EXPRESS FREIGHT RAILWAY CONSORTIUM

CIVIL,BUILDING AND TRACK WORKS,CONTRACT PACKAGE CTP-11

JNPT- VAITARANA

Project : Civil, Building & Track work for 103 Km Double Railway line.

Employer : DFCCIL (SPV set up under Ministry of Railway)


Engineer : OCG Consortium
Contractor : Express Freight Railway Consortium
Laboratory job no. QC Lab-01 RPFI No EFRC/TPL/CTP-11/La
Type of Material Coarse Aggregate 12.5mm Date of Sampling 21.02.2018
Source of Material Bampapara (Bala jee crushe Date of Testing 27.02.2018
Location Ultratech RMC PLANT Tested by jointly
Location/Chainage IR / DFC Proposed use Concrete

(AS PER IS1199-1959 (RA1999)


Test description Test result

Weight of water in calibration cylinder (W1 gm) 150

Weight of water in measuring bowl (W2 gm) 4900

Constant R (100 x W1/W2) (%) 3.06

Calibration Factor 'k' (0.98R) 2.999

Operating Pressure 'P' 0.85

Reading of water level in standpipe at operating pressure using Ist attempt 2nd attempt
aggregate in the same proportions as that of grade of concrete under
test (%) H1
0.8 0.9
Reading of water level in standpipe after releasing operating
pressure using aggregate in the same proportions as that of grade of
concrete under test (%) H2 0.7 0.7

Aggregate correction factor 'G' (H1-H2) (%)


0.1 0.2
Reading of water level in standpipe at operating pressure using the
same grade of concrete under test (%) H3
1.1 1.3
Reading of water level in standpipe after releasing operating
pressure using same of grade of concrete under test (%) H 4
0.1 0.1
Apparent air content (A1)(H3-H4) (%)
1 1.2

Air content in freshly mixed concrete (A) (A1-G) (%) 0.95

For SLT Rep For PMC Rep


Name : Name :

Sign : Sign :

Date : Date :
PL/CTP-11/Lab/788
21.02.2018
27.02.2018
jointly
Concrete

Average

0.85

0.7

0.15

1.2

0.1

1.1
EXPRESS FREIGHT RAILWAY CONSORTIUM
CIVIL,BUILDING AND TRACK WORKS,CONTRACT PACKAGE CTP-11

JNPT- VAITARANA

Project : Civil, Building & Track work for 103 Km Double Railway line.

Employer : DFCCIL (SPV set up under Ministry of Railway)


Engineer : OCG Consortium
Contractor : Express Freight Railway Consortium
Laboratory job no. QC Lab-01 RPFI No EFRC/TPL/CTP-11/LAB/846
Type of Material Date of Sampling
Source of Material Date of Testing
Location Tested by
Location/Chainage Proposed use Concrete

(AS PER IS1199-1959 (RA1999)


Test description Test result

Weight of water in calibration cylinder (W1 gm) 199.23

Weight of water in measuring bowl (W2 gm) 6031

Constant R (100 x W1/W2) (%) 3.30

Calibration Factor 'k' (0.98R) 3.23

Operating Pressure 'P' 0.60

Reading of water level in standpipe at operating pressure using Control mix Admixture mix
aggregate in the same proportions as that of grade of concrete under
test (%) H1
0.8 0.8
Reading of water level in standpipe after releasing operating
pressure using aggregate in the same proportions as that of grade of
concrete under test (%) H2 0.4 0.4

Aggregate correction factor 'G'= (H1-H2) (%)


0 0.25
Reading of water level in standpipe at operating pressure using the
same grade of concrete under test (%) H 3
2.1 1
Reading of water level in standpipe after releasing operating
pressure using same of grade of concrete under test (%) H 4
0.5 0.5
Apparent air content (A1)=(H3-H4) (%)
1 0.3125

Air content in freshly mixed concrete (A)= (A 1-G) (%) 1 0.0625

EFRC Representative Engineer Representative

Name : Name :

Sign : Sign :

Date : Date :
EXPRESS FREIGHT RAILWAY CONSORTIUM
CIVIL,BUILDING AND TRACK WORKS,CONTRACT PACKAGE CTP-11

JNPT- VAITARANA

Project : Civil, Building & Track work for 103 Km Double Railway line.

