Anda di halaman 1dari 8

HOME

Adaptation of an Open Pit Optimiser


for Underground Strategic Planning
B Roberts1 and M Bloss2

ABSTRACT
BHP Billiton Olympic Dam required a well-tested software product suitable for strategic
optimisation and scheduling of options for a potential underground mining project. The company
has a standard software package called Blasor® that is used for open pit optimisation of complex
deposits such as iron ore, copper-gold-uranium and silver-lead-zinc. It applies a mixed integer
programming formulation (MIP) to produce conceptual pushback designs and an optimised
pushback sequence. Schedules can then be run on the resulting mine designs. Existing pushback
designs can also be imported into the model and an optimum schedule generated. One of the key
advantages of Blasor is that multiple strategic mine schedules can be quickly generated according
to the various scenarios, options and constraints that are being investigated.
It was realised that Blasor, if carefully configured, could be adapted for use in underground
planning. The concept of using Blasor as an optimiser for underground strategic scenarios is to
represent the underground stope and development data in the form and structure of an open pit
mine. In simple terms, underground stoping areas are modelled in the form of pushbacks (phases)
with vertical walls. The phase dependency tools in Blasor are used to link mine blocks and their
access development drives. These underground phases are imported into the optimiser. Artificial
block models are constructed using stope design tonnage and grade data at various fixed cut-offs.
A variable cut-off grade model has also been developed using a method of parcels to represent
each cut-off grade increment.
So far, this approach has been successfully used to investigate the optimum stope design cut-
off for various strategic options, the economic potential of a series of mining and processing
configurations and to provide guidance on the optimum sequence for developing and mining the
various stoping blocks in the resource. Examination of the results has highlighted the most suitable
development paths for more detailed study.

INTRODUCTION
In modern mine planning systems it is now widespread scheduling of various scenarios and options. With insufficient
practice to apply some form of optimisation to the mine time in the project timeline to investigate, test and acquire a
extraction limits and production schedule. A number of suitable purpose-built underground optimiser there was an
open pit optimisation software packages are commercially opportunity to apply an open pit software package. BHP
available, such as Whittle (GEOVIA, 2014), Minemax Billiton has a standard software package called Blasor®
Planner (Minemax, 2014) and COMET (King, 2004; (Stone et al, 2004) that is used for open pit optimisation. It
Wooller, 2004) but the authors are aware of no comparable applies mixed integer programming to carry optimisation
underground product in common use. Underground of pit limits and pushbacks (also termed phases or stages).
optimisation tools have been developed, examples being
The resulting conceptual mine designs are then applied to
the ‘hill of value’ system (Hall and Stewart, 2004), Snowden
generate optimised schedules. Existing pushback designs can
Evaluator (Elkington, Durham and Myers, 2009) and LOBOS
also be imported into the model. One of the key advantages of
(Smith, 2007) but they are propriety products operated by
consultants on the client’s behalf. Underground scheduling Blasor is that multiple strategic mine schedules can be quickly
packages can be purchased, such as Runge XPAC and generated according to the various scenarios, options and
Geovia MineSched, but they are single-period rather than constraints that are being investigated. It was realised that
multiperiod life-of-asset optimisers. Blasor could be adapted for use in underground planning by
BHP Billiton Olympic Dam mines a very large and complex modelling the underground stope and development data in
orebody for copper, uranium, gold and silver. The asset is the form and structure of an open pit mine. This idea could
conducting a study into a potential underground expansion be implemented immediately and, after experimentation with
project and required a tool for strategic optimisation and two preliminary versions, a suitable system was developed.

1. MAusIMM(CP), Superintendent Mine Optimisation, Olympic Dam, BHP Billiton, Level 2, 55 Grenfell Street, Adelaide SA 5000. Email: brian.roberts2@bhpbilliton.com
2. MAusIMM(CP), Director Mining Studies and Technology, Olympic Dam, BHP Billiton, Level 2, 55 Grenfell Street, Adelaide SA 5000. Email: martyn.l.bloss@bhpbilliton.com

