RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN RUMAH TINGGAL 1 LANTAI


LUAS BANGUNAN : LB = 45m2, LT = +/- 65 m2
LOKASI :
TAHUN : 2018

H.SATUAN H.KESATUAN JUMLAH


NO URAIAN PEKERJAAN Kode VOL/SAT
[Rp.] [Rp.] [Rp.]

1 2 3 4 5 6 7

A PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan A. 2.2.1.4. 71,50 m2 4.500,00 321.750,00

2 Uitzet dan Bowplank A. 2.2.1.8. 41,90 m' 15.000,00 628.500,00

950.250,00

JUMLAH SUB [A] 950.250,00

B PEKERJAAN BANGUNAN LANTAI 1


I PEKERJAAN PONDASI
1 Galian tanah biasa A.2.3.1.1. 14,76 m3 39.750,00 586.710,00

2 Urugan Tanah Kembali A.2.3.1.9.1. 4,92 m3 13.247,00 65.175,24

3 Urugan pasir Bawah pondasi tebal 10cm A.2.3.1.11. 1,24 m3 165.900,00 205.716,00

4 Pas. Batu kali belah 1:8 A.3.2.1.5. 9,43 m3 642.675,00 6.060.425,25

5 Beton sloof 15/20

- Beton K.250 menggunakan alat A.4.1.1.8.2. 1,13 m3 663.197,00 750.274,77

- Pembesian A.4.1.1.17.1a. 186,34 kg 10.762,63 2.005.538,97

- Begesting 3x pakai A.4.1.1.21.2 5,03 m2 144.055,00 724.308,54

10.398.148,76

II PEKERJAAN LANTAI
1 Urugan peninggian tanah 15 cm A.2.3.1.11.1. 7,68 m3 66.300,00 509.184,00

