QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
C-001 BLDG Building Civil Works CIP IP Submitted for FW Eng review Initial Survey Survey of Excavation Compaction Rebar completed Formwork Concrete pour Blockwork Painting Backfilling Paving Building Handed
FW Eng Review Approved and Setting out existing services completed completed completed completed completed completed completed Completed over
Accepted completed
C-002 CT/DB Cable Trenches / Duct Bank CIP IP Submitted for FW Eng review Initial Survey Survey of Excavation Compaction Rebar completed Formwork Concrete pour Painting 1st layer Sand Trench released 2nd layer Sand Trench released 3rd layer Sand Trench released Trench released Sandfilling and
FW Eng Review Approved and Setting out existing services completed completed completed completed completed filling completed for 1st layer filling completed for 2nd layer filling completed for 3rd layer for Sandfilling Backfilling
Accepted completed cable pulling cable pulling cable pulling and backfilling completed
C-003 EFND Equipment Foundation CIP IP Submitted for FW Eng review Initial Survey Survey of Excavation Compaction Rebar completed Formwork Concrete pour Painting Backfilling Final Survey Foundations Foundation
FW Eng Review Approved and Setting out existing services completed completed completed completed completed completed completed scabbling Handed over
Accepted completed completed
C-004 FND Foundation CIP IP Submitted for FW Eng review Initial Survey Survey of Excavation Compaction Rebar completed Formwork Concrete pour Painting Backfilling Final Survey Foundations Foundation
FW Eng Review Approved and Setting out existing services completed completed completed completed completed completed completed scabbling Handed over
Accepted completed completed
C-005 G/P Grading and Paving CIP IP Submitted for FW Eng review Initial Survey Survey of Grading Released for Paving Paving Handed
FW Eng Review Approved and Setting out existing services Completed Paving Completed over
Accepted completed
C-006 RD Roads CIP IP Submitted for FW Eng review Initial Survey Survey of Grading Base Course Asphalt Road Signs Road Completed
FW Eng Review Approved and Setting out existing services Completed completed Completed Installed
Accepted completed
C-007 DC Drainage Channel CIP IP Submitted for FW Eng review Initial Survey Survey of Excavation Compaction Rebar completed Concrete pour Backfilling Drainage
FW Eng Review Approved and Setting out existing services completed completed completed completed Channel
Accepted completed Completed
C-008 MN RCP Manholes and RC Pipework CIP IP Submitted for FW Eng review Initial Survey Survey of Excavation Compaction Rebar completed Formwork Concrete pour Painting RC piping Manhole and RC Backfilling Manhole and RC
FW Eng Review Approved and Setting out existing services completed completed completed completed completed installed piping leak tested completed piping completed
Accepted completed
C-009 PSF Pipe support Foundation CIP IP Submitted for FW Eng review Initial Survey Survey of Excavation Compaction Rebar completed Formwork Concrete pour Painting Backfilling Pipe support
FW Eng Review Approved and Setting out existing services completed completed completed completed completed completed completed
Accepted completed
C-010 MH Manholes CIP IP Submitted for FW Eng review Initial Survey Survey of Excavation Compaction Rebar completed Formwork Concrete pour Painting Manhole leak Backfilling Manhole
FW Eng Review Approved and Setting out existing services completed completed completed completed completed tested completed Completed
Accepted completed
C-011 SB Sumps and Basins CIP IP Submitted for FW Eng review Initial Survey Survey of Excavation Compaction Rebar completed Formwork Concrete pour Painting Sumps and Backfilling Manhole
FW Eng Review Approved and Setting out existing services completed completed completed completed completed basin leak tested completed Completed
Accepted completed
C-012 TB Thrust Blocks CIP Initial Survey Survey of Excavation Compaction Rebar completed Formwork Concrete pour Painting
and Setting out existing services completed completed completed completed completed
Accepted completed
