PILE FOUNDATION

Proper selection of the foundation system (Well or Pile) is the most


crucial Engineering decision in a bridge project

Classification

I. Broadly classified as per fundamental criteria


• Precast piles
• Cast – in – situ piles
OR
• Displacement piles – Driven piles
• Non – displacement piles (Replacement piles) – Bored piles

II. Also, piles may be distinguished in the following different ways


• Based on the materials used for their construction
Timber, steel, Plain concrete, RCC, PSC or combination of any
two

• Based on the method of construction


Precast driven, Precast – bored, Bored cast-in-situ & Driven cast-
in-situ

• Based on load transmission


End bearing & friction piles

• Based on cross sectional area


Circular, rectangular, square, tubular, octagonal & H section

• Based on size
Micro piles – less than 100mm diameter but may also include
piles up to 150mm diameter
Small diameter piles: Nominal diameter is 600mm or less
Large diameter piles: Normal diameter is above 600mm

• On the basis of inclination of pile


Normal (vertical) piles & Raker (batter) piles

• Based on the end usage


Load bearing piles, sheet piles, guide piles, sand or stone
columns for drainage or consolidation
Comparison between Well and Pile foundation

Sl. Criteria Wells Piles


No
.
Massive, large carrying Slender (up to 1.50m dia in India)
1 Size capacity & large reserve & less reserve strength
strength
Strata can be judged by Driven piles – Though the
inspecting dredged soil and concrete is controlled
better quality concrete is subsequent damage may take
2 Quality achievable place. Strata cannot be
inspected. Bored piles – Concrete
under water require greater
effort
Can overcome smaller Driven piles – Difficult driving in
Obstruction
3 obstructions but once struck it case of local obstruction. Bored
s
poses major problems piles better than driven piles
No limit in open dredging. No practical limit
4 Limit in DC Pneumatic sinking up to 33m
only
Size cannot be changed. Precast piles – Less flexibility
5 Flexibility Founding level can be changed. Bored piles – Offer greatest
Less flexibility flexibility
Generally low technology work, Large diameter piles require
6 Technology requires simple equipments special equipments for handling
and driving
High due to large size and low Low due to slender and high
7 Durability
stresses slump concrete
Speed of Relatively slow Fast
8
CN
For very large spans, deep Driven piles depend on
rivers & heavy loads magnitude of work (No. of piles).
9 Economy
Bored piles are often most
economical
In alluvial rivers with high In location where free standing
scour, very week strata and height is low, Fly over, ROB,
10 Suitability
high loads or combination of shallow rivers
these factors