.00 1.00 2,250.00 -
2,250.00 1.00 2,250.00 -
2,250.00 1.00 2,250.00 -
2,250.00 1.00 2,250.00 -
6,750.00 3.00 6,750.00 -
12,506.25 1.00 12,506.25 -
7,121.23 1.00 7,121.23 -
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

5,916.75 1.00 5,916.75 -


- -
- -
10,750.00 5.00 10,750.00 -
5,040.00 24.00 5,040.00 -
108,800.00 16.00 108,800.00 -
95,380.00 76.00 95,380.00 -
262,200.00 76.00 262,200.00 -
50,800.00 20.00 50,800.00 -
122,100.00 37.00 122,100.00 -
- - - -

652,800.00 16.00 652,800.00 -


61,200.00 2.00 61,200.00 -
122,400.00 6.00 122,400.00 -
122,400.00 3.00 122,400.00 -
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

232,425.00 1.00 232,425.00 -


431,437.50 1.00 431,437.50 -
1,414,125.00 1.00 1,414,125.00 -
- -
- -
4,326,361.73 4,326,361.73

2,000,000.00
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - -
- - -
- - -
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - - -
5,550.51 3,607,833.00 5,550.51
852.97 383,835.48 852.97

2,000,000.00 3,991,668.48
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

- -
36,000.00 9.00 16,200.00 (11.00)
21,600.00 6.00 10,800.00 (6.00)
1,500.00 1.00 1,500.00 -
13,500.00 5.00 7,500.00 (4.00)
- 3.00 - 3.00
3,000.00 4.00 600.00 (16.00)
150.00 1.00 150.00 -
3,000.00 1.00 150.00 (19.00)
3,000.00 9.00 1,350.00 (11.00)
- 2.00 - 2.00
- - - -
- - - -
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

81,750.00 38,250.00

205,785.00 242.10 205,785.00


- - - -
- - - -

350,000.00 70.00 350,000.00 -


- 12.14 993.86 12.14
- 1.02 83.52 1.02
- 36.41 2,981.58 36.41
- 12.24 1,002.21 12.24
- - - -
- - - -

72,000.00 18.00 72,000.00 -


- - - -
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

- - - -
- - - -
- - - -
- - - -
1,305,600.00 192.00 1,305,600.00 -
- - - -

22,000.00 11.00 22,000.00 -


- -
- -

1,955,385.00 1,960,446.17

101,381.72 21.00 19,950.00 (85.72)


416,981.25 - - (277.99)
48,840.00 32.56 48,840.00 -
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

809,036.38 3,149.95 1,102,483.20 838.42


- -
1,928,465.33 3,443.95 2,873,220.27 1,132.42
83,889.00 392.90 229,846.50 249.50
33,813.00 153.90 60,021.00 67.20
- 392.90 - 392.90

96,772.50 22.00 165,000.03 9.10


25,000.00 1.00 42,625.75 1.00
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

56.00 - 56.00
9.89 14,441.81 9.89
134.70 7,408.57 134.70

1.30 476.62 1.30


0.05 77.53 0.05
0.11 176.21 0.11

243.27 90,496.44 243.27


321.12 391,112.42 321.12
195.84 231,751.49 195.84
963.37 1,125,239.07 963.37
2,384.92 131,170.48 2,384.92
1,165.71 64,113.89 1,165.71
1,406.59 77,362.57 1,406.59
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

213.46 78,183.91 213.46


8.89 12,718.47 8.89
17.79 28,905.62 17.79

59.77 21,891.49 59.77


2.49 3,561.17 2.49

36.72 31,209.63
56.92 - 56.92
95.00 - 95.00
20.24 1,113.02 20.24

44.39 16,257.13 44.39


1.85 2,644.61 1.85
3.70 6,010.47 3.70
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

3,544,179.18 6,878,309.39
18,840,844.54 23,987,732.80

19,176,345.94 24,141,403.38
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

Use Grade 40 for 10mm dia. Below)

36,373.69
32,558.27 Prepared by:
97,987.87

32,558.27

12,209.35 KIM SIDRICK ESCOBAR


Sr. Quantity Surveyor
29,088.00
240,775.45
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

136,158.75
105,487.20
34,320.00

84,574.75
57,138.90
12,870.00

121,883.13
94,498.95
31,460.00

56,498.00
38,092.60
8,580.00
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

164,038.88
128,562.53
42,900.00

121,883.13
94,498.95
31,460.00

53,535.30
36,261.23
8,580.00

121,883.13
94,498.95
31,460.00

34,725.60
23,441.60
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

5,720.00

45,727.50
35,528.68
12,870.00

13,952.25
9,523.15
2,860.00

49,559.25
38,825.15
12,870.00

20,190.63
15,749.83
5,720.00
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