C-013 C-General Components not yet identified Pack Submitted Pack Accepted
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
CO-001 CO Coating Inspection Pack Inspection Pack Inspection Pack Painting FW CAT "A" Punch FW/Sharq CAT "A" Punch Painting Insulation FW CAT "A" Punch FW/Sharq CAT "A" Punch
Submitted for Approved by Eng Complete Constructiom items cleared Inspection items cleared Accepted Complete Constructiom items cleared Inspection items cleared
Eng Approval Inspection Released For Inspection
Insulation
CO-002 CO ISO Coating Inspection per Painting / Isometric Painting FW CAT "A" Punch FW/Sharq CAT "A" Punch Painting Insulation FW CAT "A" Punch FW/Sharq CAT "A" Punch
Insulation Released Complete Constructiom items cleared Inspection items cleared Accepted Complete Constructiom items cleared Inspection items cleared
isometric Complete Inspection Released For Inspection
Insulation
CO-003 CO TIE-IN Coating - Tie-in and Interface Inspection Pack Inspection Pack Painting FW CAT "A" Punch FW/Sharq CAT "A" Punch Painting Insulation FW CAT "A" Punch FW/Sharq CAT "A" Punch
Submitted for Approved by Eng Complete Constructiom items cleared Inspection items cleared Accepted Complete Constructiom items cleared Inspection items cleared
and PI Points Eng Approval Inspection Released For Inspection
Insulation
CO-004 CO MECH Coating - Mechanical Inspection Pack Inspection Pack Painting FW CAT "A" Punch FW/Sharq CAT "A" Punch Painting Insulation FW CAT "A" Punch FW/Sharq CAT "A" Punch
Submitted for Approved by Eng Complete Constructiom items cleared Inspection items cleared Accepted Complete Constructiom items cleared Inspection items cleared
EQUIP Equipment Eng Approval Inspection Released For Inspection
Insulation
CO-005 F_PROOFIN Fire Proofing Submitted for FW Eng review Steelwork Equipment Fireproofing FW CAT "A" Punch FW/Sharq CAT "A" Punch
FW Eng Review Approved Released Released completed Constructiom items cleared Inspection items cleared
G Inspection
CO-006 CO-General Components not yet identified Pack Submitted Pack Accepted
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
E-001 CAB Cable EIP IP Submitted for FW Eng review Trench / Conduit Cable Pulled Cable Testing Cable Final Cable
FW Eng Review Approved / Tray released Completed Terminated Testing
Completed
E-002 EARTHING Earthing and Grounding EIP IP Submitted for FW Eng review Released for Earthing and Earthing and FW Construction Punch Items FW QC / Sharq Punch Items Released for
FW Eng Review Approved installation Grounding Grounding Punch Out completed punchout completed Hook Up
Installed Complete complete
E-003 EHT Electrical Heat Tracing EIP IP Submitted for FW Eng review Piping Released Electrical FW Construction Punch Items FW QC / Sharq Punch Items Released for
FW Eng Review Approved Tracing installed Punch Out completed punchout completed Insulation
complete
E-004 ELE EQPT Electrical Cabinets EIP IP Submitted for FW Eng review Released for Cabinet Installed Cabinet FW Construction Punch Items FW QC / Sharq Punch Items Released for
FW Eng Review Approved installation Installtion Punch Out completed punchout completed Hook Up
Complete complete
E-005 ELE MOTOR Electrical Motors EIP IP Submitted for FW Eng review Motor Installed Motor Released Cable FW Construction Punch Items IP Submitted FW Final FW QC / Sharq Punch Items Submitted For Final FW QC Submitted For Final Sharq QC Submitted For Discipline Mechanical Coupling Released For Motor Run
FW Eng Review Approved for termination Termination Punch Out completed For FW Final Engineering punchout completed Final FW QC Review Accepted Sharq Final QC Review Accepted Discipline Construction Released Issued Removed Motor Run Completed
Complete Eng Review Review Review Review Construction Completion Issed
Approved Completion
E-006 ELEC JB Electrical Junction Box EIP IP Submitted for FW Eng review Released for Junction Box Junction Box FW Construction Punch Items FW QC / Sharq Punch Items Released for
FW Eng Review Approved installation Installed Installtion Punch Out completed punchout completed Hook Up
Complete complete
E-007 LIGHT Lighting Circuit EIP IP Submitted for FW Eng review Released for Lighting Installed Lighting FW Construction Punch Items FW QC / Sharq Punch Items Released for