OREBODY MODELLING AND STRATEGIC MINE PLANNING SYMPOSIUM 2014 / PERTH, WA, 24–26 NOVEMBER 2014 249
B ROBERTS AND M BLOSS

MODELLING OF THE UNDERGROUND stope is mined by selecting the appropriate parcels to be


directed to the process stream. Other parcels are sent to the
OPERATION waste stream at no mining cost, which represents that part of
the stope remaining in the ground. Mining costs include in-
Mining block and stope modelling stope development, ground support, raise bores, production
The concept of using Blasor as an optimiser for underground drilling and blasting, loading, haulage by truck and/or rail
strategic scenarios is to represent the underground stope and backfilling. For processed parcels the mining cost is
and development data in the structure of an open pit mine. included in the ore processing cost.
In simple terms, underground mine areas are modelled Fixed COG Blasor models are also generated. These models
in the form of pit phases with vertical walls and the phase are similar to the variable COG model with the exception that
dependency tools in Blasor are used to link mine blocks and there is no parcelling. Note that fixed COG Blasor models may
their access development drives. include stockpiles but variable COG models cannot because
Using the current mineable resource model, stope shapes parcels not sent to the plant in a particular period could be
at six different cut-off grades are generated using the stockpiled and processed later. Coordinates in the artificial
Datamine Mineable Reserves Optimiser (MRO). This tool block model approximate the spatial location of each mine
generates an envelope around sets of blocks in the resource block. (See Figure 2, which also gives the phase number for
model that correspond to the specified design COG. Stope each set of stopes and development.)
shapes are then automatically generated according to given
maximum and minimum dimensions. Each set of designs is Development and mining dependencies
then classified into the three main mining areas. Areas are Figure 2 shows the dependencies within each mining block.
further divided into separate ‘stope blocks’. Each stope block Development phases are at a higher elevation than the stope
is modelled as illustrated by Figure 1. Tonnage and grades phases. To start mining a block the block access phase must
for each stope are represented by a cell in a artificial block be mined out, followed by the internal block development
model. Data for each mine block is divided into grade ranges phase. Stope phases are all then available for mining.
according to the copper equivalent value for each stope and Dependencies between mining blocks are modelled in a
these ranges are modelled in turn as separate ‘phases’ within similar way (Figure 2). For example, to start mining stopes in
the Blasor model structure. Within each phase, stope blocks H2, both development phases 1 and 2 must be mined. To start
are stacked vertically by order of copper equivalent grade, mining in H3, the block access development for H2 (phase1)
highest to lowest. Block development is also represented by must be mined, then the block access development for H3
Blasor phases. (phase 10). After phase 10, internal development for H3 can
Figure 1 shows how a ‘variable cut-off grade’ model is start (phase 11) and when this is complete the stope blocks
structured. Each block (stope) is divided into a number are available. The arrows indicate the dependencies between
of tonnage and grade parcels. The first parcel represents mine blocks.
the tonnes and grade for the highest design cut-off grade,
(4.1 CuEq in Figure 1). The incremental tonnes and grade for Development tonnages and sequence
each reduction in design COG are represented by subsequent Mine development tonnages, metres, rate and sequence are
parcels. The Blasor model chooses the COG at which each supplied from development planning and scheduling that

FIG 1 – Blasor modelling of each mine block.

250 OREBODY MODELLING AND STRATEGIC MINE PLANNING SYMPOSIUM 2014 / PERTH, WA, 24–26 NOVEMBER 2014
ADAPTATION OF AN OPEN PIT OPTIMISER FOR UNDERGROUND STRATEGIC PLANNING

FIG 2 – Blasor modelling of the underground mine.

has been carried out with Mine2–4D (MineRP, 2014). The phase within the blocks. These constraints are proportional to
development layout is therefore predefined but the sequence the tonnage within each unit (Figure 3). This relationship has
and timings can be determined by the optimisation model. If been derived from schedules produced by an underground
required, the Blasor model can be used to impose constraints version of the Runge XPAC product, which closely simulates
on mine development by either annual metres or annual
the way in which the stopes can actually be mined. For
tonnage.
example it takes into account the time lag between mining a
Stoping rates particular stope and being able to start the mining of adjacent
The structure of the Blasor UG model may allow the optimiser stopes. It also incorporates stope ramp-up and ramp-down
to mine all the high-grade stopes first if no other constraints extraction rates. Figure 3 shows the chart for the average XPAC
were imposed. To make the scenario more realistic, maximum mining rate. To test the effect of a higher ‘mining intensity’ a
mining limits are imposed on each mine block and each stope maximum XPAC mining rate can be applied instead.
4,000,000

3,500,000
y = 0.0381x + 250000
Av Block Stoping rate Mtpa

3,000,000
R² = 0.9232

2,500,000

2,000,000

1,500,000

1,000,000

500,000

Stope Block Tonnage

FIG 3 – Relationship for stope mining constraints.