Employer : DFCCIL (SPV set up under Ministry of Railway)


Engineer : OCG Consortium
Contractor : Express Freight Railway Consortium
Laboratory job no. QC Lab-01 RPFI No EFRC/TPL/CTP-11/La
Type of Material Coarse Aggregate 12.5mm Date of Sampling 21.02.2018
Source of Material Bampapara (Bala jee crushe Date of Testing 27.02.2018
Location Ultratech RMC PLANT Tested by jointly
Location/Chainage IR / DFC Proposed use Concrete

(AS PER IS1199-1959 (RA1999)


Test description Test result

Weight of water in calibration cylinder (W1 gm) 150

Weight of water in measuring bowl (W2 gm) 4900

Constant R (100 x W1/W2) (%) 3.06

Calibration Factor 'k' (0.98R) 2.999

Operating Pressure 'P' 0.85

Reading of water level in standpipe at operating pressure using Ist attempt 2nd attempt
aggregate in the same proportions as that of grade of concrete under
test (%) H1
3.4 0.9
Reading of water level in standpipe after releasing operating
pressure using aggregate in the same proportions as that of grade of
concrete under test (%) H2 0.4 0.7

Aggregate correction factor 'G' (H1-H2) (%)


3.00 0.2
Reading of water level in standpipe at operating pressure using the
same grade of concrete under test (%) H3
2.2 1.3
Reading of water level in standpipe after releasing operating
pressure using same of grade of concrete under test (%) H 4
0.5 0.1
Apparent air content (A1)(H3-H4) (%)
1.7 1.2

Air content in freshly mixed concrete (A)= (A1-G) (%) -1.3

For SLT Rep For PMC Rep


Name : Name :

Sign : Sign :

Date : Date :
PL/CTP-11/Lab/788
21.02.2018
27.02.2018
jointly
Concrete

Average

2.15

0.55

1.6

1.75

0.3

1.45
EXPRESS FREIGHT RAILWAY CONSORTIUM
CIVIL,BUILDING AND TRACK WORKS,CONTRACT PACKAGE CTP-11

JNPT- VAITARANA

Project : Civil, Building & Track work for 103 Km Double Railway line.

Employer : DFCCIL (SPV set up under Ministry of Railway)


Engineer : OCG Consortium
Contractor : Express Freight Railway Consortium
Laboratory job no. QC Lab-01 RPFI No EFRC/TPL/CTP-11/
Type of Material Date of Sampling
Source of Material Date of Testing 15.06.2018
Location Ultratech RMC PLANT Tested by jointly
Location/Chainage IR / DFC Proposed use Concrete

(AS PER IS1199-1959 (RA1999)


Test description Test result

Weight of water in calibration cylinder (W1 gm) 150

Weight of water in measuring bowl (W2 gm) 4900

Constant R (100 x W1/W2) (%) 3.06

Calibration Factor 'k' (0.98R) 2.999

Operating Pressure 'P' 0.85

Reading of water level in standpipe at operating pressure using Ist attempt 2nd attempt
aggregate in the same proportions as that of grade of concrete under
test (%) H1
3.4 0.9
Reading of water level in standpipe after releasing operating
pressure using aggregate in the same proportions as that of grade of
concrete under test (%) H2 0.4 0.7

Aggregate correction factor 'G' (H1-H2) (%)


3.00 0.2
Reading of water level in standpipe at operating pressure using the
same grade of concrete under test (%) H3
2.2 1.3
Reading of water level in standpipe after releasing operating
pressure using same of grade of concrete under test (%) H 4
0.5 0.1
Apparent air content (A1)(H3-H4) (%)
1.7 1.2

Air content in freshly mixed concrete (A)= (A1-G) (%) -1.3

For SLT Rep For PMC Rep


Name : Name :

Sign : Sign :

Date : Date :
/TPL/CTP-11/Lab/

15.06.2018
jointly
Concrete

Average

2.15

0.55

1.6

1.75

0.3

1.45
EXPRESS FREIGHT RAILWAY CONSORTIUM
CIVIL,BUILDING AND TRACK WORKS,CONTRACT PACKAGE CTP-11

JNPT- VAITARANA

Project : Civil, Building & Track work for 103 Km Double Railway line.

Employer : DFCCIL (SPV set up under Ministry of Railway)

Engineer : OCG Consortium

Contractor : Express Freight Railway Consortium

Laboratory job no. QC Lab-01 RPFI No EFRC/TPL/CTP-11/LAB/1095

Type of Material CHRYSHO HP7242(T) Date of Sampling 21.06.2018

Source of Material Concrete M-25 Grade with 1.6% admixture Date of Testing 21.06.2018

Location Phalasphe phatta lab Tested by JOINTLY

Location/Chainage Proposed use CONCRETE

(AS PER IS1199-1959 (RA1999)

Aggregate correction factor Determination Observation-1 Observation-2

Reading of water level in standpipe at operating pressure using


aggregate in the same proportions as that of grade of concrete under 0.9375 0.8125
test (%) H1
Reading of water level in standpipe after releasing operating
pressure using aggregate in the same proportions as that grade of 0.1875 0.0625
concrete under test (%) H2

Aggregate correction factor 'G'= (H1-H2) (%) 0.750 0.75

Air content Determination Control mix Admixture mix Control mix Admixture mix

Reading of water level in standpipe at operating pressure using the


same grade of concrete under test (%) H3
2.250 2.188 2.188 1.750

Reading of water level in standpipe after releasing operating


pressure using same of grade of concrete under test (%) H 4
0.250 0.188 0.250 0.0625

Apparent air content (A1)=(H3-H4) (%)


2.000 2.000 1.938 1.688

Air content in freshly mixed concrete (A)= (A1-G) (%) 1.250 1.250 1.188 0.938

EFRC Representative Engineer Representative

Name : Name :

Sign : Sign :

Date : Date :
EXPRESS FREIGHT RAILWAY CONSORTIUM
CIVIL,BUILDING AND TRACK WORKS,CONTRACT PACKAGE CTP-11

JNPT- VAITARANA

Project : Civil, Building & Track work for 103 Km Double Railway line.