FW Eng Review Approved installation Installtion Punch Out completed punchout completed Hook Up
Complete complete
E-008 TR Transformers EIP IP Submitted for FW Eng review Released for Transformer Transformer FW Construction Punch Items FW QC / Sharq Punch Items Released for
FW Eng Review Approved installation Installed Installtion Punch Out completed punchout completed Hook Up
Complete complete
E-009 ECT Electrical Cable Trench EIP IP Submitted for FW Eng review Released for 1st Trench released Trench accepted 1st Layer cable 1st Layer cable FW FW Construction FW QC/Sharq FW QC/ Sharq Released For Released for Trench released Trench accepted 2nd Layer cable 2nd Layer cable FW FW Construction FW QC/Sharq FW QC/ Sharq
FW Eng Review Approved Cable Pulling to sub contractor by sub contractor pulling pulling Constructiom Punch items Inspection Punch items Sand Filling 2nd layer Cable to sub contractor by sub contractor pulling pulling Constructiom Punch items Inspection Punch items
commenced completed Inspection cleared cleared Pulling commenced completed Inspection cleared cleared
E-010 ECTR Electrical Cable Trays EIP IP Submitted for FW Eng review Released for Tray Installed Tray Installtion FW Construction Punch Items FW QC / Sharq Punch Items Released for
FW Eng Review Approved installation Complete Punch Out completed punchout completed Cable Pulling
complete
E-011 CP Cathodic Protection EIP IP Submitted for FW Eng review Piping Released Cathodic FW Construction Punch Items FW QC / Sharq Punch Items Released for
FW Eng Review Approved Protection Punch Out completed punchout completed Hydrotesting /
installed complete Backfilling
E-012 SP Small Power EIP IP Submitted for FW Eng review Released for Small Power FW Construction Punch Items FW QC / Sharq Punch Items
FW Eng Review Approved installation installed Punch Out completed punchout completed
complete
E-013 WP Welding Outlets EIP IP Submitted for FW Eng review Released for Welding Outlets FW Construction Punch Items FW QC / Sharq Punch Items
FW Eng Review Approved installation Installed Punch Out completed punchout completed
complete
E-014 LP Lightning Protection EIP IP Submitted for FW Eng review Released for Lightning FW Construction Punch Items FW QC / Sharq Punch Items
FW Eng Review Approved installation Protection Punch Out completed punchout completed
Installed complete
E-015 FDET Fire Detection EIP IP Submitted for FW Eng review Fire Detection Test Complete FW Construction Punch Items FW QC / Sharq Punch Items
FW Eng Review Approved Installed Punch Out Completed Punch Out Completed
Complete
E-016 PA Public Address EIP IP Submitted for FW Eng review Public Address Test Complete FW Construction Punch Items FW QC / Sharq Punch Items
FW Eng Review Approved Installed Punch Out Completed Punch Out Completed
Complete
E-017 PABX-TEL Pabx/Telephone EIP IP Submitted for FW Eng review Pabx/Telephone Test Complete FW Construction Punch Items FW QC / Sharq Punch Items
FW Eng Review Approved Installed Punch Out Completed Punch Out Completed
Complete
E-018 PAGING Plant & Substation/RIB Paging EIP IP Submitted for FW Eng review Paging System Test Complete FW Construction Punch Items FW QC / Sharq Punch Items
FW Eng Review Approved Installed Punch Out Completed Punch Out Completed
Complete
E-019 CMADA CMADA EIP IP Submitted for FW Eng review CMADA Installed Test Complete FW Construction Punch Items FW QC / Sharq Punch Items
FW Eng Review Approved Punch Out Completed Punch Out Completed
Complete
E-020 EMP Electrical MOV Pack EIP IP Submitted for FW Eng review MOV Installed Motor Released Cable FW Construction Punch Items FW QC / Sharq Punch Items Lubrication Energized Released for
FW Eng Review Approved for termination Termination Punch Out completed punchout completed Checked Stroke Test
Complete complete
E-021 ECT EIP Electrical Cable Trench EIP EIP IP Submitted for FW Eng review Released for 1st Trench released Trench accepted 1st Layer cable 1st Layer cable FW FW Construction FW QC/Sharq FW QC/ Sharq Released For Released for Trench released Trench accepted 2nd Layer cable 2nd Layer cable FW FW Construction FW QC/Sharq FW QC/ Sharq