OREBODY MODELLING AND STRATEGIC MINE PLANNING SYMPOSIUM 2014 / PERTH, WA, 24–26 NOVEMBER 2014 251
B ROBERTS AND M BLOSS

PROCESS the mining sequence and schedule. The variable COG model
is also optimising design COG by stope block and time. Note
For any particular project study, a set process has been
that the curves do not follow a smooth line as the estimated
established. Circumstances that initiate a new study include:
capital cost increases for certain expansion options are not
release of a new resource model, escalation of the project to a
linear. It is important to note here that the NPVs generated
new level, eg from project identification phase to prefeasibility
for various options are heavily dependent on the investment
phase and availability of cost estimates at a higher level of
capital assumptions for mining, processing and infrastructure.
confidence.
As cost estimates at higher levels of confidence are obtained
For each cut-off grade the conceptual stope designs are by the project team, further iterations of the optimisation
fixed, as Blasor cannot optimise the stope shapes. Artificial process will be required to either confirm or modify the initial
block models for each fixed COG and a variable COG model findings.
are then produced by means of the process described earlier.
Of the fixed COGs, the lower COG gives the best value
Access development sequence, tonnages, metres and mining
for this range of mine expansion options. A larger resource
rates are supplied by the underground mine planning team
and the higher mining rates from the increase inventory of
and included in the block models. Maximum mining rates for
stope blocks means that process capacity can be filled more
each stope block and phase are calculated using data from
consistently. At the high COG, value drops after the third
existing XPAC schedules. Finally, financial data is assembled
expansion option as the higher-cost larger mill capacities
(commodity process, metal recoveries, variable costs, fixed
cannot be filled. Values rise fairly steeply up until the first
costs, etc) and processed to create the optimiser economic
expansion option then display a general trend to level off.
model. With all inputs gathered and processed into suitable
This result indicates that under a capital-constrained business
form, the Blasor underground optimisation model can be environment Expansion scale 4 would be the preferred option.
built.
A variable COG policy gives the best value up to Expansion 4
At this stage, the planning team will have drawn up a as higher cut-off and consequently higher feed grades can be
matrix of scenarios, options and constraints that are to be mined initially. At higher capacities, values between variable
investigated. The full set of cases can easily total over one and fixed 3.1 COG tend to coincide, as the variable COG
hundred. Blasor ‘projects’ for each case are run with the model is effectively mining at 3.1COG from the start. There
results being saved and recorded. Blasor output data in is some variation at the two largest capacities, mainly because
the form of schedule physicals are entered into a valuation the fixed COG model has the facility for stockpiling. Figure 5
model to generate a realistic net discounted cash flow for each shows a comparison in cumulative values between Expansion
case. The most favourable alternatives are then selected for scale 1 and Expansion scale 4. For this mining method and
more detailed planning studies, including XPAC schedules. processing alternative, the higher capital cost of the larger
Analysis of the Blasor schedules such as COG results, stope expansion is offset by higher revenues over the project life.
block timing and ore processing constraints is used to guide
this further planning work. Timing and cut-off grade for each block
Output from the model can be used to identify the most
USES FOR THE OPTIMISATION MODEL favourable sequence for developing and commencing mining
in each stoping block (one of the policies that have been
Project value, scale and cut-off grade optimised). It is not possible with this tool to optimise the
A major role in the user of the optimiser is in the assessment development network, so the access development design is
of project value (NPV) for various possible mining and fixed. However, the optimiser can select when to start mining
processing configurations and investigation of the optimum each development section and can bypass a stoping block
global COG for each of these alternatives. Figure 4 illustrates if there is one later in the sequence that presents a greater
the results from running a series of fixed COG models and contribution to value. Excel pivot tables can be used to sort the
a variable COG model for a range of large-scale mining and raw optimiser output so that the user can see the production
process capacity expansions. Uniform expansion increments from each block in each period. Figure 6 shows part of such
in excess of 1 Mt/a each are numbered 1 to 8 in order of a pivot table; each stope block is represented as a different
increasing scale. In this set of runs we are fixing project scale colour and the access developments are shaded grey. Arrows
and stope design cut-off then allowing the model to optimise indicate the development dependencies.

9,000

8,000

7,000

6,000
Project Value

5,000

4,000

3,000

2,000

1,000

0
0 1 2 3 4 5 6 7 8 9
-1,000
Expansion Option (Scale)
3.1COG 3.3COG 3.5COG 3.7COG VariableCOG

FIG 4 – Incremental value versus process capacity for five cut-off grade policies.