Employer : DFCCIL (SPV set up under Ministry of Railway)


Engineer : OCG Consortium
Contractor : Express Freight Railway Consortium
Laboratory job no. QC Lab-01 RPFI No
Type of Material Date of Sampling
Source of Material Date of Testing
Location Tested by
Location/Chainage Proposed use Concrete

(AS PER IS1199-1959 (RA1999)


Test description Test result

Weight of water in calibration cylinder (W1 gm) 199.23

Weight of water in measuring bowl (W2 gm) 6031

Constant R (100 x W1/W2) (%) 3.30

Calibration Factor 'k' (0.98R) 3.23

Operating Pressure 'P' 0.60

Reading of water level in standpipe at operating pressure using Control mix Admixture mix
aggregate in the same proportions as that of grade of concrete under
test (%) H1
12 12
Reading of water level in standpipe after releasing operating
pressure using aggregate in the same proportions as that of grade of
concrete under test (%) H2 1 1

Aggregate correction factor 'G'= (H1-H2) (%)


0.6875 0.6875
Reading of water level in standpipe at operating pressure using the
same grade of concrete under test (%) H 3
33 37
Reading of water level in standpipe after releasing operating
pressure using same of grade of concrete under test (%) H 4
3 6
Apparent air content (A1)=(H3-H4) (%)
1.875 1.938

Air content in freshly mixed concrete (A)= (A 1-G) (%) 1.1875 1.2500

EFRC Representative Engineer Representative

Name : Name :

Sign : Sign :

Date : Date :
EXPRESS FREIGHT RAILWAY CONSORTIUM
CIVIL,BUILDING AND TRACK WORKS,CONTRACT PACKAGE CTP-11

JNPT- VAITARANA

Project : Civil, Building & Track work for 103 Km Double Railway line.

Employer : DFCCIL (SPV set up under Ministry of Railway)


Engineer : OCG Consortium
Contractor : Express Freight Railway Consortium
Laboratory job no. QC Lab-01 RPFI No
Type of Material CONCRETE Date of Sampling
Source of Material Date of Testing
Location Tested by
Location/Chainage Proposed use

(AS PER IS1199-1959 (RA1999)

Air Entrap meter Calibration


Test description Test result

Weight of water in calibration cylinder (W1 gm) 199.23

Weight of water in measuring bowl (W2 gm) 6031

Constant R (100 x W1/W2) (%) 3.30

Calibration Factor 'k' (0.98R) 3.23

Operating Pressure 'P' 0.60

EFRC Representative Engineer Representative

Name : Name :

Sign : Sign :

Date : Date :
EXPRESS FREIGHT RAILWAY CONSORTIUM
CIVIL,BUILDING AND TRACK WORKS,CONTRACT PACKAGE CTP-11

JNPT- VAITARANA

Project : Civil, Building & Track work for 103 Km Double Railway line.

Employer : DFCCIL (SPV set up under Ministry of Railway)

Engineer : OCG Consortium

Contractor : Express Freight Railway Consortium

Laboratory job no. QC Lab-01 RPFI No EFRC/TPL/CTP-11/LAB/1095

Type of Material CHRYSHO HP7242(T) Date of Sampling 21.06.2018

Source of Material Concrete M-25 Grade with 1.6% admixture Date of Testing 21.06.2018

Location Phalasphe phatta lab Tested by JOINTLY

Location/Chainage Proposed use CONCRETE

(AS PER IS1199-1959 (RA1999)

Aggregate correction factor Determination Observation-1 Observation-2

Reading of water level in standpipe at operating pressure using


aggregate in the same proportions as that of grade of concrete under 0.9375 0.8125
test (%) H1
Reading of water level in standpipe after releasing operating
pressure using aggregate in the same proportions as that grade of 0.1875 0.0625
concrete under test (%) H2

Aggregate correction factor 'G'= (H1-H2) (%) 0.750 0.750

Air content Determination Control mix Admixture mix Control mix Admixture mix

Reading of water level in standpipe at operating pressure using the


same grade of concrete under test (%) H3
2.250 2.188 2.188 1.750

Reading of water level in standpipe after releasing operating


pressure using same of grade of concrete under test (%) H 4
0.250 0.188 0.250 0.0625

Apparent air content (A1)=(H3-H4) (%)


2.000 2.000 1.938 1.688

Air content in freshly mixed concrete (A)= (A1-G) (%) 1.250 1.251 1.188 1.190

EFRC Representative

Name : Name :

Sign : Sign :

Date : Date :
EXPRESS FREIGHT RAILWAY CONSORTIUM
CIVIL,BUILDING AND TRACK WORKS,CONTRACT PACKAGE CTP-11

JNPT- VAITARANA

Project : Civil, Building & Track work for 103 Km Double Railway line.