15,295.80
10,621.98
2,860.00

14,787.50
11,720.80
4,290.00

2,097,964.05

123,837.58
28,028.00
ing Plant
nt, Inc.
labon, Metro Manil

REVISED AS PER PLAN DATED


BID VARIATION
SEPT.2018 (RECEIVED 10-18-2018)

Total Amount QUANTITY Total Amount QUANTITY

98,352.16
22,422.40

71,789.90
16,816.80

361,246.84

4,586,063.66
2,699,802.00
2,714,200.94
VARIATION

REMARKS
Total Amount

62,520.90
74,799.00ADDITIVE IN COST
16,350.68
153,670.58

NO
- MOVEMENT IN
- COST

39,695.45
ADDITIVE IN COST
VARIATION

REMARKS
Total Amount

ADDITIVE IN COST
7,753.47

1,824.94
ADDITIVE IN COST
360.17

25,260.00
7,879.54
ADDITIVE IN COST
3,556.61
518.73

(9,264.51)
DEDUCTIVE IN COST
(1,322.49)
649.28
ADDITIVE IN COST
80.07
VARIATION

REMARKS
Total Amount

74,970.84
ADDITIVE IN COST
17,091.91

131,649.53
ADDITIVE IN COST
28,321.00

e Outdoor Tiles, Toilet Female, Toilet Male,


oom, Hallway, Changing Area
(87,860.11)
DEDUCTIVE IN COST
(19,523.85)

(71,096.00)

DEDUCTIVE IN COST
VARIATION

REMARKS
Total Amount

(757,992.00)
(1,795.30)
DEDUCTIVE IN COST
(2,628.02)
(53,046.14)
(14,319.10)

ntry, Meeting Room, Hallway, Changing Area


(340,727.11)
(8,548.98)
(4,985.42)
DEDUCTIVE IN COST
(77,785.60)
(21,082.49)

(106,902.25)
385.72
(32.34)
DEDUCTIVE IN COST
(3,416.63)
VARIATION

REMARKS
Total Amount

DEDUCTIVE IN COST

(917.06)

37,454.40ADDITIVE IN COST
VARIATION

REMARKS
Total Amount

69,397.34
11,289.13
ADDITIVE IN COST
25,657.11
297,505.47

29,376.00ADDITIVE IN COST

432,378.00ADDITIVE IN COST
VARIATION

REMARKS
Total Amount

14,045.44
2,284.82
ADDITIVE IN COST
5,192.78
60,212.60

16,785.12
32,765.99
37,234.08ADDITIVE IN COST
VARIATION

REMARKS
Total Amount

ADDITIVE IN COST
20,197.10
14,285.62

141,066.00ADDITIVE IN COST

215,093.02
ADDITIVE IN COST
46,653.32

14,923.47
ADDITIVE IN COST
4,855.31

464,630.40ADDITIVE IN COST
VARIATION

REMARKS
Total Amount

445,597.20ADDITIVE IN COST

11,086.52
1,803.49
ADDITIVE IN COST
VARIATION

REMARKS
Total Amount

ADDITIVE IN COST
4,098.83
47,527.76

17,265.95
33,704.60
38,300.68ADDITIVE IN COST
20,811.80
14,694.19

22,001.71
9,371.10
1,952.31ADDITIVE IN COST
3,290.82
VARIATION

REMARKS
Total Amount

ADDITIVE IN COST

8,963.46

1,444.56
249.19
51.91ADDITIVE IN COST
87.51
238.35

200,188.51
43,420.56ADDITIVE IN COST
-

10,497.43
1,707.66
ADDITIVE IN COST
3,881.04
45,002.33
VARIATION

REMARKS
Total Amount

-
-
14,966.73
29,216.34
33,200.39ADDITIVE IN COST
18,058.00
12,738.86
-
-
-
-
-
-
-
-
-
-
- NO
MOVEMENT IN
COST
VARIATION

REMARKS
Total Amount

NO
- MOVEMENT IN
- COST
-
-
-
-
-
-
-
-

1,845,454.15

(882.05)
VARIATION

REMARKS
Total Amount

(2,960.10)
(2,242.50)
(4,858.75)
(747.50)
(1,345.50)
(86.35)
(47,092.50)
(932.88)
(2,344.16)
DEDUCTIVE IN COST
(12,506.00)
(217.67)
(1,509.95)
(4,260.75)
(298,116.00)
(37,316.10)
(33,988.85)
(32,206.56)
(37,964.38)
VARIATION