FW Eng Review Approved Cable Pulling to sub contractor by sub contractor pulling pulling Constructiom Punch items Inspection Punch items Sand Filling 2nd layer Cable to sub contractor by sub contractor pulling pulling Constructiom Punch items Inspection Punch items
commenced completed Inspection cleared cleared Pulling commenced completed Inspection cleared cleared
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
Pack
E-023 GASDET Gas Detection EIP IP Submitted for FW Eng Review Gas Detection Test Complete FW Construction Punch Items FW QC / Sharq Punch Items
FW Eng Review Approved Installed Punch Out Completed Punch Out Completed
Complete
E-024 CCTV Closed-Circuit Television EIP IP Submitted for FW Eng Review CCTV Installed Test Complete FW Construction Punch Items FW QC / Sharq Punch Items
FW Eng Review Approved Punch Out Completed Punch Out Completed
Complete
E-025 OSPAS OSPAS (HotLine) Telephone EIP IP Submitted for FW Eng Review OSPAS Installed Test Complete FW Construction Punch Items FW QC / Sharq Punch Items
FW Eng Review Approved Punch Out Completed Punch Out Completed
Complete
E-026 DNET Data Network EIP IP Submitted for FW Eng Review Data Network Test Complete FW Construction Punch Items FW QC / Sharq Punch Items
FW Eng Review Approved Installed Punch Out Completed Punch Out Completed
Complete
E-027 E-General Components not yet identified Pack Submitted Pack Accepted
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
I-004 FE Flow Element Orifice Plate PC Pre-Installation Release Installed FW / Sharq FW / Sharq
Calibration Received for inspection inspection
installation accepted
I-010 ICT Instrument Cable Trench IP Released for Trench released Trench accepted Ist Layer cable Ist Layer cable FW FW Construction FW QC/Sharq FW QC/ Sharq Released For Released for Trench released Trench accepted 2nd Layer cable 2nd Layer cable FW FW Construction FW QC/Sharq FW QC/ Sharq Released For
1stCable Pulling to sub contractor by sub contractor pulling pulling Constructiom Punch items Inspection Punch items Sand Filling 2nd layer Cable to sub contractor by sub contractor pulling pulling Constructiom Punch items Inspection Punch items Sand Filling
commenced completed Inspection cleared cleared Pulling commenced completed Inspection cleared cleared
I-011 INST Instrument Cabinets IP Released for Cabinet Installed Cabinet FW Construction Punch Items FW QC / Sharq Punch Items Released for
installation Installtion Punch Out completed punchout completed Hook Up
CABINET Complete complete
I-012 INST LOOPS Instrument Loop Packs LP Pack Submitted FW Engineering Instrument JB Installed Primary Cable Secondary Instrument Pack Submitted Loop pack Final FW Submitted for Cat A and B Submitted for Discipline
For Initial Review Accepted Calibrated Installed Cable Installed Installed for Final Submitted for Construction Backpunching Punch Items Discipline Construction
Engineering Construction Final Punch Completed Construction Completion
Review Review Construction Completed Completion Issued
Walkdown
I-013 IT Instrument Trunking IP Released for Trunking Trunking FW Construction Punch Items FW QC / Sharq Punch Items Released for
installation Installed Installtion Punch Out completed punchout completed Cable Pulling
Complete complete
I-014 JBI Junction Box Instrument IP Released for Junction Box Junction Box FW Construction Submitted To CAT A Items Punch Items Submit For FW QC / Sharq CAT A Items Punch Items Released for
installation Installed Installtion Punch Out FW For Complete completed Review punchout Complete completed Hook Up
Complete complete Backpunching
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
I-027 SAT Site Acceptance Test QP SAT QP SAT QP Eng Installation SAT QP FW Construction Punch Items Cat "A" Items FW QC / Cat "A" Items Construction SAT commenced SAT complete
Submitted for review approved complete Submitted for Punch Out completed completed SHARQ Punch completed Complete
Eng review FW Construction complete Out complete
Punch Out
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
I-095 FXALL Flow Safety Alarm Low Low LP Pre-Installation Release Installed
Calibration Received for
installation
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