Employer : DFCCIL (SPV set up under Ministry of Railway)

Engineer : OCG Consortium

Contractor : Express Freight Railway Consortium

Laboratory job no. QC Lab-01 RPFI No EFRC/TPL/CTP-11/LAB/

Type of Material CAC Hyperfluid Plus G Date of Sampling 01.02.2019

Source of Material Concrete M-35 Grade with 1.4% admixture Date of Testing 01.02.2019

Location Phalasphe phatta lab Tested by JOINTLY

Location/Chainage Proposed use CONCRETE

(AS PER IS1199-1959 (RA1999)

Aggregate correction factor Determination Observation-1 Observation-2

Reading of water level in standpipe at operating pressure using


aggregate in the same proportions as that of grade of concrete under 1 1
test (%) H1
Reading of water level in standpipe after releasing operating
pressure using aggregate in the same proportions as that grade of 0.125 0.125
concrete under test (%) H2

Aggregate correction factor 'G'= (H1-H2) (%) 0.875 0.875

Air content Determination Control mix Admixture mix Control mix Admixture mix

Reading of water level in standpipe at operating pressure using the


same grade of concrete under test (%) H3
1.313 1.313 1.188 1.313

Reading of water level in standpipe after releasing operating


pressure using same of grade of concrete under test (%) H4
0.125 0.063 0.063 0.0625

Apparent air content (A1)=(H3-H4) (%)


1.188 1.250 1.125 1.250

Air content in freshly mixed concrete (A)= (A1-G) (%) 0.313 0.375 0.250 0.375

EFRC Representative

Name : Name :

Sign : Sign :

Date : Date :
EXPRESS FREIGHT RAILWAY CONSORTIUM
CIVIL,BUILDING AND TRACK WORKS,CONTRACT PACKAGE CTP-11

JNPT- VAITARANA

Project : Civil, Building & Track work for 103 Km Double Railway line.

Employer : DFCCIL (SPV set up under Ministry of Railway)

Engineer : OCG Consortium

Contractor : Express Freight Railway Consortium

Laboratory job no. QC Lab-01 RPFI No EFRC/TPL/CTP-11/LAB/

Type of Material CAC Hyperfluid Plus G Date of Sampling 01.02.2019

Source of Material Concrete M-35 Grade with 1.4% admixture Date of Testing 01.02.2019

Location Phalasphe phatta lab Tested by JOINTLY

Location/Chainage Proposed use CONCRETE

(AS PER IS1199-1959 (RA1999)

Aggregate correction factor Determination Observation-1 Observation-2

Reading of water level in standpipe at operating pressure using


aggregate in the same proportions as that of grade of concrete under 0.9375 0.9375
test (%) H1
Reading of water level in standpipe after releasing operating
pressure using aggregate in the same proportions as that grade of 0.25 0.25
concrete under test (%) H2

Aggregate correction factor 'G'= (H1-H2) (%) 0.688 0.688

Air content Determination Control mix Admixture mix Control mix Admixture mix

Reading of water level in standpipe at operating pressure using the


same grade of concrete under test (%) H3
1.125 1.250 1.188 1.250

Reading of water level in standpipe after releasing operating


pressure using same of grade of concrete under test (%) H4
0.125 0.063 0.063 0.0625

Apparent air content (A1)=(H3-H4) (%)


1.000 1.188 1.125 1.188

Air content in freshly mixed concrete (A)= (A1-G) (%) 0.313 0.500 0.438 0.500

EFRC Representative

Name : Name :

Sign : Sign :

Date : Date :
EXPRESS FREIGHT RAILWAY CONSORTIUM
CIVIL,BUILDING AND TRACK WORKS,CONTRACT PACKAGE CTP-11

JNPT- VAITARANA

Project : Civil, Building & Track work for 103 Km Double Railway line.

