P/P2-2018
ENGINEERING REMEDIAL WORKS TO SLOPES AT TOWER SMD39, SELANGAU-MATADENG 132Kv
TRANSMISSION LINE PHASE 2
METHOD STATEMENT
FOR
SITE CLEARING WORKS
This method statement describes the site clearing work for the engineering remedial
works to slopes at tower SMD39, Selangau-Matadeng 132kV transmission line. The
scope of work includes survey setting site clearing, grubbing, stripping of topsoil, etc.
3.0 RESOURCES
3.1 Manpower
Items Description Quantity
(Pax)
1. Project Manager 1
2. Site Engineer 1
3. Site Supervisor 1
4. Site Safety Supervisor 1
5. Surveyor 1
6. General Worker / Chainman 4-5
7. Machinery Operator 2
3.3 Material
Nil
• Prior to the site clearing work, setting out of the right of way and limit of
works shall be carried out by the licensed surveyor.
• Site clearing works only carried out within the right of way and limit of works
area that approved by the SO.
• Site Clearing work shall consist of the cutting and/or taking down, removal
and disposal of everything above ground level, including objects
overhanging the areas to be cleared such as tree branches.
• The material to be cleared shall include but not limited to trees, logs, brush,
undergrowth, long grasses, crops, loose vegetable matter.
• Grubbing shall consist of the removal and disposal of surface vegetation, the
bases of stumps, roots, the underground parts of structures, and other
obstructions to a depth of at least 0.5m below the original ground level.
• Striping topsoil shall consist of the removal of topsoil to an average depth
of at least 100mm below ground level.
• Clearing, grubbing and stripping topsoil shall be carried out in all areas of
remedial works construct.
• Site clearing shall not be done to the whole area within the R.O.W all at once.
• Site clearing shall only be carried out at the areas where works are intended
to be done for that day. The cleared area shall be covered up with canvas if
there are remaining works to be done
• No open burning should be allowed unless approval has been attained from
the Director General of Environment or Controller of National Resources
and Environment Board (NREB).
4.2 Disposal of Material
• The site clearing works shall be carried out using Site preparation, Site clearing
and Earthworks Inspection Form, Document No: FM-PRO-03 and to ensure the
finishing every work shall be accepted by S.O
• Work Inspection Request shall be submitted within 24hours prior to work
inspection.