2 Urugan pasir tb. 5 cm A.2.3.1.9.1. 2,56 m3 165.900,00 424.704,00

3 Beton K.100 (lantai rabat 10 cm) A.4.1.1.1. 2,56 m3 663.197,00 1.697.784,32

4 Granit 60x60 A.4.4.3.7.1. 48,60 m2 282.269,16 13.718.281,18

5 Keramik lantai Km/Wc 20x20 A.4.4.3.36. 2,63 m2 199.160,53 523.792,19

6 Conblock tebal 6 cm 12,38 m2 77.051,15 953.893,24 17.827.638,93

III PEKERJAAN DINDING


1 Pasang Bata Hebel A. 4.4.1.11. 174,80 m2 80.400,00 14.053.920,00

2 Beton Kolom K.1 (12/12)

- Beton K.250 menggunakan alat A.4.1.1.8.2. 0,94 m3 663.197,00 623.405,18

- Pembesian A.4.1.1.17.1a. 192,44 kg 10.762,63 2.071.160,52

- Begesting 3x pakai A.4.1.1.22.1. 5,25 m2 143.695,00 754.111,36

3 Kolom 12/12 (Kp)

- Beton K.250 menggunakan alat A.4.1.1.8.2. 0,18 m3 663.197,00 119.375,46

- Pembesian A.4.1.1.17.1a. 19,62 kg 10.762,63 211.162,80

- Begesting 3x pakai A.4.1.1.22.1. 0,82 m2 143.695,00 117.829,90

4 Ring Balok 15/20

- Beton K.250 menggunakan alat A.4.1.1.8.2. 0,60 m3 663.197,00 397.918,20

- Pembesian A.4.1.1.17.1a. 92,30 kg 10.762,63 993.390,75

- Begesting 3x pakai A.4.1.1.23.1 3,35 m2 148.245,00 496.620,75

5 Kolom dan Balok Gunungan 12/12

- Beton K.250 menggunakan alat A.4.1.1.8.2. 0,51 m3 663.197,00 338.230,47

- Pembesian A.4.1.1.17.1a. 78,44 kg 10.762,63 844.220,70

- Begesting 3x pakai A.4.1.1.23.1 2,85 m2 148.245,00 422.498,25

6 Balok Dak Teras depan,teras belakang dan talang beton

- Beton K.250 menggunakan alat A.4.1.1.8.2. 0,08 m3 663.197,00 53.055,76

- Pembesian A.4.1.1.17.1a. 17,26 kg 10.762,63 185.762,99

- Begesting 3x pakai A.4.1.1.23.1 0,50 m2 148.245,00 74.122,50

7 Dag beton teras depan tebal 8cm

- Beton K.250 menggunakan alat A.4.1.1.8.2. 0,28 m3 663.197,00 185.695,16

- Pembesian A.4.1.1.17.1a. 28,74 kg 10.762,63 309.317,99

- Begesting 2x pakai A.4.1.1.23.1 1,72 m2 205.095,00 352.763,40


8 Dag beton teras belakang tebal 8cm

- Beton K.250 menggunakan alat A.4.1.1.8.2. 0,34 m3 663.197,00 225.486,98

- Pembesian A.4.1.1.17.1a. 28,74 kg 10.762,63 309.317,99

- Begesting 2x pakai A.4.1.1.23.1 1,72 m2 205.095,00 352.763,40

9 Dag Talang Beton tebal 8cm

- Beton K.250 menggunakan alat A.4.1.1.8.2. 0,11 m3 663.197,00 72.951,67

- Pembesian A.4.1.1.17.1a. 12,15 kg 10.762,63 130.765,95

- Begesting 2x pakai A.4.1.1.23.1 0,69 m2 205.095,00 141.515,55

10 Plesteran dinding 1:6 A.4.4.2.6. 349,60 m2 39.745,00 13.894.852,00

11 Acian PC A.4.4.2.27. 326,48 m2 23.812,50 7.774.305,00

13 Pasang Keramik Dinding 20x40 Km/Wc A.4.4.3.54. 11,56 m2 182.010,00 2.104.035,60

14 Pasang Keramik Meja Dapur 20x20 A.4.4.3.54. 4,00 m2 182.010,00 728.040,00

15 Pasang batu alam A.4.4.3.58.3 7,56 m2 137.562,50 1.040.316,41

16 Cat Dinding ex. Catylax A.4.7.1.10.3 326,48 m2 17.828,50 5.820.648,68 56.672.452,77

IV PEKERJAAN PINTU DAN JENDELA


1 Pasang Kusen Pintu Jendela almunium 46,08 m' 32.388,50 1.492.462,08

2 Pasang Daun Pintu Utama (P1) kayu ex.meranti 1,00 unt 450.000,00 450.000,00

3 Pasang Daun Pintu kamar (P2) double teakwood 2,00 unt 355.000,00 710.000,00

4 Pasang Daun Pintu dapur (PJ1) double teakwood 1,00 unt 355.000,00 355.000,00

5 Pasang Daun Jendela kayu ex.morando 6,00 unt 327.767,50 1.966.605,00