Employer : DFCCIL (SPV set up under Ministry of Railway)

Engineer : OCG Consortium

Contractor : Express Freight Railway Consortium

Laboratory job no. QC Lab-01 RPFI No EFRC/TPL/CTP-11/LAB/2241

Type of Material CAC Hyperfluid R-250 Date of Sampling 10.04.2019

Source of Material Concrete M-40 Grade with 1.050% Admixture Date of Testing 10.04.2019

Location Phalasphe phatta lab Tested by JOINTLY

Location/Chainage Proposed use CONCRETE

(AS PER IS1199-1959 (RA1999)

Aggregate correction factor Determination Observation-1 Observation-2

Reading of water level in standpipe at operating pressure using


aggregate in the same proportions as that of grade of concrete under 1.25 1.25
test (%) H1
Reading of water level in standpipe after releasing operating
pressure using aggregate in the same proportions as that grade of 0.375 0.375
concrete under test (%) H2

Aggregate correction factor 'G'= (H1-H2) (%) 0.875 0.875

Air content Determination Control mix Admixture mix Control mix Admixture mix

Reading of water level in standpipe at operating pressure using the


same grade of concrete under test (%) H3
1.375 1.438 1.250 1.625

Reading of water level in standpipe after releasing operating


pressure using same of grade of concrete under test (%) H4
0.375 0.125 0.188 0.25

Apparent air content (A1)=(H3-H4) (%)


1.000 1.313 1.063 1.375

Air content in freshly mixed concrete (A)= (A1-G) (%) 0.125 0.438 0.188 0.500

EFRC Representative Engineer´s Representative

Name :
Name :

Sign :
Sign :

Date :
Date :
EXPRESS FREIGHT RAILWAY CONSORTIUM

CIVIL,BUILDING AND TRACK WORKS,CONTRACT PACKAGE CTP-11

JNPT- VAITARANA

Project : Civil, Building & Track work for 103 Km Double Railway line.

Employer : DFCCIL (SPV set up under Ministry of Railway)

Engineer : OCG Consortium

Contractor : Express Freight Railway Consortium

Laboratory job no. QC Lab-01 RPFI No EFRC/TPL/CTP-11/LAB/2391

Type of Material Fosroc Auramix 500 SRV Date of Sampling 18.05.2019

Source of Material Concrete M-55 Grade For PSC Girder with 1.20% Admixture Date of Testing 18.05.2019

Location Phalasphe phatta lab Tested by JOINTLY

Location/Chainage Proposed use CONCRETE

(AS PER IS1199-1959 (RA1999)

Aggregate correction factor Determination Observation-1 Observation-2

Reading of water level in standpipe at operating pressure using


aggregate in the same proportions as that of grade of concrete under 1.313 1.250
test (%) H1
Reading of water level in standpipe after releasing operating
pressure using aggregate in the same proportions as that grade of 0.375 0.4375
concrete under test (%) H2

Aggregate correction factor 'G'= (H1-H2) (%) 0.938 0.813

Air content Determination Control mix Admixture mix Control mix Admixture mix

Reading of water level in standpipe at operating pressure using the


same grade of concrete under test (%) H3
1.313 1.563 1.438 1.563

Reading of water level in standpipe after releasing operating


pressure using same of grade of concrete under test (%) H4
0.125 0.188 0.125 0.125

Apparent air content (A1)=(H3-H4) (%)


1.188 1.375 1.313 1.438

Air content in freshly mixed concrete (A)= (A1-G) (%) 0.250 0.438 0.500 0.625

EFRC Representative Engineer´s Representative

Name :
Name :

Sign :
Sign :

Date :
Date :
EXPRESS FREIGHT RAILWAY CONSORTIUM

CIVIL,BUILDING AND TRACK WORKS,CONTRACT PACKAGE CTP-11

JNPT- VAITARANA

Project : Civil, Building & Track work for 103 Km Double Railway line.

Employer : DFCCIL (SPV set up under Ministry of Railway)

Engineer : OCG Consortium

Contractor : Express Freight Railway Consortium

Laboratory job no. QC Lab-01 RPFI No EFRC/TPL/CTP-11/LAB/2503

Type of Material Chryso Delta G9414 Date of Sampling 10.06.2019

Source of Material Concrete M-35 Grade with 1.20% Admixture Date of Testing 10.06.2019

Location Phalasphe phatta lab Tested by JOINTLY

Location/Chainage Proposed use CONCRETE

(AS PER IS1199-1959 (RA1999)

Aggregate correction factor Determination Observation-1 Observation-2

Reading of water level in standpipe at operating pressure using


aggregate in the same proportions as that of grade of concrete under 1.313 1.250
test (%) H1
Reading of water level in standpipe after releasing operating
pressure using aggregate in the same proportions as that grade of 0.375 0.4375
concrete under test (%) H2

Aggregate correction factor 'G'= (H1-H2) (%) 0.938 0.813

Air content Determination Control mix Admixture mix Control mix Admixture mix

Reading of water level in standpipe at operating pressure using the


same grade of concrete under test (%) H3
1.563 1.750 1.625 1.688

Reading of water level in standpipe after releasing operating


pressure using same of grade of concrete under test (%) H4
0.125 0.188 0.125 0.125

Apparent air content (A1)=(H3-H4) (%)


1.438 1.563 1.500 1.563

Air content in freshly mixed concrete (A)= (A1-G) (%) 0.500 0.625 0.688 0.750

EFRC Representative Engineer´s Representative

Name :
Name :

Sign :
Sign :

Date :
Date :
EXPRESS FREIGHT RAILWAY CONSORTIUM

CIVIL,BUILDING AND TRACK WORKS,CONTRACT PACKAGE CTP-11

JNPT- VAITARANA

Project : Civil, Building & Track work for 103 Km Double Railway line.