REMARKS
Total Amount

(8,111.69)
(39,062.01)
(14,758.19)
(45,984.83)
(7,074.59)
(15,667.98)
(1,265.82)
DEDUCTIVE IN COST
(643,435.96)
(13,428.23)
(33,742.73)
(180,525.51)
(3,217.18)
(13,886.12)
(59,708.34)
VARIATION

REMARKS
Total Amount

-
- NO
- MOVEMENT IN
- COST
-

2,975.97
25,311.41
14,039.07
77,157.81
11,870.43
18,262.20
464.39
ADDITIVE IN COST
236,059.72
4,926.46
VARIATION

REMARKS
Total Amount

ADDITIVE IN COST

12,379.32
66,835.69
1,180.30
5,094.45
21,905.42

-
(966.59)
(4,144.85)
(2,379.05)
(4,305.63)
(662.40)
(1,559.58)
(126.17)
DEDUCTIVE IN COST
(68,808.36)
(1,363.06)
(3,425.13)
(20,248.37)
VARIATION

DEDUCTIVE IN COST
REMARKS
Total Amount

(320.89)
(1,654.68)
(6,225.52)
-
-
(882.05)
(2,960.10)
(2,242.50)
(4,858.75)
(747.50)
(1,345.50)
(86.35)
DEDUCTIVE IN COST
(47,092.50)
(892.32)
(2,242.24)
(43,264.00)
(213.79)
(1,509.95)
VARIATION

DEDUCTIVE IN COST

REMARKS
Total Amount

(4,260.75)

-
(515,895.75)
(12,707.50)
(12,707.50)
DEDUCTIVE IN COST
(4,955.93)
(1,397.83)

(128,790.68)
DEDUCTIVE IN COST
-

40,000.00ADDITIVE IN COST
VARIATION

REMARKS
Total Amount

(1,968,228.84)

-
-
-
-
-
-
-
VARIATION

REMARKS
Total Amount

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- NO
MOVEMENT IN
- COST
-
VARIATION

REMARKS
Total Amount
NO
MOVEMENT IN
COST

-
-
-
-
-
-
-
-

-
-
-
-
NO
MOVEMENT IN
COST

VARIATION

REMARKS
Total Amount

-
-
-
-
-

-
-
-
-
-
-
-
-
-
NO
MOVEMENT IN
COST
VARIATION

REMARKS
Total Amount

- NO
- MOVEMENT IN
- COST
-
-
-
-
-
-
-
-
-
-
3,607,833.00
ADDITIVE IN CO
383,835.48

3,991,668.48
VARIATION

REMARKS
Total Amount

(19,800.00)
(10,800.00)
-
(6,000.00)
DEDUCTIVE IN
-
COST
(2,400.00)
-
(2,850.00)
(1,650.00)
-
-
-
VARIATION

REMARKS
Total Amount

(43,500.00)

NO
MOVEMENT IN
- COST
-

-
993.86
83.52
ADDITIVE IN COST
2,981.58
1,002.21
-
-

-
-
VARIATION

REMARKS
Total Amount

-
-
-
- NO
MOVEMENT IN
- COST
-
-
-

5,061.17

(81,431.72)
DEDUCTIVE IN COST
(416,981.25)
-
VARIATION

REMARKS
Total Amount

293,446.83
-
944,754.94ADDITIVE IN COST
145,957.50
26,208.00
-

68,227.53
ADDITIVE IN COST
17,625.75
VARIATION

REMARKS
Total Amount

4,031.86
14,441.81ADDITIVE IN COST
7,408.57

476.62
77.53ADDITIVE IN COST
176.21

90,496.44
391,112.42
231,751.49
1,125,239.07ADDITIVE IN COST
131,170.48
64,113.89
77,362.57
VARIATION

REMARKS
Total Amount

78,183.91
12,718.47ADDITIVE IN COST
28,905.62

21,891.49
ADDITIVE IN COST
3,561.17

31,209.63
4,097.95
ADDITIVE IN COST
6,840.00
1,113.02

16,257.13
2,644.61ADDITIVE IN COST
6,010.47
VARIATION

REMARKS
Total Amount

3,349,100.02
7,333,225.56
VARIATION

REMARKS
Total Amount

###

7,333,225.56
###

CARMELO PESIGAN
Operations Manager
PROJECT : Proposed 2-Storey Residential Building
OWNER : Metrostar Realty and Development
LOCATION : Brgy. Bagong Silangan, Quezon City
SUBJECT : BILL OF QUANTITIES FOR MODEL - 1 UN
DATE :

