net/publication/273636203
CITATIONS READS
0 733
5 authors, including:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Marcin Bielecki on 17 March 2015.
Turbo-Expander Compressor
Active Magnetic Bearing
Trips Reduction - A Case Study
Objectives
Contents
Turbo-Expander - Application
Why is it important
• Key for liquid natural gas recovery
processes to enhance C3 recovery
• On spec lean LNG production
Downtime consequence
• If Turbo-Expander is down, plant can
still operate in JT-Valve bypass or
DPC modes
• Reduced feed & off-spec LNG
production, high loss
(condensate)
454
Turbo-Expander – Components
26
25
15 trips
Expander Discharge Pressure, Barg
24
23
22
21
May-06 A ug-06 Nov-06 Feb-07 May-07 A ug-07 Nov-07
Tim e , Date
Axial
Vibe
Tim e
458
Failure Mode 1 – Axial
Shuttling (Surge Failure Z12)
• RCFA Found Combination of Factors
• ATB was initially not functioning correctly (logic, stroke & setting)
• Off-design condition due to high rate operations creating low
back wheel pressure (high axial thrust load)
• Unknown high frequency (240Hz) vibration used up dynamic
capability of AMB – only seen at specific low pressure/ high flow/
speed settings
6000 32000
2 4 0 H z a x ia l - t rip s N o v'0 7 2 4 0 H z a x ia l - t rip s N o v'0 7
2 4 0 H z a x ia l - n o rm a l o p e r. A p r'0 9 2 4 0 H z a x ia l - n o rm a l o p e r. A p r'0 9
5000 8 0 H z w h irl - s t a rt -u p J a n '0 9 28000
8 0 H z w h irl - s t a rt -u p J a n '0 9
8 0 H z w h irl - lo w flo w N o v'0 9 26000 8 0 H z w h irl - lo w flo w N o v'0 9
8 0 H z w h irl - n o rm a l o p e r. A p r'0 9 8 0 H z w h irl - n o rm a l o p e r. A p r'0 9
4000 24000
22000
3000 20000
18000
2000 16000
4500 5500 6500 7500 8500 9500 10500 11500 4500 5500 6500 7500 8500 9500 10500 11500
R otor s peed [R P M ] R otor s peed [R P M ]
800000 6000
2 4 0 H z a x ia l - t rip s N o v'0 7
700000
600000 5000
8 0 H z w h irl - s t a rt -u p J a n '0 9
500000 8 0 H z w h irl - lo w flo w N o v'0 9
400000 4000
2 4 0 H z a x ia l - t rip s N o v'0 7
300000 2 4 0 H z a x ia l - n o rm a l o p e r. N o v'0 9
2 4 0 H z a x ia l - n o rm a l o p e r. A p r'0 9
200000 8 0 H z w h irl - s t a rt -u p J a n '0 9 3000
8 0 H z w h irl - lo w flo w N o v'0 9
100000
8 0 H z w h irl - n o rm a l o p e r. A p r'0 9
0 2000
60 61 62 63 64 65 66 67 0 10 20 30 40 50 60 70 80 90 100
E x p a n d e r in le t p re s s u re [ b a rg ] E x p IG V o p e n in g [ % ]
459
• Outstanding Works
• Source of high frequency (240Hz) vibration is still to be determined,
though
• ATB valve and piping to be inspected and if necessary upgraded to reduce
pressure drop
461
Failure Mode 2 – Transfer
Function Changed
• Control Loop Transfer Function (TF) Changed
• TF is the ratio of output of a control system to its input; once set
up, it represents the system signature (ie, natural frequencies)
• Change of TF during active operation is rare, but RasGas
experienced twice in 2009
462
AMB/Rotor Dyn TF
Measuement In Field
Translation Closed Loop TF
• Closed Loop TF on
Translation and Tilting mode
controllers (measured at
standstill) appear to be very
flat in the 70-120 Hz
frequency range. This is a
good indicator of system
stability.
Tilting Closed Loop TF
• Closed Loop TF should be
measured with machine in
operation to have
confirmation on stability
margins.
The standard S2M Amplification factor criteria on
a close loop transfer function is <2.5
463
Failure Mode 2 – Transfer
Function Changed
• High frequency TF change in Unit #1 unit (Figures
A1-A3)
• Mitigated by software modification
• Machine operational, but fault unknown
Phase
Magnitude
Frequency (Hz)
TF curve before the
High frequency TF change measured replacement of the
MCS (this is the
expected curve).
466
A3 – Unit #1 Controller
Modified to Counter TF Change
• Indicating instability
469
B3 – Unit #2 Machine Center
Section Root Cause
Root Cause Long term options
• Axis identification on • Spare AMB cabinet to test all
compressor side was wrong MCS before installation
(signals cables)
• Wiring was also crossed inside
MCS
• Wiring was crossed at JB
during replacement
• Static levitation can be
performed even if lower radial
coils crossed and appeared to
be stable, but in dynamic mode
unit is unstable
Summary