252 OREBODY MODELLING AND STRATEGIC MINE PLANNING SYMPOSIUM 2014 / PERTH, WA, 24–26 NOVEMBER 2014
ADAPTATION OF AN OPEN PIT OPTIMISER FOR UNDERGROUND STRATEGIC PLANNING

18,000

16,000

14,000

12,000

Cumulative Value
10,000

8,000

6,000

4,000

2,000

0
2015 2020 2025 2030 2035 2040 2045 2050 2055 2060 2065 2070 2075
-2,000

-4,000
Time
-6,000

Expansion Scale 1 Expansion Scale 4

FIG 5 – Cumulative value for two expansion options.

FIG 6 – Output for optimised mining sequence. Values in each cell indicate annual production in kilotonnes.

The variable COG model can also be used to examine come into production, then drop over time as the best material
selected COG for each stope block over time. Each parcel is exhausted.
within a cell is coded according to the COG increment it
represents. Analysis of the output, although quite time Mine development rates and process
consuming, allows the user to determine the COG at which
each stope block is being mined during each period. Figure 7
configurations
gives an example of data derived from part of an output pivot One set of development options involves development into
table. The lower COGs for the blocks that commence mining the new resource zone but with a small-scale ore processing
first correspond to a mine access ramp-up time when the expansion. In addition to estimating the value of the plant
cut-off across a smaller number of blocks must be dropped improvements, it was necessary to assess the influence of
in order to fill the mill. Cut-offs are then raised as all blocks mine development rates on project value. Figure 8 shows a

OREBODY MODELLING AND STRATEGIC MINE PLANNING SYMPOSIUM 2014 / PERTH, WA, 24–26 NOVEMBER 2014 253
B ROBERTS AND M BLOSS

FIG 7 – Output for optimised cut-off grade with time. Values in each cell indicate cut-off as CuEq per cent.

10,000

9,500

9,000

8,500
Project value

8,000

7,500

7,000

6,500

6,000
25 50 75 100 125 150 175
Mining Development Rate - % of Base Rate

No Smelter expansion Smelter expansion 1 Smelter expansion 2

FIG 8 – Value of smelter expansion and mine development rate with fixed mill capacity.

plot of the results for a fixed mill capacity with curves for no such as reporting the largest ore reserve, or achieving some
smelter expansion and two smelter capacity increase options. aspiration production target such as 1 Moz per year. To
The horizontal axis gives development rates as a percentage investigate the impact on the schedule of aiming to achieve
of a ‘base rate’ that corresponds to the current planned rate. the highest internal rate of return (IRR) or the shortest
Results indicated to the planning team that the smaller of payback period, the optimiser can be run at higher discount
the two smelter expansions was the most promising option. rates. Figure 10 shows the impact on the early years of a
Accelerated development rates show a minor improvement schedule, where the COG is raised to produce a higher head
in value but it should also be noted that the optimisation did grade. This strategy, however, can reduce the NPV for the life
not take into account the associated higher contract rates and of the project.
fixed costs due to more complex operational arrangements.
Slower development rates, however, showed a significant Obtain estimate of feed grades and product
reduction in value as production from the new high-grade
stope blocks is delayed.
quantities for different cases
The simplest type of report available is an estimate of feed
Impact of plant feed constraints grade profiles and product quantities over time (Figure 11).
For any particular mining and processing configuration the
Within Blasor, a series of Products and Attributes can be
operation will be running at different points on the grade-
calculated from the input data and used to model various
process plant constraints such as feed copper-sulfur ratios, tonnage curve. Because Blasor can run many cases in a
sulfur tonnes, and concentrate throughput. The current plant relatively short time, this data can be obtained for a range of
has a minimum copper:sulfur limit that heavily influences stope design cut-off grades, mining capacities and processing
the mining schedule. By comparing different options, the capacities.
economic value of engineering an expanded plant with
relaxed feed constraints can be estimated (Figure 9). CONCLUSIONS
The in-house adaptation of an open pit optimiser provided
Effect on the schedule of valuation criteria a readily-available tool for generating a large number of
The most usual business strategy of mining companies is to strategic mine planning solutions within a short time frame.
maximise NPV (King, 2009), but there are other measures The method has been successfully used to investigate the

254 OREBODY MODELLING AND STRATEGIC MINE PLANNING SYMPOSIUM 2014 / PERTH, WA, 24–26 NOVEMBER 2014
6,000 ADAPTATION OF AN OPEN PIT OPTIMISER FOR UNDERGROUND STRATEGIC PLANNING

5,000
Plant1 and Plant2 min
CuS=1.5
4,000

Project value
Plant1 min CuS=1.5,
Plant2 CuS unconstrained
3,000
Plant1 and Plant2 CuS
unconstrained
2,000
Plant1 and Plant2 CuS
constrained by sulphur
1,000 capacity

0
3.1 COG 3.3 COG Variable COG

FIG 9 – Impact of plant feed sulfur constraints on project value.