ITEM NO. ITEM DESCRIPTION MATERIALS


QUANTITY UNIT
Unit Cost
ESTIMATED QUANTITY FOR LABOR AND MATERIALS
1.0 Preliminaries
1.01 Mobilization and Demobilization 1.00 lot
1.02 Temporary Power and Water Supply 1.00 lot
1.03 Temporary Facilities 1.00 lot
1.04 Construction / As Built Plans 1.00 lot
1.05 Materials Testing 1.00 lot
SUB-TOTAL
2.0 Site Works / Earth Works
2.01 Excavation 31.95 cu.m.
2.02 Backfill and Soil Compaction 24.70 cu.m.
2.03 Disposal 10.15 cu.m.
2.04 Soil Poisoning
Area 86.60 sq.m.
bottle 1.00 lit.
2.05 Vapor Barrier 42.15 sq.m.
2.06 Gravel Bedding 7.06 cu.m.
SUB-TOTAL
3.0 Structural
3.01 CONCRETE WORKS
3.01.01 Column Footing & Wall Footing 3.01 cu.m.
3.01.02 Tie Beam 1.84 cu.m.
3.01.03 Columns 5.18 cu.m.
3.01.04 2nd Floor Beam 3.22 cu.m.
3.01.05 Roof Beams Including Structures Above 1.96 cu.m.
3.01.06 Slab On Grade (Interion & Exterior) 2500 5.55 cu.m.
3.01.07 Suspended Slab 2.30 cu.m.
3.01.08 Stair 1.29 cu.m.
3.01.09 Stiffener Door Opening 0.77 cu.m.
3.01.10 Lintel Beam 2.14 cu.m.
3.01.11 Ledges and Fins 1.10 cu.m.
3.02 REINFORCEMENT BARS
3.02.01 Column Footing & Wall Footing
12 mm. diameter 33.00 pcs.
10 mm. diameter 26.00 pcs.
3.02.02 Tie Beam
16 mm. diameter 13.50 pcs.
12 mm. diameter 19.50 pcs.
10 mm. diameter 50.00 pcs.
3.02.03 Columns and Planted Col.
12 mm. diameter 104.00 pcs.
10 mm. diameter 116.00 pcs.
3.02.04 2nd Floor Beam
16 mm. diameter 21.00 pcs.
12 mm. diameter 31.00 pcs.
10 mm. diameter 75.00 pcs.
3.02.05 Roof Beams Including Structures Above
12 mm. diameter 24.00 pcs.
10 mm. diameter 46.00 pcs.
3.02.06 Slab On Grade (SOG)
10 mm. diameter 57.00 pcs.
3.02.07 Suspended Slab
10 mm. diameter 92.00 pcs.
3.02.08 Stair
12 mm. diameter 14.00 pcs.
10 mm. diameter 24.00 pcs.
3.02.09 Stiffener Col;umn
12 mm. diameter N/A pcs.
10 mm. diameter N/A pcs.
3.02.10 Lintel Beam
12 mm. diameter 20.00 pcs.
10 mm. diameter 16.00 pcs.
3.02.11 Ledges and Fins
12 mm. diameter 26.00 pcs.
10 mm. diameter 10.00 pcs.
Vertical Horizontal Window & Door Openings
16 mm. diameter 16.00 pcs.
3.02.12 Masonry RSB Dowels, & other extra bars
as compliance for spec. requirement
10 mm. diameter 10.00 pcs.
3.03 FOIRMS AND BRACES
3.03.01 Tie Beam 24.50 sq.m.
3.03.02 Columns 79.24 sq.m.
3.03.03 2nd Floor Beam 40.90 sq.m.
3.03.04 Roof Beams 45.80 sq.m.
3.03.05 Stair 18.20 sq.m.
3.03.06 Stiffener Col;umn 9.03 sq.m.
3.03.07 Lintel Beam 37.02 sq.m.
3.03.08 Ledges and Fins 15.03 sq.m.
3.03.09 Others
Metal Decking (For Suspended Slab) 26.50 sq.m.
1250 mm. x 3300 mm.
2450 mm. x 3300 mm.
1350 mm. x 3300 mm.
950 mm. x 1350 mm.
1850 mm. x 2800 mm.
3.04 CONTINGENCIES
3.04.01 (Tie Wires , Welding Rod, Cutting Disc,
Concrete bond, Form oil & otheres) 1.00 lot
SUB-TOTAL
4.0 Masonry Works
4.01 CHB Laying
150 mm. Thick 2,098.00 pcs.
100 mm. Thick 219.00 pcs.
4.02 Rough Plastering 189.20 sq.m.
4.03 Skim Coating / Smooth Plastering
Exterior Walls 238.85 sq.m.