I-168 LXAHH Level Safety Alarm High High LP Pre-Installation Release Installed
Calibration Received for
installation
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
I-169 LXALL Level Safety Alarm Low Low LP Pre-Installation Release Installed
Calibration Received for
installation
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
I-225 SXALL Speed Safety Alarm Low Low LP Pre-Installation Release Installed
Calibration Received for
installation
I-228 SXSLL Speed Safety Switch Low Low LP Pre-Installation Release Installed
Calibration Received for
installation
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
I-316 MOV TEMP MOV Temp Supply PP/LP IP Submitted for IP Eng Review MOV Available Elec. Cable Stroke Test MOV Limits Set FW Construction FW Construction FW QC / Sharq FW QC / Sharq Elec. Cable
Eng Review Approved Termination Completed Punch Out Punch Items Punch Out Punch Items Removed
Completed Complete Cleared Complete Cleared
Temp. Power
Supply
I-317 CONDUIT Instrument Conduit Conduit Installed Release for
Completion
I-319 HAZCON Construction Hazard Submitted for Engieering FW Construction Cat A and B
Engineering Review Punch Cleared Punch Items
Review Approved Completed
I-321 I-General Components not yet identified Pack Submitted Pack Accepted
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
IL-001 INST LOOPS Instrument Loop Packs LP Pack Submitted FW Engineering Instrument JB Installed Primary Cable Secondary Instrument Pack Submitted Loop pack Final FW Submitted for Cat A and B Submitted for Discipline
For Initial Review Accepted Calibrated Installed Cable Installed Installed for Final Submitted for Construction Backpunching Punch Items Discipline Construction
Engineering Construction Final Punch Completed Construction Completion
Review Review Construction Completed Completion Issued
Walkdown
IL-002 IL-General Components not yet identified LP Pack Submitted Pack Accepted
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
M-001 AFC Air Fin Cooler MIP IP Submitted for FW Eng review Steelwork/Found Survey Equipment FW Construction Punch Items FW QC / Sharq Punch Items Hydrotest Tube Release For Blade Angle Pre Allignment Install Drive Belt FW Construction Punch Items FW QC / Sharq Punch Items Release for Remove Drive Released for 4hr
FW Eng Review Approved ation released Completed and Installed Punch Out completed punchout completed Bundel Piping inspection complete and Guards Punch Out completed punchout completed Electrical Hook Belt and Guards Motor Run
for installation accepeted by complete Installation complete complete up
Subcontractor
M-002 CM Compressor MIP IP Submitted for FW Eng review Steelwork/Found Survey Equipment FW Construction Punch Items FW QC / Sharq Punch Items Pre Allignment Released For Grouting Release For Released for E/I FW Construction Punch Items FW QC / Sharq Punch Items Piping Released Remove Released for 4hr
FW Eng Review Approved ation released Completed and Installed Punch Out completed punchout completed complete Grouting Completed Piping Hook Up Punch Out completed punchout completed Coupling and Motor Run
for installation accepeted by complete Installation complete Guards
Subcontractor
M-003 EJ Ejector MIP IP Submitted for FW Eng review Piping released Survey Equipment FW Construction Punch Items FW QC / Sharq Punch Items FW QC / Sharq
FW Eng Review Approved for installation Completed and Installed Punch Out completed punchout completed Final Box up
accepeted by complete inspection
Subcontractor
M-004 FAN Fans MIP IP Submitted for FW Eng review Steelwork/Found Survey Equipment FW Construction Punch Items FW QC / Sharq Punch Items Blade Tip Pre Allignment Released For Grouting Release For Released for E/I FW Construction Punch Items FW QC / Sharq Punch Items Remove Released for 4hr
FW Eng Review Approved ation released Completed and Installed Punch Out completed punchout completed inspection complete Grouting Completed Piping Hook Up Punch Out completed punchout completed Coupling and Motor Run
for installation accepeted by complete complete Installation complete Guards
Subcontractor
