Permits and Other Fees 15 days

Mobilization 5 days
Project Sign Boards 5 days
Temporary Facilities 5 days

RAMP 1 (Limits) ELECTRICAL WORKS


Clearing and Grubbing 8 days Panel Boards and Circuit Brea
Staking and Laying Out 10 days Wiring Devices, Conduits and
Excavation 15 days Electrical Wiring
Backfilling and Compaction 10 days Lighting
Embankment 15 days Energy Generating Speed Hu
Subgrade Preparation on Existing Gravel 15 days
Subgrade Preparation on Existing Pavement 15 days
Aggregate Subbase Course 10 days
Asphalt Concrete Pavement 10 days
Stone Masonry 15 days
Concrete Curb and Gutter 30 days
Toll Gate 35 days
Reinforcing Bars 5 days
Formworks 2 days
Masonry 5 days
Concreting 3 days
Drainage 25 days
Sidewalks 10 days
Guard Rail 10 days
Painting Works 10 days
Reflective Thermoplastic Stripping Materials (Yellow) 5 days
Reflective Thermoplastic Stripping Materials (White) 5 days

RAMP 2 (Limits)
Clearing and Grubbing 5 days
Staking and Laying Out 10 days
Excavation 10 days
Backfilling and Compaction 15 days
Subgrade Preparation on Existing Gravel 10 days
Subgrade Preparation on Existing Pavement 15 days
Aggregate Subbase Course 5 days
Asphalt Concrete Pavement 5 days
Toll Gate 35 days
Reinforcing Bars 5 days
Formworks 3 days
Masonry 5 days
Concreting 5 days
Drainage 15 days
Sidewalks 5 days
Guard Rail 5 days
Painting Works 10 days
Reflective Thermoplastic Stripping Materials (Yellow) 2 days
Reflective Thermoplastic Stripping Materials (White) 2 days
Retaining Wall 25 days

RAMP 3 (Limits)
Clearing and Grubbing 5 days
Staking and Laying Out 10 days
Excavation 10 days
Backfilling and Compaction 15 days
Subgrade Preparation on Existing Gravel 10 days
Subgrade Preparation on Existing Pavement 15 days
Aggregate Subbase Course 5 days
Asphalt Concrete Pavement 5 days
Toll Gate 35 days
Reinforcing Bars 5 days
Formworks 3 days
Masonry 5 days
Concreting 5 days
Drainage 15 days
Sidewalks 5 days
Guard Rail 5 days
Painting Works 10 days
Reflective Thermoplastic Stripping Materials (Yellow) 2 days
Reflective Thermoplastic Stripping Materials (White) 2 days
Retaining Wall 25 days

RAMP 4 (Limits)
Clearing and Grubbing 5 days
Staking and Laying Out 10 days
Excavation 10 days
Backfilling and Compaction 15 days
Subgrade Preparation on Existing Gravel 10 days
Subgrade Preparation on Existing Pavement 15 days
Aggregate Subbase Course 5 days
Asphalt Concrete Pavement 5 days
Toll Gate 35 days
Reinforcing Bars 5 days
Formworks 3 days
Masonry 5 days
Concreting 5 days
Drainage 15 days
Sidewalks 5 days
Guard Rail 5 days
Painting Works 10 days
Reflective Thermoplastic Stripping Materials (Yellow) 2 days
Reflective Thermoplastic Stripping Materials (White) 2 days
Retaining Wall 25 days
MANPOWER Quantity
Project Manager 1
Project Engineer 1
Surveryor 2
Electrical Engineer 1
Materials Engineer 1
Foreman 2
Safety Officer 2
Heavy Equipment Operator 27
Skilled 10
Laborer 20
Carpenter 4
Steel Man 5
Electrician 4
Painter 3
Welder 4
Diver 2

EQUIPMENT
Backhoe with Breaker 2
Dumptruck 4
Payloader 1
Backhoe 2
Road Grader 1
Road Roller 2
Water Truck 1
Bulldozer 1
Road Paver 1
Service Elf 1
Welding Machine 2
Bar Cutter 2
Bar Bender 2
Road Roller (Walk Behind) 1
Plate Compactor 1
One Bagger Mixer 2
Boom Truck 1
Service Vehicle 2
ELECTRICAL WORKS
Panel Boards and Circuit Breakers 25 days
Wiring Devices, Conduits and Fittings 30 days
Electrical Wiring 20 days
20 days
Energy Generating Speed Humps 20 days