Interior Walls 131.20 sq.m.
4.04 Rub Concrete
Exterior Walls 45.40 sq.m.
Interior Walls 27.24 sq.m.
4.05 Finishing of Window Opening Corners 33.80 lm.
4.07 Floor & Wall Finishing
Homogeneous Floor Tiles 28.60 sq.m.
Laminated Wood Planks 23.35 sq.m.
Black Pebbles 13.80 sq.m.
T & B tiles
Floor 4.80 sq.m.
Wall 30.82 sq.m.
4.08 STP Construction
100 mm. CHB Laying 13.80 pcs.
Rough Plastering 10.80 sq.m.
Gravel Bedding 0.35 cu.m.
Forms 2.30 sq.m.
RSB 10 mm. daimeter 33.00 pcs.
Concrete 0.63 cu.m.
4.09 Contingencies 1.00 lot
SUB-TOTAL
5.0 Roofing and Metal Works
5.01 Roof Trusses
Roof Sheet Panels, 1.0 m. width
5.25 m. length 9.00 pcs.
3.50 m. length 5.00 pcs.
Roof Gutter, 8' (8.85 m.) 4.00 pcs.
Ridge Roll and Flashing 8' (3.50 m.) 4.00 pcs.
Top & Bot. Chord (50mm x 50mm x 6.35 mm, 7.00 pcs.
Web Members (38 mm x 38 mm x 6.35 mm t 3.00 pcs.
Sagrods 12 mm diameter 2.00 pcs.
50 mm x 100 mm x 1.5 mm thk. Purlins 16.00 pcs.
Aluminum Insulation 1.20 m. width 60.00 lm.
5.02 Stair Railing
Hand Rail & Post 1 1/2" dia.BI Pipe 3.00 pcs.
Flat Bars 6.00 pcs.
5.03 Contingecieis 1.00 lot
SUB-TOTAL
6.0 Carpentry Works
6.01 Dry Wall Partition 27.65 sq.m.
6.02 Ceiling Works
Gypsum Board 52.00 sq.m.
Ficem Board 4.80 sq.m.
Ceiling Eaves 21.10 sq.m.
Vent Eaves 6.00 set
6.03 Stair Wood Planks
0.90 x 0.30 m. 13.00 pcs.
Triangle shape 3.00 pcs.
6.04 Carcass Cabinets Installation 4.00 sets
6.05 Fascia Board 8.70 lm.
6.06 Wooden Door Jambs & Door Panels
Wood Doors 3.00 sets
Steel Doors 2.00 sets
PVC Doors 2.00 sets
6.07 Stair Wood Hand Rail 7.20 lm.
SUB-TOTAL
7.0 Water Proofing
7.01 Membrane Waterproofing 6.50 sq.m.
7.02 Flexibond Application 78.90 sq.m.
SUB-TOTAL
8.0 Painting Works
8.01 Exterior Masonry Wall Paint 238.85 sq.m.
8.02 Exterior Ceiling Paint 21.10 sq.m.
8.03 Interior Masonry Wall Paint 131.20 sq.m.
8.04 Dry Wall Partition 55.30 sq.m.
8.05 Gypsum Board Ceiling Paint 52.00 sq.m.
8.06 Ficem Bd. Ceiling Paint 4.80 sq.m.
8.07 Carcass Cabinets 4.00 sets
8.08 Metal Surfaces
Roof Sheet & Gutter 1.00 lot
Stair Railings 1.00 lot
8.09 Wooden Doors and Door Jambs 3.00 sets
8.10 Wooden Stair Planks Area per pc. = 0.27 sq. 16.00 pcs.
8.11 Stair Handrail 7.20 lm.
SUB-TOTAL
9.0 Plumbing Works
9.01 Plumbing Roughing in
9.01.01 Water Line
25 mm. dia. PPR Pipe 9.00 pcs.
15 mm. dia. PPR Pipe 2.00 pcs.
25 mm. dia. PPR Elbow 8.00 pcs.
25 mm. dia. Tee-Pipe 6.00 pcs.
15 mm. dia. PPR Elbow 6.00 pcs.
15 mm. dia. Tee-Pipe 2.00 pcs.
25 mm. coupling reducer 5.00 pcs.
9.01.02 Sewer Line
100 mm. dia. PVC Pipe 9.00 pcs.
100 mm. dia. Elbow 4.00 pcs.
100 mm. dia. T-Pipe 6.00 pcs.
100 mm. dia. C.O. 8.00 pcs.
100 mm. dia. Y-wye pipe 4.00 pcs.
9.01.03 Storm Drain & Drainage Line
100 mm. dias. Pipe 7.00 pcs.
100 mm. dia. Elbow 10.00 pcs.
100 mm. dia T-Pipe 2.00 pcs.
50 mm. dia. Pipe 4.00 pcs.
50 mm. Dia. Elbow 6.00 pcs.
50 mm. dia. T-Pipe 2.00 pcs.
50 mm. dia. P-Trap 2.00 pcs.
9.01.04 Construction of