Employer : DFCCIL (SPV set up under Ministry of Railway)

Engineer : OCG Consortium

Contractor : Express Freight Railway Consortium

Laboratory job no. QC Lab-01 RPFI No EFRC/TPL/CTP-11/LAB/2542

Type of Material Chryso Delta G9414 Date of Sampling 19.06.2019

Source of Material Concrete M-35 Gradewith 1.30% Admixture & ACC Cement Date of Testing 19.06.2019

Location Phalasphe phatta lab Tested by JOINTLY

Location/Chainage Proposed use CONCRETE

(AS PER IS1199-1959 (RA1999)

Aggregate correction factor Determination Observation-1 Observation-2

Reading of water level in standpipe at operating pressure using


aggregate in the same proportions as that of grade of concrete under 1.313 1.250
test (%) H1
Reading of water level in standpipe after releasing operating
pressure using aggregate in the same proportions as that grade of 0.375 0.4375
concrete under test (%) H2

Aggregate correction factor 'G'= (H1-H2) (%) 0.938 0.813

Air content Determination Control mix Admixture mix Control mix Admixture mix

Reading of water level in standpipe at operating pressure using the


same grade of concrete under test (%) H3
1.500 1.625 1.563 1.625

Reading of water level in standpipe after releasing operating


pressure using same of grade of concrete under test (%) H4
0.188 0.188 0.188 0.1875

Apparent air content (A1)=(H3-H4) (%)


1.313 1.438 1.375 1.438

Air content in freshly mixed concrete (A)= (A1-G) (%) 0.375 0.500 0.563 0.625

EFRC Representative Engineer´s Representative

Name :
Name :

Sign :
Sign :

Date :
Date :
EXPRESS FREIGHT RAILWAY CONSORTIUM

CIVIL,BUILDING AND TRACK WORKS,CONTRACT PACKAGE CTP-11

JNPT- VAITARANA

Project : Civil, Building & Track work for 103 Km Double Railway line.

Employer : DFCCIL (SPV set up under Ministry of Railway)

Engineer : OCG Consortium

Contractor : Express Freight Railway Consortium

Laboratory job no. QC Lab-01 RPFI No EFRC/TPL/CTP-11/LAB/2594

Type of Material TP Buildtech Aqualoc 350L (Balajee crusher Aggregate) Date of Sampling 03.07.2019

Source of Material Concrete M-35 Gradewith 1.20% Admixture, Pawne plant Date of Testing 03.07.2019

Location Phalasphe phatta lab Tested by JOINTLY

Location/Chainage Proposed use CONCRETE

(AS PER IS1199-1959 (RA1999)

Aggregate correction factor Determination Observation-1 Observation-2

Reading of water level in standpipe at operating pressure using


aggregate in the same proportions as that of grade of concrete under 1.313 1.250
test (%) H1
Reading of water level in standpipe after releasing operating
pressure using aggregate in the same proportions as that grade of 0.4375 0.3125
concrete under test (%) H2

Aggregate correction factor 'G'= (H1-H2) (%) 0.875 0.938

Air content Determination Control mix Admixture mix Control mix Admixture mix

Reading of water level in standpipe at operating pressure using the


same grade of concrete under test (%) H3
1.500 1.625 1.563 1.625

Reading of water level in standpipe after releasing operating


pressure using same of grade of concrete under test (%) H4
0.250 0.250 0.188 0.0625

Apparent air content (A1)=(H3-H4) (%)


1.250 1.375 1.375 1.563

Air content in freshly mixed concrete (A)= (A1-G) (%) 0.375 0.500 0.438 0.625

EFRC Representative Engineer´s Representative

Name :
Name :

Sign :
Sign :

Date :
Date :
EXPRESS FREIGHT RAILWAY CONSORTIUM

CIVIL,BUILDING AND TRACK WORKS,CONTRACT PACKAGE CTP-11

JNPT- VAITARANA

Project : Civil, Building & Track work for 103 Km Double Railway line.