6 Pasang Pintu PVC Km/Wc kualitas sedang 1,00 unt 350.000,00 350.000,00

7 Cat Kayu Pintu Jendela (melamine) A.4.7.1.4. 24,94 m2 47.178,50 1.176.631,79

8 Pasang Slot Tanam Pintu A.4.6.2.2. 4,00 bh 121.273,00 485.092,00

9 Pasang Engsel Pintu A.4.6.2.5. 12,00 bh 24.097,00 289.164,00

10 Pasang Engsel Jendela A.4.6.2.6. 12,00 bh 17.395,00 208.740,00

11 Pasang Kait Angin Jendela A.4.6.2.9. 6,00 bh 30.495,00 182.970,00

12 Pasang Grendel Jendela A.4.6.2.11.2 6,00 bh 25.615,00 153.690,00

13 Pasang Kaca Bening 5 mm Jendela A.4.6.2.17.1. 4,14 m2 100.722,00 416.989,08 8.237.343,95

V PEKERJAAN PLAFOND DAN LISTRIK


1 Pasang Rangka Plafond A.4.6.1.19.6. 51,23 m2 188.804,35 9.672.446,85

2 Cat Plafond A.4.7.1.11.5 51,23 m2 19.247,00 986.023,81

3 Pasang Jaringan Listrik Baru 1300W PLN - 1,00 unit 1.800.000,00 1.800.000,00

4 Instalasi Titik Listrik (include kabel + vitting) - 7,00 ttk 150.000,00 1.050.000,00

5 Pasang Lampu SL 18 Watt ex.Philips - 7,00 bh 60.000,00 420.000,00

6 Pasang Saklar Tunggal - 4,00 bh 35.000,00 140.000,00

7 Pasang Saklar Ganda - 2,00 bh 45.000,00 90.000,00

8 Pasang Stop Kontak - 6,00 bh 30.000,00 180.000,00 14.338.470,66

VI PEKERJAAN SANITASI
1 Pasang Pipa PVC AW dia 3/4" (Air Bersih) A.5.1.1 26. 12,00 m' 16.648,13 199.777,56

2 Pasang Pipa PVC AW dia 3" (Air Limbah) A.5.1.1 30. 32,00 m' 39.752,81 1.272.089,92

3 Pasang Pipa PVC AW dia 4" (Limbah Padat) A.5.1.1 32. 9,00 m' 63.148,13 568.333,17

4 Sumur Bor Air Bersih - 8,00 m' 100.000,00 800.000,00

5 Saptictank dan sumur resapan - 1,00 unit 2.000.000,00 2.000.000,00

4.840.200,65

VII PEKERJAAN KM/WC & T.CUCI


1 Kran Air 3/4" Plastik A.5.1.1 19. 2,00 bh 78.415,63 156.831,26

2 Pasang Closet Duduk (kualitas sedang) A.5.1.1.1. 1,00 bh 2.102.000,00 2.102.000,00

3 Pasang Kran Shower - 1,00 bh 230.000,00 230.000,00

4 Pasang Washbak Dapur - 1,00 bh 1.000.000,00 1.000.000,00

5 Floor Drain A.5.1.1 14. 1,00 bh 29.800,00 29.800,00 3.518.631,26

VIII PEKERJAAN ATAP


1 Pasang Rangka Atap Baja Ringan 66,00 m3 125.000,00 8.250.000,00

2 Pasang Penutup Atap Ex.Genteng Morando 66,00 m2 62.500,00 4.125.000,00

3 Pasang Nok Ex.Morando 5,50 m' 37.500,00 206.250,00

4 Pasang Lisplank Finish Cat 14,00 m' 58.000,00 812.000,00

13.393.250,00

TOTAL [B] 129.226.136,98


JUMLAH TOTAL [A]+[B] 130.176.386,98
Terbilang : Seratus Tiga Puluh Juta Seratus Tujuh Puluh Tujuh Ribu Rupiah
DIBULATKAN 130.177.000,00

Luas Bangunan 45 m2
Harga Per m2 2.892.808,60
RENCANA ANGGARAN BIAYA
JALAN DAN DRAINASE SALURAN BUANG AIR KOTOR

I PEKERJAAN JALAN DAN DRAINASE SALURAN BUANG AIR KOTOR


1 Galian tanah untuk drainase A.2.3.1.1. 74,40 m3 39.750,00 2.957.400,00

2 Pasangan buis beton 1m x 0,8 m sepanjang +/- 93m' 33,48 m3 3.591.750,00 120.251.790,00

untuk drainase kanan dan kiri jalan

3 Pengurugan kembali bekas galian tanah drainase 24,80 m3 66.300,00 1.644.240,00

4 Pemadatan tanah untuk jalan 44,18 m3 29.500,00 1.303.310,00

5 Pasir urug bawah paving tebal 5cm 11,04 m3 165.900,00 1.831.536,00

6 Paving Block tebal 8cm 220,88 m2 109.750,00 24.241.580,00

7 Pasang Cansteen 33,48 m' 89.551,15 2.998.172,50

TOTAL 155.228.028,50