TIME SCHEDULE

PROGRAM : PEMBANGUNAN RUMAH TI NGGAL


PEKERJAAN : KOTA SOLOK

JANGKA WAKTU PELAKSANAAN


NO. UARAIAN PEKERJAAN BOBOT BULAN KE. I BULAN KE. II BULAN KE. III BULAN KE. IV
(%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

I PEKERJAAN PENDAHULUAN 1.77 1.77

II PEKERJAAN TANAH 2.45 1.23 1.23

III PEKERJAAN PONDASI 11.39 3.80 3.80 3.80

IV PEKERJAAN BETON 22.22 7.41 7.41 7.41

V PEKERJAAN DINDING 24.59 8.20 8.20 8.20

VI PEKERJAAN ATAP 15.83 5.28 5.28 5.28

VII PEKERJAAN KUSEN, PINTU DAN JENDELA 3.24 1.62 1.62

VIII PEKERJAAN SANITAIR 2.48 1.24 1.24

IX PEKERJAAN ELEKTRIKAL 0.77 0.39 0.39

X PEKERJAAN PLAFOND 5.78 2.89 2.89

XI PEKERJAAN FINISHING 9.46 2.37 2.37 2.37 2.37

RENCANA BOBOT PERMINGGU 100.0 1.77 1.23 5.02 3.80 11.21 7.41 7.41 8.20 8.20 13.48 6.90 6.90 6.50 6.88 2.75 2.37
RENCANA KOMULATIF BOBOT PERMINGGU - 1.77 3.00 8.02 11.82 23.02 30.43 37.84 46.04 54.23 67.71 74.61 81.50 88.00 94.88 97.63 100.00
REALISASI BOBOT PERMINGGU
REALISASI KOMULATIF BOBOT PERMINGGU
DEVIASI ( + / - )