Design problem
Design a suitable vessel for storing 10 ton LPG (Liquefied Petroleum Gas) at a temperature of 25 ○. Consider
LPG to be a mixture of propane and butane in the ratio 9.5:1. The shape and the material of construction of
the vessel are to be selected. The vessel should be provided with a suitable head (cover), required number
of nozzle, suitable joints and supports. The design report should contain:
1
2. Design of the internals
A) Estimation of saturation vapour pressure of n-propane and n- butane at 298K
𝐵
log10Psat = A - 𝑇+𝐶
where Psat is saturated vapour pressure (torr)
T is temperature in ○C
A, B, C is Antonie Constant
Table-1
Substance A B C
n- propane 6.82972 813.20 248
n-butane 6.83029 945.9 240
Hence
sat
Ppropane = 9.45 bar
sat
Pbutane = 2.43 bar
B) Estimating the number of moles and the mole fraction of n-propane and n-butane
In LPG weight ratio is given as 9.5:1
Assuming ideal solution
Total capacity 10 ton = 10000 kg
Table-2
2
9.5×10000
Amount of propane = kg
9.5+1
= 9047.6 kg
1×10000
Amount of butane = kg
1+9.5
= 952.38 kg
9047.6×10000
Moles of propane =
40.097
ηpropane = 225642.8
952.38×10000
Moles of butane = 58.123
ηbutane = 16385.59
225642.8
Mole fraction of propane (yp) =
225642.8+16385.59
yp = 0.88
Hence yp = 0.88
yb = 0.12
sat
Pmix = Partial pressure of the above liquid
sat sat
= yp Ppropane + yb Pbutane
= (0.88× 9.45) + (0.12 × 2.43)
= 8.60 bar
An allowance of 5% of the working pressure is added to the working pressure to obtain the design
pressure.
Design pressure = working pressure + 5% allowance pressure
= 9.03 bar
3
= (0.88× 369.8) + (0.12 × 425.1)
= 376.436K
TCM = 376.436K
Trm = 0.79
= ypPCP + ybPCB
= (0.88× 42.48) + (0.12 × 37.96)
= 41.93 bar
G) Calculation of reduced pressure of the mixture
Prm = reduced pressure of the mixture
𝑃
=
𝑃𝐶𝑀
9.03
=
41.93
Prm = 0.215
H) Calculation of density
Using Lydersen, Greenkorn and Hougen correlation :
ρ𝑀 𝑉𝐶𝑀
ρr = =
ρ𝐶𝑀 𝑉𝑀
ρr = reduced density
ρ𝑀 = density of the mixture
ρ𝐶𝑀 = critical density of the mixture
VCM = critical volume of the mixture
VM = volume of the mixture
Average molecular weight of the mixture = Mav
4
Mav = ypMpropane + ybMbutane
= 4.87×10-3 mol.cm-3
Then ρ𝐶𝑀 = (4.87×10-3 mol.cm-3) × Mav
= (4.87×10-3 mol.cm-3) × (45.78 gm.mol-1)
= 0.2229 gm.cm-3
= 222.9 kg.m-3
ρ𝑀 = ρ𝐶𝑀 × ρr
= 222.9 kg.m-3 × 2.5
= 557.25 kg.m-3
= 0.557 g.cm-3
Hence
ρ𝑀 = 0.557 g.cm-3
= 17.94 m3
5
VM = 17.94 m3
Several iteration are performed to obtain Dcalculated from Lcalculated. A few of them are shown here
L (assumed) D (calculated)
12 1.37
11 1.43
10 1.50
9 1.59
So we choose
L = 11 m
D = 1.45 m
= 18.16 m3
volume of the mixture
Total number of vessel required = N =
volume of the each vessel
6
17.94
N=
18.16
N = 0.98 ~ 1
Hence
N=1
3. Mechanical design
PD
Circumferential Stress, fp =
2t
PD
Longitudinal Stress, fa =
4t
P = internal pressure
D = mean internal diameter of the shell
Both the above stresses are tensile, since the circumferential stress is greater; this is taken as the design
pressure. The shell is generally formed by a joint in the longitudinal direction, which is consider in terms
of joint efficiency.
PD PDi PDo
t= = =
2fJ 2fJ−P 2fJ+P
P = design pressure
D = mean diameter
J = Joint efficiency
f = design or permissible stress at design temperature
Di = internal diameter
Do = outside diameter
7
Permissible stress at 35℃ ∶
f = allowable stress = 160 N/mm2
J = Joint efficiency = 0.85 [Joshi: Process Equipment Design; Table E-2]
PDi
t=
2fJ−P
0.903 N/mm2 ×1450 mm
= (2×160×0.85−0.903)
N/mm2
= 4.82 mm
t = 4.82mm
PDo
Also t= [Joshi: Process Equipment Design, Equation 6.3, Page - 128]
2fJ+P
For vessel diameter 1-2m, minimum shell thickness must be 7mm. this value include a corrosion allowance
of 2mm.
Hence, outer diameter Do = Di + 2t
= 1450 + (2× 7)
= 1464 mm
Do = 1464 mm
Calculation of stresses
[Joshi: Process Equipment Design; 6.8.1.2; Page-129]
Stress in circumferential direction due to internal pressure, fp. This is also known as tangential or hoop stress.