Employer : DFCCIL (SPV set up under Ministry of Railway)

Engineer : OCG Consortium

Contractor : Express Freight Railway Consortium

Laboratory job no. QC Lab-01 RPFI No EFRC/TPL/CTP-11/LAB/2639

Type of Material Chryso Optima K9335 Date of Sampling 18.07.2019

Source of Material Concrete M-55 Grade with 1.10% Admixture Date of Testing 18.07.2019

Location Phalasphe phatta lab Tested by JOINTLY

Location/Chainage Proposed use CONCRETE

(AS PER IS1199-1959 (RA1999)

Aggregate correction factor Determination Observation-1 Observation-2

Reading of water level in standpipe at operating pressure using


aggregate in the same proportions as that of grade of concrete under 1.313 1.250
test (%) H1
Reading of water level in standpipe after releasing operating
pressure using aggregate in the same proportions as that grade of 0.375 0.4375
concrete under test (%) H2

Aggregate correction factor 'G'= (H1-H2) (%) 0.938 0.813

Air content Determination Control mix Admixture mix Control mix Admixture mix

Reading of water level in standpipe at operating pressure using the


same grade of concrete under test (%) H3
1.500 1.688 1.563 1.750

Reading of water level in standpipe after releasing operating


pressure using same of grade of concrete under test (%) H4
0.125 0.188 0.125 0.1875

Apparent air content (A1)=(H3-H4) (%)


1.375 1.500 1.438 1.563

Air content in freshly mixed concrete (A)= (A1-G) (%) 0.438 0.563 0.625 0.750

EFRC Representative Engineer´s Representative

Name :
Name :

Sign :
Sign :

Date :
Date :
EXPRESS FREIGHT RAILWAY CONSORTIUM

CIVIL,BUILDING AND TRACK WORKS,CONTRACT PACKAGE CTP-11

JNPT- VAITARANA

Project : Civil, Building & Track work for 103 Km Double Railway line.

Employer : DFCCIL (SPV set up under Ministry of Railway)

Engineer : OCG Consortium

Contractor : Express Freight Railway Consortium

Laboratory job no. QC Lab-01 RPFI No EFRC/TPL/CTP-11/LAB/2659

Type of Material Chryso Optima K9335+Ultratech Cement Date of Sampling 24.07.2019

Source of Material Concrete M-55 Grade with 1.10% Admixture Date of Testing 24.07.2019

Location Phalasphe phatta lab Tested by JOINTLY

Location/Chainage Proposed use CONCRETE

(AS PER IS1199-1959 (RA1999)

Aggregate correction factor Determination Observation-1 Observation-2

Reading of water level in standpipe at operating pressure using


aggregate in the same proportions as that of grade of concrete under 1.313 1.250
test (%) H1
Reading of water level in standpipe after releasing operating
pressure using aggregate in the same proportions as that grade of 0.375 0.4375
concrete under test (%) H2

Aggregate correction factor 'G'= (H1-H2) (%) 0.938 0.813

Air content Determination Control mix Admixture mix Control mix Admixture mix

Reading of water level in standpipe at operating pressure using the


same grade of concrete under test (%) H3
1.438 1.625 1.563 1.688

Reading of water level in standpipe after releasing operating


pressure using same of grade of concrete under test (%) H4
0.125 0.188 0.188 0.125

Apparent air content (A1)=(H3-H4) (%)


1.313 1.438 1.375 1.563

Air content in freshly mixed concrete (A)= (A1-G) (%) 0.375 0.500 0.563 0.750

EFRC Representative Engineer´s Representative

Name :
Name :

Sign :
Sign :

Date :
Date :
EXPRESS FREIGHT RAILWAY CONSORTIUM

CIVIL,BUILDING AND TRACK WORKS,CONTRACT PACKAGE CTP-11

JNPT- VAITARANA

Project : Civil, Building & Track work for 103 Km Double Railway line.

Employer : DFCCIL (SPV set up under Ministry of Railway)

Engineer : OCG Consortium

Contractor : Express Freight Railway Consortium

Laboratory job no. QC Lab-01 RPFI No EFRC/TPL/CTP-11/LAB/2719

Type of Material Admixture Aqualoc TP 3Z5 +Ultratech Cement Date of Sampling 16.08.2019

Source of Material Concrete M-35 Grade with 1.25% Admixture Date of Testing 16.08.2019

Location Phalasphe phatta lab Tested by JOINTLY

Location/Chainage Proposed use CONCRETE

(AS PER IS1199-1959 (RA1999)


Correction Factor & Operating Pressure

Weight of water in calibration cylinder (w gm) 200.4

Weight of water in measuring bowl (W gm) 6001.0

Constant R (100 x w/W) (%) 3.339

Calibration Factor 'k' (0.98R) 3.273

Operating Pressure 'P' 0.650

Aggregate correction factor Determination Observation-1 Observation-2

Reading of water level in standpipe at operating pressure using


aggregate in the same proportions as that of grade of concrete under 1.313 1.250
test (%) H1
Reading of water level in standpipe after releasing operating
pressure using aggregate in the same proportions as that grade of 0.375 0.4375
concrete under test (%) H2

Aggregate correction factor 'G'= (H1-H2) (%) 0.938 0.813

Air content Determination Control mix Admixture mix Control mix Admixture mix

Reading of water level in standpipe at operating pressure using the


same grade of concrete under test (%) H3
1.375 1.688 1.500 1.625

Reading of water level in standpipe after releasing operating


pressure using same of grade of concrete under test (%) H4
0.188 0.250 0.250 0.125

Apparent air content (A1)=(H3-H4) (%)


1.188 1.438 1.250 1.500

Air content in freshly mixed concrete (A)= (A1-G) (%) 0.250 0.500 0.438 0.688

EFRC Representative Engineer´s Representative

Name :
Name :

Sign :
Sign :

Date :
Date :
EXPRESS FREIGHT RAILWAY CONSORTIUM

CIVIL,BUILDING AND TRACK WORKS,CONTRACT PACKAGE CTP-11

JNPT- VAITARANA

Project : Civil, Building & Track work for 103 Km Double Railway line.