M-005 FD Dryer MIP IP Submitted for FW Eng review Steelwork/Found Survey Equipment FW Construction Punch Items FW QC / Sharq Punch Items Pre Allignment Released For Grouting Release For Released for E/I Released for FW Construction Punch Items FW QC / Sharq Punch Items FW QC / Sharq
FW Eng Review Approved ation released Completed and Installed Punch Out completed punchout completed complete Grouting Completed Piping Hook Up Painting and Punch Out completed punchout completed Final Box up
for installation accepeted by complete Installation Insulation complete inspection
Subcontractor
M-006 FLTR Filter MIP IP Submitted for FW Eng review Steelwork/Found Survey Equipment FW Construction Punch Items FW QC / Sharq Punch Items Released For Grouting Release For Released for E/I Released for FW Construction Punch Items FW QC / Sharq Punch Items FW QC / Sharq
FW Eng Review Approved ation released Completed and Installed Punch Out completed punchout completed Grouting Completed Piping Hook Up Painting and Punch Out completed punchout completed Final Box up
for installation accepeted by complete Installation Insulation complete inspection
Subcontractor
M-007 H- Heat Exchanger MIP IP Submitted for FW Eng review Steelwork/Found Survey Equipment FW Construction Punch Items FW QC / Sharq Punch Items Released For Grouting Release For Released for E/I Released for FW Construction Punch Items FW QC / Sharq Punch Items FW QC / Sharq
FW Eng Review Approved ation released Completed and Installed Punch Out completed punchout completed Grouting Completed Piping Hook Up Painting and Punch Out completed punchout completed Final Box up
XCHANGER for installation accepeted by complete Installation Insulation complete inspection
Subcontractor
M-008 LFT-P Overhead Crane MIP IP Submitted for FW Eng review Steelwork/Found Survey Erect Rails FW Construction Punch Items FW QC / Sharq Punch Items Install Overhead Final Allignment Released for E/I FW Construction Punch Items FW QC / Sharq Punch Items Electrical Perform Load FW QC / Sharq
FW Eng Review Approved ation released Completed and Punch Out completed punchout completed Crane complete Hook Up Punch Out completed punchout completed Installation test Final Box up
for installation accepeted by complete complete Complete inspection
Subcontractor
M-009 PE Package Equipment MIP IP Submitted for FW Eng review Steelwork/Found Survey Equipment FW Construction Punch Items FW QC / Sharq Punch Items Pre Allignment Released For Grouting Release For Released for E/I FW Construction Punch Items FW QC / Sharq Punch Items Remove Released for 4hr 4hr Motor Run
FW Eng Review Approved ation released Completed and Installed Punch Out completed punchout completed complete Grouting Completed Piping Hook Up Punch Out completed punchout completed Coupling and Motor Run Completed
for installation accepeted by complete Installation complete Guards
Subcontractor
M-010 PUMP PUMPS MIP IP Submitted for FW Eng review Steelwork/Found Survey Equipment FW Construction Punch Items FW QC / Sharq Punch Items Pre Allignment Released For Grouting Release For Released for E/I FW Construction Punch Items FW QC / Sharq Punch Items Piping Released Remove Released for 4hr
FW Eng Review Approved ation released Completed and Installed Punch Out completed punchout completed complete Grouting Completed Piping Hook Up Punch Out completed punchout completed Coupling and Motor Run
for installation accepeted by complete Installation complete Guards
Subcontractor
M-011 SL Silencer MIP IP Submitted for FW Eng review Steelwork/Found Survey Equipment FW Construction Punch Items FW QC / Sharq Punch Items FW QC / Sharq
FW Eng Review Approved ation released Completed and Installed Punch Out completed punchout completed Final Box up
for installation accepeted by complete inspection
Subcontractor
M-012 SSH Safety Shower / Eye Wash / MIP IP Submitted for FW Eng review Steelwork/Found Survey Equipment Released For Grouting Released For Released For FW Construction Punch Items FW QC / Sharq Punch Items FW QC / Sharq
FW Eng Review Approved ation released Completed and Installed Grouting Accepted Piping E&I Punch Out Completed Punch Out Completed Final Box Up
Drinking Fountain for installation accepeted by complete Inspection
Subcontractor
