LEGACY OIL SDN BHD (856886-X)

PROJECT TITLE : 1,000MW PRAI CCPP/MALAYSIA

Form F. Manpower(Staff & Labor) Mobilization Schedule

NO. DESCRIPTION PEAK ASSUMED NUMBER OF MOBILIZATION PER EACH CALENDAR MONTH REMARK


ManPower 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47
1 STAFF
Project Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Project Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Technical Engineer 2 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1
Piping Engineer 3 1 1 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 1 1 1
Mechannical Engineer 3 1 1 1 2 2 3 3 3 3 3 3 3 3 3 3 3 3 2 2 2 1 1 1 1
Structure Engineer 2 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
QS Engineer 2 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Superintendence 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Supervisor 3 1 1 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 1 1 1
Document Control ( DCC / Clerk) 5 1 2 2 4 4 4 5 5 5 5 5 5 5 5 5 4 2 2 2 2 2 2 2 2
QA/QC 4 1 3 3 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 2
HSE Coordinator 2 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1
SUB TOTAL 29 12 16 20 24 27 28 29 29 29 29 29 29 29 29 29 28 26 25 25 23 22 18 16 13

2 LABOR
Foreman 5 1 2 2 3 4 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 3 2
Mechanical Fitter 12 4 4 8 8 10 12 12 12 12 12 12 12 12 12 12 12 12 12 12 6 6 6 4 2
Structure Fitter 12 2 4 4 4 12 12 12 12 12 12 8 8 8 8 8 8 8 6 6 6 6 2 2 2 2
Pipe Fitter 16 2 2 2 10 10 16 16 16 16 16 16 16 16 12 12 12 12 6 6 6 6 2 2
Instrument Fitter 8 2 4 4 8 8 8 8 8 8 8 8 8 8 6 6 6 6 4 4 4 4
Rigger  48 6 6 12 18 18 24 24 36 36 48 48 48 48 48 48 48 48 48 48 48 48 24 24 24 6
Millwright 6 1 2 2 2 6 6 6 6 6 6 6 4 4 4 2 2 2 2 2 2 2
Grinder 18 1 2 2 2 6 10 16 18 18 18 18 18 18 18 18 18 18 18 18 18 18 10 10 2 2
Semi Skill 20 2 2 4 16 16 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 10 10 4 4
Store Keeper 2 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Welder (SMAW) 18 4 8 8 18 18 18 18 18 18 18 18 18 18 15 15 15 10 8 8 4 4 2
Welder (TIG) 12 2 6 6 10 10 12 12 12 12 12 12 12 12 12 12 10 8 8 4 4 2 2
Welder (3G4G) 12 1 2 2 3 3 4 12 12 12 12 12 12 12 12 12 10 6 6 6 6 4 4 2 2 2
Material Coodinator 2 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Hydrotester 18 6 6 6 18 18 18 18 18 18 18 18 18 18 12 12 12 6 6
General Worker 30 6 10 10 15 20 20 24 30 30 30 30 30 30 30 30 30 30 30 20 20 20 20 20 20 20
Cleaner 6 2 2 2 3 3 3 3 4 4 6 6 6 6 6 6 4 4 4 4 4 4 4 4 4
SUB TOTAL 245 18 36 44 71 113 137 176 212 219 231 241 241 241 241 241 233 224 220 206 193 177 125 119 89 66

TOTAL 274