9.02 Plumbing Fixtures Installation


9.02.01 Water Closet 2.00 sets
9.02.02 Lavatory Including Lav. Faucet 2.00 sets
9.02.03 Tissue and Soap Holder 2.00 sets
9.02.04 Shower Set 2.00 sets
9.02.05 Shower Mixer 2.00 sets
9.02.06 T&B / Shower Floor Drain 2.00 sets
9.02.07 Kitchen Sink Including Kitchen Faucet & 1.00 sets

SUB-TOTAL
10.0 Electrical Works
10.01 Electrical Roughing In
1" dia. PVC Pipe 3.00 pcs.
3/4" PVC Pipe 20.00 pcs.
1/2" PVC Pipe 75.00 pcs.
Junction Box 50.00 pcs.
Utility Box 30.00 pcs.
1" RSC Piupe 1.00 pcs.
1" Entrance Cap 1.00 pcs.
1" Locknut Bushing 1.00 pcs.
10.02 Panel Board and Circuit Breaker 1.00 pcs.
10.03 Electrical Wires and Devices
2.0 mm dia. THHN Wire 3.00 box
3.5 mm dia. THHN Wire 4.00 box
5.5 mm. dia THHN Wire 1.00 box
10.04 Electrical lighting fixtures instrallation
Surface Mounted pinlights 2.00 units
Circuit Pinlight with glass cover 5.00 units
Circular Pinlight without glass 8.00 units
10.05 Outlets
WeatherProof 2.00 units
Counter Height 1.00 units
Range Hood 2.00 units
Convenience 10.00 units
Refrigerator 1.00 units
CCTV 2.00 units
Water Heater 1.00 units
ACU 2.00 units
Telephone 2.00 units
SUB-TOTAL

GRAND TOTAL

GRAND TOTAL (VAT INCLUSIVE)

Submitted By:
y Residential Building
and Development
ngan, Quezon City
ES FOR MODEL - 1 UNIT

MATERIALS LABOR
Total Amount
Unit Cost Unit Cost
OR AND MATERIALS

-
PROJECT : Proposed 2-Storey Residential Building
OWNER : Metrostar Realty and Development
LOCATION : Brgy. Bagong Silangan, Quezon City
SUBJECT : BILL OF QUANTITIES FOR MODEL - 2 UN
DATE :