M-013 VESSEL Vessel MIP IP Submitted for FW Eng review Steelwork/Found Survey Equipment FW Construction Punch Items FW QC / Sharq Punch Items Pre Allignment Released For Grouting Release For Released for E/I Released for Open Manways FW Construction Punch Items FW QC / Sharq Punch Items Install Internals
FW Eng Review Approved ation released Completed and Installed Punch Out completed punchout completed complete Grouting Completed Piping Hook Up Painting and Punch Out completed punchout completed
for installation accepeted by complete Installation Insulation complete
Subcontractor
M-014 MIXER Mixer MIP IP Submitted for FW Eng review Piping released Survey Equipment FW Construction Punch Items FW QC / Sharq Punch Items FW QC / Sharq
FW Eng Review Approved for installation Completed and Installed Punch Out completed punchout completed Final Box up
accepeted by complete inspection
Subcontractor
M-015 BRV Tank Breather Valve MIP IP Submitted for FW Eng review Steelwork/Found Survey Calibrated Installation Removed for Sent to vendor Returned from Reinstated after FW / Sharq FW / Sharq
FW Eng Review Approved ation released Completed and Complete Final Calibration for final vendor after final calibration inspection inspection
for installation accepeted by calibration final calibration accepted
Subcontractor
M-016 FDF Forced Draft Fans MIP IP Submitted for FW Eng review Steelwork/Found Survey Equipment FW Construction Punch Items FW QC / Sharq Punch Items Blade Tip Pre Allignment Released For Grouting Release For Released for E/I FW Construction Punch Items FW QC / Sharq Punch Items Remove Released for 4hr
FW Eng Review Approved ation released Completed and Installed Punch Out completed punchout completed inspection complete Grouting Completed Piping Hook Up Punch Out completed punchout completed Coupling and Motor Run
for installation accepeted by complete complete Installation complete Guards
Subcontractor
M-017 TANK Major Storage Tank Inspection Pack Inspection Pack Foundation Shell Erection FW CAT "A" Punch FW/Sharq CAT "A" Punch Released For Grouting Submitted For NDE Cleared Released For Hydro Test Reinstatement Secondary FW Construction CAT "A" Punch FW/Sharq CAT "A" Punch Released For
Submitted for Approved by Eng Release Complete Constructiom items cleared Inspection items cleared Grouting Complete FW for NDE Hydrotesting Complete Complete Erection Inspection items cleared Inspection items cleared Painting and
Eng Approval Inspection Clearance Complete Insulation
M-018 SP Spheres Inspection Pack Inspection Pack Foundation Shell Erection FW CAT "A" Punch FW/Sharq CAT "A" Punch Released For Grouting Submitted For NDE Cleared Released For Hydro Test Reinstatement Secondary FW CAT "A" Punch FW/Sharq CAT "A" Punch Released For
Submitted for Approved by Eng Release Complete Constructiom items cleared Inspection items cleared Grouting Complete FW for NDE Hydrotesting Complete Complete Erection Constructiom items cleared Inspection items cleared Painting and
Eng Approval Inspection Clearance Complete Inspection Insulation
M-019 M-General Components not yet identified Pack Submitted Pack Accepted
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
P-002 CP Underground piping Test type Inspection Pack Inspection Pack Cleanliness FW Construction Punch items FW/Sharq FW/Sharq Released For Reinstatement Ready for water
Submitted for Approved by Eng Complete Punch cleared Inspection Punch items Reinstatement Complete filling
cleanliness inspection pack Eng Approval cleared
P-005 PI Interface Points - Piperacks & Test type Inspection Pack Inspection Pack Release Release Released to Cleanliness Welding and fit FW Construction Punch items FW/Sharq/EPC FW/Sharq/EPC
Submitted for Approved by Eng requested from received from Subcontractor Complete up complete Punch cleared Inspection Punch items
Undergrounds Eng Approval EPC EPC cleared
P-007 PTPU Piping Test Package Test type TP Submit For Initial Engrg Trench Construction FW Construction CAT "A" Punch FW/Sharq Pre Pre Hydro TP Submit For Final Submitted to QC Cleared Released For Hydro Test Reinstatement FW Construction FW Construction FW/Sharq Post FW/Sharq Post Released for Backfilling
Initial Engrg Review Excavation Complete Punch items cleared Hydro Punch 'Punchlist A Final Eng Engineering FW for QC Hydrotesting Complete Complete Post Punch Punch cleared Punch Punch Cleared Backfilling Complete