P (Di +t)
ft =
2t
N
(0.903 ) ×(1450+7)
mm2
=
2×7
= 93.97 N/mm2
ft =93.97 N/mm2
PDi
f1 = (tensile)
4t
N
0.903 2 ×1450
mm
f1 =
4×7
f1 = 46.76 N/mm2
8
b. Due to weight of the vessel and contents (vertical only) –
𝑊
f2 = (compressive)
𝜋𝑡(Di +𝑡)
10000kg ×10 m/s2
f2 =
π × 7 ×(1450+7)
f2 = 3.12 N/mm2
Combining the stresses on the basis of shear strain energy theory criterions, the equivalent stress is–
1⁄
2
fR = [(f2t − ft fa + f2a + 3f2s ] [Joshi: Process Equipment Design; Equation 6.11]
c) Design of head
PRc W
th = [Joshi: Process Equipment Design; Equation 6.23]
2fJ
Where, P = design pressure
R c = Crown radius
9
W = stress intensification factor
1 R
= 4 (3 + √Rc )
1
R1 = knuckle radius
= 6% of Di
= 0.06 × 1450
= 87 mm
For crown radius (R c ), it is equal to or less than the diameter of the head.
R c = Di = 1450 mm
Then
1 R
W = 4 (3 + √Rc )
1
1 1450
= 4 (3 + √ )
87
= 1.77
PRc W
th =
2fJ
N
0.903×1450×1.77
mm2
=
2×160×0.85
= 8.52
However, a standard value is chosen for designing purpose of th = 10 mm
d) Design of nozzles
As in the pressure vessel, the total diameter Do = 1470 mm = 57.87 inch
According to IS 2825, for Do> 39 inch;
Internal diameter of nozzle ID = 10 inch
Nozzle thickness is taken as th = 6mm
Hence, Do = 254 mm + (2× 6) mm [10 inch = 254 mm]
= 266 mm
e) Gasket design
Gasket are used to make the metal to metal surface leak proof. Gasket are elasto-plastic material and
relatively softer than the flange material. A preliminary estimation of gasket is done using the following
expression:
Residual gasket force = (Gasket seating force) – (Hydrostatic pressure force)
The residual gasket force should be greater than that required to prevent the leakage of internal fluid.
This condition results the final expression in the form of –
10
DOG Y−pm
=√ [Joshi: Process Equipment Design; page-174]
DIG Y−p(m+1)
𝑤ℎ𝑒𝑟𝑒, DOG = outside gasket diameter
DIG = inside gasket diameter
p = design pressure
Y = minimum design seating stress
m = gasket factor
From the above equation we get outside gasket diameter 1490 mm for a flat asbestos gasket of internal
diameter 1450 mm and 3.2 mm thickness is used to cover the raised face.
1490−1450
Width of the gasket = = 20 mm
2
1 DOG −DIG
Basic gasket setting width, bo = [Joshi: Process Equipment Design; Table-6.7]
2 2
1 1490−1450
=
2 2
= 10 mm
Since bo > 6.3 mm [Joshi: Process Equipment Design; page-175; fig: 6.33]
The gasket is compressed under tight pressure. So required bolt load is given by –
π
Wm2 = π(2b)Gmp + 4 G2 p [Joshi: Process Equipment Design; page-175; fig: 6.37]
Where, 2b = effective gasket or joint contact surface width under pressure
m = gasket factor
p = design pressure
11
π
Wm2 = π(2b)Gmp + 4 G2 p
𝜋
= (𝜋 × 2 × 7.9 × 1470 × 2 × 0.903) + ( 4 × 14702 × 0.903)
= 1664.319 KN
Wm1 Wm2
To calculate the required (minimum) bolt cross-sectional area, Am1 = and Am1 =
fa fb
[Joshi: Process Equipment Design; page-175; fig: 6.38]
Wm1 Wm2
Therefore, Am1 = and Am2 =
fa fb
408.613 KN 1664.319 𝐾𝑁
= =
58.7 N/mm2 54.5 N/mm2
= 69.610 cm2 = 305.37 cm2
Since, Am2 > Am1, we consider Am2 is the cross section of the bolt.
The total number of the bolts may be approximately equal to mean diameter of gasket in cm
divided by 2.5 and should be multiple of 4.
1470
Number of bolts, nb =
10×2.5
= 58.8
~ 60 (𝑎𝑠 𝑖𝑡 𝑠ℎ𝑜𝑢𝑙𝑑 𝑏𝑒 𝑚𝑢𝑙𝑡𝑖𝑝𝑙𝑒 𝑜𝑓 4)
nb = 60 since 60 is multiplied of 4
π
Area of the bolts, Am2 = D2 nb
4
Am2×4
D=√
π×nb
305.37×4
=√
𝜋×60
= 2.54 cm
Specification:
Using M/8 bolts
Pitch diameter: 16.375 mm
Minor diameter: 14.480 mm
12
𝜋 1 16.3752 14.482
Actual Bolt area = [ + ] × 60
42 102 102
= 112.58 cm2
Bolt area is given by –
2πGNYa
Ab = [Joshi: Process Equipment Design; page-176; Equation-6.40]
fa
N
2𝜋×11.2 ×1470mm×20mm
mm2
= N
58.7
mm2
= 352.45 cm2
The bolt area suggested hence satisfactory.
Outside diameter of the flange = Pitch circle diameter + (2× bolt diameter)
= 1553 + (2× 25.4 mm)
= 1603.8 mm
g) Design of flange
Flange thickness is given by –
p
tf = G√Kf + C [Joshi: Process Equipment Design; Equation-6.41]
1
Where, K= 1.5 Wm hG
[0.3+ ]
HG
= 1532.54 KN
13
Now Wm = Wm1 + Wm2
= (408.613 + 1664.319) KN
= 2072.932 KN
Therefore
1
K= 1.5 Wm hG
[0.3+ HG ]
1
= 1.5×2072.932×31.5
[0.3+ 1532.4×1470 ]
= 2.91
Then
p
tf = G√Kf
0.903
= 1470 √
2.91×95
= 84 mm
14
Summary
15