ITEM NO. ITEM DESCRIPTION MATERIALS


QUANTITY UNIT
Unit Cost
ESTIMATED QUANTITY FOR LABOR AND MATERIALS
1.0 Preliminaries
1.01 Mobilization and Demobilization lot 1.00
1.02 Temporary Power and Water Supply lot 1.00
1.03 Temporary Facilities lot 1.00
1.04 Construction / As Built Plans lot 1.00
1.05 Materials Testing lot 1.00
SUB-TOTAL
2.0 Site Works / Earth Works
2.01 Excavation cu.m. 31.95
2.02 Backfill and Soil Compaction cu.m. 24.70
2.03 Disposal cu.m. 10.15
2.04 Soil Poisoning
Area sq.m. 86.60
bottle lit. 1.00
2.05 Vapor Barrier sq.m. 42.15
2.06 Gravel Bedding cu.m. 7.06
SUB-TOTAL
3.0 Structural
3.01 CONCRETE WORKS
3.01.01 Column Footing & Wall Footing cu.m. 3.01
3.01.02 Tie Beam cu.m. 1.84
3.01.03 Columns cu.m. 5.18
3.01.04 2nd Floor Beam cu.m. 3.22
3.01.05 Roof Beams Including Structures Above cu.m. 1.96
3.01.06 Slab On Grade (Interion & Exterior) 2500 PSI cu.m. 5.55
3.01.07 Suspended Slab cu.m. 2.30
3.01.08 Stair cu.m. 1.29
3.01.09 Stiffener Door Opening cu.m. 0.77
3.01.10 Lintel Beam cu.m. 2.14
3.01.11 Ledges and Fins cu.m. 1.10
3.02 REINFORCEMENT BARS
3.02.01 Column Footing & Wall Footing
12 mm. diameter pcs. 33.00
10 mm. diameter pcs. 26.00
3.02.02 Tie Beam
16 mm. diameter pcs. 13.50
12 mm. diameter pcs. 19.50
10 mm. diameter pcs. 50.00
3.02.03 Columns and Planted Col.
12 mm. diameter pcs. 104.00
10 mm. diameter pcs. 116.00
3.02.04 2nd Floor Beam
16 mm. diameter pcs. 21.00
12 mm. diameter pcs. 31.00
10 mm. diameter pcs. 75.00
3.02.05 Roof Beams Including Structures Above
12 mm. diameter pcs. 24.00
10 mm. diameter pcs. 46.00
3.02.06 Slab On Grade (SOG)
10 mm. diameter pcs. 57.00
3.02.07 Suspended Slab
10 mm. diameter pcs. 92.00
3.02.08 Stair
12 mm. diameter pcs. 14.00
10 mm. diameter pcs. 24.00
3.02.09 Stiffener Col;umn
12 mm. diameter pcs. N/A
10 mm. diameter pcs. N/A
3.02.10 Lintel Beam
12 mm. diameter pcs. 20.00
10 mm. diameter pcs. 16.00
3.02.11 Ledges and Fins
12 mm. diameter pcs. 26.00
10 mm. diameter pcs. 10.00
Vertical Horizontal Window & Door Openings
16 mm. diameter pcs. 16.00
3.02.12 Masonry RSB Dowels, & other extra bars
as compliance for spec. requirement
10 mm. diameter pcs. 10.00
3.03 FOIRMS AND BRACES
3.03.01 Tie Beam sq.m. 24.50
3.03.02 Columns sq.m. 79.24
3.03.03 2nd Floor Beam sq.m. 40.90
3.03.04 Roof Beams sq.m. 45.80
3.03.05 Stair sq.m. 18.20
3.03.06 Stiffener Col;umn sq.m. 9.03
3.03.07 Lintel Beam sq.m. 37.02
3.03.08 Ledges and Fins sq.m. 15.03
3.03.09 Others
Metal Decking (For Suspended Slab) sq.m. 26.50
1250 mm. x 3300 mm.
2450 mm. x 3300 mm.
1350 mm. x 3300 mm.
950 mm. x 1350 mm.
1850 mm. x 2800 mm.
3.04 CONTINGENCIES
3.04.01 (Tie Wires , Welding Rod, Cutting Disc,
Concrete bond, Form oil & otheres) lot 1.00
SUB-TOTAL
4.0 Masonry Works
4.01 CHB Laying
150 mm. Thick pcs. 2,098.00
100 mm. Thick pcs. 219.00
4.02 Rough Plastering sq.m. 189.20
4.03 Skim Coating / Smooth Plastering
Exterior Walls sq.m. 238.85
Interior Walls sq.m. 131.20
4.04 Rub Concrete
Exterior Walls sq.m. 45.40
Interior Walls sq.m. 27.24
4.05 Finishing of Window Opening Corners lm. 33.80
4.07 Floor & Wall Finishing
Homogeneous Floor Tiles sq.m. 28.60
Laminated Wood Planks sq.m. 23.35
Black Pebbles sq.m. 13.80
T & B tiles
Floor sq.m. 4.80
Wall sq.m. 30.82
4.08 STP Construction
100 mm. CHB Laying pcs. 13.80
Rough Plastering sq.m. 10.80
Gravel Bedding cu.m. 0.35
Forms sq.m. 2.30
RSB 10 mm. daimeter pcs. 33.00
Concrete cu.m. 0.63
4.09 Contingencies lot 1.00
SUB-TOTAL
5.0 Roofing and Metal Works
5.01 Roof Trusses
Roof Sheet Panels, 1.0 m. width
5.25 m. length pcs. 9.00
3.50 m. length pcs. 5.00
Roof Gutter, 8' (8.85 m.) pcs. 4.00
Ridge Roll and Flashing 8' (3.50 m.) pcs. 4.00
Top & Bot. Chord (50mm x 50mm x 6.35 mm, thk.) pcs. 7.00
Web Members (38 mm x 38 mm x 6.35 mm thk.) pcs. 3.00
Sagrods 12 mm diameter pcs. 2.00
50 mm x 100 mm x 1.5 mm thk. Purlins pcs. 16.00
Aluminum Insulation 1.20 m. width lm. 60.00
5.02 Stair Railing
Hand Rail & Post 1 1/2" dia.BI Pipe pcs. 3.00
Flat Bars pcs. 6.00
5.03 Contingecieis lot 1.00
SUB-TOTAL
6.0 Carpentry Works
6.01 Dry Wall Partition sq.m. 27.65
6.02 Ceiling Works
Gypsum Board sq.m. 52.00
Ficem Board sq.m. 4.80
Ceiling Eaves sq.m. 21.10
Vent Eaves set 6.00
6.03 Stair Wood Planks
0.90 x 0.30 m. pcs. 13.00
Triangle shape pcs. 3.00
6.04 Carcass Cabinets Installation sets 4.00
6.05 Fascia Board lm. 8.70
6.06 Wooden Door Jambs & Door Panels
Wood Doors sets 3.00
Steel Doors sets 2.00
PVC Doors sets 2.00
6.07 Stair Wood Hand Rail lm. 7.20
SUB-TOTAL
7.0 Water Proofing
7.01 Membrane Waterproofing sq.m. 6.50
7.02 Flexibond Application sq.m. 78.90
SUB-TOTAL
8.0 Painting Works
8.01 Exterior Masonry Wall Paint sq.m. 238.85
8.02 Exterior Ceiling Paint sq.m. 21.10
8.03 Interior Masonry Wall Paint sq.m. 131.20
8.04 Dry Wall Partition sq.m. 55.30
8.05 Gypsum Board Ceiling Paint sq.m. 52.00
8.06 Ficem Bd. Ceiling Paint sq.m. 4.80
8.07 Carcass Cabinets sets 4.00
8.08 Metal Surfaces
Roof Sheet & Gutter lot 1.00
Stair Railings lot 1.00
8.09 Wooden Doors and Door Jambs sets 3.00
8.10 Wooden Stair Planks Area per pc. = 0.27 sq.m. pcs. 16.00
8.11 Stair Handrail lm. 7.20
SUB-TOTAL
9.0 Plumbing Works
9.01 Plumbing Roughing in
9.01.01 Water Line
25 mm. dia. PPR Pipe pcs. 9.00
15 mm. dia. PPR Pipe pcs. 2.00
25 mm. dia. PPR Elbow pcs. 8.00
25 mm. dia. Tee-Pipe pcs. 6.00
15 mm. dia. PPR Elbow pcs. 6.00
15 mm. dia. Tee-Pipe pcs. 2.00
25 mm. coupling reducer pcs. 5.00
9.01.02 Sewer Line
100 mm. dia. PVC Pipe pcs. 9.00
100 mm. dia. Elbow pcs. 4.00
100 mm. dia. T-Pipe pcs. 6.00
100 mm. dia. C.O. pcs. 8.00
100 mm. dia. Y-wye pipe pcs. 4.00
9.01.03 Storm Drain & Drainage Line
100 mm. dias. Pipe pcs. 7.00
100 mm. dia. Elbow pcs. 10.00
100 mm. dia T-Pipe pcs. 2.00
50 mm. dia. Pipe pcs. 4.00
50 mm. Dia. Elbow pcs. 6.00
50 mm. dia. T-Pipe pcs. 2.00
50 mm. dia. P-Trap pcs. 2.00
9.01.04 Construction of