Employer : DFCCIL (SPV set up under Ministry of Railway)

Engineer : OCG Consortium

Contractor : Express Freight Railway Consortium

Laboratory job no. QC Lab-01 RPFI No EFRC/TPL/CTP-11/LAB/2814

Type of Material Admixture Aqualoc TP 3Z5 +Ultratech Cement Date of Sampling 06.09.2019

Concrete M-35 Grade with 1.30% Admixture


Source of Material Date of Testing 06.09.2019
(Ultratech RMC Khoni)

Location Phalasphe phatta lab Tested by JOINTLY

Location/Chainage Proposed use CONCRETE

(AS PER IS1199-1959 (RA1999)


Correction Factor & Operating Pressure

Weight of water in calibration cylinder (w gm) 200.4

Weight of water in measuring bowl (W gm) 6001.0

Constant R (100 x w/W) (%) 3.339

Calibration Factor 'k' (0.98R) 3.273

Operating Pressure 'P' 0.650

Aggregate correction factor Determination Observation-1 Observation-2

Reading of water level in standpipe at operating pressure using


aggregate in the same proportions as that of grade of concrete under 1.313 1.250
test (%) H1
Reading of water level in standpipe after releasing operating
pressure using aggregate in the same proportions as that grade of 0.375 0.4375
concrete under test (%) H2

Aggregate correction factor 'G'= (H1-H2) (%) 0.938 0.813

Air content Determination Control mix Admixture mix Control mix Admixture mix

Reading of water level in standpipe at operating pressure using the


same grade of concrete under test (%) H 3
1.500 1.750 1.500 1.688

Reading of water level in standpipe after releasing operating


pressure using same of grade of concrete under test (%) H 4
0.125 0.125 0.188 0.125

Apparent air content (A1)=(H3-H4) (%)


1.375 1.625 1.313 1.563

Air content in freshly mixed concrete (A)= (A1-G) (%) 0.438 0.688 0.500 0.750

EFRC Representative Engineer´s Representative

Name :
Name :

Sign :
Sign :

Date :
Date :
EXPRESS FREIGHT RAILWAY CONSORTIUM

CIVIL,BUILDING AND TRACK WORKS,CONTRACT PACKAGE CTP-11

JNPT- VAITARANA

Project : Civil, Building & Track work for 103 Km Double Railway line.

Employer : DFCCIL (SPV set up under Ministry of Railway)

Engineer : OCG Consortium

Contractor : Express Freight Railway Consortium

Laboratory job no. QC Lab-01 RPFI No EFRC/TPL/CTP-11/LAB/2833

Type of Material Admixture Aqualoc TP 3Z5 + ACC Cement Date of Sampling 11.09.2019

Concrete M-35 Grade with 1.30% Admixture


Source of Material Date of Testing 11.09.2019

Location Phalasphe phatta lab Tested by JOINTLY

Location/Chainage Proposed use CONCRETE

(AS PER IS1199-1959 (RA1999)


Correction Factor & Operating Pressure

Weight of water in calibration cylinder (w gm) 200.4

Weight of water in measuring bowl (W gm) 6001.0

Constant R (100 x w/W) (%) 3.339

Calibration Factor 'k' (0.98R) 3.273

Operating Pressure 'P' 0.650

Aggregate correction factor Determination Observation-1 Observation-2

Reading of water level in standpipe at operating pressure using


aggregate in the same proportions as that of grade of concrete under 1.313 1.250
test (%) H1
Reading of water level in standpipe after releasing operating
pressure using aggregate in the same proportions as that grade of 0.375 0.4375
concrete under test (%) H2

Aggregate correction factor 'G'= (H1-H2) (%) 0.938 0.813

Air content Determination Control mix Admixture mix Control mix Admixture mix

Reading of water level in standpipe at operating pressure using the


same grade of concrete under test (%) H3
1.500 1.750 1.625 1.688

Reading of water level in standpipe after releasing operating


pressure using same of grade of concrete under test (%) H 4
0.125 0.125 0.250 0.125

Apparent air content (A1)=(H3-H4) (%)


1.375 1.625 1.375 1.563

Air content in freshly mixed concrete (A)= (A1-G) (%) 0.438 0.688 0.563 0.750

EFRC Representative Engineer´s Representative

Name :
Name :

Sign :
Sign :

Date :
Date :