2.8%

2.6%
Copper feed grade

2.4%

2.2%

2.0%

1.8%

1.6%

1.4%
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1
2
3
4
5
6
7
8
9

Year
Low Discount Rate High Discount Rate

FIG 10 – Copper feed grade with low and high discount rates.
2.60%

2.40%

2.20%
Copper feed grade 

2.00%

1.80%

1.60%

1.40%
2015 2025 2035 2045 2055 2065 2075
Year
Expansion1 Expansion2 Expansion3 Expansion4

FIG 11 – Copper feed grade by expansion capacity.

optimum stope design cut-off for various strategic options, example, can be readily applied to this work (Wooller, 2004).
the economic potential of a series of mining and processing It is not being suggested that such models could replace
configurations and to provide guidance on the optimum a custom-built underground optimiser for more detailed
sequence for developing and mining the various stoping blocks studies but the results and insights that they create can be
in the resource. Examination of the results has highlighted the used as part of a business case for further planning studies.
most suitable development paths for more detailed study,
thereby reducing the required number of detailed planning REFERENCES
exercises and reducing the impact of scheduling studies on
Elkington, T, Durham, R and Myers, P, 2009. Optimising value
the overall study project calendar.
for an underground project configuration, in Proceedings
By re-configuring the input data in a similar way, it may Orebody Modelling and Strategic Mine Planning Conference 2009,
be possible to adapt other pit optimisation packages for use pp 250–256 (The Australasian Institute of Mining and Metallurgy:
in high-level underground strategic planning. COMET, for Melbourne).

OREBODY MODELLING AND STRATEGIC MINE PLANNING SYMPOSIUM 2014 / PERTH, WA, 24–26 NOVEMBER 2014 255
B ROBERTS AND M BLOSS

GEOVIA, 2014. The world’s most trusted strategic mine MineRP, 2014. Mine2–4D – the benchmark in mine planning solutions
planning software [online]. Available from: <http://www. [online]. Available from: <http://www.minerpsolutions.com/
gemcomsoftware.com/sites/default/files/products/whittle/ docs/default-source/salescollateral/mine2-4d.pdf> [Accessed:
GEOVIA_Whittle_Brochure.pdf> [Accessed: 13 August 2014]. 18 August 2014]
Hall, B E and Stewart, C A 2004. Optimising the strategic mine plan Smith, M, 2007. Life of business optimisation – the mathematical
– methodologies, findings, successes and failures, in Proceedings programming approach, in Proceedings Project Evaluation 2007,
Orebody Modelling and Strategic Mine Planning Conference 2004, pp 139–146 (The Australasian Institute of Mining and Metallurgy:
pp 49–58 (The Australasian Institute of Mining and Metallurgy: Melbourne).
Melbourne).
Stone, P, Froyland, G, Menabde, M, Law, B, Pasyar, R and
King, B, 2004. Integrated strategy optimisation for complex Monkhouse, P, 2004. Blasor – blended iron ore mine planning
operations, in Proceedings Orebody Modelling and Strategic Mine optimisation at Yandi, in Proceedings Orebody Modelling and
Planning Conference 2004, pp 391–397 (The Australasian Institute Strategic Mine Planning Conference 2004, pp 285–288 (The
of Mining and Metallurgy: Melbourne). Australasian Institute of Mining and Metallurgy: Melbourne).
King B, 2009. Optimal mining principles, in Proceedings Orebody Wooller, R, 2004. Optimising multiple operating policies for
Modelling and Strategic Mine Planning Conference 2009, pp 1–6 (The exploiting complex resources — an overview of the COMET
Australasian Institute of Mining and Metallurgy: Melbourne). scheduler, in Proceedings Orebody Modelling and Strategic Mine
Planning Conference 2004, pp 77–89 (The Australasian Institute of
Minemax, 2014. Mine Scheduler – strategic mine schedule
Mining and Metallurgy: Melbourne).
optimisation [online]. Available from: <http://www.minemax.
com/downloads/Minemax-Scheduler-White-Paper.pdf>
[Accessed: 8 August 2014].

256 OREBODY MODELLING AND STRATEGIC MINE PLANNING SYMPOSIUM 2014 / PERTH, WA, 24–26 NOVEMBER 2014

Anda mungkin juga menyukai