9.02 Plumbing Fixtures Installation


9.02.01 Water Closet sets 2.00
9.02.02 Lavatory Including Lav. Faucet sets 2.00
9.02.03 Tissue and Soap Holder sets 2.00
9.02.04 Shower Set sets 2.00
9.02.05 Shower Mixer sets 2.00
9.02.06 T&B / Shower Floor Drain sets 2.00
9.02.07 Kitchen Sink Including Kitchen Faucet & Hose Bibb sets 1.00

SUB-TOTAL
10.0 Electrical Works
10.01 Electrical Roughing In
1" dia. PVC Pipe pcs. 3.00
3/4" PVC Pipe pcs. 20.00
1/2" PVC Pipe pcs. 75.00
Junction Box pcs. 50.00
Utility Box pcs. 30.00
1" RSC Piupe pcs. 1.00
1" Entrance Cap pcs. 1.00
1" Locknut Bushing pcs. 1.00
10.02 Panel Board and Circuit Breaker pcs. 1.00
10.03 Electrical Wires and Devices
2.0 mm dia. THHN Wire box 3.00
3.5 mm dia. THHN Wire box 4.00
5.5 mm. dia THHN Wire box 1.00
10.04 Electrical lighting fixtures instrallation
Surface Mounted pinlights units 2.00
Circuit Pinlight with glass cover units 5.00
Circular Pinlight without glass units 8.00
10.05 Outlets
WeatherProof units 2.00
Counter Height units 1.00
Range Hood units 2.00
Convenience units 10.00
Refrigerator units 1.00
CCTV units 2.00
Water Heater units 1.00
ACU units 2.00
Telephone units 2.00
SUB-TOTAL

GRAND TOTAL

GRAND TOTAL (VAT INCLUSIVE)

Submitted By:
y Residential Building
and Development
ngan, Quezon City
ES FOR MODEL - 2 UNIT

MATERIALS LABOR
Total Amount
Unit Cost Unit Cost
OR AND MATERIALS

Anda mungkin juga menyukai