1.

)DIKETAHUI :

PROYEK JALAN DENGAN PANJANG JALAN 5 KM = 5000 M,


LEBAR 12 M,
TEBAL LAPISAN 30 CM = 0,30 M
AKAN DIURUG / DITIMBUN
.
DITANYAKAN :

HITUNGLAH VOLUME DAN ANALISA KEBUTUHAN SERTA BIAYA HARGA PELAKSANAANNYA…


JAWABANNYA :

1. SURVEY LOKASI,KUALITAS DAN SUMBER MATERIAL


2. ANALISA KEBUTUHAN ALAT,DAN HARGA SEWANYA
3. RENCANAKAN KEBUTUHAN PEKERJA SERTA MANDOR

RENCANA LOKASI PENGAMBILAN MATERIAL GUNUNG PENGSONG

VOLUME :

=5.000 x 0,3 x 12 = 18.000 M3

ANALISIS KEBUTUHAN ALAT :

1.) EXCAVATOR (HARGA SEWA RP. 3,500.000) 10 JAM /HARI


LUAS BUCKET = 0,8 M3
DIASUMSIKAN ALAT EXCAVATOR MENGANKUT SERTA MENGGALI MATERIAL ADALAH
4 MENIT. JADI, 60/4 = 15 KALI MENGANGKUT
JADI VOLUME YANG DIHASILKAN 1 EXCAVATOR = 15 x 0,8 x 10 = 120 M3/HARI
MAKA, 18.000/120 = 150 HARI
 BILA MEMAKAI 3 EXCAVATOR MAKA 150/3 = 50 HARI
 HARGA SEWA ALAT 150 x 3,500.000 = RP. 525,500.000

2.) DUMP TRUCK (HARGA SEWA RP. 350.000) 10 JAM /HARI


LUAS BAK = 4 M3
DIASUMSIKAN TRUCK DAPAT MENGANGKUT MATERIAL BOLAK BALIK GUNUNG
PENGSONG-KE PROYEK SEBANYAK 8 KALI.
JADI VOLUME YANG DIHASILKAN 1 DUMP TRUCK = 4 x 8 = 32 M3/HARI
MAKA, 18.000/32 = 563 HARI
 BILA MEMAKAI 12 DUMP TRUCK MAKA 563/12 = 47 HARI
 HARGA SEWA ALAT 563 x 350.000 = RP. 197,050.000

3.) MOTOR GRADER (HARGA SEWA RP. 1,700.000) 10 JAM /HARI


KECEPATAN = 5 KM/JAM
LUAS BLADE = 3,7 M3
KOEFISIEN = 2,6 M3
DIASUMSIKAN MOTOR GRADER DAPAT MERATAKAN MATERIAL DALAM SEHARI
SEBANYAK 500 M3/HARI.
JADI VOLUME YANG DIHASILKAN 1 MOTOR GRADER = 18.000/500 = 36 HARI
 HARGA SEWA ALAT 36 x 1,700.000 = RP. 61,200.000

4.) ROAD ROLLER (HARGA SEWA RP. RP. 350.000) 10 JAM /HARI
KECEPATAN = 6 KM/JAM
DIASUMSIKAN ROAD ROLLER DAPAT MEMADATKAN MATERIAL DALAM SEHARI
SEBANYAK 300 M3/HARI.
JADI VOLUME YANG DIHASILKAN 1 ROAD ROLLER = 18.000/300 = 60 HARI
 BILA MEMAKAI 2 ROAD ROLLER MAKA 60/2 = 30 HARI
 HARGA SEWA ALAT 60 x 350.000 = RP. 21,000.000

5.) WATER TANK (HARGA SEWA RP. RP. 250.000) 10 JAM /HARI
VOLUME WATER TANK = 5000 LITER
DIASUMSIKAN WATER TANK DAPAT MENGAIRI DALAM SEHARI SEBANYAK 500
M3/HARI.
JADI VOLUME YANG DIHASILKAN 1 WATER TANK = 18.000/500 = 36 HARI
 HARGA SEWA ALAT 36 x 250.000 = RP. 9,000.000

REKAPITULASI BIAYA SEWA ALAT :

I. HARGA SEWA ALAT EXCAVATOR 150 x 3,500.000 = RP. 525,500.000


II. HARGA SEWA ALAT DUMP TRUCK 563 x 350.000 = RP. 197,050.000
III. HARGA SEWA ALAT MOTOR GRADER 36 x 1,700.000 = RP. 61,200.000
IV. HARGA SEWA ALAT ROAD ROLLER 60 x 350.000 = RP. 21,000.000
V. HARGA SEWA ALAT WATER TANK 36 x 250.000 = RP. 9,000.000

TOTAL BIAYA SEWA ALAT = RP. 813,750.000

ESTIMASI (KIRA-KIRA) BIAYA PEKERJA DAN MANDOR :

BILA HARI YANG DITARGETKAN ATAU HARI TERLAMA MASA PENGERJAAN ADALAH 50 HARI.

 PEKERJA
BILA UPAH PEKERJA SESUAI HARGA STANDAR UPAH PERATURAN GURBERNUR
PROVINSI NTB TAHUN 2016 DAERAH LOMBOK =
RP. 60.500,/HARI,
DAN JUMLAH PEKERJA 30 ORANG.
MAKA UPAH PEKERJA BILA DIAMBIL LAMA KERJA 50 HARI x 60.500 x 30 =
RP. 90,750.000.
 MANDOR
BILA UPAH MANDOR SESUAI HARGA STANDAR UPAH PERATURAN
GURBERNUR PROVINSI NTB TAHUN 2016 UNTUK DERAH LOMBOK =
RP. 94.600,/HARI
DAN MANDOR 7 ORANG
MAKA UPAH MANDOR BILA DIAMBIL LAMA KERJA 50 HARI x 94.600 x 7 =
RP. 33,110.000.

REKAPITULASI HARGA SEWA ALAT DAN BIAYA UPAH :

I. TOTAL BIAYA SEWA ALAT = RP. 813,750.000.


II. TOTAL UPAH PEKERJA = RP. 90,750.000.
III. TOTAL UPAH MANDOR = RP. 33,110.000.

TOTAL BIAYA KESELURUHAN : RP. 937,610.000 (SEMBILAN RATUS TIGA PULUH TUJUH JUTA
ENAM RATUS SEPULUH RIBU RUPIAH)

RATA – RATA BIAYA JALAN PERKILOMETER PANJANG.

= MAKA RP. 937,610.000 / 5 KM = RP. 187,522.000/KM