Underground Review Approved Handed over Items Cleared Review Review Review
Approved
P-008 PSV Pressure Safety/Relief Valve Calibrated Installation Removed for Sent to vendor Returned from Reinstated after FW / Sharq FW / Sharq
Complete Final Calibration for final vendor after final calibration inspection inspection
calibration final calibration accepted
P-011 TEST PACK Piping Test Package Test type TP Submit For Initial Eng Construction FW Construction CAT "A" Punch FW/Sharq Pre Pre Hydro TP Submit For Final Submitted to NDE Cleared Released For Hydro Test Reinstatement FW Construction FW Construction FW/Sharq Post FW/Sharq Post Released for Released For Released for
Initial Eng Review Complete Punch items cleared Hydro Punch Punchlist A Final Eng Engineering FW for NDE Hydrotesting Complete Complete Post Punch Punch cleared Punch Punch Cleared Painting and Line Cleaning Instruments
Review Approved Items Cleared Review Review Clearance Insulation
Approved
P-012 TIE-IN Piping Tie-ins Test type TP Submit For Initial Engrg Construction FW Construction CAT "A" Punch FW/Sharq Pre Pre Hydro TP Submit For Final Submitted to NDE Cleared Released For Hydro Test Reinstatement FW Construction FW Construction FW/Sharq Post FW/Sharq Post Released for Released For Released for
Initial Eng Review Complete Punch items cleared Hydro Punch 'Punchlist A Final Eng Engineering FW for NDE Hydrotesting Complete Complete Post Punch Punch cleared Punch Punch Cleared Painting and Line Cleaning Instruments
Review Approved Items Cleared Review Review Clearance Insulation
Approved
P-016 US Utility Stations Installation Hose Couplings FW/ Sharq FW/ Sharq
Complete Installed inspection inspection
accepted
P-017 USR/H Utility Hose Rack / Hoses Installation Hoses Installed FW/ Sharq FW/ Sharq
Complete inspection inspection
accepted
P-018 P-General Components not yet identified Test Type Pack Submitted Pack Accepted
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
PRECOM General Components not yet identified Pack Submitted Pack Accepted
-006
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
S-001 STEELWOR Platforms and Supports Inspection Pack Inspection Pack Foundation Primary Steel FW Construction CAT "A" Punch FW/Sharq CAT "A" Punch Released For Grouting Secondary FW CAT "A" Punch FW/Sharq Final Punch items Released For Released for
Submitted for Approved by Eng Release Erected Inspection items cleared Inspection items cleared Grouting Complete Steelwork Constructiom items cleared Inspection cleared Painting Fire Proofing
K Inspection Pack Eng Approval Erected Final Inspection
S-002 S-General Components not yet identified Pack Submitted Pack Accepted
QP Index Q-Pack Type Type Description QStep-1 QStep-2 QStep-3 QStep-4 QStep-5 QStep-6 QStep-7 QStep-8 QStep-9 QStep-10 QStep-11 QStep-12 QStep-13 QStep-14 QStep-15 QStep-16 QStep-17 QStep-18 QStep-19 QStep-20 QStep-21 QStep-22
TO-001 DC Discipline Completion Sub Contractor FW Walkdown FW/Sharq Cat FW QC DCC Issued to
QP Submitted Complete "A" Punch List Acceptance Sub Contractor
Cleared
TO-002 MC Mechanical Completion CCC issued to Released for Pre Pre Comm MCC issued for FW/Sharq Final FW/Sharq Final FW/Sharq MCC accepted All req'd punch Comm RFU Certificate RFU accepted RFSU RFSU accepted Sharq care and
Sub Contractor Comm. Completed Sharq Walkdown Walkdown Punch List bySharq list items cleared Completed Issued for Sharq by Sharq Certificate by Sharq custody
Acceptance Request Completed Cleared Acceptance Issued for Sharq
Acceptance
TO-003 SHD System Handover Dossier Sharq care and As-built dwgs Mechanical Spares Available Final Issue for client All Exception Provisional Provisional
custody available Catalogues Documentation Acceptance items cleared Turnover Turnover
available Available Acceptance Acceptance
issued to Sharq accepted by
Sharq
TO-004 Turnover Tracking of Quality Packs MC date Qpack due date Civils Steelwork Piping Coating Mechanical Electrical Instruments Instrument loops Submitted to FW Accepted FW Rejected FW Submitted to Accepted PMT Rejected PMT Returned for Accepted Qpack
PMT scanning + copies
(Sub system dossiers) received